NIGHTINGALE L ANE June 2009

advertisement
UNDER CONSTRUCTION
NIGHTINGALE L ANE
STORM DRAINAGE IMPROVEMENT PROJECT
Dear Resident:
June 2009
Charlotte-Mecklenburg Storm Water Services is currently in the construction
phase of the Nightingale Lane Storm Drainage Improvement Project. United
Construction was awarded the construction contract in February 2009 and
began work on March 16, 2009.
United Construction has been working along the new section of stream.
The connection of the new stream to McMullen Creek is now complete
and they plan to progress upstream to Blue Heron Drive in late July. The
contractor has started to place the pipe, so residents may notice an increase
in construction activities along the streets.
Construction updates will be sent approximately every four months.
However, if you would like to receive more frequent updates via email,
please send your email address to William Harris with “Nightingale Email
List” in the subject heading.
For more information, please visit our website at http://stormwater.
charmeck.org and click on Storm Water Projects, Storm Water Projects
again, and then Nightingale.
Contractors install step pools in the main
channel near the tie-in to McMullen Creek.
If you have any questions, please contact one of the following team
members:
On-site Construction Inspector:
Scott Ackerman: 980-721-3653
E-mail: sackerman@ci.charlotte.nc.us
Construction Manager:
Gary Stansbury: 704-336-2667
E-mail: gstansbury@ci.charlotte.nc.us
Project Manager:
William Harris : 704-353-1147
E-mail: wtharris@ci.charlotte.nc.us
A construction inspector will be on site daily to address any questions or
concerns. Please note that efforts are taken to minimize disruption to
nearby property owners.