Construction Updates Presentation 09-14-2011

advertisement
Bond Construction Update
Facilities Advisory Committee
Long Beach Community College District
September 14, 2011
EDUCATE  ENGAGE  EMPOWER
1
Agenda

Completed Construction Projects






Current Construction Projects






LAC Building A – Student Services Retrofit
LAC Building I (Bookstore)
LAC Master Landscape
LAC Stadium Parking Lot Lights and Veterans Stadium Lights
PCC MDAB (Multi-Disciplinary Academic Building)
Upcoming Construction Projects





District Wide – Monument Signs
LAC South Walkway Extension
LAC Infrastructure Improvements Project and District Wide –
Energy Efficiency Project
LAC W Trailers Demo
PCC Tech 1 (Sheet Metal)
LAC PCC Building CC Retrofit
LAC Math Technology Building
PCC Building GG
LAC Building C Retrofit
Q&A
2
Completed Construction Projects
District Wide – Monument Signs
Measure E 2008
LAC Bldg. Designator
LAC Monument Sign
PCC Monument Sign
 District Wide Monument Signs.
 Locations:
 LAC-Clark/Conant
 PCC-20th/Walnut Ave.
3
Completed Construction Projects
LAC South Walkway Extension
Measure E 2008
 Project complete
 Palm trees to be replaced August 2011
 Continues Master Plan pedestrian corridor
4
Completed Construction Projects
LAC Infrastructure Improvement Project and
District Wide Energy Efficiency Project
Measure E 2008



Total annual estimated savings of 1.5 mil. Kwh
Project started Fall 2009; currently hydro seeding all
affected areas(All phases)
Majority of existing building HVAC systems to be
upgraded and connected to the Central Plant


Exterior lighting and controls upgrades





Buildings B,C,D,E,G, & H are connected
All parking lots north of Lew Davis are on new system
New Reclaimed Water tie-ins to irrigation connected
New gas lines installed for Buildings B, C, D, E, G, H,
J, M, N, and P
New domestic lines installed for Buildings B, C, D, E,
F, G, H, I Trailers, J, K,L, M, N, P
Construction completed Summer 2011
5
Completed Construction Projects
LAC W Trailers Demo - Measure E 2008



Project addresses storm run off issues with bio
swales
Site converted to a parking lot
Project completed Summer 2011
6
Completed Construction Projects
PCC Tech 1 (Sheet Metal) - Measure E 2008



Construction started Summer 2011
Equipment and utilities installed
Projected completed before start of Fall semester 2011
7
Current Construction Projects
LAC Building A – Student Services Retrofit
Measure E 2008



New home for A&R, Counseling, Health Services,
Cashier, Transfer Center
Project currently in structural upgrade
End of construction anticipated Summer 2012
8
Current Construction Projects
LAC Building I - Measure E 2008





Adds additional 4,000 square feet to existing building
Architecture to match LAC Mediterranean Theme
Work on framing and utilities underway
End of Construction anticipated Fall 2011
Move in planned for late January or early Feburary
9
Current Construction Projects
LAC Master Landscape - Measure E 2008





Currently in Design Phase(Finalizing design)
Plans to be submitted to DSA in August
Quad areas North and South of Bldg. A will bid Fall 2011
Remaining areas designed at 25%
Scope includes new hardscape/landscape and pedestrian
pathways
10
Current Construction Projects
PCC MDAB
(Multi-Disciplinary Academic Building)
Measure E 2008




MDAB building remodel project
Phase 1 of 2 currently under construction
Project currently in demolition and structural reinforcement
Phase 1 Project to be completed Summer 2012
11
Current Construction Projects
Stadium Parking Lot Lights and Stadium Lighting
Measure E 2008

Stadium parking lot lights

Construction commenced 9/12

Work will start in South East portion of parking lot

Install energy efficient lights with controls capabilities

Stadium lighting retrofit

Awaiting final DSA approval
12
Upcoming Construction Projects
PCC Building CC Retrofit - Measure E 2008





Houses the Fitness Center, Gymnasium, Weight Room, and
Faculty and Staff Offices
Swing space located on PCC Campus (Bldg. GG)
Approved by DSA on 1/27/11. Currently in bid process
To be completed concurrently with MDAB project phase 1
Anticipated end of construction Fall 2012
13
Upcoming Construction Projects
LAC Math Technology Building – Measure E 2008

Will house Math and Culinary Arts
instructional program as well as
Reprographics


Design Build delivery method
Requesting Qualifications (RFQ) –
Due 8/3
Shortlisted and interviewed 10
respondents (9/7-9/9)



Select 3 and request for proposals
Anticipated start of construction
2013
14
Upcoming Construction Projects
PCC Building GG - Measure E 2008


Design Build delivery method
Request for Qualifications (RFQ)



Start in September and due late October
Building to house Health Services, EOPS, DSPS, Financial Aid, Cashier, A&R,
and Counseling
Estimated start of construction December 2013
15
Upcoming Construction Projects
LAC Building C Retrofit - Measure E 2008



Hired Architect to do design work
Currently in schematic phase
Work includes modernization of structure, classrooms spaces, and
office areas
16
liberal arts
Liberal Arts Campus
Site Plan
pacific coast
Pacific Coast Campus
Site Plan
QUESTIONS
&
ANSWERS
EDUCATE  ENGAGE  EMPOWER
19
Download