FORM – PSR v2 Monthly Project Status Report Project Name Exchange 2010 Upgrade IS Project Code IS-0192 Project Manager Alec Coleman Project Sponsor Gregor Waddell Report Period From 1 Dec 2010 Report Period To 24 Dec 2010 RAG Status Green Report Number 2 Milestones (from draft PPD – still to be confirmed) Planned Date (from PPD) Produce an Architectural Design for Exchange 2010 installation, including storage levels required for the increased archiving period, backup and recovery and performance monitoring and tuning procedures. Jan 2011 Produce Architectural Design for Symantec eVault and integration with Exchange 2010 Jan 2011 Complete Evault Upgrade Jan 2011 Build a working, supportable and manageable pilot Exchange 2010 environment. Feb 2011 Produce strategy for migration of Outlook 2010 Client. Produce a strategy for migrating to Microsoft Forefront Online Protection for Exchange (FOPE). Expected Date Date Completed Feb 2011 Feb 2011 Knowledge transfer/training of ISMS staff Mar 2011 Provide guidance and light-touch training regime for staff, integrating with OCS 2007 and Windows 7 rollouts. Mar 2011 Complete Pilot in ISMS Apr 2010 Complete Rollout and Training by Jun 2011 End Project Activities Jul 2011 Progress achieved this period Placed formal orders with Blue Source and Salford Workshop held between Salford and technical team on 15/12 D:\401285086.doc Page 1 of 4 Version 2: January 2008 FORM v2.1 – PSR Workshop held between Blue Source and technical team on 20/12 Procedure received from Blue Source for the upgrade. Meeting held with HR to discuss training – note HR do not believe that a training need analysis will be of use. Placed order with Phoenix for IT Academy CBT following agreement from Gregor and Joe Produced draft training plan for Outlook 2010 and sent to Brendan Hoare to add OCS training Held meeting with Gregor, Joe and Rob to discuss dependencies Refined PPD and plans following meetings with consultancies Outlook for next period Obtain design from Salford Refine and agree PPD and Project plan Determine who will be the Project senior user Agree Design, PPD at Project Board Submit Change Requests for Evault Upgrade Deploy new EV Client Upgrade Evault to Version 9 (25/1/11) Implement server infrastructure for Exchange 2010 Key Risks Potential Extent of Impact (H, M, L) Likelihood of Occurrence (H, M, L) Progress / Support Required Incompatibilities between clients still using Outlook 2003 and Exchange 2010/eVault 9 provision. M M Plan the pilot (and later the rollout) very carefully so as to avoid such issues. Wide range of tests to scope the issues. Disruption to service transitions / migrations. any M M Plan the pilot (and later the rollout) very carefully so as to avoid such issues. Impairment of our DR position during transitions / migrations M M Plan the pilot (and later the rollout) very carefully so as to avoid such issues. Interruption to in / out flow of email during transition. M H Design a means of trialing new provision first and building confidence and knowledge transfer to Ops. Impairment of anti-virus service during transition (leading to risk of mass infection etc). M H Design a means of trialing new provision first and building confidence and knowledge transfer to Ops. An extensive training plan will need to be drawn up which, based on past experience will take up the majority of an administrators time for at least 3 months. M H Plan for additional resource. Rollout following user training needs to be closely managed and failure to achieve proper co-ordination will impact staff perception M M Planning between training organiser and Ops during rollout. Good communications strategy needed. Network Capacity issues create bottlenecks a performance problems M H OCS project to confirm that this is not an issue. during D:\401285086.doc Page 2 of 4 Version 2.1: October 2009 FORM v2.1 – PSR when rolling out OCS We are using different consultancies for the design of Exchange 2010 and Evault which could result in an inconsistent approach. M M Manage the suppliers and ensure ISMS technical team are aware of what both suppliers have designed. M H Manage implementation around availability of staff. Book resources in the Resource planner. Key Project Issues Priority (H, M, L) Progress / Support Required The current project plan for the new Exchange environment is for later implementation than the expiry of Sophos Pure Message email scanning in Exchange 2003 environment on 30/3/10. H Determine dependencies and decide whether earlier implementation of Exchange 2010 is possible. Alternatively extend Sophos Pure Message Blue Source have advised that it is necessary to deploy the Latest EV client before we can carry out the EV upgrade. H Operations will test the new client and raise a change request for rollout in mid-Jan. Key technical staff will be unavailable during January/February due to Exchange 2010 training as follows: 17th January – Richard Mainprize 10th January – Nigel, Tim, Ian and Simon 7th February - Rob Also Rob will not be available for 5 further days in January and Ian has leave booked in early Jan. Change Requests Status Priority (H ,M ,L) Progress / Support Required Two change requests to be produced next month by Ops for EV upgrade. Not yet drafted h NH,TS to produce Change Requests VARIANCE RAG REASON Budget Variance Amber 60K has been allowed for in the original budget. This is insufficient for anything other than the basic design, implementation of the Exchange environment and training of ISMS staff. We expect to become clearer on this once the design has been received from Salford. Out of the budget we have spent £16,435 and have £43,564 left. Schedule Variance (time) Green Key technical staff will be unavailable during January/February due to Exchange 2010 training as follows: 17th January – Richard Mainprize 10th January – Nigel, Tim, Ian and Simon 7th February - Rob Also Rob will not be available for 5 further days in January Resource Variance Green Resources have been requested and approved for D:\401285086.doc Page 3 of 4 Version 2.1: October 2009 FORM v2.1 – PSR January – but see risks above. Scope Variance Amber Project Kick off meeting agreed that OCS 2007 client deployment be included within project scope. The kick-off meeting agreed that the project will investigate a training needs analysis with HR for aspects that are not in scope e.g. Office 2010, Windows 7. Details of training needs are awaited from HR. Update 22/12, HR advise that a TNA would not be much help and do not propose to do this. Quality Variance Green Stakeholder Issue Green Risk Level Green Graham Howarth is not prepared to be senior user but has suggested Bill Pollard. Gregor will ask CMT whether there are any other volunteers. D:\401285086.doc Page 4 of 4 Version 2.1: October 2009