ADDENDUM #2
Date:
March 24, 2015
To:
Bidders of Record
Project:
Bid Packages 4, 14, 15
Annual Major Maintenance FY 16
SPECIAL NOTE: Addendum #1 information shall supersede the information contained in the
Contract Documents
This Addendum forms a part of the Contract Documents and modifies the original Bidding
Documents dated December 20, 2014 and related addenda and clarifications. Acknowledge receipt of
this Addendum in the space provided on the Bid Form. Failure to do so may subject the Bidder to
disqualification.
PreBid Meeting Minutes & Site Walks; 3/9/15
Bid / Construction Schedule
Bids due: March 30, 2015 @ 1:00PM
Selection of successful bidders: April 7, 2015
Construction Start Date: May 26, 2015
Project Completion Date: Reference Proposal Form and
http://www.wesleyan.edu/construction/majormaint/FY_16/FY_16.html
Housing Opens/Students Arrive on campus: August 14, 2015
All bedroom hardware shall be revised to Arrow ML 13 SR 26D 306 281, Keyway AR
1.
All Interior locks to be standard-duty cylindrical
2.
Interior locks to be Arrow ML 13 SR 26D 306 281, 121/124. No Substitute. Meets
3.
All cylinders must be manufactured by “KABA”.
4.
Provide extended Curved lip strikes as required.
BID PACKAGE #4:
35 Home Avenue – Interior / Exterior Renovations
1. Abatement contractor shall to demolish all walls in both bathrooms on second floor. General
contractor to remove demolition of walls from his proposal.
53AB Home Avenue – Interior / Exterior Renovations
1. Reference clarification photo sheets P-5-14, P-5-15 & P-5-16 dated March 24, 2015.
2. Photos show:
a. Existing 200 amp panel located in the garage.
b. North & east side bathroom walls showing available access for rough-in work.
c. Concrete floor in garage at base of proposed CMU wall.
3. Contractor to insulate exposed walls of basement level bathroom inside storage area.
Major Maintenance FY16
Project Number 2016000000
ADDENDUM # 2
Page 1
3/24/15
BID PACKAGE #14:
40 Home Avenue – Exterior Painting / Storm Window Installation
1. Q: The 2 Large Windows on the front and left Elevation cannot be made in Cottage
Style Double Hung. Can these be provided as equal top and bottom sash?
A: Furnish and install fixed storm windows for these two windows.