Turnberry Tower Arlington Luxury Condominium Lawrence P. Warner Jr. Construction Management Arlington, Virginia Location 1881 Rosslyn Associates c/o Turnberry Associates Owner Facchina Construction General Contractor BBG-BBGM Architects & Interiors Architect Monday, April 13th, 2009 Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Construction Management Presentation Outline Project Introduction Analysis 1 Window Wall Attachment with Reinforced Concrete Analysis 2 Supply Water System Analysis 3 Site Logistics Plan for Drywall Deliveries Summary & Conclusions Acknowledgments Questions? Monday, April 13th, 2009 Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Construction Management Location: Rosslyn, Arlington County, VA Presentation Outline Project Size: Project Introduction 6 Stories Below Grade 26 Stories Above Grade 750,000 SF Analysis 1 Window Wall Attachment with Reinforced Concrete Project Cost: Analysis 2 Supply Water System Construction Schedule: Analysis 3 Site Logistics Plan for Drywall Deliveries Owner: $250 Million September 2006– September 2009 1881 Rosslyn Associates c/o Turnberry Associates Summary & Conclusions Architect: Acknowledgments BBG-BBGM Architecture & Interiors Questions? General Contractor: Aerial View of Arlington, VA Facchina Construction (Formerly Facchina-McGaughan, LLC.) Monday, April 13th, 2009 Function: Delivery Method: LEED Desired: Luxury Condominiums Design-Bid-Build LEED Certified Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Quick Facts Construction Management Presentation Outline • Building is being constructed in two parts: • Underground Paring Garage (6 Levels) • Tower Levels (25 Levels) – No 13 Floor Project Introduction • Tower structure made up of post-tension concrete Analysis 1 Window Wall Attachment with Reinforced Concrete • Each unit will have floor to ceiling glass and varying ceiling heights between 9’ and 12’ Analysis 2 Supply Water System Curtain Wall • Glass in each unit will be either: • Window Wall (located behind the balconies) • Curtain Wall (corners of the building) Analysis 3 Site Logistics Plan for Drywall Deliveries • Building has 11 elevators with 2 miles of rail • Private Elevators for some units Summary & Conclusions Acknowledgments Questions? Window Wall Monday, April 13th, 2009 Exterior View of Turnberry Tower Arlington Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Construction Management Window Wall Attachment with Reinforced Concrete Problem: Presentation Outline • When the General Contractor was hired there was NO subcontractor for the exterior skin of the building Project Introduction • No design on how to connect the curtain wall and window wall to the post tension slabs Analysis 1 Window Wall Attachment with Reinforced Concrete • Submittals were submitted late and were rejected numerous times for the window wall • The window wall needed to be installed into the cured post tension decks • As a result of hitting post tension tendons: Analysis 2 Supply Water System Goal: Analysis 3 Site Logistics Plan for Drywall Deliveries • Find out why post tension concrete was used • Act as the GC during preconstruction and suggest using reinforced concrete slabs Summary & Conclusions • Accelerate the schedule Acknowledgments • Reduce the costs (no remediation needed) Questions? Monday, April 13th, 2009 Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Why Use Post Tension Concrete? Construction Management Many details like supports for the window wall were not designed….so WHY Post Tension Concrete? Presentation Outline Project Introduction Federal Aviation Administration: Analysis 1 Window Wall Attachment with Reinforced Concrete • Has final decision on height due to proximity to Reagan National Airport • Only 4.8 Miles from site to airport Analysis 2 Supply Water System Why PT Concrete? Analysis 3 Site Logistics Plan for Drywall Deliveries • Building is currently at +409.70 (within 1/8” of the FAA allowance) Summary & Conclusions • Larger floor to floor heights allows for the desired ceiling heights in the units by the owner 4.8 Miles Acknowledgments • Allows for an extra floor to be squeezed into the building from the thinner slabs Questions? • Extra money from sales of the units $17.6 Million Monday, April 13th, 2009 Map of Arlington, VA Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Direct Design Method Construction Management Presentation Outline (Structural Breadth) Used to find thickness of concrete slab and amount of steel needed to create a reinforced concrete slab Assumptions for Design Project Introduction FRAME A • 20” x 20” columns Analysis 1 Window Wall Attachment with Reinforced Concrete • Per ASCE 7-05 Table 4.1, Live Load = 40 psf • Dead Load (Concrete Self Weight) = 137.5 psf • The slab would be #6 Rebar at 60 ksi Using ln/33 = 10.9” Column Strip Middle Strip FRAME B + Moment 92 ft-k 62 ft-k - Moment 214 ft-k 72 ft-k Column Strip Middle Strip + Moment 87 ft-k 58 ft-k Concrete Slab = 11” Thick Analysis 2 Supply Water System Amount of #6 Rebar per foot Analysis 3 Site Logistics Plan for Drywall Deliveries Summary & Conclusions Column Strip Middle Strip Acknowledgments Questions? Monday, April 13th, 2009 FRAME A + Moment - Moment (Bottom (Top Bars) Bars) 8 13 8 8 FRAME B + Moment - Moment (Bottom (Top Bars) Bars) 8 12 8 8 - Moment 201 ft-k 67 ft-k Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Construction Management Post Tension Concrete Schedule Presentation Outline Original Construction Schedule Project Introduction • Included 10-11 day duration for each slab to be completed • Concrete erection from 12/28/07 to 9/8/08 (including roof top machine rooms) • Each slab is broken into 3 sections Analysis 1 Window Wall Attachment with Reinforced Concrete • Concrete pour for each zone would occur during 1 day and would take 5 hours Analysis 2 Supply Water System Analysis 3 Site Logistics Plan for Drywall Deliveries Summary & Conclusions 1 Acknowledgments Questions? Monday, April 13th, 2009 2 3 Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Construction Management Reinforced Concrete Schedule Presentation Outline There will be 2 different options for reinforced concrete that will be explored due to How would converting to reinforced concrete affect the schedule? the FAA height restrictions: Project Introduction Option 1:forReinforced with adjusted story heights • Would take 12 days each slab to Concrete be completed • Concrete pour for each zone would occur during 1 day and would take 8 hours (additional 4”) • Able to use the same Peri Girder Truss Table formwork Analysis 1 Window Wall Attachment with Reinforced Concrete Option 2: Reinforced Concrete removing one story • Each slab is broken into 3 sections Analysis 2 Supply Water System Analysis 3 Site Logistics Plan for Drywall Deliveries Summary & Conclusions Acknowledgments Questions? Flying Forms Monday, April 13th, 2009 Post Tension Option1: Reinforced (Height Adj.) Option 2: Reinforced (One Story Removed) Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Cost Comparison Construction Management Construction Cost of Post Tension Concrete System Presentation Outline Description Structural Systems Cost Comparison for Turnberry Tower Arlington Structural System Project Introduction Analysis 1 Window Wall Attachment with Reinforced Concrete Analysis 2 Supply Water System Residential Units Total Structural Cost Cost per SF Post Tension Concrete 247 $20,658,837 $27.55 Reinforced Concrete – Option 1 (Adjusting Story Height) 247 $22,975,867 $30.63 Reinforced Concrete – Option 2 (Removing 1 Story) Analysis 3 Site Logistics Plan for Drywall Deliveries 235 $22,651,046 Average Costs Summary & Conclusions Concrete: $125 / cubic yard Rebar: $1000 / ton PT Cable: $1.15 / pound Acknowledgments Questions? (prices obtained from concrete subcontractor during 4th quarter of 2008) Monday, April 13th, 2009 $30.20 Cast In Place Concrete including placing and stripping formwork, placing rebar, placing concrete, and finishing concrete Qty Unit Material Labor Equipment Total Cost 37351 CY $273.65 $257.21 $22.23 $20,658,837 TOTAL $27.55 per SF Construction Cost of Reinforced Concrete System (Adjusting Story Height) Description Qty Unit Material Labor Equipment Total Cost Cast In Place Concrete including placing and stripping formwork, placing rebar, placing concrete, and finishing concrete 44072 CY $241.88 $257.21 $22.23 $22,975,867 TOTAL $30.63 per SF Construction Cost of Reinforced Concrete System (Removing One Floor) Description Cast In Place Concrete including placing and stripping formwork, placing rebar, placing concrete, and finishing concrete Qty Unit Material Labor Equipment Total Cost 43355 CY $243.01 $257.21 $22.23 $22,651,046 TOTAL $30.20 per SF Turnberry Tower Arlington Luxury Condominiums Concrete Schedule: Post Tension vs. Reinforced Lawrence P. Warner Jr. Schedule Comparison Construction Management IN THE END: Similarities Between Concrete Systems Schedules Presentation Outline • Same formwork system Post Tension Concrete Project Introduction • “Learning Curve” for workers with both systems Start: December 28th, 2007 End: September 8th, 2008 Possibly Delays in Post Tension Concrete System Schedule Analysis 1 Window Wall Attachment with Reinforced Concrete • Reinforced Ruptured post tension tendons Concrete Analysis 2 Supply Water System • Delays from inspectors Start: December 28th, 2007 End: September 2nd, 2008 – Option 1 (adjusting story height) th, 2008 – Option Possibly Delays Reinforced Concrete System Schedule End: Augustin18 2 (removing one story) Analysis 3 Site Logistics Plan for Drywall Deliveries • Pour days are longer so weather must cooperate Summary & Conclusions • Larger amount of rebar must be in place Option 1: Saves 4 Days Acknowledgments Option 2: Saves 16 Days Questions? Monday, April 13th, 2009 Post Tension Concrete Reinforced Concrete Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Conclusion & Recommendation Construction Management Presentation Outline Post Tension Concrete Project Introduction System Cost Schedule: Begin End Cost vs. PT Schedule vs. PT Analysis 1 Window Wall Attachment with Reinforced Concrete Analysis 2 Supply Water System Analysis 3 Site Logistics Plan for Drywall Deliveries Reinforced Concrete (Adjusting Story Height) Option 1 Reinforced Concrete (Removing One Story) Option 2 $23.0 M $22.6 M $40.2 12/28/2007 9/2/2008 12/28/2007 8/18/2008 $2.4 M $2.3 - 4 Days $19.5MM $2.0 - 16 Days $20.6 M $20.7 12/28/2007 9/8/2008 - System to Use: Post Tension Concrete • Most Cost Effective System (even with PT blowouts) Summary & Conclusions • Maximum amount of units to sell Acknowledgments • Desired Floor to Ceiling Height Questions? • Schedule is not impacted drastically • More time needs to be spent to join systems Monday, April 13th, 2009 Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Supply Water System Construction Management Problem: Presentation Outline Project Introduction • CPVC Pipe installation is very time consuming compared to other methods Analysis 1 Window Wall Attachment with Reinforced Concrete • CPVC Pipe connections require glue based products that emit Volatile Organic Compounds (VOC’s) Analysis 2 Supply Water System Goal: Analysis 3 Site Logistics Plan for Drywall Deliveries • Research alternative systems that could be used in the place of CPVC Pipe Summary & Conclusions • Look at an alternative system that could accelerate the installation process and reduce cost Acknowledgments Questions? • Examine the LEED impact the VOC’s given off by the glue for the CPVC Pipe have on the rating of the building Monday, April 13th, 2009 CPVC Piping Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Existing System Construction Management Presentation Outline Hybrid: CPVC with Copper Project Introduction • CPVC branches off of the copper and delivers water to each unit • Copper is used as risers through the building • Size varies between 1” and ½” Analysis 1 Window Wall Attachment with Reinforced Concrete • Pipe is connected using glue, which emits VOC’s • Hangs from of hangers that were embed into the slabs above Analysis 2 Supply Water System Analysis 3 Site Logistics Plan for Drywall Deliveries Summary & Conclusions Acknowledgments Questions? Monday, April 13th, 2009 CPVC piping in ceiling space Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Suggested System: Propress Construction Management (Mechanical Breadth) Propress System Presentation Outline • Uses copper pipes that are mechanically connected with Propress fittings Project Introduction • Much faster to install than glue for CPVC Pipe (more pipe installed per day) • Does not emit any VOC’s Analysis 1 Window Wall Attachment with Reinforced Concrete • No soldering required Analysis 2 Supply Water System Analysis 3 Site Logistics Plan for Drywall Deliveries Summary & Conclusions Acknowledgments Questions? Connecting Copper Pipe with Propress system Monday, April 13th, 2009 Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. CPVC Pipe vs. Propress System Construction Management Presentation Outline Comparing CPVC vs. Propress Supply Water Systems (Per Typical Unit) Project Introduction CPVC System Propress System (2006) Cost of Supply Arlington Total Water System to Units in Turnberry Tower Total Analysis 1 Window Wall Attachment with Reinforced Concrete Item Cost Per Pipe Unit Fittings Analysis 2 Supply Water System $8,424 Analysis 3 Site Logistics Plan for Drywall Deliveries Mat. CostCPVCHrs. SystemLabor Cost Total$856.48 Cost for $350.26 247 Units Total Cost 10Man Hours $649 $1,505 Total Hours 58 per Unit$3,844 for 247$4,194 Units $2,080,728 102 25,194 Item Mat. Cost System Hrs. (2006) Labor Cost Propress Cost Pipe Per Unit Fittings Total$956.42 Cost for $2,010.92 247 Units $9,072 $2,240,784 Summary & Conclusions 20,995 $2,261 Misc. Companents $56.90 0 $0 $57 Total $1,670 102 $6,754 $8,424 4,199 $2,667 ($160,056) Misc. Companents $54.57 0 $0 $55 Total $3,428 85 $5,644 $9,072 Note: Cost of copper in 2006 was $3.10 per pound Monday, April 13th, 2009 85 34 Acknowledgments Questions? 10 Hours$648 Total Hours $1,604 Man 41 per Unit$2,735for 247$4,746 Units Hanger Hanger Time Savings Using Propress System over CPVC System (Man Hours) Components $405.87 34 $2,261 $2,667 Components $405.87 Cost Savings Using Propress System over CPVC System ($) Total Cost Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. LEED Impact Construction Management Presentation Outline (Critical Industry Issue) Credit 4.1 – Indoor Air Quality (Low Emitting Materials: Adhesives & Sealants) • To qualify for this credit, must meet the following limits: Project Introduction Analysis 1 Window Wall Attachment with Reinforced Concrete • Adhesive Primer for Plastic 550 g/L • Contact Adhesive 80 g/L • Point was obtained for this project, so the limits WERE met • Only 1 point available for this credit Analysis 2 Supply Water System LEED 2009 Analysis 3 Site Logistics Plan for Drywall Deliveries • No changes in LEED 2009 to obtain point • Only 1 point available for this credit Summary & Conclusions Acknowledgments Future? Questions? • Future editions may have restriction of 0 VOC’s allowed • May have building points for meeting certain VOC levels Monday, April 13th, 2009 Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Construction Management Conclusion & Recommendation System to Use: CPVC System Presentation Outline • Savings in cost of at least $160,000 for the entire building • Has no LEED impact (products used fall within LEED limits) Project Introduction • Less copper on site means the reduced risk of theft Analysis 1 Window Wall Attachment with Reinforced Concrete What about today??? If the project were designed today, Propress System should be used! Analysis 2 Supply Water System • Price of copper is lower than it was in 2006 • If the units were designed today, they would cost $7518 which is less than CPVC Analysis 3 Site Logistics Plan for Drywall Deliveries Summary & Conclusions Cost of Supply Water System to Units in Turnberry Tower Arlington CPVC System Acknowledgments Propress System Cost Per Total Cost for 247 Man Hours per Total Hours for 247 Cost Per Total Cost for 247 Man Hours per Total Hours for 247 Unit Unit Units Unit Units Units Unit Units $8,424 $2,080,728 102 25,194 $7,518 $1,856,946 85 20,995 Time Savings Using Propress System over CPVC System (Man Hours) 4,199 Questions? Cost Savings Using Propress System over CPVC System ($) Monday, April 13th, 2009 $223,782 Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Site Logistics Plan for Drywall Deliveries Construction Management Problem: Presentation Outline • Delivery lane was either busy or in use by concrete deliveries Project Introduction • East side of the site was not being utilized Analysis 1 Window Wall Attachment with Reinforced Concrete • County Police Officers were threatening to issue stop work orders Analysis 2 Supply Water System Goal: • Modify the site utility plan to allow for deliveries on the east side of the site Analysis 3 Site Logistics Plan for Drywall Deliveries • Allow for drywall to be delivered during work hours to cut down on the overtime needing to be paid Summary & Conclusions Acknowledgments Questions? Exterior View From East Monday, April 13th, 2009 Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Existing Site Plan Construction Management Comments about site: Presentation Outline • Area around site is congested • Need constant communication with county to close roads and sidewalks Project Introduction • Covered walkway was installed to reduce the disturbance of pedestrian traffic around the site Analysis 1 Window Wall Attachment with Reinforced Concrete • West side of the site was modified to allow for the delivery lane Reasons this site plan was used: Analysis 2 Supply Water System • County was strict with not affecting vehicular traffic (especially during rush hour) • West side of the site was on the same level as the lobby level which could be used as storage Analysis 3 Site Logistics Plan for Drywall Deliveries Summary & Conclusions Acknowledgments Questions? N Monday, April 13th, 2009 Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Construction Management Referring to Arlington County about use of Fort Myer Dr. Presentation Outline Project Introduction Analysis 1 Window Wall Attachment with Reinforced Concrete Analysis 2 Supply Water System Analysis 3 Site Logistics Plan for Drywall Deliveries Summary & Conclusions Acknowledgments Aerial View of Arlington, VA Questions? • Fort Myer Drive is deemed a main access road • Must be clear for traffic flow during both morning and afternoon rush hour • County was more strict because of problems that occurred during excavation Monday, April 13th, 2009 Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Construction Management Modifying the Site Plan for Drywall Deliveries Presentation Outline Project Introduction Analysis 1 Window Wall Attachment with Reinforced Concrete Analysis 2 Supply Water System Analysis 3 Site Logistics Plan for Drywall Deliveries Summary & Conclusions 40’ Drywall Truck Acknowledgments Questions? Monday, April 13th, 2009 Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Construction Management Conclusion & Recommendation How would the 2nd Level be affected? Presentation Outline • 2nd Level will not be affected thanks to SIPS (Could be used as lay down area) • Level 7 is being erected with concrete with activity on the 2nd Level begins Project Introduction • Reshores are only required 3 levels below the working deck Analysis 1 Window Wall Attachment with Reinforced Concrete • Level 3 will be used as the mock up for MEP clashes How will the material hoist be affected? Analysis 2 Supply Water System • When tower crane is not being used, more use of outriggers Analysis 3 Site Logistics Plan for Drywall Deliveries Recommendation: Use the Modified Site Plan if Arlington County would approve Summary & Conclusions • Will allow for other deliveries to the site besides drywall Acknowledgments Questions? Monday, April 13th, 2009 Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Construction Management Summary & Conclusions Analysis 1 – Window Wall Attachment with Reinforced Concrete Presentation Outline Recommendation: Use designed Post Tension Slabs • Cheapest System (even with PT blowouts) Project Introduction • Maximum amount of units to sell Analysis 1 Window Wall Attachment with Reinforced Concrete • Desired Floor to Ceiling Height • Schedule is not impacted drastically Analysis 2 – Supply Water System Analysis 2 Supply Water System Recommendation: Use designed CPVC Pipe System Analysis 3 Site Logistics Plan for Drywall Deliveries • Savings in cost of at least $160,000 for the entire building Summary & Conclusions • Less copper on site means the reduced risk of theft Acknowledgments • If building was designed today, Propress system would be cheaper • Has no LEED impact (products used fall within LEED limits) Analysis 3 – Site Logistics Plan for Drywall Deliveries Questions? Recommendation: Use Modified Site Plan if permitted by Arlington County • This site plan can save money as seen by the examples Monday, April 13th, 2009 • Will allow for other deliveries to the site besides drywall Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Acknowledgments Construction Management Penn State Architectural Engineering Faculty Presentation Outline Dr. David Riley Professor Kevin Parfitt Professor Robert Holland Dr. Michael Horman Project Introduction Analysis 1 Window Wall Attachment with Reinforced Concrete Turnberry Limited Mark Babbitt Dave White Facchina Development Facchina Construction (Formerly Facchina-McGaughan, LLC.) Analysis 2 Supply Water System Analysis 3 Site Logistics Plan for Drywall Deliveries Summary & Conclusions Tony Cortés Derek Dickenson Richard Roberts G. R. Nicholas Holland Josue Leon Fellow AE students, especially J.J. Magnolia Plumbing Mom, Dad, and Joey Acknowledgments Questions? Bill Stewart Monday, April 13th, 2009 Robert Mitchell Nicole Lucas Kim McKitish Friends & Family Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Cost Comparison Construction Management Post Tension Concrete Presentation Outline Structural Systems Cost Comparison for Turnberry Tower Arlington Structural System Post Tension Concrete Reinforced Concrete (Removing 1 Story) Reinforced Concrete (Adjusting Story Height) Project Introduction Total Material Cost Analysis 1 Window Wall Attachment with Reinforced Concrete Item Concrete Reinforcing Steel Miscellaneous Items Analysis 2 Supply Water System TOTAL TOTAL PER CY Amount 37,351 CY 3071 Tons Total Cost $4,668,875 $3,071,000 $2,481,385 Residential Units 247 Total Structural Cost $20,658,837 Average Costs $10,221,260 $273.65 Concrete: $125 / cubic yard Rebar: $1000 / ton PT Cable: $1.15 / pound Analysis 3 Site Logistics Plan for Drywall Deliveries Construction Cost of Post Tension Concrete System Summary & Conclusions Description Cast In Place Concrete including placing and stripping formwork, placing rebar, placing concrete, and finishing concrete Acknowledgments Questions? Monday, April 13th, 2009 Qty Unit Material Labor Equipment Total Cost 37351 CY $273.65 $257.21 $22.23 $20,658,837 TOTAL $27.55 per SF (prices obtained from concrete subcontractor during 4th quarter of 2008) Cost per SF $27.55 Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Cost Comparison Construction Management Option 1: Reinforced Concrete Adjusting Story Height Presentation Outline Project Introduction Structural Systems Cost Comparison for Turnberry Tower Arlington Structural System Post Tension Concrete Reinforced Concrete (Adjusting Story Height) Reinforced Concrete (Removing 1 Story) Total Material Cost Item Concrete Reinforcing Steel Miscellaneous Items Analysis 1 Window Wall Attachment with Reinforced Concrete Amount 44072 CY 3983 Tons TOTAL TOTAL PER CY Analysis 2 Supply Water System Total Cost $5,508,994 $3,398,200 $1,753,108 Residential Units 247 247 Total Structural Cost $20,658,837 $22,975,867 $10,660,302 $241.88 Analysis 3 Site Logistics Plan for Drywall Deliveries Average Costs Construction Cost of Reinforced Concrete System (Adjusting Story Height) Summary & Conclusions Acknowledgments Questions? Monday, April 13th, 2009 Description Qty Unit Material Labor Equipment Total Cost Cast In Place Concrete including placing and stripping formwork, placing rebar, placing concrete, and finishing concrete 44072 CY $241.88 $257.21 $22.23 $22,975,867 Concrete: $125 / cubic yard Rebar: $1000 / ton PT Cable: $1.15 / pound (prices obtained from concrete subcontractor during 4th quarter of 2008) TOTAL $30.63 per SF Cost per SF $27.55 $30.63 Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Cost Comparison Construction Management Option 2: Reinforced Concrete Removing One Story Presentation Outline Structural Systems Cost Comparison for Turnberry Tower Arlington Structural System Post Tension Concrete Reinforced Concrete (Adjusting Story Height) Reinforced Concrete (Removing 1 Story) Project Introduction Total Material Cost Analysis 1 Window Wall Attachment with Reinforced Concrete Item Concrete Reinforcing Steel Miscellaneous Items Analysis 2 Supply Water System TOTAL TOTAL PER CY Amount 43355 CY 3363 Tons Total Cost $5,419,369 $3,363,200 $1,753,108 Residential Units 247 247 235 Total Structural Cost $20,658,837 $22,975,867 Cost per SF $27.55 $30.63 $22,651,046 $30.20 $10,535,677 $243.01 Analysis 3 Site Logistics Plan for Drywall Deliveries Average Costs Construction Cost of Reinforced Concrete System (Removing One Floor) Summary & Conclusions Description Acknowledgments Cast In Place Concrete including placing and stripping formwork, placing rebar, placing concrete, and finishing concrete Questions? Monday, April 13th, 2009 Qty Unit Material Labor Equipment Total Cost 43355 CY $243.01 $257.21 $22.23 $22,651,046 Concrete: $125 / cubic yard Rebar: $1000 / ton PT Cable: $1.15 / pound (prices obtained from concrete subcontractor during 4th quarter of 2008) TOTAL $30.20 per SF Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Comparing Site Plans Construction Management Example of how the Modified Site Plan would help Presentation Outline Existing Site Logistics Plan Project Introduction # of Boards Stocked During 40 Hour Week Analysis 1 Window Wall Attachment with Reinforced Concrete 400 Analysis 2 Supply Water System Cost for 4 Man Crew (Standard Wage) $22 per person per hour # of Boards Stocked During Overtime 600 Cost for 4 Man Crew (1.5 Standard Wage) $33 per person per hour Total Cost for 4 Man Crew for 1000 Boards: $5,632 Proposed Site Logistics Plan # of Boards Stocked During 40 Hour Week Analysis 3 Site Logistics Plan for Drywall Deliveries Summary & Conclusions 600 Cost for 4 Man Crew (Standard Wage) $22 per person per hour # of Boards Stocked During Overtime 400 Cost for 4 Man Crew (1.5 Standard Wage) $33 per person per hour Total Cost for 4 Man Crew for 1000 Boards: Acknowledgments Note: Turnberry Tower Arlington has 91,000 sheets of drywall Questions? Assuming that productivity increases by 20% during a 40 hour week: • $750 saved per 1000 boards Monday, April 13th, 2009 $4,880 Turnberry Tower Arlington Luxury Condominiums Lawrence P. Warner Jr. Comparing Site Plans Construction Management Example of how the Modified Site Plan would help Presentation Outline Existing Site Logistics Plan Project Introduction # of Boards Stocked During 40 Hour Week Analysis 1 Window Wall Attachment with Reinforced Concrete 400 Analysis 2 Supply Water System Cost for 4 Man Crew (Standard Wage) $22 per person per hour # of Boards Stocked During Overtime Cost for 4 Man Crew (1.5 Standard Wage) $33 per person per hour 600 Total Cost for 4 Man Crew for 1000 Boards: $5,632 Proposed Site Logistics Plan # of Boards Stocked During 40 Hour Week Analysis 3 Site Logistics Plan for Drywall Deliveries Summary & Conclusions 1000 Cost for 4 Man Crew (Standard Wage) $22 per person per hour # of Boards Stocked During Overtime Cost for 4 Man Crew (1.5 Standard Wage) 0 $33 per person per hour Total Cost for 4 Man Crew for 1000 Boards: Acknowledgments $3,520 Note: Turnberry Tower Arlington has 91,000 sheets of drywall Questions? Assuming that productivity increases and no overtime is needed in a 40 hour week: • $2000 saved per 1000 boards Monday, April 13th, 2009