University of North Florida ADMINISTRATION & FINANCE Departmental Status Report for Space Committee Meeting Director: Department: Date: Zak Ovadia Campus Planning Design & Construction April 1, 2015 I. SELECTED ACTIVE PROJECTS NOTE ALL SCHEDULES ARE TENTATIVE 1. Student Assembly Building (Sanctuary): Design and Construction of sanctuary building of approximately 6,500 square feet to serve as a venue for group events. Tentative Schedule: Programming Complete Conceptual Permitting Complete RFQ for Consultants Complete Short-listing & Interv. Complete Program Verification Complete Schematic Design Complete Design Development Complete Construction Docs. February 2014 Construction TBD Changes from last month: Construction Documents are Complete. Field House for Basketball: Design and construction of basketball courts and general extensive renovations to the Aquatic Center to eliminate the pool. Tentative Schedule: Programming TBD RFQ for Consultants TBD Short-listing & Interv. November 2013 Program Verification December 2013 Schematic Design February 2014 Design Development February 2014 Select CM March 2014 Construction Docs. TBD Construction TBD Changes from last month: Construction proceeding as scheduled. No new issues this period. Zak Ovadia 1 4. New Outdoor Swimming Pool: Design and Construction of an outdoor Olympic-size pool and diving pool north of the existing Student Wellness Complex. Tentative Schedule: Programming TBD RFQ for Consultants TBD Short-listing & Interv. TBD Program Verification TBD Schematic Design TBD Design Development TBD Select CM TBD Construction Docs. TBD Construction TBD Changes from last month: Documents are complete but still waiting for Dynamic flyby visual. 5. Skinner-Jones Hall: Programming and Schematic Design: Programming, Schematic Design, Feasibility Study to re-purpose this building. Program will other buildings having related departments (Math, Engineering, Health, etc). Tentative Schedule: RFQ for Consultants August 2013 Short List for interview September 2013 Programming February 2014 Schematic Design TBD Design Development TBD Select CM TBD Construction Docs. TBD Construction TBD Changes from last month: Prelim. Program for the S&E was delivered last week. Consultant has also delivered the program for SJ. Documents distributed to Deans and Provost for comments. A meeting was held with the Deans and Provost on March 24. Meetings with various user groups are being scheduled ASAP to review Space Data Sheets. Zak Ovadia 2 6. Library Learning Commons: Reconfigure First and Second Floors to create a studentcentric learning commons. Co-locate the Help Desk from Bldg. 15, and remodel entry lobby. Tentative Schedule: Programming February 2014 Program Verification March 2014 Schematic Design March 2014 Design Development April 2014 Construction Docs. complete Construction various phases Changes from last month: Currently working on front Reception Desk and turnstiles. Project is no longer schedule due to scheduling issues and technical challenges with the turnstiles and the 3M security gates. New completion date is at the end of May. 7. Bldg 9 – Second Floor: Project is to create 2 temporary spaces for the Theater Group practice as well as for Nofa Dixon to layout the tiles for the next project. CPDC met with Jay Coleman in the space on August 4 to discuss scope of project. Changes from last month: Project for the theater group is now re-activated. The lowest bid was roughly $52,250 and the highest was $76,858. 8. Math Emporium: Met with Scott Hochwald to review program. There may be limitations regarding occupancy load in the space as well as availability of data and power for all stations expected to be in the space. Further evaluation of scope of project still ongoing. Changes from last month: 9. Construction documents are complete ready for bidding. Surplus tables from the Library are in storage and so are 24 chairs from the Herbert Center. Client group is re-thinking program requirements and will advise if there are any changes. No changes this period. Religious Centers: Engage Civil Engineer to provide a feasibility study and an order of magnitude cost for providing utility services to a grouping of four buildings. Tentative Schedule: NO CHANGE. Zak Ovadia 3 10. Athletic and Recreation Facilities: This project includes Soccer Fields, Tennis Courts, Sand Volleyball courts and a Javelin Throw. Athletics issued a Req. for additional fees for JBC to complete construction documents. Athletics will administer the construction themselves. Construction Documents completed. Project is now complete. 11. Department of Sculpture Move to Building 6: This building is now called the “UNF Annex”. A complete scope definition and anticipated costs was forwarded to the client and the administration for deliberation. Academic Affairs is currently funding the electrical work needed to hook up the band saw and the table saw since these two components serve the current curriculum and cannot wait. Work in bidding phase. No other work is planned until funds are identified. 12. Office of Academic Testing: This project entails the feasibility of relocating the OAT to Hicks Hall Consultant was engaged to do a preliminary layout of the space and produce an order of magnitude cost analysis for consideration. Zak Ovadia 4