4A6(1) Disaster Report – Milford Haven Bridge Group 7: Stephen Cantrell Chris Hodge Chris McKeown Peter Weldon 4A6(1) Disaster Report – Milford Haven Bridge Introduction: Our Group’s case study was the Milford Haven Bridge, which collapsed in South Wales in 1970. The bridge was of a steel box girder design, and collapsed due to errors with the box girder. Originally conceived to be completed in 1971, work was halted for over two years due to the collapse and the bridge finally opened in 1975, when it was renamed the Cleddau Bridge. This type of bridge was most prominent in the years subsequent to WWII, as military powers realized that they needed to cross much larger spans, with bridges they could quickly construct. This meant that they needed to come up with a design which had a much lower depth (and hence weight) than the current setup they were using, which was basically a grouping of I-beams fixed together side-by-side. The box girder they developed can effectively be considered to be an I-beam with two webs. The beauty of this is that it allows a much wider span on the flanges, and also thicker flanges can be used. The closed ‘cell’, as it is known, gives this cross section much better torsional stiffness and strength than its competitors. The cantilevers on the top flange were only introduced with the advent of higher grade steels. The bottom tie (or flange) manages to alleviate the induced stress from these additions. Whilst this cross section is sufficient for spans, at the pier supports, it requires further bracing. This can be in two main forms, either thickening of the diaphragms, or addition of vertical stiffeners above the supports. Why Did the Milford Haven Bridge Collapse?: The collapse of the Milford Haven Bridge occurred on the 2nd of June 1970. This boxgirder bridge was constructed from sections of steel box girders that were prefabricated and moved over the previously built sections, aligned in place and welded. Thus this bridge was erected by cantilevering. With this method of construction the cross frame above a pier support suffers extra loading due to the cantilevering part. 1 4A6(1) Disaster Report – Milford Haven Bridge The collapse occurred as one of the final sections of the second span was being moved out along the cantilever. This section slid forward down the cantilever, buckled at the support and collapsed into the river killing four men, including the site-engineer. Therefore it was the extra loading due to the cantilevering method used that caused the failure. This type of loading should not cause any problems, provided that the diaphragm of the girder has been designed to carry this extra load. Unfortunately this was not the case in this situation. There was no substantial stiffening of the section other than the six pier supports and abutments, and an investigation of the failure showed that the collapse was due to the buckling of the diaphragm at the support of the second span. The diaphragm was torn away from the sloping web near the bottom. This caused reduction in the lever arm between flanges resisting negative bending moment at the support. The reduction of this distance increased the tendency of the bottom flange to buckle, as this increased the force needed in each flange to carry the moment with the reduced lever arm. The total load transmitted by the diaphragm to the bearings just before collapse was computed as 9700kN. This load would not have caused any problem provided the diaphragm was designed to carry it. Allowing for likely values of distortion and residual stress, the calculated design strength was found to be as low as 5000kN. Thus, the failure was essentially due to design inadequacy of a pier support diaphragm. 2 4A6(1) Disaster Report – Milford Haven Bridge The Outcomes of the Milford Haven Bridge Collapse: Following the collapse of the Milford Haven Bridge, the Merrison Committee of Inquiry into the Design and Erection of Steel Box Girder Bridges was set up and tasked with investigating the cause of the disaster. The committee found in 1973 that the cause of the failure was, indeed, inadequate design of the pier support diaphragm, but also considered "the failure of site organisation between the parties as of more general significance". The committee’s opinion was that BS153 (the only British steel bridge design and construction Code of Practice current in the 1960's) was inadequate for applications like the Milford Haven bridge, and thought that there was a need to consider wider implications for the construction of steel box girder bridges. Because of this, the Merrison Committee prepared Interim Design and Workmanship Rules. These dealt with the design of steel plated components and their connections, and the effects of welding residual stresses and geometric imperfections linked to fabrication tolerances. These rules, along with further research, formed the basis of a new British Standard BS5400, parts 3, 6, and 10. This British Standard contains comprehensive rules for steel box girders, and the implementation of the recommendations contained in the report led to wide-ranging changes in contractual procedures and in checking designs and construction procedures. Work was halted after the accident while the Merrison Committee investigated, and was only restarted in October of 1972, and opened to traffic in March 1975, with the new name the Cleddau Bridge. The final cost was £11.83million. The original contract was awarded in 1968 for £2.1 million. £7 million of the overspend was attributed to changes in the design to comply with the Merrison recommendations. £3 million of this came from an out of court settlement with between the County Council and the consulting engineers. This serves as a prime example of how errors in design and insufficient communication can be very costly for engineers. The collapse is regarded as the last major bridge disaster in the United Kingdom. 3 4A6(1) Disaster Report – Milford Haven Bridge References: - Department of the Environment (Merrison Committee of Inquiry) (1973) - Inquiry into the Basis of Design and Method of Erection of Steel Box Girder Bridges. - Bridle, Ron; Porter, John (2002) - The Motorway Achievement: Frontiers of Knowledge and Practice. Thomas Telford Ltd. pp. 346–348. ISBN 978-0727731975. - http://www.istructe.org/knowledge/topic_areas/learning-from-structural-failure/Pages/steel-boxgirder-bridges.aspx, referencing: Merrison Committee of Inquiry (1973) - Inquiry into the Basis of Design and Method of Erection of Steel Box Girder Bridges. Picture 1: http://www.geograph.org.uk/photo/845071 Picture 2: http://www.newcrossing.gov.bm/photo-library/pages/engineering-options-2.html Picture 3: http://www.istructe.org/knowledge/topic_areas/learning-from-structuralfailure/Pages/steel-box-girder-bridges.aspx Picture 4: http://theconstructor.org/structures/box-girder-specifications-advantagesdisadvantages/2166/ 4