Gary Donohoe
Joseph Gill
Aisling Kearney
James Thompson
History
Construction
Collapse
Reasons for Collapse
Actions Taken
Conclusions
The Milford Haven Bridge is now known as The Cleddau Bridge since its collapse during construction in 1970
It spans the River Cleddau between Neyland and Pembroke Dock in Wales
Milford Haven in the mid 1960’s had grown to become a major oil port capable of handling some of the worlds largest tankers
The bridge was built because only a ferry service existed to travel across the river at the time
Construction began in September 1968
The bridge collapsed in 1970 resulting in the loss of four lives
Construction recommenced in 1972
The bridge opened to traffic in 1975 and approximately 885,900 vehicles used it in its first year
This figure has grown to almost 4 million in 2006
It is still in use as a toll bridge
The bridge has 7 spans and rests on 6 piers
It is a box girder design
The shape of the girder makes its inherently strong
The box girders can be bolted or welded together to form a section which behaves like a single beam
This presents solutions to designers as when used appropriately it can created a very strong and stiff beam
The collapse of the partially completed bridge happened on Tuesday 2nd June 1970
A 70m cantilever collapsed on the south bank
The collapse happened as one of the 150ton sections was being cantilevered into position to connect the road span of the bridge to the second of the 100-feet-high reinforced concrete pillars, on the Pembroke
Dock side
During construction the stresses are quite different of what might be expected on completion of the bridge
The structure just appeared to fold
Improved steel producing techniques meant that designers could be more confident of the strengths of steel being consistent and so section sizes could be reduced
At the time the stresses which arise during construction were not fully appreciated
There was no substantial stiffening of the box sections other than at the pier support’s of the bridge
This meant that during construction the box section developed very large moments causing it to buckle about the pier it was being constructed from
This and two other box girder bridge disasters led to the formation of the
Merrison Commission
They looked at the adequacy of existing codes in relation to box girders
They set down guidelines for stress analysis and the way in which box girders were to be connected
These were formalised in BS 5400 and led to the creation of specialised sections dealing with box girders
Other recommendations included clarifying the roles of the engineer and contractor, such as vetting of design and construction methods
It was recommended that the design rules should be used only by suitably experienced designers
This failure occurred due to the fact that the engineers were pushing the boundaries of their knowledge at the time of this incident
The disaster led to a better understanding of the complexities of steel box girder design
Armed with this knowledge, more powerful computers, and the updated codes, we are hopeful that a disaster like this will not happen again