Minneapolis Bridge Collapse_17.pptx

advertisement
Minneapolis Bridge Collapse
group 17
Safety Examination
•
•
•
The structure of the bridge being flawed was first noted in 1990, when it was
declared ‘Structurally deficient’ and was said to be in need of repair due to the
severe corrosion of its bearings.
Further reports discovered other structural problems with the bridge cracking in
the transverse trusses, little or no movement from the severely corroded bearings
and deformation in the main trusses connected to these bearings.
There was little or no redundancy in the main truss system, which meant if one
single truss failed the bridge as a whole would almost certainly collapse.
Why did this happen?
After its collapse the gusset plates were found to be undersized
and roughly half of the required thickness for the intended load of
the bridge. Gusset plates are rectangles of steel that hold several
girders at connecting points. This load had also increased over the
life of the bridge and this contributed to failure.
How was this allowed to happen?
•
Prior to the collapse a wide-scale steel reinforcement project was planned for the
bridge but was later cancelled in favour of periodic safety inspections.
•
The inspections never checked the thickness of the gusset plates so calculated a
higher load capacity than the actual bridge could sustain.
•
Since the bridge had opened an extra 2” of concrete had been added to the
roadway (an additional 20% of the dead weight of the bridge).
•
At the time of the collapse roughly 261,000kg of construction equipment and
materials were situated on the deck.
•
The gusset plate problem was only discovered after inspection of the ruins. Many
other bridges in Minnesota State had the same design flaw and were retrofitted
with additional structural redundancy.
Since the collapse.....
•
•
•
25 similar truss bridges and their gusset plates were inspected after the collapse
and more inspectors were hired to increase the frequency of inspections.
Bridge inspection in the area has been adopted to better inspect the size and
strain in gusset plates.
There are new directives as to where construction contractors can place materials
on bridges and increased loading must be checked before use.
Download