MASSACHUSETTS INSTITUTE OF TECHNOLOGY HAYSTACK OBSERVATORY WESTFORD, MASSACHUSETTS 01886 Telephone: Fax: 978-692-4764 781-981-0590 4 June 2002 TO: Distribution FROM: Alan R. Whitney SUBJECT: 29 May 2002 e-VLBI telecon summary Attendees: Lee Foster, Pat Gary, Chuck Kodak, Kevin Kranacs, Paul Lang, Bill Wildes – GSFC Steve Bernstein, Lorraine Prior, Peter Schultz – Lincoln Laboratory Tom Lehman – ISI-E Richard Crowley, Kevin Dudevoir, Hans Hinteregger, Mike Titus, Alan Whitney – Haystack Observatory This telecon is one of an ongoing series of telecons to prepare for gigabit/sec e-VLBI demonstrations between NASA GSFC and MIT Haystack Observatory using a combination of network facilities including all or part of Glownet, Bossnet, ISI-E, SuperNet, Max and GSFC/HECN. Status Reports The attached figures of the e-VLBI path have been updated to reflect current status and are pretty much self-explanatory; critical status items are indicated in red. In addition, the following comments are relevant: − Bossnet problems • Peter reported that the Bossnet OC-48 link is still down (since 30 April). LL is debugging, but problem has not been fully isolated; optical power received at D.C. from Baltimore is 15dB down. Link was up for a few minutes 29 May but then down again. People must be sent to debug the bad optical segment; hopefully this will happen within next week. Good possibility that problem is in Quest fiber between Baltimore and D.C. • Tom reported that, before Bossnet went down on 30 April, he observed single-stream TCP from ISI-E to LL at ~900 Mbps, but slow in other direction. When link was up briefly a week ago, the opposite was observed; could send from LL to ISI-E at ~900, but reverse was slow. Hopefully, once the Bossnet problem is fully resolved, we will be able to sustain ~900 Mbps in both directions. • Tom can provide someone in D.C. to assist in the Bossnet debugging; tentatively scheduled for Tuesday, 04 June 02. minutes13.doc 6/5/2002 1 • Tom has heard that someone might have been investigating the placing of some equipment in the Bossnet rack in Baltimore in preparation for FC02(?) around 30 April; details unknown, but might be worthwhile to investigate in relation to current Bossnet problem. Jerry Sobieski at MAX should know the details. − Tom reported that additional test workstations (G7A and G7B) have been added at ISI-E, along with another Summit 5i (G4). − G4 Mac system purchased by Bill Wildes has been deployed to GGAO (at L6) and named ‘pluto’; has been tested to confirm K7/L1 link from GSFC Bldg 28 to GGAO. − Thanks to several people, a fairly complete detailed list of test workstations has now been assembled. Alan will distribute this information via e-mail to e-VLBI group; will include skeleton information on Mark 5 systems at A1, B1, B3 and L4. − Lorraine reported that Lincoln radar is back on-line on Glownet, so e-VLBI must return to scheduled usage, as in the past. − Juniper M160 (H7) has still not been configured to use path H9. Pat and Tom will contact Jerry Sobieski to try to get this resolved. Performance Testing Tom reported significantly better performance from ISI-E (G7) to Superglide (E5A) at LL than from ISI-E (G7) to the Dell Poweredge 500C (E5), also at LL. The reason for the difference is currently unknown. Tom is actively involved in a study to determine why data-transfer performance is so variable among various platforms between same network nodes. Variables include motherboards, PCI chip sets, interrupt handling, CPU’s, NIC’s, OS kernel, etc. Kevin would like to get OS tuning parameters of all test systems in order to try to understand performances differences. Steve reminded everyone that the Juniper router at E7 also services traffic from MIT campus over which we have no control and which shares with e-VLBI on OC-48 link F1. Other Alan reported that Haystack is preparing a proposal to NSF in collaboration with MIT Laboratory for Computing Science and MIT LL. The proposal includes developing special protocols for e-VLBI to better utilize network facilities, as well as infrastructure building and testing for e-VLBI. Pat reported that GSFC is testing ‘class-of-service’ features with both Extreme and Cisco switches. Extreme switches were easy to configure and use; Cisco switches were very difficult to configure and could not be made functional – a trouble report has been filed with Cisco. Action Items Alan: Distribute workstation configuration information to group. Steve: Keep tabs on status of Bossnet and notify group when problem is fixed. Pat/Tom: Work with Jerry Sobieski to configure Juniper M160 at H7. minutes13.doc 6/5/2002 2 Next telecon Next telecon will be Mon, 24 June 2002 at 2 pm. xc: Steve Bernstein, LL Jim Calvin, LL Lorraine Prior, LL Leslie Weiner, LL Herbert Durbeck, GSFC Lee Foster, GSFC Pat Gary, GSFC Chuck Kodak, GSFC Kevin Kranacs, GSFC Paul Lang, GSFC Aruna Muppalla, GSFC Bill Wildes, GSFC Dan Magorian, UMCP Tom Lehman, ISI Jerry Sobieski, Max Richard Crowley, Haystack Kevin Dudevoir, Haystack Hans Hinteregger, Haystack Arthur Niell, Haystack Joe Salah, Haystack minutes13.doc 6/5/2002 3 Westford Antenna Millstone RPE Bldg (Lorraine) Dedicated no scheduling GigE WS/ Mark 5 Summit 1i 1 A2 A1 GigE 8 Alpine A4 3804 A3 Dedicated no scheduling 28-1A 14 B1 Summit 15 100 Mb 28-1B B8 B4 B6 B7 Hub B10 B9 To HS switch B3 Corr Cntl Cmptr GlowNet Congress St Boston (~50 km) Amp Cisco 1500 Connection made for e-VLBI E3 GigE Alpine 3804 E2 E1 D2 Lincoln Lab (Lorraine/Steve/Jim) Schedule to be coordinated with LL E4A Test WS From ISI-E (’Superglide’) GigE E6 E4 GigE Test WS Cisco 1500 3l (2 GigE + 1 OC-48) GlowNet (~100 km) D1 Bossnet (Steve/Jim) ISI-E Scheduling on Bossnet calendar E7 Juniper OC-48 1310 M20 E8 GigE E5 (Shared with LL on scheduled basis) GigE B11 D3 WDM E5A WDM GigE 5i 13 WS/ Mark 5 C3 16 GigE GigE Dell Poweredge 2500 GigE B5 B2 LL C2 Haystack Correlator WS/ Mark 5 Schedule to be coordinated with LL C1 MIT Campus WDM F1 E9 155x Amp Amp F2 Bossnet currently down Other users (no control) To be upgraded to OC-48 Dell Poweredge 500SC (provided by Haystack) Figure 1: e-VLBI Path - Haystack to ISI-E evlbi011.cdr 04 June 02 ISI-E (Tom) Test WS Scheduling on Bossnet calendar Summit 5i GE G6 G7 GE G6A G5 Test WS Test WS G7A G7B Tuner Bossnet G1 G6B OC-48 Summit 5i G4 Switch GigE H2 GigE G9 G3 G11 OC-48 Borrowed OC-48 interface - may not be able to keep G10 H4 No jumbo frames Juniper M160 H8 GigE H9 Primary e-VLBI path Not yet configured for H9 path J3 Test WS? J2 H3 H6 Other users ( no control) Cisco 4912 Switch GigE Summit 5i H10 GigE J5 J4 WDM GigE on loan from GSFC H11 2 GigE LuxN J6 J1 Need details OC-48 Juniper M160 MAX/UMCP (Jerry/Dan) GigE No scheduling; sufficient capacity for e-VLBI Backup plan Juniper M40 H7 MAX performance node; need details Test WS? H5 H1 G12 GigE GigE Trans- ponder G2 GE G6C G8 OC-48 WDM MAX @ ISI-E (Jerry) LX (~14km) GGAO/Bldg 201 (Pat/Chuck) GSFC/Bldg 28 (Pat/Paul/Kevin/Bill F.) GigE K2 WDM Will try to schedule either K2 or K3 exclusively for e-VLBI experiment G4 Mac with Yellowdog Linux K3 K1 K6 Test WS GGAO Antenna Trailer (Bill W./Chuck) K4 Summit 5i GigE LX (~7.25km) K7 1310 Dedicated - no scheduling necessary GigE Summit L1 5i (~500m) L2 K5 Test WS GigE L3 L5 K6A Windows PC (Lee Foster) G4 Mac SX Mark 5 L4 Test WS L6 evlbi012.cdr Figure 2: e-VLBI Path - ISI-E to GSFC/GGAO 04 June 02