UNDER CONSTRUCTION City View STORM DRAINAGE IMPROVEMENT PROJECT Dear Resident: May 2014 Construction continues for Charlotte-Mecklenburg Storm Water Services’ City View Storm Drainage Improvement Project. Work at Brook Crossing Court is now substantially complete as well as the channel work between Dorn Circle and Streamside Drive. Work on the stream section between Streamside Drive and Campbell Creek Lane is complete, and rehabilitation of the culvert under Streamside Drive is 95% complete. For more information about this project, please visit our website to view project updates and exhibits at: http://stormwater.charmeck.org. Click on Storm Water Projects drop down menu in the green bar, then Active Projects and City View. Contractor working on channel downstream of Dorn Circle. Engineering & Property Management Storm Water Services Division 600 East Fourth Street Charlotte, North Carolina 28202 City View Project Update HIGHLIGHTS If you have any questions, please contact one of the following project team members: On-site Construction Inspector: Charlotte Drzewiecki: 704-361-7597 Email: cdrzewiecki@charlottenc.gov Construction Supervisor: Steve Canter: 704-336-7047 E-mail: scanter@charlottenc.gov Project Manager: Chad Nussman: 704-336-5676 Email: cnussman@charlottenc.gov A construction inspector will be on site daily to address any questions or concerns. Please note efforts are taken to minimize disruption to nearby properties.