Miller Children’s Hospital Pediatric Inpatient Addition Long Beach, CA

advertisement
Miller Children’s Hospital
Pediatric Inpatient Addition
Long Beach, CA
Presentation Outline
• Building Background
• Existing Systems Summary
• Electrical Breadth – PV Panels
• System Sizing
• Cost Estimate and Payback
• Design Objectives
• Electrical System Integration
• Mechanical Depth – CHP
• Summary and Recommendation
• CHP Screening Process
• Energy Analysis
• Central Plant Redesign
• Electrical System Integration
• Cost Breakdown and Emissions
• Summary and Recommendation
• Conclusions
Building Background
• General Building Information
Owner
• Miller Children’s Hospital
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth – CHP
• CHP Screening Process
• Energy Analysis
• Central Plant Redesign
• Electrical System Integration
• Cost Breakdown and Emissions
• Summary and Recommendation
Project Size
• Electrical Breadth – PV Panels
• 127,000 square feet
Building Background
• The Pediatric Inpatient Addition
• System Sizing
Total Cost
• Cost Estimate and Payback
• $151,000,000 (estimated)
- 4-Story Hospital Facility
Design-bid-build
- 7 Operating Rooms
Completion Date
- Neonatal Intensive Care Unit
• Fall 2009
- Utilizes Green Roof System
• Electrical System Integration
• Summary and Recommendation
• Conclusions
Existing Systems Summary
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth – CHP
• CHP Screening Process
• Energy Analysis
Mechanical System
• Electrical Breadth – PV Panels
• System Sizing
• Cost Estimate and Payback
• Electrical System Integration
• Summary and Recommendation
• Conclusions
Existing Systems Summary
Chilled Water Flow Diagram
• 7 Air Handling Units (located on roof)
• Constant Volume with Space Reheat
• HEPA Filters Used for Operating Rooms
• (2) 500 ton Centrifugal Water Cooled Chillers
• (2) Induced Draft Cooling Towers
• (2) 2,000 MBh Gas-Fired Hot Water Boilers
• Central Plant Redesign
• Electrical System Integration
• Cost Breakdown and Emissions
• Summary and Recommendation
Hot Water
Flow Diagram
Condenser Water
Flow Diagram
Existing Systems Summary
Existing Systems Summary
Electrical System Single Line Diagram
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth – CHP
• CHP Screening Process
Electrical System
• Electrical Breadth – PV Panels
• System Sizing
• Cost Estimate and Payback
• Electrical System Integration
• Summary and Recommendation
• Conclusions
• Electric Utility – Southern California Edison
• 480Y/277V 3-phase 4-wire secondary
• (2) 750 kW emergency generators
• 10,000 kW redundant transformer
- Miller Children’s Hospital
• Energy Analysis
- Does not serve loads
• Central Plant Redesign
- For future use and owner preference
• Electrical System Integration
• Cost Breakdown and Emissions
• Summary and Recommendation
Design Objectives
Design Objectives
Energy Consumption
• Electricity - 5,900,000 kWh/year
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth – CHP
• CHP Screening Process
Main Objectives
• Electrical Breadth – PV Panels
• System Sizing
• Cost Estimate and Payback
• Electrical System Integration
• Reduce energy consumption
• Save money in operational costs
• Cut back on emissions
• Gas - 38,000 therms/year
Operational Costs
• Electricity - $1,100,000/year
• Gas - $30,000/year
• Summary and Recommendation
• Conclusions
Emissions (Utility Generated)
• Energy Analysis
• NOX – 6,000 lbs/year
• Central Plant Redesign
• SOX – 5,000 lbs/year
• Electrical System Integration
• CO2 – 3,800 lbs/year
• Cost Breakdown and Emissions
• Summary and Recommendation
Annual Energy Consumption
Mechanical Depth
Combined Heat & Power
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth – CHP
• CHP Screening Process
• Energy Analysis
• Central Plant Redesign
• Electrical System Integration
• Cost Breakdown and Emissions
• Summary and Recommendation
CHP Screening Process
• Electrical Breadth – PV Panels
• System Sizing
• Cost Estimate and Payback
Energy Costs and Consumption
• Spark Spread
-The difference between electricity and
• Electrical System Integration
gas rates in $/MMBtu
• Summary and Recommendation
- Higher spread favors CHP
• Conclusions
Mechanical Depth
Combined Heat & Power
• Cost of electricity ( > $0.05/kWh)
• Cost of gas( < $4.00/MMBtu)
General Factors Affecting CHP
Mechanical Depth
Combined Heat & Power
Mechanical Depth
Combined Heat & Power
Electric Load Profiles
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth – CHP
• CHP Screening Process
• Energy Analysis
• Central Plant Redesign
• Electrical System Integration
Energy Analysis
• Electrical Breadth – PV Panels
• System Sizing
• Cost Estimate and Payback
• Electrical System Integration
• Summary and Recommendation
• Conclusions
• Peak Electric Load
- September 6 at 5:00 pm
- 900 kW
• Peak Heating Load
- January 1 at 7:00 am (TOA = 40°F)
-1,700 MBh
• Peak Cooling Load
• Cost Breakdown and Emissions
- September 6 at 5:00 pm (TOA = 91°F)
• Summary and Recommendation
- 225 tons
Mechanical Depth
Combined Heat & Power
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth – CHP
• CHP Screening Process
• Energy Analysis
• Central Plant Redesign
• Electrical System Integration
• Cost Breakdown and Emissions
• Summary and Recommendation
Energy Analysis
• Electrical Breadth – PV Panels
• System Sizing
• Cost Estimate and Payback
• Electrical System Integration
• Summary and Recommendation
• Conclusions
• Peak Electric Load – 900 kW
- 15% over-sizing
- 1,035 kW generator required
• Use reciprocating engine
- Little heating needed
• Cannot use absorption cooling
- Generator size too small
• Generator Operation Condition
- Demand output
Mechanical Depth
Combined Heat & Power
Caterpillar Reciprocating Engine
Mechanical Depth
Combined Heat & Power
Mechanical Depth
Combined Heat & Power
CHP System Schematic and Annual Energy Use
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth - CHP
• CHP Screening Process
• Energy Analysis
• Central Plant Redesign
• Electrical System Integration
• Cost Breakdown and Emissions
• Summary and Recommendation
Energy Analysis
• Electrical Breadth – PV Panels
• System Sizing
• Cost Estimate and Payback
• Electrical System Integration
• Summary and Recommendation
• Conclusions
• Recovered Heat Energy
• System Schematic
Mechanical Depth
Combined Heat & Power
Mechanical Depth
Combined Heat & Power
Existing Central Plant
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth – CHP
• CHP Screening Process
Central Plant Redesign
• Electrical Breadth – PV Panels
• System Sizing
• Cost Estimate and Payback
• Electrical System Integration
• Summary and Recommendation
• Conclusions
• Located north of the Pediatric Inpatient
Addition
• Comprised of:
- Pump Room
- Chiller Room
• Energy Analysis
- Electrical Switchgear
• Central Plant Redesign
- Emergency Generator Room
• Electrical System Integration
-Transformer Yard
• Cost Breakdown and Emissions
• Summary and Recommendation
CHP Plant Redesign
• New Generator Room – 1,180 sq. ft.
Central Plant Area = 4,700 sq. ft.
New Central Plant Area = 5,880 sq. ft.
25% Increase
Mechanical Depth
Combined Heat & Power
Mechanical Depth
Combined Heat & Power
Existing Central Plant
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth – CHP
• CHP Screening Process
• Energy Analysis
• Central Plant Redesign
• Electrical System Integration
• Cost Breakdown and Emissions
• Summary and Recommendation
Electrical System Integration
• Electrical Breadth – PV Panels
• System Sizing
• Cost Estimate and Payback
• Electrical System Integration
• Summary and Recommendation
• Conclusions
• Generator replaces redundant
transformer
• Key Switch
• Fire pump moved
• Emergency generators not required by
code
Mechanical Depth
Combined Heat & Power
CHP Cost Data
Mechanical Depth
Combined Heat & Power
CHP Annual Operational Data
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth – CHP
• CHP Screening Process
Cost Breakdown and Emissions
• Electrical Breadth – PV Panels
• System Sizing
• Estimated Cost: $1,600,000
• Annual Building Operational Cost
• Cost Estimate and Payback
• Electrical System Integration
• Summary and Recommendation
• Conclusions
Savings: $340,000/year
• Less maintenance costs for the system
• Estimated Payback: Less than 5 years
• Energy Analysis
• Central Plant Redesign
• Electrical System Integration
• Cost Breakdown and Emissions
• Summary and Recommendation
• EPA Combined Heat and Power Partnership:
Catalogue of CHP Technologies
• R.S. Means: Cost Works
Mechanical Depth
Combined Heat & Power
Mechanical Depth
Combined Heat & Power
Emissions Data
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth – CHP
• CHP Screening Process
• Energy Analysis
Cost Breakdown and Emissions
• Electrical Breadth – PV Panels
• System Sizing
• Decrease in SOX and CO2 emissions
• Increase in NOX emissions
• Cost Estimate and Payback
- Generator less efficient at part-load
• Electrical System Integration
- Higher emissions per unit of energy generated
• Summary and Recommendation
- Utility generator operates at higher efficiency
• Conclusions
Cat Selective Catalytic
Reduction Systems
- California guidelines in place for utility emissions
• Reduces CO by 93%
• Reduces hydrocarbons by more than 40%
• Catalytic Reduction Systems
• Central Plant Redesign
- Treats exhaust gas after it leaves the engine
• Electrical System Integration
- Uses toxic reagents such as ammonia
• Cost Breakdown and Emissions
- Potential health risks with venting and on-site
• Summary and Recommendation
Cat Oxidation Catalysts
storage
• Reduces CO by 93%
• Reduces NOX by up to 90%
Mechanical Depth
Combined Heat & Power
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth – CHP
• CHP Screening Process
• Energy Analysis
• Central Plant Redesign
Summary and Recommendation
• Electrical Breadth – PV Panels
• Total System Cost: $1,850,000
• System Sizing
- Includes Catalytic Reduction System
• Cost Estimate and Payback
- 1.5% increase in overall project cost
• Electrical System Integration
• Total Annual Savings: $320,000/year
• Summary and Recommendation
• Conclusions
System Cost
Annual Savings
CHP Equipment Costs: $1,100,000
CHP Operation Savings: $410,000/year
Central Plant Expansion: $500,000
Maintenance Costs: $90,000/year
Catalytic Reduction System: $250,000
Total Annual Savings: $320,000/year
Total CHP System Cost: $1,850,000
Important Notes
Maintenance Costs
• Efficient CHP systems utilize ALL
- Includes maintenance costs for CRS
CHP Maintenance Costs: $65,000/year
recovered heat
- 30% reduction in operational costs
CRS Maintenance: $25,000/year
• Size of building electric demand plays a
Total Maintenance Cost: $90,000/year
big role ( > 2 Megawatts)
• Payback Period: Less than 6 years
• Electrical System Integration
• Reduced Emissions with CRS
• Cost Breakdown and Emissions
• Recommendation: Install CHP System
• Summary and Recommendation
Mechanical Depth
Combined Heat & Power
• Utility rates very important factor
Electrical Breadth
Photovoltaic Panels
Electrical Breadth
Photovoltaic Panels
Areas
• Pediatric Inpatient Addition
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth – CHP
• CHP Screening Process
• Energy Analysis
System Sizing
• Electrical Breadth – PV Panels
• Photovoltaic array located on roof
• System Sizing
- Pediatric Inpatient Addition upper roof
• Cost Estimate and Payback
- Pediatric Inpatient Addition lower roof
• Electrical System Integration
- Miller Children’s Hospital roof
• Summary and Recommendation
• Conclusions
• Total panel coverage: 12,310 sq. ft.
• BP Solar panel selected
• Central Plant Redesign
- Model BP 175B
• Electrical System Integration
- Rated power: 175W
• Cost Breakdown and Emissions
- 14% Nominal Efficiency
• Summary and Recommendation
• 900 PV panels used
- Upper roof: 7,700 sq. ft.
- Lower roof: 3,240 sq. ft.
• Miller Children’s Hospital: 11,060 sq. ft.
• Assumed Coverage
- PIA: 80%
- MCH: 60% (rooftop equipment)
• Assumed 80% Usable PV Area
• Total Panel Coverage: 12,310 sq. ft.
• Individual Panel Area: 13.56 sq. ft.
• 900 Panels Calculated
PV Panel Coverage
Electrical Breadth
Photovoltaic Panels
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth – CHP
• CHP Screening Process
• Energy Analysis
Electrical Breadth
Photovoltaic Panels
Incentives Package
System Cost
Incentive): $478,980
• Development & Engineering Fees: $70,000
• Federal Investment (10%) Tax Credit: $197,582
• PV Modules: $945,000
• State Solar Energy (7.5%) Tax Credit: $148,187
• Module Support Structure: $123,100
• Federal Accelerated Depreciation (34% tax rate):
• Renewable energy delivered:
• Inverter: $100,800
$328,770
• System Installation: $236,000
• State Depreciation Savings (8% tax rate): $38,679
245,000 kWh/year
• Total Cost: $1,482,250
• Total Package: $1,192,200
Cost Estimate and Payback
• Electrical Breadth – PV Panels
• System Sizing
• Cost Estimate and Payback
• Electrical System Integration
• Maximum capacity: 140 kW AC
• Summary and Recommendation
• Electricity savings: $46,000/year
• Conclusions
• System cost: $1,482,250
• Central Plant Redesign
• Incentives package: $1,192,200
• Electrical System Integration
• Payback Period: 7 years
• Cost Breakdown and Emissions
• Summary and Recommendation
• California State Rebate (Performance Based
Net PV System Cost by Year
Electrical Breadth
Photovoltaic Panels
Electrical Breadth
Photovoltaic Panels
Commercial PV Inverter Diagram
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth – CHP
• CHP Screening Process
• Energy Analysis
• Central Plant Redesign
• Electrical System Integration
• Cost Breakdown and Emissions
• Summary and Recommendation
Electrical System Integration
• Electrical Breadth – PV Panels
• PV Inverter
• System Sizing
- Converts DC current into AC current
• Cost Estimate and Payback
-Solectria PVI Gridtie Inverters
• Electrical System Integration
- Miller Children’s Hospital: 60 kW
• Summary and Recommendation
• Conclusions
- Pediatric Inpatient Addition: 82 kW
Electrical Breadth
Photovoltaic Panels
Electrical Breadth
Photovoltaic Panels
PV Electrical System Single Line Diagram
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth – CHP
• CHP Screening Process
• Energy Analysis
• Central Plant Redesign
• Electrical System Integration
• Cost Breakdown and Emissions
• Summary and Recommendation
Electrical System Integration
• Electrical Breadth – PV Panels
• Electrical System
• System Sizing
- Spare breaker on main distribution panel (#4)
• Cost Estimate and Payback
- New breaker size: 200A
• Electrical System Integration
- Inverters connected through single feeder
• Summary and Recommendation
• Conclusions
- Feeder size: (4) 3/0 + (1) #6 ground
- Conduit size: 2”
- Distance to main distribution panel: 240 ft
- % Voltage drop: 1.56% < 2%
- System sized using NEC 2005
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth – CHP
• CHP Screening Process
• Energy Analysis
• Electrical Breadth – PV Panels
Electrical Breadth
Photovoltaic Panels
Electrical Breadth
Photovoltaic Panels
Summary and Recommendation
Summary and Recommendation
• $46,000 annual savings
• Non-renewable energy savings
• Cost Estimate and Payback
• Payback period of 7 years
• Greenhouse gas reductions
• Electrical System Integration
• Not possible without incentives package
• Recommendation: Install PV System
• System Sizing
• Summary and Recommendation
• Conclusions
- Costs more than to purchase from utility
• Risky decision
• Central Plant Redesign
- Available money fluctuates
• Electrical System Integration
- Could be cut off if funds run out
• Cost Breakdown and Emissions
• Summary and Recommendation
Conclusions
Presentation Outline
• Building Background
• Existing Systems Summary
• Design Objectives
• Mechanical Depth – CHP
• CHP Screening Process
Design Goals
• Electrical Breadth – PV Panels
• System Sizing
• Reduce energy consumption
• Cost Estimate and Payback
• Save money on operational costs
• Electrical System Integration
• Summary and Recommendation
• Cut back on emissions
• Conclusions
• Energy Analysis
Can be achieved with energy efficient
• Central Plant Redesign
mechanical systems and renewable
• Electrical System Integration
• Cost Breakdown and Emissions
• Summary and Recommendation
energy sources
Miller Children’s Hospital
Pediatric Inpatient Addition
Long Beach, CA
Special Thanks to:
Dr. James Freihaut – AE Department
Rick Savely – Taylor Architects
Becky Haines – JBA Consulting Engineers
Questions?
Marc Haines – JBA Consulting Engineers
Ed Butera – JBA Consulting Engineers
David Maino – Integrated Design Studios, Inc
The JBA Costa Mesa office staff
Kerry Hickman – Cashman Equipment
Also, a special thanks to my parents for
all their support over the years
Download