FORM – PSR v2 Monthly Project Status Report Project Name Exchange 2010 Upgrade IS Project Code IS-0192 Project Manager Alec Coleman Project Sponsor Gregor Waddell Report Period From 1 Apr 2011 Report Period To 28 Apr 2011 RAG Status Amber Report Number 6 Milestones Planned Date (from PPD) Expected Date Date Completed Produce an Architectural Design for Exchange 2010 installation, including storage levels required for the increased archiving period, backup and recovery and performance monitoring and tuning procedures. Feb 2011 Mar 2011 Apr 2011 Produce Architectural Design for Symantec eVault and integration with Exchange 2010 Jan 2011 Jan 2011 Jan 2011 Complete Evault Upgrade Jan 2011 Jan 2011 Jan 2011 Build a working, supportable and manageable pilot for Exchange 2010 environment. Apr 2011 May 2011 Feb 2011 Mar 2011 Mar 2011 Feb 2011 Mar 2011 Mar 2011 Knowledge transfer/training of ISMS staff Apr 2011 May 2011 Provide guidance and light-touch training regime for staff, integrating with OCS 2007. Mar 2011 Apr 2011 Complete Pilot in ISMS May 2011 Jun 2011 Complete Rollout and Training by Aug 2011 Sep 2011 End Project Activities Sep 2011 Oct 2011 Produce strategy for migration of Outlook 2010 Client. Produce a strategy for migrating to Microsoft Forefront Online Protection for Exchange (FOPE). Progress achieved this period We are probably 4 weeks behind the original plan but it is essential that the entire infrastructure is thoroughly tested prior to the pilot and this has been causing some problems with regard to network backup issues and operational work. Progress has been made as follows: Salford, Rob and Nigel have completed the following: Configured Forefront Proxy settings on CHE-I-MBX02, CAM-I-MBX01, CAM-I-MBX02, CAM-I-CAS01, CAM-ICAS02 to enable engine definition updates. Requested a Certificate needed for Exchange 2010 Imported certificate into all members of the Exchange Organization. Configured remaining storage and remaining off site database replicas (DB01, currently only one clustered off site to CAM-MBX01) Setup Edge Transport Server in Cambridge Site (CAM-S-ET02) Tested Forefront Started Testing Failover Tested Load Balancer Progressed re-skinning OWA (with Adrian Brett’s input) Created SCCM deployment package Commenced client testing using the SCCM package Presented paper to CMT and obtained agreement to the rollout/training plan Issued email to Faculty/Service contacts seeking nominations for Co-ordinator and Super-Users Agreed communications for the Bulletin Conducted dummy training session with Ixion and ascertained that they are effective trainers. Drafted POR in readiness for signature for 20 days training from Ixion D:\612937345.doc Page 1 of 4 Version 2: January 2008 FORM v2.1 – PSR Obtained hardware for OCS deployment to early adopters Purchased Sophos Pure Message contract extension Set up dates on 12/13 May for training ISMS CST in readiness for pilot commencement Started to receive nominations for Super-Users and have made provision for them to attend a session in Chelmsford on the afternoon of the 12th Started proof of concept using a few Outlook 2010 clients rolled out to Sarah Gyles, Alec Coleman, Jennie Wood, Michael Viner and Andy Parr (N.B these are still using the Exchange 2003 backend rather than the Exchange 2010 environment) Updated risk log, budget, project plan. Tested MS Academy Outlook CBT training Outlook for next period Resolve issues with Networker backups – EMS have released an update (Rob) Rob to make NLB even more resilient. A script to be produced which will make NLB more service–aware. Install Evault extensions ready to include in OWA 2010 Salford are on site 11, 12, 13th May. Test Failover using Ian’s test plan and document results (Ian, Nigel, Rob) Test Load Balancer using Ian’s test plan and document results (Rob) Identify any issues with the tier status of the email system and flag up to Gregor e.g. do we need more SAN space to provide for time-lagged backups? Complete proof of concept using a few Outlook 2010 clients Produce Change Request for migration of ISMS mailboxes subject to testing Complete re-skinning OWA (Needs Adrian Brett’s input) Obtain all Faculty/Service nominations for Co-ordinator and Super Users Sign order for 20 days training with Ixion Hold training for ISMS CST on 12/13 May in readiness for pilot commencement Michael and Andy to publicise training availability to the rest of ISMS – drop in workshops probably Obtain documentation and quick reference cards from Ixion Determine CBT approach – MS Academy or MS free interactive software Produce and issue communications for the pilot (Gregor/Jenny/Michael/Alec) Ensure that an approach is agreed for OCS training by handing over from Brendan to Ixion on 12/13 May Agree training approach with Super Users and wave roll out plan (Alec/Jenny/Faculties/Services) Approve change request for Pilot Migrate ISMS mailboxes Commence pilot in ISMS Produce Questionnaire for ISMS pilotees. Changes to STUNA - (Chris/Ian) Block book Helmore 355 and Queens 207 and ensure these are set up with the appropriate software and hardware for OCS. Ascertain approach for visually impaired member of staff who uses Jaws software. Project Board meeting The following is a selection of key risks only. A full list of Risks Services/ISMS/Projects_Office/Projects/IS-0192 Exchange 2010 Upgrade/Risk Log. Key Risks is available on the J: Drive at: Potential Extent of Impact (H, M, L) Likelihood of Occurrence (H, M, L) Progress / Support Required any M M Plan the pilot (and later the rollout) very carefully so as to avoid such issues. Update at Project Team 4/5/11. Agreed that the risk is static whilst we undergo testing in readiness for the pilot. Impairment of our DR position during transitions / migrations M M Plan the pilot (and later the rollout) very carefully so as to avoid such issues. Interruption to in / out flow of email during transition. M H Design a means of trialing new provision first and building confidence and knowledge transfer to Ops. Update at Project Team 4/5/11. Agreed that the risk remain as static we are still testing. Disruption to service transitions / migrations. during D:\612937345.doc Page 2 of 4 Version 2.1: October 2009 FORM v2.1 – PSR An extensive training plan will need to be drawn up which, based on past experience will take up the majority of an administrators time for at least 3 months. M H CMT/Executive Board have agreed training approach using Super-Users. Nominations are starting to come in so that we can commence training. Rooms are being booked, order is ready to go to Ixion. Rollout following user training needs to be closely managed and failure to achieve proper co-ordination will impact staff perception M M Planning between training organiser and Ops during rollout. Update at Project Team 4/5/11. Comms has begun with the paper to CMT and email to Faculties and Services. M M Testing of Outlook 2010 against current versions available. Produced test plan carry out tests. Priority (H, M, L) Progress / Support Required Incompatibility between the different versions of Office that will reside on the desktop: Key Project Issues Change Requests Status Priority (H ,M ,L) Progress / Support Required 2010-0237 – Extend AD Schema for Exchange 2010 Approved M Implemented 10 Jan 2011 2010-0244 – Deploy new EV Client Approved H Implemented 17 Jan 2011 2010-0226 – Deploy XP SP3 to all PCs Approved H Implemented in ISMS Dec 2010 rollout to faculties Jan-Mar 2011 2011 - Upgrade Evault Server Approved H Implemented 24 Jan 2011 Routing email via the new environment to avoid Sophos renewal Approved H Approval received but it was subsequently agreed to extend the Sophos Pure Message instead. None in April VARIANCE RAG REASON Budget Variance Green Magic is showing a spend of £51,370 as at 27 April 2011 and we have a total committed spend of £63,000 including the training that can now be ordered from Ixion. The budget was increased from £60K to £72K so we are within budget. Schedule Variance (time) Resource Variance Amber We have fallen behind with the infrastructure testing and build due to a combination of technical issues and operational activity taking precedent. Also, Easter holidays have compounded the delays with the infrastructure. Also, the delay in the issue of communications seeking Super-Users has had a corresponding delay in planning the training. The Risk level is Amber. Amber Resources have been requested and approved for May. Ian and Rob were out for much of April and there were several Bank Holidays so this has limited how much can be achieved. Quality Variance Green Green Stakeholder Issue Green No scope changes. Testing has identified that certain mailboxes may not migrate successfully if they are corrupted. CMT has agreed the paper submitted to them by Gregor/Tony. Service Directors and Business Managers have been emailed seeking nominations for Super-Users. Input has been provided to a draft Bulletin article. Scope Variance D:\612937345.doc Page 3 of 4 Version 2.1: October 2009 FORM v2.1 Risk Level Amber – PSR We have fallen behind with the infrastructure testing and build due to a combination of technical issues and operational activity taking precedent. Also, Easter holidays have compounded the delays with the infrastructure. Also, the delay in the issue of communications seeking Super-Users has had a corresponding delay in planning the training. The Risk level is Amber. One of the drivers for early migration to Exchange 2010 has been removed in that the Board has agreed to extend the contract for Sophos Pure Message. D:\612937345.doc Page 4 of 4 Version 2.1: October 2009