G09 Milford Haven Bridge Collapse.pptx

advertisement

Milford Haven Bridge Collapse

Group 9

Gary Donohoe

Joseph Gill

Aisling Kearney

James Thompson

 History

 Construction

 Collapse

 Reasons for Collapse

Contents

 Actions Taken

 Conclusions

History

 The Milford Haven Bridge is now known as The Cleddau Bridge since its collapse during construction in 1970

 It spans the River Cleddau between Neyland and Pembroke Dock in Wales

 Milford Haven in the mid 1960’s had grown to become a major oil port capable of handling some of the worlds largest tankers

 The bridge was built because only a ferry service existed to travel across the river at the time

 Construction began in September 1968

 The bridge collapsed in 1970 resulting in the loss of four lives

 Construction recommenced in 1972

 The bridge opened to traffic in 1975 and approximately 885,900 vehicles used it in its first year

 This figure has grown to almost 4 million in 2006

 It is still in use as a toll bridge

 The bridge has 7 spans and rests on 6 piers

Construction

 It is a box girder design

 The shape of the girder makes its inherently strong

 The box girders can be bolted or welded together to form a section which behaves like a single beam

 This presents solutions to designers as when used appropriately it can created a very strong and stiff beam

Collapse

 The collapse of the partially completed bridge happened on Tuesday 2nd June 1970

 A 70m cantilever collapsed on the south bank

 The collapse happened as one of the 150ton sections was being cantilevered into position to connect the road span of the bridge to the second of the 100-feet-high reinforced concrete pillars, on the Pembroke

Dock side

 During construction the stresses are quite different of what might be expected on completion of the bridge

 The structure just appeared to fold

Reasons for Collapse

 Improved steel producing techniques meant that designers could be more confident of the strengths of steel being consistent and so section sizes could be reduced

 At the time the stresses which arise during construction were not fully appreciated

 There was no substantial stiffening of the box sections other than at the pier support’s of the bridge

 This meant that during construction the box section developed very large moments causing it to buckle about the pier it was being constructed from

Actions Taken as a Result of The

Milford Haven Collapse

 This and two other box girder bridge disasters led to the formation of the

Merrison Commission

 They looked at the adequacy of existing codes in relation to box girders

 They set down guidelines for stress analysis and the way in which box girders were to be connected

 These were formalised in BS 5400 and led to the creation of specialised sections dealing with box girders

 Other recommendations included clarifying the roles of the engineer and contractor, such as vetting of design and construction methods

 It was recommended that the design rules should be used only by suitably experienced designers

Conclusion

 This failure occurred due to the fact that the engineers were pushing the boundaries of their knowledge at the time of this incident

 The disaster led to a better understanding of the complexities of steel box girder design

 Armed with this knowledge, more powerful computers, and the updated codes, we are hopeful that a disaster like this will not happen again

Download