Project Status:
Charlotte-Mecklenburg Storm Water
Services and engineering consultant,
WK Dickson & Co., Inc., have finalized
the construction plans and begun
the bid phase. During this phase, the
final design plans will be circulated to
qualified contractors for a competitive
bidding process.
Next Steps:
After City Council approval, the
construction contract is awarded to
the lowest responsible bidder. The bid
phase typically lasts 6 to 9 months.
For more information:
Please contact
Adrian Cardenas, Project Manager
acardenas@charlottenc.gov
704-336-4682
StormWater.CharMeck.org
Meadowridge Storm Drainage Improvement Project
Engineering & Property Management
Storm Water Services Division
600 East Fourth Street
Charlotte, North Carolina 28202
Investing in Infrastructure
Charlotte has an aging public storm drainage system, much of which is past its
useful life. The City repairs, replaces and installs new storm drainage infrastructure
when it deteriorates or becomes too small to handle increases in stormwater.
Investing in infrastructure protects public safety, guards private property, improves
water quality and enhances quality of life.
The Meadowridge Storm Drainage Improvement Project goal is to improve the
storm drainage infrastructure within the neighborhood, reducing the channel
erosion and flooding concerns.
For more information: StormWater.CharMeck.org