02-04-2015 Space Committee Update

advertisement
University of North Florida
ADMINISTRATION & FINANCE
Departmental Status Report for Space Committee Meeting
Director:
Department:
Date:
Zak Ovadia
Campus Planning Design & Construction
February 4, 2015
I. SELECTED ACTIVE PROJECTS
NOTE ALL SCHEDULES ARE TENTATIVE
1.
Student Assembly Building (Sanctuary): Design and Construction of sanctuary
building of approximately 6,500 square feet to serve as a venue for group events.
Tentative Schedule:
Programming
Complete
Conceptual Permitting Complete
RFQ for Consultants Complete
Short-listing & Interv. Complete
Program Verification Complete
Schematic Design
Complete
Design Development Complete
Construction Docs.
February 2014
Construction
TBD
Changes from last month:
Construction Documents are
progressing to 85%. No
changes this period. Meeting
with Slater, Trueblood and
Croft on Feb. 5th.
Aquatic Center Re-purposing for Basketball: Design and construction of basketball
courts and general extensive renovations to the Aquatic Center to eliminate the pool.
Tentative Schedule:
Programming
TBD
RFQ for Consultants TBD
Short-listing & Interv. November 2013
Program Verification December 2013
Schematic Design
February 2014
Design Development February 2014
Select CM
March 2014
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Construction proceeding as
scheduled. Working with
users on a “wish list” should
there be residual funds in the
project.
Zak Ovadia
1
4. New Outdoor Swimming Pool: Design and Construction of an outdoor Olympic-size
pool and diving pool north of the existing Student Wellness Complex.
Tentative Schedule:
Programming
TBD
RFQ for Consultants TBD
Short-listing & Interv. TBD
Program Verification TBD
Schematic Design
TBD
Design Development TBD
Select CM
TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Consultant was charged with
justifying the costs by getting
reliable cost estimates.
Package was received on
January 29 - Being reviewed.
5. Skinner-Jones Hall NORTH: Programming and Schematic Design:
Programming, Schematic Design, Feasibility Study to re-purpose this building.
Program will include Skinner-Jones Hall SOUTH as well as other buildings having
related departments (Math, Engineering, Health, etc).
Tentative Schedule:
RFQ for Consultants August 2013
Short List for interview September 2013
Programming
February 2014
Schematic Design
TBD
Design Development TBD
Select CM
TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
One option was selected.
Consultant is currently working
on space allocation to fit
concept. Consultant was also
asked to do the programming
for the Science and Engineering
Building. Prelim. Program for
the S&E was delivered last
week. Consultant currently
working on program for SJ.
Zak Ovadia
2
6. Library Learning Commons: Reconfigure First and Second Floors to create a studentcentric learning commons. Co-locate the Help Desk from Bldg. 15, and remodel
entry lobby.
Tentative Schedule:
Programming
February 2014
Program Verification March 2014
Schematic Design
March 2014
Design Development April 2014
Construction Docs.
complete
Construction
various phases
Changes from last month:
Book moves on both floors are
complete. Carpeting
installation on the second
floor as well as electrical and
data cabling are complete.
Electrical/Data modification
on the first floor are
substantially complete. All
furniture pieces have been
delivered and mostly installed.
Currently working on front
Reception Desk and turnstiles.
No issues this period. Project
is on schedule.
7. Bldg 9 – Second Floor: Project is to create 2 temporary spaces for the Theater Group
practice as well as for Nofa Dixon to layout the tiles for the next project. CPDC
met with Jay Coleman in the space on August 4 to discuss scope of project.
Changes from last month:
Project on hold until further
notice.
8. Math Emporium: Met with Scott Hochwald to review program. There may be
limitations regarding occupancy load in the space as well as availability of data and power for
all stations expected to be in the space. Further evaluation of scope of project still ongoing.
Changes from last month:
9.
Construction documents are
complete ready for bidding.
Surplus tables from the Library
are in storage and so are 24
chairs from the Herbert Center.
Client group is re-thinking
program requirements and
will advise if there are any
changes.
Religious Centers: Engage Civil Engineer to provide a feasibility study and an order of
magnitude cost for providing utility services to a grouping of four buildings.
Tentative Schedule:
NO CHANGE.
Zak Ovadia
3
10. Athletic and Recreation Facilities: This project includes Soccer Fields, Tennis Courts,
Sand Volleyball courts and a Javelin Throw.
JBCPE was charged with producing schematic drawings
and an Order of Magnitude cost estimates for the
four components of this project. Report was
submitted on December 12 including the cost
analysis. Cannot proceed with any of the
components until funds are identified.
11. Department of Sculpture Move to Building 6: This building is now called the “UNF
Annex”.
The Sculpture Lab vacated their space in the Fine Arts
Bldg. (45) starting on December 19 with the exception
of the Induction Furnace. This element of the equipment
will require mechanical and electrical drawings and a
code analysis of the ventilation system before it can be
moved. A complete scope definition and anticipated
costs was forwarded to the client and the
administration for deliberation. CPDC is currently
funding the electrical work needed to hook up the
band saw and the table saw since these two
components serve the current curriculum and cannot
wait.
Zak Ovadia
4