FORM – PSR v2 Monthly Project Status Report Project Name Exchange 2010 Upgrade IS Project Code IS-0192 Project Manager Alec Coleman Project Sponsor Gregor Waddell Report Period From 4 Jan 2011 Report Period To 31 Jan 2011 RAG Status Amber Report Number 3 Milestones (from draft PPD – still to be confirmed) Planned Date (from PPD) Expected Date Produce an Architectural Design for Exchange 2010 installation, including storage levels required for the increased archiving period, backup and recovery and performance monitoring and tuning procedures. Jan 2011 Feb 2011 Produce Architectural Design for Symantec eVault and integration with Exchange 2010 Jan 2011 Jan 2011 Jan 2011 Complete Evault Upgrade Jan 2011 Jan 2011 Jan 2011 Build a working, supportable and manageable pilot for Exchange 2010 environment. Feb 2011 Mar 2011 Feb 2011 Feb 2011 Feb 2011 Feb 2011 Knowledge transfer/training of ISMS staff Mar 2011 Mar 2011 Provide guidance and light-touch training regime for staff, integrating with OCS 2007. Mar 2011 Apr 2011 Complete Pilot in ISMS Apr 2011 Apr 2011 Complete Rollout and Training by Jun 2011 Jun 2011 End Project Activities Jul 2011 Jul 2011 Produce strategy for migration of Outlook 2010 Client. Produce a strategy for migrating to Microsoft Forefront Online Protection for Exchange (FOPE). Date Completed Progress achieved this period Placed formal orders with Blue Source and Salford for the design consultancy Obtained design from Salford and sought clarification on a number of points Produced training plan, risk log, communications plan, project website, updated budget report and PPD. Agreed that Alan Turner FHSC be senior user Held project Board meeting – agreed approach towards training Super-Users Agreed terms of reference for Project and Executive Board with Gregor Submitted Change Requests for Evault Upgrade, Deployed new EV Client; Upgraded Evault to Version 9 (25/1/11) Produced rollout plan for the upgrade of PC’s to XPSP 3 and commenced deployment in Library on 28/1/11. Commenced implementation of server infrastructure for Exchange 2010 Obtained details from Sophos regarding Pure Message as mitigation against slippage External training provided to Ian Kitching, Nigel Holderness, Tim Smyth, Richard Mainprize and Simon Harvey on Exchange 2010. Drafted communications for Gregor to send out to HoD’s seeking nominations for co-ordinator. Outlook for next period Continue roll out XP SP2 in waves for to all 900 PC’s that need the upgrade Ensure that interim SAN is implemented (dependency on another project) Decide how to progress updates to the email policy – JGM is contacting new ISMS director. Agree communications plan for the upgrade Agree training with training provider D:\612938419.doc Page 1 of 4 Version 2: January 2008 FORM v2.1 – PSR External training on Exchange 2010 for Rob Spalding Project team meeting with Salford to agree Design Purchase additional days consultancy from Salford Purchase training days for Super User training Purchase hardware and software pending decision on what to order Update and agree PPD Build architecture for Exchange 2010 Ensure that an approach is agreed for OCS deployment and hardware provision Determine whether to purchase Sophos Pure Message contract extension Obtain nominations for co-ordinators and Super users from services and faculties. Agree wave roll out plan Ensure order placed for 200 headsets and webcams for OCS / Live Meeting (dependency on another project) Key Risks Potential Extent of Impact (H, M, L) Likelihood of Occurrence (H, M, L) Progress / Support Required Incompatibilities between clients still using Outlook 2003 and Exchange 2010/eVault 9 provision. M M Plan the pilot (and later the rollout) very carefully so as to avoid such issues. Wide range of tests to scope the issues. Disruption to service transitions / migrations. any M M Plan the pilot (and later the rollout) very carefully so as to avoid such issues. Impairment of our DR position during transitions / migrations M M Plan the pilot (and later the rollout) very carefully so as to avoid such issues. Interruption to in / out flow of email during transition. M H Design a means of trialing new provision first and building confidence and knowledge transfer to Ops. Impairment of anti-virus service during transition (leading to risk of mass infection etc). M H Design a means of trialing new provision first and building confidence and knowledge transfer to Ops. An extensive training plan will need to be drawn up which, based on past experience will take up the majority of an administrators time for at least 3 months. M H Plan for additional resource. Rollout following user training needs to be closely managed and failure to achieve proper co-ordination will impact staff perception M M Planning between training organiser and Ops during rollout. Good communications strategy needed. Network Capacity issues create bottlenecks a performance problems when rolling out OCS M H OCS project to confirm that this is not an issue. We are using different consultancies for the design of Exchange 2010 and Evault which could result in an inconsistent approach. M M Manage the suppliers and ensure ISMS technical team are aware of what both suppliers have designed. M H Manage implementation around availability of staff. Book resources in the Resource planner. during Key technical staff will be unavailable during February due to Exchange 2010 training as follows: 7th February - Rob D:\612938419.doc Page 2 of 4 Version 2.1: October 2009 FORM v2.1 Exchange/Outlook 2010 rollout will require the OCS Outlook add-ins. The add in is available in both 32-bit and 64-bit versions; The latter will become relevant once Windows-7 is deployed. There is therefore a need to determine which version is used. Loan SAN storage plus free space on existing SAN is insufficient to implement Salford’s design, limiting the size & scope of the ISMS pilot. Impact on the validity & usefulness of the pilot. SAN won't be available in time; risk of loan not being extended – PSR M M Testing using test schedule proposed by Brendan 10/1/11 M M Design the scaling-down to ensure maximum usefulness, e.g. for database backup & resilience testing (IK) M H Extend loan of HDS SAN; Purchase new SAN (GW) M M Ensure that the project is not dependent on a DMZ which will be delivered under another project (IK) Key Project Issues Priority (H, M, L) Progress / Support Required The current project plan for the new Exchange environment is for later implementation than the expiry of Sophos Pure Message email scanning in Exchange 2003 environment on 30/3/10. H Determine dependencies and decide whether earlier implementation of Exchange 2010 is possible. Alternatively extend Sophos Pure Message. Sophos will extend for 6 months at a cost of £3750 plus VAT. That the need for a DMZ could jeopardise the project Change Requests Status Priority (H ,M ,L) Progress / Support Required 2010-0237 – Extend AD Schema for Exchange 2010 Approved M Implemented 10 Jan 2011 2010-0244 – Deploy new EV Client Approved H Implemented 17 Jan 2011 2010-0226 – Deploy XP SP3 to all PCs Approved H Implemented in ISMS Dec 2010 rollout to faculties Jan-Mar 2011 2011 - Upgrade Evault Server Approved H Implemented 24 Jan 2011 VARIANCE RAG REASON Budget Variance Amber 60K has been allowed for in the original budget (but this was before any project planning had been started). This is insufficient for anything other than the basic design, implementation of the Exchange environment and training of ISMS staff. We expect to become clearer on this once we have agreed the design from Salford and then we can determine exactly what software and hardware to purchase. Out of the budget we have spent £16,435 and have £43,564 left. We estimate that a budget of nearer £75-80K will be needed. Schedule Variance (time) Green Key technical staff were unavailable during January due to Exchange 2010 training as follows: 17th January – Richard Mainprize 10th January – Nigel, Tim, Ian and Simon 7th February - Rob Also Rob was not available for 5 further days in January. This has had an impact on agreeing the Salford design. Resource Variance Green Resources have been requested and approved for February – but see risks above. D:\612938419.doc Page 3 of 4 Version 2.1: October 2009 FORM v2.1 Scope Variance Amber Quality Variance Green Stakeholder Issue Green – PSR OCS 2007 client deployment is included within project scope and needs to be planned. Alan Turner has agreed to be the senior user. Gregor will email HoD’s about the need for Super Users and a report has been drafted for CMT. Risk Level Amber Due to available budget and slight slippage in view of Ops/A&D availability in January overall risk level is Amber. D:\612938419.doc Page 4 of 4 Version 2.1: October 2009