Energy and Utilities Alert April 2007 Authors: Harvard P. Spigal 503.226.5788 harvard.spigal@klgates.com Eric E. Freedman 206.370.7627 eric.freedman@klgates.com Roger D. Stark 202.778.9435 roger.stark@klgates.com Donald A. Kaplan 202.661.6266 don.kaplan@klgates.com Lisa H. Tucker 202.661.6211 lisa.tucker@klgates.com K&L Gates comprises approximately 1,400 lawyers in 22 offices located in North America, Europe and Asia, and represents capital markets participants, entrepreneurs, growth and middle market companies, leading FORTUNE 100 and FTSE 100 global corporations and public sector entities. For more information, please visit www.klgates.com. www.klgates.com Order 890: Framing the Costs of Transmission Access On February 16, 2007, the Federal Energy Regulatory Commission (the “Commission,” or “FERC”) adopted Order No. 890, Preventing Undue Discrimination and Preferences in Transmission Service (“Order 890”), which amends FERC’s regulations governing the provision of transmission service and requires revisions to the pro forma Open Access Transmission Tariff (“OATT”) adopted in Order Nos. 888 and 889.1 Transmission providers are required to submit filings revising their OATTs within two to seven months after the formal publication of Order 890 on March 15, 2007. Order 890 is intended to expand “nondiscriminatory access” to the transmission grid, increase customer access to new generating resources, facilitate the increased use of renewable energy (in part, by including “conditional firm” transmission service that responds to the needs of renewable energy generators), and enhance overall access to the grid by requiring transmission providers to calculate, in a uniform and transparent manner, the amount of capability available in the transmission network to accommodate additional requests for transmission services. • As discussed below, Order 890 also may have effects beyond those expressly contemplated by the Commission. For example: • As more transmission capacity becomes available to independent generators, short and medium term needs for additional generation may decrease; • Increased transmission access may affect locational-based capacity markets, and in particular capacity charges in such markets; • The change in rules regarding the “rolling over” of transmission reservations may free up previously committed transmission capacity; and • Expanded access to the transmission grid may result in increased costs for owners of intermittent generation resources. Collectively, Order 890’s changes to the pro forma OATT should make more transmission capacity available by requiring greater uniformity in the calculation of transmission capacity, creating greater opportunities for transmission customers to reassign unused transmission capacity and discouraging “warehousing” of unused capacity. The key components of Order 890, and their potential consequences, are discussed in further detail below. Discussion Order 890 will have important ramifications for existing stakeholders and prospective investors. As highlighted below, various provisions of the order are expected to provide increased opportunities to secure valuable transmission capacity. 1. Numerous requests for rehearing have been filed with respect to Order 890. Thus certain elements of the rule as proposed and as discussed below may change. Energy and Utilities Alert Consistency and Transparency of Available Transfer Capability Calculations Summary. Order 890 gives the electric industry specific guidance regarding the calculation of the amount of capability available in a transmission network to accommodate additional requests for transmission services (referred to as “available transfer capability,” or “ATC”). Order 890 at P 207. Order 890 also establishes a firm deadline for implementing requirements to increase consistency in the processes for calculating ATC and exchanging ATC data among transmission providers. Order 890 at P 223. Implications. For years transmission customers and interconnecting generators have struggled with inconsistent calculations of ATC. Requiring consistency in the calculation of ATC will have an impact on the ability of generators and other transmission customers to move power under firm transmission arrangements. Requiring such consistency will free up new capacity in some cases, but in other cases will eliminate previously available capacity. The requirement will, for example, make it more difficult for transmission providers to vary from published ATC figures, leaving them little flexibility to accept or reject transmission requests close to their published limits. Coordinated, Open and Transparent Transmission Planning Summary. Order 890 requires coordinated, open and transparent transmission planning on both a subregional and regional level. Order 890 at P 435. It adopts nine planning principles that each transmission provider will be required to follow. Each transmission provider must develop a proposal for implementing these principles within 75 days after the formal publication of Order 890 on March 15, 2007, and must incorporate such principles in its OATT within seven months after such date. Order 890 at P 442. Implications. The Order 890 transmission planning reforms will extend to all transmission owners the wide-open stakeholder processes that currently take place within regional transmission organizations. These requirements may move to the federal arena many issues that previously were resolved at the state level. Forcing transmission providers to participate in regional planning processes is likely to result in larger facilities being built across multiple transmission areas. Regional planning may also lead to a more regional allocation of costs for such facilities. Over time, the requirement that transmission owners participate in regional planning processes addressing congestion as well as reliability concerns may have a significant impact on energy prices. Transmission Pricing Reforms Summary. Order 890 reforms several of the transmission and ancillary service pricing provisions of the pro forma OATT: • Energy and Generator Imbalance Charges. Order 890 adopts a new schedule to the pro forma OATT that provides for generator imbalance payments and credits, based on specified deviation bands and reforms energy imbalance pricing. Order 890 at P 627. •C apacity Reassignment Pricing. Order 890 eliminates the existing price cap on the reassignment of point-to-point transmission capacity. Before Order 890, transmission customers were limited to charging the transmission provider’s filed rate for reassigned capacity. Order 890 permits customers to resell capacity at full market prices. Order 890 at P 808. •Crediting of Customer-Owned Facilities. Order 890 removes the requirement that, in order to be eligible for transmission credits, a facility must be part of the transmission provider’s joint planning process. Going forward, a network transmission service customer can receive credits against transmission service charges for new transmission facilities if the facilities are integrated into the operations of the transmission provider’s facilities. Order 890 at P 753. Implications. Order 890 permits transmission providers to assess imbalance charges based on the transmission provider’s actual incremental costs to supply the imbalance energy. Such pricing will make the costs for such services more difficult for customers to predict and the charges associated with such services more difficult for customers to audit. Order 890’s generation imbalance charges are likely to increase the cost of operating many generating units. Intermittent resources are more susceptible to fluctuations in output and thus will be more susceptible to imbalance charges. April 2007 | Energy and Utilities Alert The Commission has tried to temper the effects of these charges by exempting intermittent resources from the higher penalties associated with the highest imbalance deviation band, but intermittent generation will nonetheless remain subject to penalties in lower bands. Order 890’s transmission customer credit and capacity resale provisions are important benefits for transmission customers, particularly generation developers. The credit provisions reduce the cost to developers of interconnecting to a transmission provider’s system where network upgrades are required. Eliminating the requirement that customer-owned facilities be part of the transmission provider’s joint transmission plan should lead to more customer-owned facilities being eligible for transmission credits and may also make some generation interconnections possible by providing funds to finance required network upgrades that would not be otherwise eligible for credits. The rule also eliminates any disincentive for transmission providers to exclude customer-owned facilities from the transmission provider’s joint transmission plan. The resale provisions of Order 890 could be a source of short and medium-term revenue for transmission customers that commit to long-term reservations (as they must do under the new rollover provisions of the tariff) but that do not necessarily need all of the capacity in the early years of that commitment. Improvements to Point-to-Point Service Summary. Order 890 adopts a “conditional firm” component to long-term point-to-point service to address circumstances in which firm service can be provided for most, but not all, hours during the period requested. Order 890 also reforms existing requirements for the provision of redispatch service. Order 890 at P 911. Implications. Conditional firm service is designed in part to provide a low-cost alternative for intermittent renewable generation. Requiring transmission providers to provide a conditional firm service will make more transmission available on a firm basis. By definition, however, such service may not be available during peak service periods. Reform of Rollover Rights Summary. Order 890 increases from one to five years the minimum term of a transmission service contract for which a customer may seek rollover rights. Order 890 at P 1231. Order 890 also requires that a transmission customer eligible for rollover rights provide one year’s advance notice of whether or not it will exercise its right to renew the contract. Order 890 at P 1245. Implications. Increasing the minimum term of “rolled over” transmission rights from one year to five years is likely to decrease the number of transmission service contracts that elect rollover treatment and thus to make available transmission capacity that would have otherwise remained committed. As noted above, the Commission has removed the price cap on reassigning point-to-point transmission capacity, thus making it easier for long-term firm point-to-point customers to trade excess capacity. This change also will tend to increase the availability of transmission capacity and may create a more robust secondary market for transmission capacity. Changes to Reservation Priority Provisions Summary. Order 890 requires that transmission providers give certain pre-confirmed transmission service requests priority over other requests submitted in the same time period. Order 890 at P 1401. Order 890 adds price as a tie-breaker in determining priority in the reservation queue when the transmission provider is offering discounted transmission service. Order 890 at P 1410. Implications. Giving priority to pre-confirmed transmission requests will ensure that customers that committed to securing transmission service will have a greater likelihood of receiving such service. The change will also prevent customers from hoarding potential transmission service by submitting multiple service requests that the customer does not intend to honor. Order 890 requires transmission customers with pre-confirmed transmission requests to take full service in the event the transmission provider offers the requested service. Order 890 also maintains the existing incentive for long-term service in the pro forma OATT by continuing to give priority to non-confirmed longterm service requests over pre-confirmed short-term service requests. April 2007 | Energy and Utilities Alert K&L Gates comprises multiple affiliated partnerships: a limited liability partnership with the full name Kirkpatrick & Lockhart Preston Gates Ellis LLP qualified in Delaware and maintaining offices throughout the U.S., in Berlin, and in Beijing (Kirkpatrick & Lockhart Preston Gates Ellis LLP Beijing Representative Office); a limited liability partnership (also named Kirkpatrick & Lockhart Preston Gates Ellis LLP) incorporated in England and maintaining our London office; a Taiwan general partnership (Kirkpatrick & Lockhart Preston Gates Ellis) which practices from our Taipei office; and a Hong Kong general partnership (Kirkpatrick & Lockhart Preston Gates Ellis, Solicitors) which practices from our Hong Kong office. K&L Gates maintains appropriate registrations in the jurisdictions in which its offices are located. A list of the partners in each entity is available for inspection at any K&L Gates office. This publication/newsletter is for informational purposes and does not contain or convey legal advice. The information herein should not be used or relied upon in regard to any particular facts or circumstances without first consulting a lawyer. Data Protection Act 1998—We may contact you from time to time with information on Kirkpatrick & Lockhart Preston Gates Ellis LLP seminars and with our regular newsletters, which may be of interest to you. We will not provide your details to any third parties. Please e-mail london@klgates.com if you would prefer not to receive this information. ©1996-2007 Kirkpatrick & Lockhart Preston Gates Ellis LLP. All Rights Reserved. April 2007 |