Long Beach Community College District
November 9, 2011
1
Completed Construction Projects
LAC W Trailers Demo
PCC Tech 1 (Sheet Metal)
Current Construction Projects
LAC Building A – Student Services Retrofit
LAC Building I (Bookstore)
LAC Master Landscape
LAC Stadium Parking Lot Lights and Veterans Stadium Lights
PCC MDAB (Multi-Disciplinary Academic Building)
LAC PCC Building CC Retrofit
Upcoming Construction Projects
LAC Math Technology Building
PCC Building GG
LAC Building C Retrofit
Q & A
2
Completed Construction Projects
LAC W Trailers Demo - Measure E 2008
Project addressed storm run off issues with bio swales
Site converted to a parking lot
Project completed Summer 2011
3
Completed Construction Projects
PCC Tech 1 (Sheet Metal) - Measure E 2008
Construction started Summer 2011
Equipment and utilities installed
Projected completed before start of Fall semester 2011
4
Current Construction Projects
LAC Building A – Student Services Retrofit
Measure E 2008
New home for A&R, Counseling, Health Services,
Cashier, Transfer Center
Project currently in structural upgrade
New contractor in place
End of construction anticipated Summer 2012
5
Current Construction Projects
LAC Building I - Measure E 2008
Adds additional 4,000 square feet to existing building
Architecture to match LAC Mediterranean Theme
Work on framing and utilities underway
End of construction anticipated Fall 2011
Move in planned for late January or early Feburary
6
Current Construction Projects
LAC Master Landscape - Measure E 2008
Currently in Design Phase(Finalizing design)
Plans to be submitted to DSA November 2 nd
Quad areas North and South of Bldg. A will bid Fall 2011
Remaining areas designed at 25%
Scope includes new hardscape/landscape and pedestrian pathways
7
Current Construction Projects
Stadium Parking Lot Lights and Stadium Lighting
Measure E 2008
Stadium parking lot lights
Construction commenced 9/12
All bases have been installed
Currently in the process of installing light poles/fixtures
Install energy efficient lights with controls capabilities
Stadium lighting retrofit
Awaiting final DSA approval
8
Current Construction Projects
PCC MDAB
(Multi-Disciplinary Academic Building)
Measure E 2008
MDAB building remodel project
Phase 1 of 2 currently under construction
Project currently in demolition and structural reinforcement
Phase 1 Project to be completed Summer 2012
9
Upcoming Construction Projects
PCC Building CC Retrofit - Measure E 2008
Houses the Fitness Center, Gymnasium, Weight Room, and
Faculty and Staff Offices
Swing space located on PCC Campus (Bldg. GG)
Approved by DSA on 1/27/11
Bid process complete. Awarded to Angeles
To be completed concurrently with MDAB project phase 1
Anticipated end of construction Fall 2012
10
Upcoming Construction Projects
LAC Math Technology Building – Measure E 2008
Will house Math and Culinary Arts instructional program as well as
Reprographics
Design Build delivery method
Requesting Qualifications (RFQ) – was due 8/3
Shortlisted and interviewed 10 respondents (9/7-9/9)
Selected 3 and are currently requesting for proposals
Pre-RFP meeting with contractors to take place on 10/27
Anticipated start of construction
2013
11
Upcoming Construction Projects
PCC Building GG - Measure E 2008
Design Build delivery method
Request for Qualifications (RFQ)
Start in November and due mid December
Building to house Health Services, EOPS, DSPS, Financial Aid, Cashier, A&R, and Counseling
Estimated start of construction December 2013
12
Upcoming Construction Projects
LAC Building C Retrofit - Measure E 2008
Hired Architect to do design work
Currently in schematic phase
Work includes modernization of structure, classrooms spaces, and office areas
13
Liberal Arts Campus
Site Plan
Pacific Coast Campus
Site Plan