MASSACHUSETTS INSTITUTE OF TECHNOLOGY HAYSTACK OBSERVATORY WESTFORD, MASSACHUSETTS 01886 Telephone: Fax: 978-692-4764 781-981-0590 10 August 2002 TO: Distribution FROM: Alan R. Whitney SUBJECT: 9 August 2002 e-VLBI telecon summary Attendees: Lee Foster, Bill Fink, Pat Gary, Paul Lang – GSFC Steve Bernstein, Lorraine Prior, Peter Schultz – Lincoln Laboratory Tom Lehman – ISI-E Richard Crowley, Hans Hinteregger, Arthur Niell, Mike Titus, Alan Whitney – Haystack Observatory This telecon is one of an ongoing series of telecons to prepare for gigabit/sec e-VLBI demonstrations between NASA GSFC and MIT Haystack Observatory using a combination of network facilities including all or part of Glownet, Bossnet, ISI-E, SuperNet, Max and GSFC/HECN. ACTION ITEMS ARE HIGHLIGHTED IN RED. Status Reports The attached figures of the e-VLBI path have been updated to reflect current status and are pretty much self-explanatory; critical status items are indicated in red. In addition, the following comments are relevant: − Peter reported that Bossnet will be down 1-2 hours on 21 August as LL tries to isolate the problem causing the OC-48 link to work improperly. Peter will notify everyone of exact down times when that is known. The Bossnet problem appears to be somewhere in the path between New York and Newark. − Tom has received some 10 Gbps equipment (Nortel Passport 8500 with beta software) that he would like to try on Bossnet over the next month or so. He will send equipment to LL. This equipment was purchased by DARPA; Tom does not know cost, but will look into it. Since no one yet has a 10Gbps source, testing will take place using multiple simultaneous GigE streams up to at least 4-5 Gbps. − Lee reported he has found information on the web about a 10 Gbps host; Lee will distribute reference via e-mail. − Bill reported that the asymmetric performance results observed by Kevin some weeks ago were due to an MTU mismatch between the ISI-E Juniper M40 (G10), which was set at 4448, and the MAX Juniper M160 (H3), which was set at 4470. Kevin had noted that the minutes16.doc 8/10/2002 1 asymmetry disappeared when he set the MTU size down to 4448 and things worked well. − Bill reported that Abilene is planning to go to 9K MTU size, so we should plan to upgrade to 9K as well if possible. − Bill reported that, prior to the near-Gbps performance tests that Kevin did on 18 July, he had discovered a high number of retries on link H6 in the direction from UMCP to ISI-E which limited aggregate throughput to ~150 Mbps. Reseating connections on UMCP equipment raised speed to ~700Mbps, but not to ~950Mbps expected. Temporary fix was to re-route UMCP-to-ISI traffic the other (long) way around the MAX ring; a subsequent sustained 2-hr test by Bill showed 931Mbps UMCP-to-LL and 906Mbps in reverse direction (MTU=4448). Kevin’s tests on 18 July were carried out with this asymmetric configuration. The reason for the problem in the direct link from UMCP to ISI-E is not clear and needs further investigation; Bill, Tom, Jerry and Dan will pursue this. − Pat reported nuttcp package has now been ported to Windows. Lee’s testing showed 860880Mbps from ‘xly’ (K6A) to Pluto (L6). − Pat suggested that we plan to convene a face-to-face ‘team’ meeting of e-VLBIL project team, perhaps next spring, in advance in the international e-VLBI meeting to be held in The Netherlands in spring 2003. All agreed this is a good idea, and would be an opportunity for planning and organizing future e-VLBI activities. Alan will pick up the ball on this and begin to get organized; Haystack will be happy to host such a meeting, but some people waxed less than enthusiastic for Boston in January or February; we will keep this in mind! − Alan reported that Haystack, in collaboration with MIT LL and MIT Lab for Computer Science, has been awarded an NSF grant under the Strategic Technology for Internet (STI) program to develop an IP protocol specifically designed for e-VLBI and similar applications. This project will attempt to make best use of unused (‘scavenged’) bandwidth in a ‘background’ mode which does not interfere with higher priority ‘foreground’ usesr. The project is funded for 3 years and includes demonstrations of high-speed e-VLBI connections both with the U.S. and to Europe and Japan. Alan will distribute the text of the proposal to the group. Pat expressed a strong interest in trying to obtain GSFC support to evolve GSFC capabilities in parallel with the activities under the NSF grant. − Alan reported that Haystack and Bill Wildes are working to organize e-VLB connections from Kokee Park in Hawaii to Haystack and from Univ. of Regensburg in Germany to Haystack, both probably at OC-3. Excellent cooperation is being received from PMRF (Pacific Missile Range Facility) people on Kauai and from the Germans in working to establish these links. The goal is have demonstrate both of these with the next couple of months. Haystack will contact Steve Corbato (corbato@internet2.edu), director of Abilene, to coordinate the use of peered connection to Abilene at ISI-E. − Alan will give a short presentation on U.S. e-VLBI activities at the URSI meeting in The Netherlands later this month and a longer presentation in November in Korea. He will prepare some slides to share with everyone. − Haystack is planning to spruce up the e-VLBI web page at the Haystack web site in the near future. Some recent work has been done on the Mark 5 web page and it is looking a lot better (http://web.haystack.mit.edu/mark5/Mark5.htm). minutes16.doc 8/10/2002 2 − Lee suggested everyone should take at look at the 10GigE Alliance web site (http://www.10gea.org/) for up-to-date information on 10GigE stuff. − Alan reported that Haystack is planning to send two Mark 5 systems down to GGAO by ~16 Aug. The plan is to use two Mark 5 systems in parallel at both the Westford and GGAO antennas to achieve a near-Gbps aggregrate data rate. An additional copper GigE port is available on the switch (L2) at GGAO for the second Mark 5 (first Mark 5 will be also be copper). It appears that an additional SX port is available at Westford (first Mark 5 will also be SX). Lorraine and Kevin will check and Haystack will procure necessary NIC cards. Control of the Mark 5’s will be on a different network with minimal traffic; a VLAN might be set up for this purpose. Performance Testing Kevin did a 10-hour performance test on 18 July that showed an average of ~960Mbps GGAO-toHaystack and ~900Mbps Haystack-to-GGAO (see attached Figure). Kevin will document these results in a formal memo. As reported above, a sustained 2-hr test by Bill (immediately followed Kevin’s 18 July test) showed 931Mbps UMCP-to-LL and 906Mbps in reverse direction (MTU=4448). Tom reported he had done some performance testing between ISI-E and LL and found numbers similar to what Kevin and Bill reported in tests between Haystack and GGAO. As reported above, Lee’s testing showed 860-880Mbps from ‘xly’ (K6A, a Windows machine) to Pluto (L6). Next telecon Next telecon will be Mon, 26 Aug 2002 at 2 pm. xc: Steve Bernstein, LL Jim Calvin, LL Lorraine Prior, LL Leslie Weiner, LL Herbert Durbeck, GSFC Lee Foster, GSFC Pat Gary, GSFC Chuck Kodak, GSFC Kevin Kranacs, GSFC Paul Lang, GSFC Aruna Muppalla, GSFC Bill Wildes, GSFC Dan Magorian, UMCP Tom Lehman, ISI Jerry Sobieski, Max Richard Crowley, Haystack Kevin Dudevoir, Haystack Hans Hinteregger, Haystack Arthur Niell, Haystack Joe Salah, Haystack minutes16.doc 8/10/2002 3 Westford Antenna Millstone RPE Bldg (Lorraine) Mark 5 A1 SX SX A1A A2 Dedicated no scheduling 1 Summit 1i GigE A2A Mark 5 GigE 8 Alpine A4 3804 A3 Dedicated no scheduling SX 28-1A 14 B1 Summit 15 13 WS/ Mark 5 100 Mb B8 B4 B6 B7 Hub B10 B9 To HS switch B3 Corr Cntl Cmptr GlowNet Congress St Boston (~50 km) Amp E6 E3 GigE E2 E4A Test WS 3l (2 GigE + 1 OC-48) GlowNet Alpine 3804 E4 GigE Test WS Bossnet (Steve/Jim) ISI-E Scheduling on Bossnet calendar GigE Juniper M20 1310 E7 E8 GigE E5 (~100 km) D1 Shared with MIT traffic Cisco 1500 E1 D2 Lincoln Lab (Lorraine/Steve/Jim) Schedule to be coordinated with LL Cisco 1500 GigE B11 D3 WDM E5A WDM GigE 5i SX 28-1B (Shared with LL on scheduled basis) C3 16 GigE GigE Dell Poweredge 2500 (’evlibhay’) GigE B5 B2 LL C2 Haystack Correlator WS/ Mark 5 Schedule to be coordinated with LL C1 MIT Campus WDM F1 E9 Other users (no control) To be upgraded to OC-48 155x Amp Amp F2 Bossnet currently running GigE pending investigation and repair (’superglide’) (’evlbill’) From ISI-E Dell Poweredge 500SC (provided by Haystack) Figure 1: e-VLBI Path - Haystack to ISI-E evlbi011.cdr 10 Aug 02 ISI-E (Tom) Test WS Scheduling on Bossnet calendar Test WS G5 G7B G6 GE G6B (’kame’) G8 OC-48 WDM Summit 5i (’omega’) Tuner Bossnet GE G7 MAX @ ISI-E (Jerry) G6C ponder G1 OC-48 Switch GigE G3 H5 H2 GigE G11 OC-48 Juniper M160 GigE H8 GigE H9 Primary e-VLBI path J3 Test WS? J2 Borrowed OC-48 interface - may not be able to keep H3 Needs configuration H6 Other users ( no control) Cisco 4912 Switch GigE Summit 5i H10 GigE J5 J4 WDM GigE on loan from GSFC H11 2 GigE l’s LuxN J6 J1 Need details OC-48 Juniper M160 MAX/UMCP (Jerry/Dan) No jumbo frames No scheduling; sufficient capacity for e-VLBI H4 Frame relay encapsulation G10 H7 MAX performance node; need details Test WS? Backup plan Juniper M40 G9 H1 G12 GigE GigE Trans- G2 Summit 5i G4 LX (~14km) GSFC/Bldg 28 (Pat/Paul/Kevin/Bill F.) K4 K1 WDM Will try to schedule either K2 or K3 exclusively for e-VLBI experiment G4 Mac with Yellowdog Linux (’clifford’) GGAO/Bldg 201 (Pat/Chuck) GigE K2 GigE LX (~7.25km) 1310 K7 Summit 5i K3 K5A K5 Test WS K6 Test WS K6A K5B Cisco 12016 K6B GGAO Antenna Trailer (Bill W./Chuck) L4 L2 Dedicated - no scheduling necessary (~500m) GigE Summit L3 GigE L1 5i L5 G4 Mac (’pluto’) RJ-45 Test WS RJ-45 L3A RJ-45 Mark 5 L4A Mark 5 L6 Windows PC (’xly’) evlbi012.cdr Figure 2: e-VLBI Path - ISI-E to GSFC/GGAO 10 Aug 02