Research Journal of Applied Sciences, Engineering and Technology 4(9): 1062-1066, 2012 ISSN: 2040-7467 © Maxwell Scientific Organization, 2012 Submitted: October 31, 2011 Accepted: November 18, 2011 Published: May 01, 2012 Optimal Parameter Selection of Gas-Fired Units for Distributed Cogeneration in an Industrial Town Based on an Industrial Service Company Perspective Meisam Ansari, Mohammad Sadegh Payam, Mostafa Abdollahi and Asadollah Salami Dehkordi Department of Electrical Engineering, Boroujen Branch, Islamic Azad University, Boroujen, Iran Abstract: Industrial service companies incentivize the investors to install distributed generation, to improve network environmental performance and efficiency. This paper proposes an approximated dynamic approach for optimal parameter selection of gas-fired units to supply electrical and thermal loads in an industrial town considering industrial service company perspective. A cost-benefit analysis with considering gas units, heat recovery system and distribution network constrains is performed for Optimal sizing, placement and timing for CHP installation. The main objective of the model is to minimize the company’s operating costs in five years. Two aspects are considered in problem formulation: priority of the heat generation or electricity generation. Also, a multi objective genetic algorithm is used to solve the problem. Moreover, the PIKO feeder, one of the MANAVI substation feeders in TEHRAN, is employed as the study system. The simulation results show a significant decrease in the industrial service company operating costs, especially loss costs in five years. Key words: Distributed cogeneration, distributed network reinforcement, genetic algorithm INTRODUCTION Distributed systems are used commonly in the networks to decrease transmission and distribution losses. Using cogeneration systems, with total efficiency more than %70, is one of the effective strategies for optimizing energy consumption. However, if require parameters don’t select properly, it may cause to decrease the planes performance. Developing in technology has created a wide choice especially in Combine Heat and Power (CHP) units that can be competing in costs decrease. In this case, Distributed Generation (DG) installation problem is formulated with various objective functions and is solved using several methods. In (Hashemi, 2009), an offline model is developed by authors for optimal operation in a three generation system (combine heat and power and cooling system). Where, the objective function is maximizing the annual benefit of the CCHP systems. In (Sanaye and Reaessi, 2009) the authors are introduced a method to estimate optimal capacity and number of gas micro-turbines to use in a system with specific electrical and thermal load curve. The objective function is maximizing total benefit from selling power and heat. In (Giaccone and Canova, 2009) a method is proposed to specify a cogeneration system for industrial users while, the objective function is maximizing net present value. In (Sun, 2008) a method to determine the CHP systemparameters from a manufactures perspective is presented. In this paper, the objective function is maximizing Internal Rate of Return (IRR). Also, in (Favuzza et al., 2007) an approach is suggested to reinforce distributed network by DG installation and a dynamic ant colony optimization algorithm is used to solve the problem. In Keane et al. (2007) and Harrison et al. (2007) the authors are expressed the impact of DG interconnection policy on distributed network and power purchasing quality from DGs. In these studies, the interaction between distributed generation developer and distributed network operator is evaluated. In this study, the expansion of CHP units in an industrial town is developed. The problem is formulated as an optimization problem based on industrial service company perspective. The problem is solved using a dynamic method to minimize the operation cost in several years. PROBLEM FORMULATION In general view, it’s required to evaluate CHP installation problem in several aspects such as technical constraints, units characteristics, environmental affects, economical evaluations and etc. The most important parameters required to determine a cogeneration plane in a distributed network, are placement, timing and capacity of gas-fired units. The problem is definable based on investor perspective, industrial company perspective or local consumer perspective. In this study, the problem is defined based on distributed company perspective. Control variables, constraints and objective function are three main parts that should be specified to formulate an optimization problem. Corresponding Author: Mohammad Sadegh Payam, Department of Electrical Engineering, boroujen branch, Islamic Azad University, Boroujen, Iran, P.O. Box 88715/141, Tel.: +983824223812; Fax: +983824223812 1062 Res. J. Appl. Sci. Eng. Technol., 4(9): 1062-1066, 2012 Control variables include place, time and capacity of gas-fired units. In this study, an approximated dynamic approach is used to determine these variables. The problem is solved for one year in this method. Then the achieved plan is considered and the problem solve for next year. This process continues until completion of study. It is necessary to estimate the Load Duration Curve (LDC) into several steps for mathematical formulation. Objective function: The industrial companies add units to their networks with operation cost decreasing purpose. Thus the objective function defines by decreasing costs purpose for N years. These costs include following items. Cost of purchasing power from network: The power price curve estimate into N steps similar to LDC. Equation (1) shows the calculation of this cost: f NET pur ( n ,t ) (1 rN ) n . c N (t ).[ E load (n, t ) E CHP (n, t )] E load (n, t ) (1 re ) n . PL(t ). h(t ) (1) f ENS (n, t ) h( t ) U .[(1 rN ) n . PLi (t ) 8760 i i max min{(1 rN ) n . PLi (t ), PCHP i }]. Cs (t ).(1 rs ) (5) n Therefore, we can calculate the ENS in distributed network without islanding possibility, before and after DG installation. Heat recovery revenue: This revenue belongs to DG owners but it cause to give priority to the buses with thermal load for install DG by subtracting this item from total cost. There are two views in considering this item: In the first view, the thermal load is on priority. In the other word, the main goal of DG installation is supply local thermal load and generated power can be used by local electrical load or can be sold to the network. Total thermal required by local load must supply by units. In this view, heat recovery is equal to local thermal load and it can be calculated by following equation: E CHP (n, t ) i 1 PCHPi (n, t ). h(t ). KCHP nCHP R rec ( n , t ) U n bf . C f .(1 rh ) . QDi ( t ). h ( t ). K CHP (6) i Cost of power purchasing from installed units: Considering legal rules in IRAN, the DGs can sell their power with bilateral contract by guaranty rate or participate in the power market and compete with other gencos. In this paper, bilateral contract by guaranty rate is used to define the problem. Equation (2) shows the formulation of this cost: f CHP pur (n, t ) (1 rc )n. Cc (t ). E CHP (n, t ) (2) In the second view, DG units will be installed on the network to generate the power and selling to the network or local electrical load. In this case heat recovery can be used from local thermal load. Total thermal recovered maybe cannot supply total requirement and then we have to use some boilers to provide total requirement. Heat recovery is equal or less than local consumption anyway. Eq. (7) shows calculation of this parameter: Rrec (n, t ) Loss cost: Equation (3) shows the calculation of loss cost: f loss (n, t ) CN (t ).(1 rN ) n . Eloss (n, t ) nbus nbus 1 Eloss (n, t ) h(t ). j 1 Rij . I ij2 (n, t ) j 1 2 h( t ) U .(1 re ) n . PLi (t ). Cs (t ).(1 rs )n 8760 i i ij . r j Ui n h i CHPi ( n, t )}. (7) i U bf .C f .h(t ). KCHP (3) Finally total annual cost can be calculated using following equations: Cost of energy not supply: Equation (4) use to estimate the Energy Not Supply (ENS) when there are no DG units in network and it’s not possible to make island in abnormal condition: f ENS (n, t ) min{(1 r ) .QD (t ),Q N 1 tot cos t cos t (n, t ).(1 I ) n 0 N n t cos t (n, t ) f NET pur (n, t ) f CHP pur (n, t ) (8) f loss (n, t ) f ENS (n, t ) Rrec (n, t ) (4) j when DG units exist in the network and making island is not possible, each unit can just supply the local load connected to it. In this case Eq. (5) can be used to estimate the ENS: Constraints: The constraints include 3 parts: network constraints, DG constraints and heat recovery system constraints. Equation (9) shows network constraints. These formulas define optimal power flow for the network: 1063 Res. J. Appl. Sci. Eng. Technol., 4(9): 1062-1066, 2012 The second part is about the heat recovered limitation for DG units, which shown as: QCHPi (n, t ) kheat . PCHPi (n, t ) Units will be installed by two perspectives, if local thermal load exist. This subject is expressed in section 1-3. Equation (12) and (13) show these constraints for thermal priority and electrical priority respectively: Fig. 1: Diagram for PIKO feeder Table 1: Required parameter to solve the problem rn rh rc 0.05 0.05 0.02 Cf Ubf ra 0.05 49 0.25 PFkmin N khrat 1.1 0.85 5 T PL H Cn 1 3339 730 0.075 2 3172 730 0.072 3 3005 730 0.069 4 2838 730 0.066 5 2671 730 0.063 6 2504 730 0.060 7 2337 730 0.057 8 2170 730 0.053 9 2003 730 0.050 10 1836 730 0.047 11 1670 730 0.044 12 1503 730 0.041 Cc 0.048 0.048 0.048 0.048 0.048 0.048 0.048 0.048 0.048 0.048 0.048 0.048 rc 0.03 KCMP 0.9 I 0.12 Cs 0.075 0.072 0.069 0.066 0.063 0.060 0.057 0.053 0.050 0.047 0.044 0.041 VV (G sin B cos ) P P VV (G cos B sin ) 1 PG PL 2 P . I i j ij ij i j ij ij ij Li i 1 n bus i 1 ij i i i 1 i 1 j 1 ij 2 2 ij 0 (9) Units constraints include two basic parts. First part is electrical constraints. Equation (10) shows constraints for this part: Case study: The PIKO feeder, one of the MANAVI substation feeders in TEHRAN, is considered as a case study. The diagram of this feeder is shown in Fig. 1. Network information, lines characterize and breakers locations are illustrated in Fig. 1. Other parameters that need to simulate the problem shown in Table 1. SIMULATION RESULTS min max PCHPi PCHPi PCHPi PCHPi PCHPi q CHPii 2 PF min (15) constraints (c(x)#0) and it’s defined by (a = *d(x)* for equality constraints (d(x) = 0). The algorithm may loss its basic aim if penalty factors are very effective. We use “it” to prevent this. This parameter decrease linear by the algorithm iteration and its value is in [0 1] interval. V min Vi V max 2 (14) The “a” is defined by a c( x ) c( x ) for inequality / Fij / Fijmax min max qCHPi qCHPi qCHPi cos ti P rimary cos t penalty fact e it .a ij n bus (13) A penalty factor method is used to consider constraints in the algorithm. These factors are multiplied by the fitness function. Equation (15) shows that how the constraints are considered. ij n bus n bus QCHPi (n, t ) Qboiler i (n, t ) QDi (t ).(1 rh ) n fiti 1 n bus Gi (12) Performance by GA: A standard genetic algorithm is used to solve this problem. Equation (14) shows the fitness function for each chromosome. n bus i 1 QCHPi (n, t ) QDi (t ).(1 rh ) n In (13), if Qboiler i is positive, this means that we need auxiliary boiler to supply local thermal load and if its negative, this means that heat recovered from units can supply local thermal load. Table 2: optimal plan specification in 5 years Capacity (Kw) ----------------------------------------------------------------------No. Bus Year 1 Year 2 Year 3 Year 4 Year 5 6 848 0 0 0 0 12 0 0 0 729 0 13 1060 0 0 0 0 14 0 1131 0 0 0 Total 1908 3039 3039 3768 3768 qGi q Li (11) (10) Table 2 shows optimal plan for gas-fired unit’s installation in 5 next years. As it can be seen, the units are installed at first, second and third years. Total capacity are installed in the first year, is 848 kW in bus 6 and 1060 kW in bus 13. Then at the second year, 1314 kW capacity 1064 Res. J. Appl. Sci. Eng. Technol., 4(9): 1062-1066, 2012 457.45 Year 1 Year 4 851.02 457.40 851.00 850.98 457.30 Mwh Mwh 457.35 457.25 457.20 850.94 850.92 457.15 850.90 457.10 1 2 3 4 5 6 7 8 9 10 11 12 850.88 1 851.10 2 3 4 5 6 7 8 9 10 11 12 9 10 11 12 Year 2 851.10 851.05 Year 5 851.05 851.00 Mwh Mwh 850.96 850.95 851.00 851.95 850.90 851.90 850.85 1 2 3 4 5 6 7 8 9 10 11 12 851.85 2000 1 Year 3 1500 2 3 4 5 6 7 8 Annual purchased energy from units Mwh Years 1000 1 2 3 4 5 500 0 1 2 3 4 5 6 7 8 9 10 11 12 Energy [Mwh] 5487.4 10211.6 10211.6 10211.7 18946.2 Fig. 2: Energy purchasing from units in each step Table 3: Comparing parameters before and after units installation for 5 years (all parameters in Mwh) without DG with DG Loss 240.1 104.4 purchasing from net 112820.5 57616.3 purchasing from DG 0.0 55068.5 Energy not supply 18.2 11.8 Heat recovered 0.0 49808.1 Total 0 0 Table 4: Comparing costs before and after units installation for 5 years (all costs in 1000 Euros) without DG with DG Improvement (%) Loss 18.9 9.0 52.3 purchasing from net 6827.9 3486.9 48.9 purchasing from DG 0.0 2615.8 0 Energy not supply 1.4 0.9 32.7 Heat recovered 0.0 716.0 0 Total 6846.8 6111.7 10.7 is installed in bus 14. Finally the plan is finished by installing 729 kW in bus 12 at third year .Thus developing units plan complete for 5 next years. Total electrical capacity is installed on the feeder is 3768 kW. Considering Fig. 1 and Table 2, the buses are selected for installing DG are ended buses and have thermal consumption. This means ended buses are suitable for DG development. Table 3 shows comparing parameters before and after units’ installation for 5 years (all parameters in Mwh). Also, Table 4 shows operation costs before and after developing units in the network. As can be seen, the total loss improvement is 82% in five years. Its equivalent 9.9e3 Euros considering power price in IRAN. ENS is decreased about 54% in five years. It is equivalent 500 Euros. ENS is total energy that industrial company buys from market but cannot sells to costumers because of faults occur in its network. This value maybe increases, if industrial companies have to pay fine to costumers because of interruption service. After implementation the plan, thermal recovered is more than 49 GWH equivalent 716e3 Euros. This reduction in fuel consumption is very impressive. Comparing numerical results shows that the most revenue of using CHP in network is heat recovery. Finally total operation costs is reduced more than 14% equivalent 735e3 Euros in five years. Figure 2 shows energy purchased from gas-fired units in each years. As can be seen, in the first steps -related to full load hours- energy purchased is more than latest steps related to light load hours. Because in the full load hours market price is higher than billateral contracts rate and in the light load hours, it is lower than bilateral contracts rate. 1065 Res. J. Appl. Sci. Eng. Technol., 4(9): 1062-1066, 2012 Mwh 60 without DGs with DGs 40 20 0 1 2 4 5 Fig. 3: Comparing between annual loss before and after units installation Mwh 6 without DGs with DGs 4 constrains for gas units, heat recovery system and distribution network. The obtained results from the case study, show impressive revenue from heat recovery and significant improvement in active power loss. Also results show energy not supply decrease by using DG in the network without any automatic equipment to manage outages. Final results show that using CHP units allow the industrial company to use of maximum possible network capacity and response to load growth by using a full or an approximated dynamic view to solve the problem is possible. The method developed in this paper has a good friendship by restructured environment in order to supply energy for industrial towns. REFERENCES 2 0 1 2 4 5 Fig. 4: Comparing between annual ENS before and after units installation Figure 3 and 4 show annual loss and annual energy not supply respectively. Considering these figures, both ENS and loss decrease after installing the units. Although these figures show affect of developing units in the network decrease in the last years. This is because of occurring a kind of saturation in the network by increasing the total capacity installed. Therefore, it is necessary to consider total distributed capacity installed in each network, shall not be more than a specific value. Final results show that improvement in ENS is less than loss because studied feeder not equipped by automatic device for automation in abnormal condition. If automatic equipments exist in feeder and we can make the islands, results can be better. CONCLUSION Using cogeneration, gas-fired units in the distributed network cause to improve energy efficiency. In this paper optimal sizing, placement and timing for CHP installation is obtained through a cost-benefit analysis subject to Favuzza, S., G. Graditi, M.G. Ippolito and E.R. Sanseverino, 2007. Optimal electrical distribution systems reinforcement planning using gas micro turbines by dynamic ant colony search algorithm. IEEE T. Power Syst., 22(2): 580-587. Giaccone, L. and A. Canova, 2009. Economical comparison of CHP systems for industrial user with large steam demand. Appl. Energ., 86(6): 904-914. Harrison, G.P., A. Piccolo, P. Siano and A.R. Wallace, 2007. Exploring the tradeoffs between incentives for distributed generation developers and DNOS. IEEE T. Power Syst., 22(2): 821-828. Hashemi, R., 2009. A developed offline model for optimal operation of combined heating and cooling and power systems. IEEE T. Energ. Conver., 24(1): 222-229. Keane, A., E. Denny and M.O. Malley, 2007. Quantifying the impact of connection policy on distributed generation. IEEE T. Energ. Conver., 22(1): 189-196. Sanaye, S. and M. Reaessi, 2009. Estimating the power and number of micro turbines in small-scale combined heat and power systems. Appl. Energ., 86: 895-903. Sun, Z.G., 2008. Energy efficiency and economic feasibility analysis of cogeneration system driven by gas engine. Energ. Build., 40: 126-130. 1066