REDEKER CENTER EXPANSION Construction Update Current Work NE Addition: - Installing exterior handrails - Food service equipment moved into Savory's SE Addition: - Cast stone and brick installed at new dock - Flooring complete in Fresh Beginnings - Food service equipment being reinstalled West Addition: - Carpet flooring installed in the North lounge - Ceiling grid installed in new office and dining area - Aluminum composite panels being installed June 21, 2013 REDEKER CENTER EXPANSION Construction Update Food service equipment installed in Savory's Communal table installed in the North dining area Finish painting complete at the new Savory's Light fixtures installed at the check out area in Biscotti's Northeast Addition REDEKER CENTER EXPANSION Construction Update Handrails being installed between Rider Hall and Redeker Center Cast stone and brick installed at the new dock Concrete work complete at loading dock, will soon be installing dock levelers Looking south across the expanded receiving area Southeast Addition REDEKER CENTER EXPANSION Construction Update CMU walls constructed for new storage closet in the receiving area Equipment being reinstalled in the pot wash area Flooring complete in Fresh Beginning's, food service equipment being installed Countertops installed in new bathrooms on first floor Southeast Addition REDEKER CENTER EXPANSION Construction Update West elevation, insulation installed Installing aluminum composite panels over the insulation, the panels come in different sizes and shades of color New steam manhole installed at the Northwest corner of the building Looking West over the North lounge towards the new DOR conference room and computed lab West Addition REDEKER CENTER EXPANSION Construction Update Carpet flooring installed in the DOR conference room Looking North towards the new break room in the DOR offices Finish painting complete at the new booth areas Carpet flooring installed in the new West dining area West Addition