American University Master Commissioning Plan Revision 1.1 March 5, 2012 American University Master Commissioning Plan Revision 1.1 Table of Contents Section 1 2 3 4 5 6 7 Page Introduction ......................................................................................... 2 Commissioning Team Members......................................................... 3 Systems to be Commissioned ........................................................... 4 Commissioning Process Matrix ......................................................... 6 Commissioning Process Flowchart ................................................... 9 Commissioning Activities Narratives .............................................. 10 Commissioning Documentation....................................................... 29 American University Master Commissioning Plan Page 1 Revision 1.1 March 5, 2012 1 Introduction Commissioning is defined as a systematic process of assuring by verification and documentation, from the design phase to a minimum of one year after construction that all building facility systems perform interactively in accordance with the design documentation and intent, and in accordance with the owner’s operational needs, including preparation of operations personnel. This Commissioning Plan is intended to be a roadmap for the parties involved in the Commissioning process. It lists the systems to be commissioned, the Commissioning process activities, and the roles and responsibilities for each party involved. The goals of the Commissioning Plan are to identify and define the following: Systems to be commissioned. Commissioning team members. Commissioning activities. Commissioning Team member responsibilities for each Commissioning activity. Documentation requirements from each activity and Commissioning Team member. Schedule parameters (i.e., how will Commissioning activities integrate into the other project delivery milestones?). Acceptance criteria for the completion of commissioning. The Commissioning Process Matrix and Flowchart graphically depict the commissioning process and its flow from the Planning Phase through the Warranty Phase. These are intended to be a quick reference for identifying the fundamental components of commissioning and their relationship to each other. The Master Commissioning Process Narrative provides more detail regarding the activities, responsibilities, and deliverables associated with each activity in the Commissioning Process Matrix and Flowchart. For each Matrix row and Flowchart box, there is a corresponding narrative description. To supplement these sections, Section 7 includes Commissioning documentation templates and examples. American University Master Commissioning Plan Page 2 Revision 1.1 March 5, 2012 2 Commissioning Team Members Role Project Manager Company American University Title Construction Manager American University Construction Manager Facilities Management American University Cx Authority Name Phone Number Email Address Project Manager American University Other University Departments American University American University American University Architect Design Team Mechanical Engineer Electrical Engineer General Contractor Mechanical Contractor Construction Team Electrical Contractor TAB Contractor Controls Contractor Project Manager Commissioning Manager Lead Mechanical Lead Electrical American University Master Commissioning Plan Page 3 Revision 1.1 March 5, 2012 3 Systems to be Commissioned SYSTEMS Mechanical Systems HVAC System Indoor Air Quality Monitoring System Energy Management System Domestic Water Booster System Domestic Hot Water System Irrigation Controls Grey Water Systems Life Safety Systems Fire Suppression System Fire Alarm System Smoke Management Systems TBD TBD TBD TBD TBD TBD TBD TBD 100% TBD Electrical Systems Normal Power Systems (mains, power distribution, and breakers) Emergency Electrical Power (emergency generators, automatic transfer switches, mains, power distribution, and breakers) Critical Power (mains, power distribution, breakers, and uninterruptible power supplies) Lighting Controls Vertical Transport Systems Building A/V & Communications Systems Security Systems Card Access Cameras American University Master Commissioning Plan SAMPLING TBD TBD TBD TBD TBD TBD TBD TBD Page 4 Revision 1.1 March 5, 2012 Building Envelope Walls Windows Roof/Flashing Subgrade Waterproofing Insulation Air and Vapor Barriers Expansion Joints TBD TBD TBD TBD TBD TBD TBD Specialty Systems Classroom/Conference Room Audio-Visual, Lighting, & Communications Kitchen Systems Laboratory Support Systems American University Master Commissioning Plan Page 5 TBD TBD TBD Revision 1.1 March 5, 2012 4 Commissioning Process Matrix The following matrix tabulates the major commissioning activities; when they occur during the project life cycle; and the commissioning team member roles and responsibilities for each activity. For additional detail, please refer to Section 6: Commissioning Activities Narratives. In the Commissioning Team Member columns an “R” indicates the responsible team member for each activity, and a “✓” indicates a team member who needs to participate in the activity. Cx Manager Construction Team Design Team Other AU Departments AU Facilities Cx Authority AU Construction Mgr AU Project Manager COMMISSIONING TEAM MEMBERS Warranty Acceptance Construction Design Planning PROJECT PHASES Preliminary Commissioning Plan ✓ Owner’s Project Requirements (OPR) Document ✓ ✓ ✓ Design Phase Commissioning Coordination Meetings ✓ ✓ ✓ ✓ ✓ R Basis of Design (BOD) Document ✓ ✓ R ✓ O&M Documentation Planning ✓ R ✓ O&M Training Planning ✓ R ✓ Warranty Planning ✓ ✓ R ✓ Commissioning Design Reviews ✓ ✓ ✓ ✓ ✓ ✓ R Preliminary Prefunctional Checklists & Functional Performance Tests ✓ ✓ R Final Commissioning Plan ✓ ✓ ✓ ✓ ✓ R Commissioning Specification ✓ ✓ ✓ R Construction Phase Commissioning Coordination Meetings American University Master Commissioning Plan R ✓ ✓ R ✓ ✓ ✓ ✓ Page 6 ✓ ✓ ✓ R Revision 1.1 March 5, 2012 Cx Manager ✓ ✓ ✓ ✓ R O&M Manual Reviews ✓ ✓ ✓ R O&M Training Agenda Reviews ✓ ✓ ✓ R Systems Training Planning ✓ ✓ ✓ ✓ R Occupant Training Planning ✓ ✓ ✓ Final Prefunctional Checklists & Trend Log Specifications ✓ ✓ ✓ R Final Functional Performance Tests ✓ ✓ ✓ R Design Team Submittal Reviews AU Facilities Cx Authority ✓ Warranty R Acceptance ✓ ✓ Construction ✓ Design Commissioning Schedule Planning Construction Team Other AU Departments AU Construction Mgr COMMISSIONING TEAM MEMBERS AU Project Manager PROJECT PHASES R Acceptance Phase Commissioning Coordination Meetings ✓ ✓ ✓ ✓ R Test, Adjust, and Balance (TAB) Report Review ✓ ✓ ✓ ✓ R Systems Training Delivery ✓ ✓ ✓ ✓ R O&M Training Delivery ✓ ✓ R ✓ Prefunctional Checklist Completion ✓ R ✓ Functional Performance Test Plans ✓ ✓ ✓ R Functional Performance Testing ✓ ✓ ✓ R Trend Log Review ✓ ✓ ✓ R ✓ ✓ ✓ ✓ ✓ ✓ R Commissioning Action List American University Master Commissioning Plan ✓ ✓ ✓ ✓ Page 7 Revision 1.1 March 5, 2012 Other AU Departments ✓ ✓ R ✓ ✓ ✓ Design Team Cx Manager ✓ AU Facilities Cx Authority AU Construction Mgr AU Project Manager Warranty Acceptance Construction COMMISSIONING TEAM MEMBERS Construction Team Functional Performance Re-Testing Design Planning PROJECT PHASES Warranty Information Hand-off ✓ R Occupant Training Delivery ✓ ✓ ✓ ✓ Deferred Testing ✓ ✓ ✓ R As Built Documentation Review ✓ ✓ ✓ ✓ ✓ R Commissioning Report ✓ ✓ Systems Manual & On-Going Cx Plan ✓ ✓ Warranty Phase Check-up & Meeting ✓ On-Going Commissioning Activities American University Master Commissioning Plan R R ✓ ✓ R ✓ ✓ ✓ ✓ ✓ ✓ R R Page 8 Revision 1.1 March 5, 2012 5 Commissioning Process Flowchart Planning Phase Design Phase Construction Phase Acceptance Phase Warranty Phase On-Going Cx Phase Preliminary Commissioning Plan Design Phase Commissioning Coordination Meetings Construction Phase Commissioning Coordination Meetings Acceptance Phase Commissioning Coordination Meetings Warranty Information Hand-off On-Going Commissioning Activities Owner’s Project Requirements (OPR) Document Basis of Design (BOD) Document Commissioning Schedule Test, Adjust, and Balance (TAB) Report Review Occupant Training Delivery O&M Documentation Planning Submittal Reviews Systems Training Delivery Deferred Testing O&M Training Planning O&M Manual Reviews O&M Training Delivery As-Built Documentation Review Warranty Planning O&M Training Agenda Reviews Prefunctional Checklists Completion Commissioning Report Commissioning Design Reviews Systems Training Planning Functional Performance Test Plans Systems Manual & On-Going Commissioning Plan Preliminary Prefunctional Checklists & Functional Performance Tests Occupant Training Planning Functional Performance Testing Warranty Phase Check-up & Meeting Final Commissioning Plan Final Prefunctional Checklists & Trend Log Specifications Trend Log Review Commissioning Specification Final Functional Performance Tests Commissioning Action List Go to Construction Phase Go to Acceptance Phase Go to Design Phase On-Going Operations On-Going Cx Phase Functional Performance Re-Testing Go to Warranty Phase American University Master Commissioning Plan Page 9 Revision 1.1 March 5, 2012 6 Commissioning Activities Narratives Preliminary Commissioning Plan The Preliminary Commissioning Plan will focus on identifying project-specific commissioning activities, commissioning team members, and roles and responsibilities for all team members as part of the commissioning process. The Preliminary Commissioning Plan will be prepared by the Facilities Management Commissioning Authority and will be incorporated into requests for proposal for Design Team and Commissioning Manager services. Example prefunctional checklists (PFCs) and functional performance test procedures (FPTs) will be included in the Preliminary Commissioning Plan as appendices to demonstrate level of rigor required of future commissioning team members. Owner’s Project Requirements (OPR) Document The Owner’s Project Requirements (OPR) will quantitatively define the performance and operational requirements for the commissioned systems. These performance requirements will be the acceptance criteria against which the systems will be judged. They will include parameters such as temperatures, flows, pressures, moisture content, light fixture types, light levels, warranty information requirements, central system availability/tie-in capability, electrical spare capacity requirements, building automation system requirements, etc. For LEED certification purposes, the OPR must include the following sections: Owner and User Requirements Environmental and Sustainability Goals Energy Efficiency Goals Indoor Environmental Quality Requirements Equipment and System Expectations Building Occupant and Operations and Maintenance Requirements The Facilities Management Commissioning Authority will oversee the development of the OPR, but critical input will be needed from the Project Manager, Occupant/User Groups, and the Design Team. The Commissioning Manager will maintain the OPR throughout the duration of the project, editing as necessary to reflect American University performance expectation changes. American University Master Commissioning Plan Page 10 Revision 1.1 March 5, 2012 Design Phase Commissioning Coordination Meetings The Commissioning Manager will plan, facilitate and document Design Phase Commissioning Coordination Meetings. The coordination meetings are intended to help every team member understand and execute their roles and responsibilities within the commissioning process, to coordinate the details of current and upcoming commissioning activities, and to review outstanding action items. The first meeting will be a Design Phase Commissioning Kickoff Meeting to review the specifics of the Commissioning process, identify representatives to the Commissioning Team, and establish communication and documentation protocols for implementing the Commissioning process as effectively and efficiently as possible. This meeting provides an overview so that the team understands the big picture and the benefits they will accrue by participating in the process. Subsequent Commissioning Coordination Meetings will be held as frequently as deemed necessary by the Commissioning Manager to remain integrated into the Design Phase process and to coordinate Commissioning deliverables into the bid documents. Basis of Design (BOD) Document The Basis of Design (BOD) documents the Design Team’s approach to achieving the requirements of the OPR. It describes the types of equipment to be used, system configurations, systems interactions, and general operating strategies. It also documents any general rules, philosophies, and assumptions made by the Design Team. This document will be created and managed by the Design Team and reviewed by the Facilities Management Commissioning Authority and the Commissioning Manager. Throughout the life of the project, the Commissioning Manager will monitor the design evolution and bring any deviations from the BOD to the attention to the Design Team. If changes to the system design and operational strategies are made during the project, a final BOD will be prepared by the Design Team at the end of construction. Operations & Maintenance (O&M) Documentation Planning In the Construction Phase, the Contractor will facilitate and manage the delivery of accurate, meaningful, and timely operation and maintenance (O&M) documentation to the Facilities Management Commissioning Authority. Planning for this will take place in the Design Phase in order to incorporate project-customized requirements into the contract documents. The Commissioning Manager will participate in the discussion and definition of requirements for O&M documentation (e.g., hardcopy & electronic copy requirements, equipment O&M criteria, planned maintenance schedules, systems manual and on-going commissioning criteria, etc.) with the Facilities Management Commissioning Authority. The Commissioning Manager will American University Master Commissioning Plan Page 11 Revision 1.1 March 5, 2012 coordinate with the Design Team to confirm that project specifications reflect American University’s O&M documentation requirements. Operations & Maintenance (O&M) Training Planning To achieve successful operations & Maintenance (O&M) training delivery, the Facilities Management Commissioning Authority needs to start with a well-thought-out, un-hurried process for planning the training process. The Commissioning Manager will involve the Facilities Management Commissioning Authority as much as possible to define what training the Facilities Management staff needs and wants in order to understand the systems and equipment that they will have to operate. This will involve customizing training to match the level of experience and detail that AU Facilities Management will require for each system. The Commissioning Manager will participate in the discussion and definition of requirements for O&M training (e.g., differentiating between systems and equipment training; addressing levels of training; O&M shift coordination; video recording expectations; training agenda and documentation requirements, etc.) with the Facilities Management Commissioning Authority. The outcome of the training planning process will be an O&M Training Plan matrix to be included in the bid documents. The Commissioning Manager will coordinate with the Design Team to confirm that project specifications reflect American University’s O&M training requirements. Refer to Section 7 for a Training Plan example. Warranty Planning The warranty information requirements will be defined in the contract documents and will define how the warranty information is transitioned from the Contractor to the Facilities Management Commissioning Authority at the end of construction. The Facilities Management Commissioning Authority and the Commissioning Manager will work with the Project Manager to define the warranty information format which will include, at a minimum, master equipment lists; warranty start and end dates; manufacturer contact information; extended warranty (if any) details; planned maintenance activities required to keep equipment under warranty; etc. The Commissioning Manager will coordinate with the Design Team to confirm that project specifications reflect American University’s warranty requirements. Commissioning Design Reviews The Facilities Management Commissioning Authority, the AU Construction Manager, AU Other Departments, and the Commissioning Manager will review the design documents at predetermined design phase milestones (e.g., DD, 50% CD, 100% CD/Permit documents). For LEED certification purposes, at least one commissioning design review at the 50% CD phase is required, along with a backcheck to confirm incorporation of commissioning review comments into the final construction documents. American University Master Commissioning Plan Page 12 Revision 1.1 March 5, 2012 The Commissioning Manager will review the design drawings and specifications for the following commissioning-related items: Compliance with the Owner’s Project Requirements. Clarity of the design. Clear integration requirements between equipment and systems Equipment accessibility and maintainability. Ability to test and validate system operation. O&M Documentation, Training, and Warranty details Comments will be categorized as follows: Critical: Issues which in the Commissioning Manager’s professional opinion are related to a system’s ability to achieve the Owner’s Project Requirements performance criteria. Question: Requests for clarification of intent. Suggestion: Design features which can meet the Owner’s Project Requirements but for which the Commissioning Manager has a recommendation for improved efficiency, increased reliability, and/or lower life cycle cost. Coordination: Although a commissioning review is not a coordination review, the Commissioning Manager will note coordination items noticed during the course of the commissioning review. Along with the Commissioning Manager’s comments, the Commissioning Manager will collect and consolidate comments from the Facilities Management Commissioning Authority and AU Other Departments. The Design Team will respond in writing to each of the comments provided. Refer to Section 7 for the Document Review Template. Preliminary Prefunctional Checklists & Functional Performance Tests The Commissioning Manager will prepare preliminary prefunctional checklists and functional performance test procedures for the systems to be commissioned based on the design documents. There shall be one prefunctional checklist and one functional performance test procedure for each commissioned system. These preliminary documents should be included in the Final Commissioning Plan and incorporated into the bid documents to demonstrate anticipated level of rigor to the Contractor. If project-specific prefunctional checklists and functional performance test procedures cannot be developed, sample documents for similar system types will suffice. Refer to Section 7 for examples of both Prefunctional Checklists and Functional Performance Test Procedures. These examples are intended to communicate format and level of rigor. The actual project checklists and test procedures will be customized to match the final design requirements for each system. American University Master Commissioning Plan Page 13 Revision 1.1 March 5, 2012 Final Commissioning Plan The Commissioning Manager will prepare the Final Commissioning Plan, building on and editing the Preliminary Commissioning Plan to reflect the project at the end of the Design Phase. The systems to be commissioned section will be refined to represent the quantity and types of systems in the final construction documents. Sampling strategies pertaining to the functional performance testing will be detailed in the Final Commissioning Plan. The Final Commissioning Plan will be incorporated into the bid documents by reference. Commissioning Specification The Commissioning Manager will prepare a Commissioning Specification to be included in the construction documents. The Commissioning Specification will detail the Contractor’s responsibilities (as outlined in the Final Commissioning Plan) during the Construction, Acceptance, and Warranty Phases of the project. The Design Team will incorporate the Commissioning Specification into the Division 1 specification section. The Commissioning Specification will include, but not be limited to commissioning-related scheduling; submittal management; prefunctional checklists; functional performance testing; O&M and systems manuals; O&M and systems training; as-built drawings; and warranty management. Furthermore, the Commissioning Specification will include language defining incentive program(s), if applicable, established to encourage Contractor readiness for functional performance testing. The Commissioning Manager will recommend coordination language to be included in other Design Team specification sections that will direct the Contractors’ attention to the Division 1 Commissioning Specification for required commissioning activities. The Design Team will incorporate, as they deem appropriate, the coordination language into their respective specification sections. American University Master Commissioning Plan Page 14 Revision 1.1 March 5, 2012 Construction Phase Commissioning Coordination Meetings The Commissioning Manager will plan, facilitate and document Construction Phase Commissioning Coordination Meetings. The coordination meetings are intended to help every team member understand and execute their roles and responsibilities within the commissioning process, to coordinate the details of current and upcoming commissioning activities, and to review outstanding action items. The first meeting will be a Construction Phase Commissioning Kickoff Meeting to review the specifics of the Commissioning process, identify new representatives to the Commissioning Team, and establish communication and documentation protocols for implementing the Commissioning process as efficiently and effectively as possible. This meeting provides an overview so that the team understands the big picture and the benefits they will accrue by participating in the process. Subsequent Commissioning Coordination Meetings will be held as frequently as deemed necessary by the Commissioning Manager to remain integrated into the Construction Phase process. Frequency will vary throughout the construction as the Commissioning process requirements vary depending on what is happening on the construction site. Commissioning Scheduling There will not be a separate commissioning schedule. The Contractor will be required to incorporate commissioning activities into the master construction schedule. The Commissioning Manager will assist the Contractor, as needed, to understand the relationship between construction and commissioning activities. The Facilities Management Commissioning Authority will regularly review the master construction schedule in order to coordinate the availability of Facilities Management staff for critical commissioning activities. Master construction schedule commissioning milestones will include, but not be limited to, O&M manual submissions; training agenda submissions; training delivery; prefunctional checklist completion; functional performance testing; system manual and on-going commissioning plan submissions; as-built drawing submissions; and the warranty information hand-off. Some of the activities may require multiple milestones due to some systems following a different construction schedule than others. Submittal Reviews The Commissioning Manager will identify submittals associated with systems to be commissioned that need to be reviewed by the Commissioning Manager and Facilities Management staff. The Facilities Management Commissioning Authority, AU Other Departments, and the Commissioning Manager will review the submittals concurrent with the Design Team. American University Master Commissioning Plan Page 15 Revision 1.1 March 5, 2012 The Contractor will send copies of the selected submittals to the Facilities Management Commissioning Authority and to the Commissioning Manager simultaneous with issuing them to the Design Team for review. The Facilities Management and AU Other Departments reviewers will submit their comments to the Commissioning Manager who will consolidate all comments and forward them to the Design Team. The Design team will incorporate the commissioning comments, at their discretion, into their formal submittal review responses to the Contractor. The Design Team will provide written responses to each submittal review comment to the Commissioning Manager. Commissioning submittal review comments will focus on the same areas as the commissioning design reviews (e.g. compliance with the OPR, clarity of the design, integration coordination, accessibility and maintainability, O&M training and documentation requirements, and the ability to test and validate system operation). Refer to Section 7 for the Document Review Template. The Commissioning Manager and Facilities Management Commissioning Authority will be given access to all approved submittals after processing by the Design Team. Operations & Maintenance (O&M) Manual Reviews Early submission of the O&M manuals will help ensure they are complete and approved prior to the start of the AU Facilities Management staff training. The manuals will serve a critical part of the training program. The Commissioning Manager will identify O&M manuals associated with systems to be commissioned that need to be reviewed by the Commissioning Manager and Facilities Management staff. The Facilities Management reviewers will submit their comments to the Commissioning Manager who will consolidate all comments and forward them to the Contractors. O&M Training Agenda Reviews Each training session - represented by a row in the Training Plan (refer to Section 7 for a Training Plan example) - will have a Training Agenda. The Training Agenda requires specific detailed information about the content of its respective session. The agenda will be completed by the Contractor responsible for the training session and will be reviewed by the Facilities Management Commissioning Authority and the Commissioning Manager. The Facilities Management reviewers will submit their comments to the Commissioning Manager who will consolidate all comments and forward them to the Contractors. During delivery of the O&M training sessions, each approved Training Agenda form will be used to document attendees of the training session and to formalize American University’s acceptance of the training. American University Master Commissioning Plan Page 16 Revision 1.1 March 5, 2012 System Training Planning Whereas the O&M Training sessions will pertain to individual pieces of equipment, the Systems Training sessions will focus on how those components are uniquely put together as systems for the project. The Commissioning Manager will facilitate the development of a Systems Training program. The purpose of this training will be to present all of the commissioned systems; their design intent; schematic diagrams; sequences of operation; integration with other systems; and areas of the building served by the systems. Although facilitated by the Commissioning Manager, Systems Training will be a collaborative effort between the Design Team, the Contractors, and the Commissioning Manager; each delivering their area of expertise for each system. Systems training planning will require defining the type and level of training required for the systems; number of sessions; video recording expectations; training agenda; and presentation/documentation materials. The Commissioning Manager will compile Systems Training presentation materials from documents submitted by the Design Team and the Construction Team. Occupant Training Planning With an understanding that some building systems require certain behaviors from building occupants and system users in order to perform as intended, the Commissioning Manager will facilitate the development of an Occupant Training program. The Occupant Training program will introduce, in appropriately technical terms for the occupants, the systems impacting the occupied spaces. The training will also present the various ways in which the occupants may be able to influence system performance (i.e., opening doors and windows, adjusting thermostats, introducing space heaters, moving furniture, overriding occupancy sensors, etc.) and establish ground rules for building occupant behavior. Training planning will require defining the type and level of training required for the project; future occupant coordination; video recording expectations; training agenda; and presentation/documentation materials. Final Prefunctional Checklists & Trend Log Specifications The Commissioning Manager will finalize Prefunctional Checklists (PFCs) customized for each system to be commissioned after reviewing approved submittals, requests for information, change orders, supplemental instructions, and other construction phase modifications and/or additions. The Commissioning Manager will issue final PFCs to the Facilities Management Commissioning Authority for review and comment. Upon incorporation of accepted Facilities Management Commissioning Authority comments, the Commissioning Manager will issue final PFCs for completion and sign-off by the Contractor during final system checkout. The PFCs shall be used to document that key system-level installation, startup, programming, coordination, integration, and testing activities have been completed. These are not contractor American University Master Commissioning Plan Page 17 Revision 1.1 March 5, 2012 quality control checklists for each piece of equipment but system-level confirmation of readiness for the system’s Functional Performance Test. The General Contractor will be responsible for overseeing the completion of the checklists by the Subcontractors, because each system typically requires the participation of multiple Subcontractors to be complete and ready for testing. Examples of Prefunctional Checklist items include, but are not limited to, pipe pressure testing; duct air leakage testing; electrical wiring; major equipment startup; variable frequency drive setup; controls point-to-point checkout; controls programming; test, adjust, and balance completion and issues resolution; successful completion of the contractor-only dry run of the Functional Performance Test, etc. PFCs for systems controlled and /or monitored by central campus energy management system (EMS) include a requirement that building automation system graphics screen is complete, points have been properly mapped to the central EMS, and AU Facilities Management personnel have access to view system status and operation. PFCs for systems controlled and/or monitored by the building automation system also include requirements for building automation system trend logs to be programmed prior to the start of Functional Performance Testing. These requirements will include the points to be trended, the frequency of the trends, and the points to be included together on color graphic trend logs when submitted for review. Final Functional Performance Tests The Commissioning Manager will finalize Functional Performance Test Procedures (FPTs) for each system to be commissioned after reviewing approved submittals, requests for information, change orders, supplemental instructions, and other construction phase modifications and/or additions. The following are the minimum requirements for American University FPTs: Step-by-Step Script FPTs should dictate a chronological list of steps to be followed. The steps should be scripted in an efficient manner, minimizing the level of redundancy between steps as much as practical. The intent of testing is to demonstrate performance of each mode of system operation as effectively and efficiently as possible. Repeatable Although the Commissioning Manager will develop and oversee the execution of FPTs when they are implemented at the end of construction, the test procedures are required to be designed to be referenced by future Facilities Management staff for recommissioning purposes. As such, the test procedures should be designed to stand alone and be understood by reasonably knowledgeable building operations personnel without the Commissioning Manager’s involvement. American University Master Commissioning Plan Page 18 Revision 1.1 March 5, 2012 The action required for each step should not be open to interpretation in the field. For example, a step that reads, “Put the system into economizer mode,” does not explain how that should be done. The Commissioning Manager should define whether that should be accomplished by overriding outdoor air inputs, overriding return air inputs, changing setpoints, overriding the economizer mode software point, or some other method appropriate for the system and sequence being tested. Given the differences between building automation systems and their programming, a systems’ reaction is likely to vary depending on how the action is performed. To the greatest extent practical, this needs to be understood by the Commissioning Manager prior to the start of field testing. Unambiguous Pass/Fail Acceptance Criteria For each step of the test procedure, there should be a pass/fail definition of acceptable response. This typically is a description of how each device in a system is designed to react to the scripted action imposed on the system. In the interest of field testing efficiency, the acceptance criteria should be clearly defined in terms that everyone in the field can understand and agree on. Valves and dampers should “open” or “close;” fans and pumps shall “start” or “stop;” modulating devices shall “modulate higher” or “modulate lower.” Simply stating that the system should respond “as specified,” is not acceptable in an FPT procedure. Customized Each test procedure must reflect the final design and approved shop drawings for the unique systems in each project. There should be nothing “not applicable” in a project’s FPT, i.e., if a step or reaction is not applicable, it should be removed from the procedure. Sampling Strategies The Contractor can employ a sampling strategy to functionally test a fraction of the total number of non-life safety or non-critical equipment that are identical or near identical pieces of equipment (e.g., terminal units, occupancy sensors, exhaust fans, etc.). The sampling strategy must be well-defined and approved by AU Facilities during the Design Phase and documented in the Final Commissioning Plan and the Commissioning Specification. The sampling strategy must define the applicable project-specific equipment, the percent of randomly selected equipment to be tested, the failure rate threshold, and recourse plan if excessive failures are discovered. The Mechanical, Electrical, TAB, and Controls Contractors will review and comment on the efficiency and safety of the proposed test steps, and the Facilities Management Commissioning Authority will review for completeness and rigor. The Commissioning Manager will incorporate Facilities Management Commissioning Authority’s and the Contractors’ recommendations as appropriate. It is the review activity that helps prevent surprises in the field on test day. Upon incorporation of the accepted Facilities Management Commissioning Authority and Contractor American University Master Commissioning Plan Page 19 Revision 1.1 March 5, 2012 comments, the Commissioning Manager will issue final FPTs for use in the system functional performance testing process. Refer to Section 7 for examples of both Prefunctional Checklists and Functional Performance Test Procedures. These examples are intended to communicate format and level of rigor. The actual project checklists and test procedures will be customized to match the final design requirements for each system. American University Master Commissioning Plan Page 20 Revision 1.1 March 5, 2012 Acceptance Phase Commissioning Coordination Meetings The Commissioning Manager will plan, facilitate and document Acceptance Phase Commissioning Coordination Meetings. These meetings will be heavily focused on system readiness for Functional Performance Testing and scheduling of that testing. Acceptance Phase Commissioning Coordination Meetings will be held as frequently as deemed necessary by the Commissioning Manager to keep the Commissioning process on track for completion prior to Substantial Completion. Test, Adjust, and Balance (TAB) Report Review The TAB Contractor will prepare a balancing report documenting that all air and hydronic systems have been adjusted and are within acceptable design values. The Facilities Management Commissioning Authority and the Commissioning Manager will review the report submitted by the TAB Contractor, concurrent with the Design Team as the TAB Contractor completes work on individual systems (i.e., not all systems need to be balanced before the reporting process begins). The Commissioning Manager will verify that all required data has been collected, that the measured results are in compliance with the design documents, and that any non-compliance items have been resolved and rebalanced prior to the start of Functional Performance Testing. The Facilities Management reviewers will submit their comments to the Commissioning Manager who will consolidate all comments and forward them to the Design Team. The Design team will address these comments, incorporating them as appropriate into their formal TAB report review response to the Contractor. The Design Team will provide written responses to each TAB report review comment to the Commissioning Manager. Refer to Section 7 for an example of the Document Review Template. Systems Training Delivery The Commissioning Manager will facilitate the scheduling of Systems Training with the Facilities Management Commissioning Authority, the Design Team, and the Construction Team. The training events will be coordinated for the convenience of the trainees, i.e., between shifts, manageable amounts of training at a time to accommodate trainees’ other responsibilities, etc. The Commissioning Manager will lead the Systems Training sessions with most agenda items presented by members of the Design Team and Construction Team. The Facilities Management Commissioning Authority will schedule and coordinate the video recording of the Systems Training sessions with American University resources. American University Master Commissioning Plan Page 21 Revision 1.1 March 5, 2012 O&M Training Delivery After the Training Agendas have been reviewed and accepted by the Facilities Management Commissioning Authority, the Commissioning Manager will convene a meeting with the Contractors and the Facilities Management Commissioning Authority to schedule the individual O&M Training sessions. The training events will be coordinated for the convenience of the trainees, i.e., between shifts, small amounts of training at a time to accommodate trainees’ other responsibilities, etc. Training will be concurrent with equipment start-up by the Contractor. The Contractor will formally document each training session and the acceptance of the training. Documentation of Facilities Management acceptance will require that someone representing the trainees formally and in writing accept each training session as complying with that session’s Training Agenda. The Commissioning Manager will collect this documentation in the form of fully executed Training Agendas and include them as part of the Final Commissioning Report. The Facilities Management Commissioning Authority will schedule and coordinate the video recording of the O&M Training sessions with American University resources. Prefunctional Checklists Completion The prefunctional checklists are used to document that the systems are fully installed, connected, started-up, programmed, integrated and have successfully passed their respective Functional Performance Tests in a contractor-only dry run. Fully executed Prefunctional Checklists are the Contractor’s validation that the systems are ready for successful Functional Performance Testing witnessed by Facilities Management and the Commissioning Manager. The Prefunctional Checklists will be documented in writing by personnel representing the responsible Contractors; multiple Subcontractors will need to sign-off on each system’s checklist. These checklists are primarily inspections and procedures to prepare the equipment or system for initial operation (e.g., oil levels, fan belt tension, labels affixed, gauges in place, sensor calibration, etc.). However, some checklist items entail simple testing of a component, a piece of equipment or system (such as measuring the voltage imbalance on a three phase pump motor of a chiller system). Each piece of equipment is to receive full checkout by the Contractors. No sampling strategies will be permitted. All building automation system trend logs required for a system must be programmed and collecting data before the PFCs are completed and submitted by the Contractors. Functional Performance Test Plans The Commissioning Manager will prepare and distribute Functional Performance Test Plans prior to the start of Functional Performance Testing. This will allow the Construction Team to review the proposed testing schedule; to understand which test procedures will be conducted during a specific testing period; to schedule the appropriate people to be in attendance for each test; and to verify that the necessary equipment is available when testing begins. American University Master Commissioning Plan Page 22 Revision 1.1 March 5, 2012 The Facilities Management Commissioning Authority will schedule Facilities Management staff to participate in and witness Functional Performance Testing based on the schedule outlined in each Test Plan. Functional Performance Testing Functional Performance Testing is the technical culmination of the Commissioning process for systems acceptance by the Facilities Management Commissioning Authority and should be performed prior to Substantial Completion. The Commissioning Manager will field-direct, witness, and document the Functional Performance Test Procedure (FPT) for each system to be commissioned. Although the Commissioning Manager directs the tests, the Contractors will manipulate the systems and controls in accordance with the FPTs reviewed and accepted by all team members before the start of testing. The Facilities Management representatives will witness and participate in the Functional Performance Testing, as determined by Facilities Management, to understand how the systems operate and how optimal performance can be maintained. Trend Log Review The Contractor will download and submit electronic trend data to the Commissioning Manager for review at a time scheduled by the Facilities Management Commissioning Authority and the Commissioning Manager. This may be prior to the start of Functional Performance Testing, immediately following Functional Performance Testing, or after occupancy. The trend data will be submitted in editable spreadsheet format and in color graphs designed as specified in the Prefunctional Checklist for each affected system. Any trend logs demonstrating performance not meeting the construction document requirements will be re-run, following remediation of the problems, and re-submitted to the Commissioning Manager for review. Commissioning Action List The Commissioning Manager will maintain a Commissioning Action List - starting in the Design Phase and continuing through the Warranty Phase - to track the status of all Commissioningrelated items. The Commissioning Action List includes process-related and technical-related issues associated with successful completion of the Commissioning process. For each deficiency found during Functional Performance Testing, the Commissioning Manager will add the item to the Commissioning Action List. The Commissioning Action List is the vehicle for communicating, tracking, and documenting the status and correction of each deficiency. The Commissioning Manager shares the Commissioning Action List with the Contractors who inform the Commissioning Manager in writing upon correction of each problem with an American University Master Commissioning Plan Page 23 Revision 1.1 March 5, 2012 explanation of what was done to resolve the issue. If the Functional Performance Test demonstrates a system performs as designed but does not meet the OPR criteria for that system, the associated Commissioning Action List item will be assigned to the Design Team to engage them in the issue resolution process. Upon notification of the completion of a Commissioning Action Item, the Commissioning Manager will schedule re-testing for the affected system to verify satisfactory resolution of the deficiency. Refer to Section 7 for the Commissioning Action List template. Functional Performance Re-Testing The Commissioning Manager will field-direct, witness, and document Functional Performance Re-Testing for each system that failed to pass its initial FPT. For systems tested with a sampling strategy, as defined in the Final Functional Performance Test Procedures, additional samples will need to be tested during re-testing if the failures of the initial sample exceed the failure rate threshold. The extent and level of rigor of retesting will be as the Commissioning Manager deems necessary to confirm successful resolution of the initial deficiencies without sacrificing performance elements which had originally passed the system FPT. Although the Commissioning Manager directs the re-tests, the Contractors will manipulate the systems and controls. Facilities Management representatives will witness and participate in the Functional Performance Re-Testing as determined by Facilities Management. American University Master Commissioning Plan Page 24 Revision 1.1 March 5, 2012 Warranty Information Hand-off The Contractor and the AU Construction Manager will provide warranty information to the Facilities Management Commissioning Authority for the commissioned systems. The warranty information will be transferred prior to Substantial Completion and will include, but not be limited to, master equipment list; warranty start and end dates; manufacturer contact information; extended warranty (if any) details; planned maintenance activities required to keep equipment under warranty; etc. The Facilities Management Commissioning Authority will review and approve the warranty information submitted at the end of construction for compliance with the specifications. Occupant Training Delivery The Commissioning Manager will facilitate the scheduling and delivery of Occupant Training with the Facilities Management Commissioning Authority and representatives of the building occupants. The training events will be coordinated for the convenience of the trainees, i.e., between shifts, manageable amounts of training at a time to accommodate trainees’ other responsibilities, etc. The Commissioning Manager will lead the Occupant Training sessions with participation by the Facilities Management Commissioning Authority. The Facilities Management Commissioning Authority will schedule and coordinate the video recording of the Occupant Training sessions with American University resources. Deferred Testing Functional Performance Tests (FPTs) may need to be deferred until after Substantial Completion for a variety of reasons. The most common reasons include (1) HVAC systems may need to have different weather conditions than those at the end of construction and (2) commissioned systems may need to have a load put on them before testing can be considered meaningful. FPTs that occur after Substantial Completion will be conducted, documented, and tracked in a manner identical to the Acceptance Phase process. As-Built Documentation Review The AU Construction Manager will provide the Facilities Management Commissioning Authority with as-built documentation including, but not limited to, (1) record installation drawings and (2) the final building automation system controls manual. The as-built building automation system controls manual will include the final “as commissioned” system schematics, sequences of operations, setpoints, and alarm limits. These documents will be reviewed by the Commissioning Manager and Facilities Management staff. The Facilities Management reviewers will submit their comments to the Commissioning American University Master Commissioning Plan Page 25 Revision 1.1 March 5, 2012 Manager who will consolidate all comments and forward them to the AU Construction Manager for resolution by the Design and Construction Teams. Commissioning Report Following resolution and/or acceptance of all Commissioning Action Items, the Commissioning Manager will prepare the Commissioning Report. The report will be a compilation of documentation (both technical and process-related) associated with the Commissioning process. It will be prefaced with an Executive Summary documenting the final system status compared to the Owner’s Project Requirements document. The Commissioning Report will include at least the following sections: 1. Introduction 2. Executive Summary 3. Owner’s Project Requirements 4. Basis of Design 5. Commissioning Plan 6. Commissioning Specification Section 7. Commissioning Action List 8. Commissioning Coordination Meeting Minutes 9. Warranty Phase Check-up Meeting Minutes 10. Design Review Comments 11. Submittal Review Comments 12. TAB Report Review Comments 13. As-Built Documentation Review Comments 14. O&M Manual Review Comments 15. O&M Training Plan 16. O&M Training Agendas (fully executed) 17. Systems Training Agendas 18. Occupant Training Agendas 19. Prefunctional Checklists (fully executed) 20. Functional Performance Test Plans 21. Blank Functional Performance Test Procedures The Commissioning Manager will submit the Commissioning Report to the Facilities Management Commissioning Authority for review. The Commissioning Manager will amend the Commissioning Report at the end of the Warranty Phase to document pertinent Warranty Phase activities, findings, decisions, etc. American University Master Commissioning Plan Page 26 Revision 1.1 March 5, 2012 Systems Manual & On-Going Commissioning Plan The Commissioning Manager will collect and compile the Systems Manual & On-Going Commissioning Plan, based on American University standards for this document. At a minimum, these document shall include the following for the commissioned systems: Owner’s Project Requirements Basis of Design Integrated Building Systems Operating Instructions System Schematic Diagrams As-Built Control Sequences of Operation and Initial Setpoints Planned Maintenance Activities and Recommended Frequencies Recommended Control System Sensor & Actuator Calibration Frequencies Recommended Building Automation System Trend Logs for On-Going Commissioning Monitoring and Evaluation 9. Recommended System Re-Testing Frequencies 10. Blank Functional Performance Test Procedures for Re-Testing 1. 2. 3. 4. 5. 6. 7. 8. In the Design Phase the Commissioning Manager will prepare an outline of the Systems Manual & On-Going Commissioning Plan along with assigned roles and responsibilities for project team members to produce the various elements of the document. These requirements will be incorporated into the Commissioning Specification and included in the bid documents. During the Construction Phase, the Commissioning Manager, Design Team, and Construction Team will prepare a preliminary schedule of when each element will be submitted to the Commissioning Manager over the course of the project. The Commissioning Manager will submit the Systems Manual & On-Going Commissioning Plan to the Facilities Management Commissioning Authority for review. Warranty Phase Check-up & Meeting No later than 2 month before the end of the Warranty Phase, a warranty meeting will be planned, facilitated, and documented by the Commissioning Manager. This meeting is an opportunity for Facilities Management and other AU Department representatives to provide feedback on the effectiveness and efficiency of the new equipment and systems. The Design Team and Construction Team are required to participate in the warranty meeting. The Facilities Management Commissioning Authority will oversee the collection of operations issues, concerns, challenges, etc., throughout the Warranty Phase in order for the warranty meeting to be as comprehensive and meaningful as practical. Information received by the Design Team and Construction Team will be used to track and correct warranty-related issues; to contribute to future Owner's Project Requirements documents; and to refine American University’s project delivery process. American University Master Commissioning Plan Page 27 Revision 1.1 March 5, 2012 On-Going Commissioning Activities AU Facilities addresses changes in occupancy, use, maintenance and repair and makes periodic adjustments and reviews of building operating systems and procedures essential for optimal energy efficiency and service provision. American University Master Commissioning Plan Page 28 Revision 1.1 March 5, 2012 7 Commissioning Documentation A. Commissioning Action List Template B. Document Review Template C. Training Plan Example D. Training Agenda Example E. Example Prefunctional Checklists F. Example Functional Performance Test Procedures American University Master Commissioning Plan Page 29 Revision 1.1 March 5, 2012 AMERICAN UNIVERSITY COMMISSIONING ACTION LIST TEMPLATE ACTION ITEM # 1 DATE LOGGED 02/20/12 2 02/20/12 3 02/20/12 ENTRY TYPE Meeting Minutes Document Review Verbal 4 02/20/12 5 6 RESPONSIBLE TEAM MEMBER(S) ITEM DESCRIPTION AU Submit requested documentation Review RFIs for commissioningCx manager related issues. QSE Submit requested documentation Correct deficiency QSE TECHNICAL CATEGORY General COMMENT GENERATOR MEM General MEM General MEM Site Observation General CEM 02/20/12 Verification Testing Mechanical RTE Controls Contractor 02/20/12 Meeting Minutes Mechanical MSM Controls Contractor Correct system schematic in as-built controls documentation. Perform point-to-point checkout of control system points mapped to the campus front end computer after communications have been established. STATUS OPEN EXPECTED COMPLETION DATE 2/22/2012 STATUS UPDATE CLOSE DATE 2/21/12: Documentation submitted 02/21/12: This was the problem, this is how it was fixed. Cx Manager to verify. 02/21/12 ON GOING CLOSED 2/22/2012 READY TO VERIFY 2/22/2012 AS BUILTS 2/22/2012 DEFERRED 12/31/12 7 8 9 American University Commissioning Action List Template 2/23/2012 Page 1 of 1 AMERICAN UNIVERSITY COMMISSIONING REVIEW COMMENTS TEMPLATE American University Comment Number MECHANICAL Project Name Document Set (Name, Date) C = Critical CO = Coordinate S = Suggestion Q = Question E = Energy Initial Comment Date Comment Generator Type Number Date System(s) CO 3/7/2011 RTE Dwg M4.1 2/21/2012 HVAC M001 M002 C Reference 3/7/2011 RTE Spec 15823 2/21/2012 HVAC Status Commissioning Review Comment Design Team Response The hot water supply pipe riser going up from Will be corrected in 100% CD CLOSED the 2nd floor is not shown entering the 3rd documents. floor. OPEN Commissioning Manager Backcheck Confirmed corrected. If the boiler manufacturer's control panel is to control the boilers and their on/off/modulating control, this specification section should include a sequence of operation for that control. Also, the points to be shared between the boiler control panel and the central automation system need to be define. ELECTRICAL E001 LIFE SAFETY L001 American University Review Comments Template Page 1 of 1 2/23/2012 EXAMPLE: O&M STAFF EQUIPMENT TRAINING PLAN Description Scope 1 EQUIPMENT Spec Section Pre-Occ 1Pre-Occ 1Pre-Occ Scope A Scope B Scope C Post-Occ Hours Hours Hours Hours Trainer Information MECHANICAL Heat Pumps Heat Pumps Hydronic Pumps Hydronic Pumps Rooftop Units Rooftop Units Energy Recovery Units/Heat Recovery Units Energy Recovery VAV Terminal Units VAV Terminal Terminal Heaters (UH, BBH, IFR) Terminal Heaters Guard Shack Air Conditioning Unit ACU Exhaust Fans Makeup Air Units HVLS Fans Direct Steam Heater Domestic Hot Water Mixing Valves VFDs Plant Systems Controls Office Systems Controls ELECTRICAL Lighting Controls 4 4 2 Total Hours Video Recorded Primary Responsible Contractor 8 Mech 2 Mech 4 4 8 Mech 4 4 8 Mech 2 Mech 1 Mech 2 1 2 Exhaust Fans Makeup Air Units HVLS Fans Direct Steam Domestic Hot Water VFDs 1 2 Plant Systems Office Systems Lighting Controls 2 Mech 8 Mech 1 1 Mech 2 2 Mech 1 1 Mech 2 4 Mech/Elec 8 4 12 Mech 8 4 12 Mech 8 4 12 Elec 4 Company E-mail Phone number Date Time Tracking Location Agenda Approved Training Session Complete Training Session Approved Mech 1 4 Name Scheduling 1 General Scope Codes (refer to the specific equipment Training Agenda for additional details) A. Provide an overview of the purpose and operation of this equipment, including required interactions of trainees with the equipment. (Approximately 15 to 30 minutes) B. At an intermediate level , provide technical information regarding the purpose, operation and maintenance of this equipment, expecting that serious malfunctions will be addressed by factory reps. (Approximately 1 to 2 hours) C. At a very technical level , provide information regarding the purpose, operation, troubleshooting and maintenance of this equipment, expecting that almost all operation, service and repair will be provided by the trainees. (Hours vary by level of complexity.) American University Page 1 of 1 12-15-2008 Training Plan Example EXAMPLE VAV TERMINAL UNITS WITH REHEAT RADIATION PREFUNCTIONAL CHECKLIST THIS FORM TO BE COMPLETED BY GENERAL CONTRACTOR NAME: ________________________________________________ Contractor Notes ACCEPTANCE CRITERIA DEVICE LOCATIONS VAV box controller, reheat shutoff valves, strainer, reheat 1 control valve, and volume damper are easily accessible. 2 VAV box, reheat coil, and radiation are replaceable without removing other systems (ductwork, conduit, piping, etc.). VAV thermostat is not subjected to direct sunlight or other temperature influencing sources. POWER AND COMMUNICATION 3 VAV 0-067 VAV 1-025 DATE APPROVED DATE APPROVED DATE APPROVED DATE APPROVED DATE APPROVED DATE APPROVED 4 Control damper responds to BMS commands. DATE APPROVED DATE APPROVED 5 Hot water reheat control valve responds to BMS commands. DATE APPROVED DATE APPROVED 6 Radiation control valve responds to BMS commands. DATE APPROVED DATE APPROVED 7 BMS graphics screen is complete and points have been properly mapped to the central energy management system (EMS) DATE APPROVED DATE APPROVED DATE APPROVED DATE APPROVED DATE APPROVED DATE APPROVED DATE APPROVED DATE APPROVED 11 DATE APPROVED DATE APPROVED 12 Successful leak test results submitted (233600-3.3). DATE APPROVED DATE APPROVED 13 Successful operational test results submitted (233600-3.3). DATE APPROVED DATE APPROVED DATE APPROVED DATE APPROVED System is able to fully execute all steps of the sequence of operations and is able to maintain all system setpoints. SENSOR CALIBRATION Airflow sensor is calibrated and showing accurate values at 9 the BMS front-end computer. 8 10 Thermostat temperature sensor is calibrated and showing accurate values at the BMS front-end computer. Local thermostat temperature setpoint matches BMS temperature setpoint. EQUIPMENT STARTUP AND QUALITY CONTROL TESTS REPORTS & DOCUMENTATION 14 Associated air handling unit PFC has been submitted. 15 Air side testing, adjusting, and balancing information has been submitted and deficiencies corrected. DATE APPROVED DATE APPROVED 16 Water side testing, adjusting, and balancing information has been submitted and deficiencies corrected. DATE APPROVED DATE APPROVED American University Cx Plan Prefunctional Checklist Page 1 of 1 E1 PFC Terminal Units EXAMPLE.xls EXAMPLE LIGHTING CONTROLS PREFUNCTIONAL CHECKLIST THIS FORM TO BE COMPLETED BY GENERAL CONTRACTOR NAME: ________________________________________________ Lighting Control System Service Area Contractor Notes ACCEPTANCE CRITERIA INSTALLATION Lighting Controller located and mounted in a location where 1 audible noise is acceptable DATE APPROVED 2 Lighting Controller voltage wiring is at least six (6) feet from sound and electronic equipment wiring. DATE APPROVED 3 Clearance on left and right side of the relay cabinets is 1 1/2 " or greater DATE APPROVED 4 Lighting Control cabinets are easily accessible for adjustment, repair, and replacement. DATE APPROVED 5 Cabinets are cleaned of all dust, debris, metal particles. DATE APPROVED 6 Relay cabinet anchored and supported per manufacturer's recommendations DATE APPROVED 7 Boardroom Dimming system installation complete and operational DATE APPROVED 8 Ultrasonic ceiling mounted occupancy sensors are located a minimum of six (6) feet from HVAC supply/return vents DATE APPROVED 9 Sensors mounted over doorways are placed one (1) foot inside threshold. DATE APPROVED 10 All occupancy sensors are easily accessible for adjustment, repair, and replacement. DATE APPROVED 11 All daylight photosensors are easily accessible for adjustment, repair, and replacement. DATE APPROVED 12 Digital Pushbutton Stations are installed and operate designated light fixtures according to the construction documents. DATE APPROVED 13 Outdoor photocell is mounted facing northern sky and pointed away from nighttime light sources. DATE APPROVED 14 Component/subsystems are clearly and correctly identified with temporary/permanent labels DATE APPROVED 15 Fluorescent ballasts are installed such that both lighting fixture and ballast are grounded. DATE APPROVED 16 Dedicated power circuit provided and used only for power to the control electronics in the relay cabinets DATE APPROVED 17 Minimum 18AWG stranded wire installed for all low voltage wiring DATE APPROVED 18 All field wiring is completed DATE APPROVED American University Cx Plan Prefunctional Checklist Checklist Page 1 of 3 E2 PFC Lighting Controls.xls EXAMPLE LIGHTING CONTROLS PREFUNCTIONAL CHECKLIST THIS FORM TO BE COMPLETED BY GENERAL CONTRACTOR NAME: ________________________________________________ Lighting Control System Service Area 19 20 21 22 23 23.a 23.b 23.c Contractor Notes ACCEPTANCE CRITERIA All connections securely fastened in accordance with recommended torque values Verify labeling of field and interconnecting wiring is completed Verify circuit breakers feeding lighting circuits are rated for intended purpose For best lamp life, verify installed fluorescent lamps have a logged 100 hours of operation prior to any dimming or testing of dimming. Network installation(s) is per manufacturer's recommendations: Manufacturer's recommended network wiring has been installed Network cable not in close proximity to AC wiring and all control/power wiring in conduit Network cable is run separately from line voltage and does not pass near any source of electrical noise such as fluorescent circuits or motor wiring. DATE APPROVED DATE APPROVED DATE APPROVED DATE APPROVED DATE APPROVED DATE APPROVED DATE APPROVED DATE APPROVED 23.d Network drain/shields are tied together at connectors. DATE APPROVED 23.e Network drain/shields are grounded at one point only DATE APPROVED Last control station or dimmer cabinet on each end of network run has been terminated with jumper per manufacturer's requirements. No bare conductors showing at terminations on low voltage 23.g input wiring. SAFETY DEVICES Emergency input contact to Lighting Controllers (including Mini Z 24 daylight harvest controllers) wired if applicable 23.f American University Cx Plan Prefunctional Checklist Checklist DATE APPROVED DATE APPROVED DATE APPROVED Page 2 of 3 E2 PFC Lighting Controls.xls EXAMPLE LIGHTING CONTROLS PREFUNCTIONAL CHECKLIST THIS FORM TO BE COMPLETED BY GENERAL CONTRACTOR NAME: ________________________________________________ Lighting Control System Service Area Contractor Notes ACCEPTANCE CRITERIA POWER AND COMMUNICATION 25 All occupancy sensors activate the appropriate light fixtures. DATE APPROVED 26 All daylight photosensors are connected, programmed and operating properly. DATE APPROVED 27 Exterior lighting photocell connected, programmed and operating properly. DATE APPROVED 28 Digital Pushbutton Stations connected, programmed and operating properly. DATE APPROVED 29 Dimming system Class 2 Wiring installed as required by manufacturer's requirements including use of CAT5 wiring DATE APPROVED 30 All control system programming is complete DATE APPROVED Control system programs backed up to prevent loss during power outage as applicable. SENSOR CALIBRATION All occupancy sensors have been set to the time delays outlined 32 in the OPR. 31 DATE APPROVED DATE APPROVED 33 All daylight photosensors have been set to the light levels outlined in the OPR or at minimum levels per IESNA standards DATE APPROVED 34 Exterior photocell has been set DATE APPROVED EQUIPMENT STARTUP AND QUALITY CONTROL TESTS Each circuit has been tested for short circuits before connection 35 to relay. Proper operation of each relay has been verified by using the override buttons REPORTS & DOCUMENTATION 36 37 DATE APPROVED DATE APPROVED None. American University Cx Plan Prefunctional Checklist Checklist Page 3 of 3 E2 PFC Lighting Controls.xls EXAMPLE MV SWITCHGEAR ATO PREFUNCTIONAL CHECKLIST THIS FORM TO BE COMPLETED BY GENERAL CONTRACTOR NAME: ________________________________________________ MV ATO Service Area All Contractor Notes ACCEPTANCE CRITERIA Switchgear Automatic Transfer Operation (ATO) 1 Wiring is completed (interconnection, control power etc.) DATE APPROVED 2 Control wiring has been verified. DATE APPROVED 3 Temporary control power is available so the operation of the switches can be verified before the utility energizes the feeders. DATE APPROVED 4 Switches have been opened and closed manually and using the controls on the front panel. DATE APPROVED 5 The sequence of operation has been successfully performed (automatic transfer operation). DATE APPROVED 6 Temporary Power available for test equipment. DATE APPROVED 7 Installation is complete and ready for verification testing. DATE APPROVED American University Cx Plan Prefunctional Checklist E3 PFC EXAMPLE MV Switchgear w ATO.xls Page 1 of 1 EXAMPLE GENERATOR PREFUNCTIONAL CHECKLIST THIS FORM TO BE COMPLETED BY GENERAL CONTRACTOR NAME: ________________________________________________ Engine Generator Service Area All Contractor Notes ACCEPTANCE CRITERIA Engine Generator Ground bus(ses) have been installed and terminated to 1 ground grid system DATE APPROVED 2 Permanent labels for bus, section, breakers and devices installed DATE APPROVED 3 Electrical equipment clean of construction debris, dust, and moisture and egress routes from electrical room are unobstructed. DATE APPROVED 4 All bolted connections securely fastened in accordance with recommended torque values DATE APPROVED 5 Generator neutral bus is solidly grounded by factory-installed bonding jumper as specified for a four-pole system DATE APPROVED 6 Generator frame and enclosure bonded to ground DATE APPROVED 7 Generator anchored in place according to manufacturer’s recommendations DATE APPROVED 8 All bolted electrical connections have been tightened to their proper torque values. (Note: some connections will be disconnected as part of the functional testing. These connections will be field torqued to proper settings at the conclusion of the field-testing.) DATE APPROVED 9 Manufacturer’s field service personnel have completed preliminary checkout and startup DATE APPROVED 10 Engine lube oil system is fully operational and free of leaks DATE APPROVED 11 Engine coolant system is fully operational and free of leaks DATE APPROVED 12 Fuel supply system tank is full and ready for operation DATE APPROVED 13 Engine exhaust is fully operational and free of leaks DATE APPROVED 14 Engine exhaust has rain cap installed at exterior outlet DATE APPROVED 15 Engine exhaust has condensate drain installed at silencer DATE APPROVED 16 Batteries are fully charged and in service DATE APPROVED Generator remote annunciation panel is remotely installed, 17 electrically connected and fully operational to comply with NFPA 110, Level 1 system. DATE APPROVED American University Cx Plan Prefunctional Checklist Page 1 of 2 E4 PFC EXAMPLE Generator.xls EXAMPLE GENERATOR PREFUNCTIONAL CHECKLIST THIS FORM TO BE COMPLETED BY GENERAL CONTRACTOR NAME: ________________________________________________ Engine Generator Service Area All Contractor Notes ACCEPTANCE CRITERIA Generator remote E-stop is remotely installed, electrically 18 connected and fully operational to comply with NFPA 110, Level 1 system DATE APPROVED Generator control wiring to building management control panel is installed, electrically connected and fully operational DATE APPROVED All Overcurrent protective devices have been installed at the 20 proper ampere rating and all settings have been adjusted to match the final approved system Coordination Study. DATE APPROVED 21 Utility Power is available and connected for system operation DATE APPROVED 19 22 All status and alarm indicators are installed and functioning properly. DATE APPROVED All field and interconnecting wiring is completed and labeled 23 at each end with visible and readable tags, printed markings on the conductors are NOT acceptable DATE APPROVED Testing agency or manufacturer's representative has been 24 scheduled to perform the test and the commissioning authority has been notified of the testing date. DATE APPROVED Test equipment requirements have been reviewed with the testing agency or manufacturer's representative. DATE APPROVED 25 26 Power available for test equipment. DATE APPROVED 27 Installation is complete and ready for verification testing. DATE APPROVED American University Cx Plan Prefunctional Checklist Page 2 of 2 E4 PFC EXAMPLE Generator.xls THIS FORM TO BE COMPLETED BY GENERAL CONTRACTOR NAME: ________________________________________________ EXAMPLE AUTOMATIC TRANSFER SWITCH PREFUNCTIONAL CHECKLIST Automatic Transfer Switch Service Area All Contractor Notes ACCEPTANCE CRITERIA Automatic Transfer Switch 1 Electrical room grounding system complete. DATE APPROVED 2 Ground bus(ses) have been installed and terminated to ground grid system DATE APPROVED 3 Doors to electrical room installed and locks or temporary security measures installed. DATE APPROVED 4 Electrical room clear of storage, temporary equipment, etc. DATE APPROVED 5 6 7 Permanent labels for bus, section, breakers and devices installed Electrical equipment clean of construction debris, dust, and moisture and egress routes from electrical room are unobstructed. All bolted connections securely fastened in accordance with recommended torque values DATE APPROVED DATE APPROVED DATE APPROVED 8 Working clearances meet NEC and contract documents and ATS has been installed on a level housekeeping pad DATE APPROVED 9 ATS anchored per manufacturer’s instruction DATE APPROVED 10 All enclosure panels and doors in place, fitted, undamaged DATE APPROVED All field and interconnecting wiring is completed and labeled 11 at each end with visible and readable tags, printed markings on the conductors are NOT acceptable DATE APPROVED NORMAL and EMERGENCY sources are available for testing. DATE APPROVED 12 All settings have been adjusted to Engineer's provided settings. Testing agency has been scheduled to perform the test and 14 the commissioning authority has been notified of the testing date. Test equipment requirements have been reviewed with the 15 testing agency. 13 16 Installation is complete and ready for verification testing. American University Cx Plan Prefunctional Checklist DATE APPROVED DATE APPROVED DATE APPROVED DATE APPROVED Page 1 of 1 E5 PFC EXAMPLE Automatic Transfer Switch.xls EXAMPLE VAV WITH REHEAT AND PERIMETER HEAT FUNCTIONAL PERFORMANCE TEST Passed 0 Tested 0 Pass? Initial Test Date ? Retest 1 ? Retest 2 ? VAV 0-067 Room(s) Served Max Cooling CFM Min Cooling CFM Max Heating CFM Min Heating CFM Occupied Space Temperature Cooling Setpoint Occupied Space Temperature Heating Setpoint ACTION DEVICE LOCATIONS 1 Observe VAV box 2 Observe reheat coil location. 3 4 5 Observe reheat hot water valve location Observe perimeter radiation hot water valve location VAV 1-025 2,400 1,200 2,400 1,200 VAV 1-061 1,100 1,050 1,100 1,050 2,400 1,200 2,400 1,200 Notes ACCEPTANCE CRITERIA Removable without removing ductwork or piping. Re-heat coil removable without removing ductwork or piping. Accessible for maintenance or replacement Accessible for maintenance or replacement Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Airflow increases to cooling maximum CFM. Pass? Pass? Pass? Reheat valve is closed. Pass? Pass? Pass? Pass? Pass? Pass? Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Pass? Pass? Pass? Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Observe temperature sensor location Temporary location TEST INITIATION 6 Record Initial Performance Parameters Space temperature setpoint Space temperature VAV discharge temperature Supply airflow setpoint Supply airflow Damper position Reheat valve position Perimeter heating valve position OCCUPIED COOLING 7 8 Perimeter heating valve is closed. Override the space temperature to: cooling setpoint plus 4 F. (Or adjust Record airflow setpoint control setpoints to achieve the same Record airflow system reaction.) Record damper position VAV discharge temperature is about equal to the AHU discharge air temperature. Record VAV discharge temperature Override the space temperature to: VAV airflow. cooling setpoint minus 1.5 F. (Or Reheat valve position. adjust control setpoints to achieve the Perimeter heating valve position. same system reaction.) After 5 to 10 minutes, record the system VAV discharge temperature. parameters. Record damper position American University Cx Plan Functional Performance Test Page 1 of 2 F1 FPT Terminal Units EXAMPLE.xlsx EXAMPLE VAV WITH REHEAT AND PERIMETER HEAT FUNCTIONAL PERFORMANCE TEST Passed 0 Tested 0 Pass? Initial Test Date ? Retest 1 ? Retest 2 ? VAV 0-067 Room(s) Served Max Cooling CFM Min Cooling CFM Max Heating CFM Min Heating CFM Occupied Space Temperature Cooling Setpoint Occupied Space Temperature Heating Setpoint ACTION OCCUPIED HEATING 9 Override the space temperature to: heating setpoint minus 4 F. (Or adjust control setpoints to achieve the same system reaction.) Override the outside air temperature to 39 F (or change perimeter heating lock-out setpoint). VAV 1-025 2,400 1,200 2,400 1,200 VAV 1-061 1,100 1,050 1,100 1,050 2,400 1,200 2,400 1,200 Notes ACCEPTANCE CRITERIA Airflow at heating CFM. Reheat valve opens to100% before the perimeter heating valve opens? Sequence of operation is not clear. Perimeter heating valve opens to 100%. Discharge air temperature increases Record airflow Record damper position Record VAV discharge temperature Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Override the outside air temperature 10 to 41 F (or change the perimeter heating lock-out setpoint). Perimeter heating valve closes. Pass? Pass? Pass? Override the outside air temperature 11 to 39 F (or change the perimeter heating lock-out setpoint). Perimeter heating valve opens. Pass? Pass? Pass? Perimeter heating valve closes to 0% open prior to the reheat valve closing? Sequence of operation is not clear. Pass? Pass? Pass? Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Insert Value Perimeter heating valve position. Insert Value Insert Value Insert Value VAV discharge temperature. Insert Value Insert Value Insert Value Alarm to the operator's console. Pass? Pass? Pass? Alarm to the operator's console. Pass? Pass? Pass? Terminal unit resumes normal operation Pass? Pass? Pass? Override the space temperature to: heating setpoint plus 1.5 F. (Or adjust control setpoints to achieve the VAV airflow 12 same system reaction.) After 5 to 10 Record damper position minutes, record the system Reheat valve position. parameters. UNOCCUPIED MODE 13 Not applicable for this project. ALARMS Override the space temperature to 5 14 F below the space temperature setpoint. Override the space temperature to 5 15 F above the space temperature setpoint. TEST CONCLUSION Deactivate any system over-rides 16 (setpoints, sensors, modes). American University Cx Plan Functional Performance Test Page 2 of 2 F1 FPT Terminal Units EXAMPLE.xlsx EXAMPLE LIGHTING CONTROL SYSTEM FUNCTIONAL PERFORMANCE TEST TEST EQUIPMENT REQUIRED Test Name Light Level Equipment Description Light Level Meter Action Expected Result Status Comments Notes/Reference Initial Date INSTALLATION Prior to functional testing, for best lamp life, verify installed fluorescent lamps have a logged 100 hours of operation prior to any dimming or testing of dimming. a b 1.1 Verify Installation of lighting control devices. c 1.2 Verify installation of lighting controllers Pass? Pass? Outdoor photocell is mounted facing northern sky and pointed away from nighttime light sources. Pass? a Lighting Controller located and mounted in a location where audible noise is acceptable Pass? b Lighting Controller voltage wiring is at least six (6) feet from sound and electronic equipment wiring. Pass? c e f Check the lighting circuit breakers to ensure that they are duty rated. Pass? d d 1.3 Ultrasonic ceiling mounted occupancy sensors are mounted a minimum of six (6) feet from HVAC supply/return vents Sensors mounted over doorways are placed one (1) foot inside threshold. All occupancy and daylight photo sensors are easily accessible for adjustment, repair, and replacement. Clearance on left and right side of the relay cabinets is 1 1/2 " or greater Lighting Control cabinets are easily accessible for adjustment, repair, and replacement. Cabinets are cleaned of all dust, debris, metal particles. Relay cabinet anchored and supported per manufacturer's recommendations Record results in applicable sensor worksheets when checking function of those sensors Pass? Pass? Pass? Pass? a Circuit breaker shall be rated for switching functions “SWD” Pass? a Correct occupancy sensing devices have been installed. Pass? OPEN OFFICE SPACE LIGHTING CONTROL 2.1 Verify that the occupancy sensing devices installed match with drawings, shop drawings and specifications. 2.2 Time controller function controls lighting in Open Office Spaces as expected a b a 2.3 Lighting in open office spaces comes on at __ am and turns off at __ pm. A blink warning occurs 5 minutes prior to lighting shut off. Lighting in each zone turns ON when initiating override Pass? Record results for each Open Office space in Time Clock worksheet Pass? Pass? Verify override control for each lighting zone. American University Cx Plan Functional Performance Test Page 1 of 6 Lighting Control F2 FPT EXAMPLE Lighting Controls.xls EXAMPLE LIGHTING CONTROL SYSTEM FUNCTIONAL PERFORMANCE TEST 2.3 Action Verify override control for each lighting zone. b c 2.4 2.5 Verify daylighting control within open office spaces. a Before __ am or after __ pm and after lighting in a particular zone has automatically turned off, walk by occupancy sensor and confirm that lighting controlled by the occupancy sensor turns on. Pass? Record results for each sensor in Occupancy Sensor worksheet. Note that time ON may be user selected at time other than __am to __pm. Record actual time settings. b After a time delay of __ minutes, lighting in area controlled by occupancy sensor turns off Pass? Note that sensors can be set to shorter timeout settings for these test, but must be set back to original setting - see worksheet Verify daylight photosensor controls - record test data for each daylight photosensor in Daylight Photosensor worksheet Verify occupancy sensor control of lighting during evening and weekend hours. Review system programming options Return all changed control parameters and conditions to their pre-set values. American University Cx Plan Functional Performance Test a Confirm that schedules can be re-assigned and confirm that modified schedules respond as expected. Confirm that holiday schedule is programmed as required. Time of day schedule, occupancy sensor timeout delay and photosensor light level setpoints are returned to initial settings. Page 2 of 6 Notes/Reference Initial Date Verify time in minutes of override control. Pass? a b 2.7 Comments Light level setpoint for Open Office Spaces to be verified prior to initiating this test confirm that light level meets or exceeds IES recommended standards at the task surface (50 fc assumed). Record results for each photosensor in Daylight Photosensor worksheet a 2.6 Expected Result Status Lighting in other zones (not pressed) remains OFF until the zone override is initiated for each Pass? particular zone. Lighting override times out after _____ minutes and Pass? lighting turns OFF. Pass? Pass? Pass? Lighting Control F2 FPT EXAMPLE Lighting Controls.xls EXAMPLE LIGHTING CONTROL SYSTEM FUNCTIONAL PERFORMANCE TEST Action HALLWAYS AND LOBBY LIGHTING CONTROL 3.1 Verify that the occupancy sensing devices installed match with drawings, shop drawings and specifications. 3.2 Time controller function controls lighting in Hallways and Lobbies as expected 3.3 Expected Result a a b Correct occupancy sensing devices have been installed. Lighting in Hallways and Lobbies comes on at __ am and turns off at __ pm. A blink warning occurs 5 minutes prior to lighting shut off. Comments Notes/Reference Initial Date Pass? Pass? Record results for each Hallway and Lobby space in Time Clock worksheet Pass? a Lighting in Lobby turns on when initiating override Pass? b Lighting in other zones (not Lobby) remain off. Lighting override times out after _____ minutes and Lobby lighting turns off. Pass? Verify override control for Lobby lighting zone. c 3.4 Status a Before __ am or after __ pm (same as Open Office space time settings) and after lighting in Hallways have automatically turned off, walk by occupancy sensor and confirm that Hallway lighting controlled by the occupancy sensor turns on. b After a time delay of __ minutes, lighting in Hallway controlled by occupancy sensor turns off Verify occupancy sensor control of Hallway Lighting during evening and weekend hours. Pass? Verify time in minutes of override control. Pass? Record results for each sensor in Occupancy Sensor worksheet. Note that time on may be user selected at time other than __am to __pm but should be same as Open Office Space. Record actual time settings. Pass? Note that sensors can be set to shorter timeout settings for these test, but must be set back to original setting - see worksheet Time of day schedule, occupancy sensor timeout delay and photosensor light level setpoints are Pass? returned to initial settings. BATHROOM/RESTROOM, STORAGE CLOSETS AND ENCLOSED CORRIDORS - OCCUPANCY SENSOR VERIFICATION 3.5 Return all changed control parameters and conditions to their pre-set values. a 4.1 Verify that the occupancy sensing devices installed match with drawings, shop drawings and specifications. a Correct occupancy sensing devices have been installed. Pass? 4.2 Verify all ceiling mounted occupancy sensing devices. a Ceiling mounted occupancy sensing devices have been installed in the locations show on the design drawings. Pass? 4.3 Verify that lighting turns on when motion is sensed a 4.4 Remain motionless for occupancy sensor timeout setting a 4.5 Return all changed control parameters and conditions to their pre-set values. a American University Cx Plan Functional Performance Test Upon entering the room, the light fixtures will switch ON. Light fixtures will remain on for __ minutes in Restroom/Bathrooms, __ minutes in storage/mechanical closets and __ minutes for enclosed corridors Occupancy sensor timeout delays are returned to initial settings. Page 3 of 6 Record each room in Occupancy Sensor (OS) worksheet Pass? Pass? Note that sensors can be set to shorter timeout settings for these tests, but must be set back to original setting - see Occupancy Sensor Worksheet Pass? Lighting Control F2 FPT EXAMPLE Lighting Controls.xls EXAMPLE LIGHTING CONTROL SYSTEM FUNCTIONAL PERFORMANCE TEST Action Expected Result PRIVATE OFFICES AND CONFERENCE ROOM - LIGHTING CONTROL VERIFICATION Status 5.1 Verify that the occupancy sensing devices installed match with drawings, shop drawings and specifications. a Correct occupancy sensing devices have been installed. Pass? 5.2 Verify all occupancy sensing devices. a Occupancy sensing devices PIR/Ultrasonic and have been installed in the locations show on the design drawings. Pass? 5.3 Verify that lighting turns on when motion is sensed a Upon entering the room, the light fixtures will switch ON. Pass? 5.4 Remain motionless for occupancy sensor timeout setting a Light fixtures will remain on for __ minutes in Private Offices, and __ minutes in Conference Rooms 5.5 After lighting has turned off, turn on again with motion. a 5.6 Verify override control switch operation a Return all changed control parameters and a. conditions to their pre-set values. MECHANICAL/ELECTRICAL ROOMS AND COMPUTER ROOMS 5.7 Upon movement detected, the light fixtures will switch ON. By pressing low voltage override switch, lighting is turned off by tenant even though movement is being detected by occupancy sensor. Occupancy sensor timeout delays are returned to initial settings. Pass? Initial Date Record each room in OS w override worksheet Note that sensors can be set to shorter timeout settings for these tests, but must be set back to original setting - see Occupancy Sensor Worksheet Pass? Pass? Verify that the ON/OFF switches installed match with drawings, shop drawings and specifications. a Correct switches have been installed. Pass? 6.2 Verify ON operation of ON/OFF digital switches a Pressing switch turns lighting ON. Pass? Pass? 6.3 Verify OFF operation of room lighting control a Light fixtures will blink after __ minutes (5 minute "blink warn") and then will turn OFF automatically after 5 minutes. 6.4 After lighting has turned OFF, turn on again with ON/OFF digital switch. a Pressing switch turns lighting ON. Pass? 6.5 After "blink warn" has occurred, but before 5 minutes are up, press digital switch a Lighting remains ON for an additional ___ minutes before turning OFF automatically. Confirm that 5 minute "blink warn" again initiates. Pass? 6.6 Return all changed control parameters and conditions to their pre-set values. a OFF timeout delays are returned to initial settings. Pass? Page 4 of 6 Notes/Reference Pass? 6.1 American University Cx Plan Functional Performance Test Comments Record rooms tested Note that sensors can be set to shorter timeout settings for these tests (greater than 5 minute blink warn), but must be set back to original setting - see ON/OFF Worksheet Lighting Control F2 FPT EXAMPLE Lighting Controls.xls EXAMPLE LIGHTING CONTROL SYSTEM FUNCTIONAL PERFORMANCE TEST Action BOARD ROOM LIGHTING CONTROL Expected Result a b 7.1 Verify that Multizone Dimmer/Controller and accessories installed per manufacturer's recommendations. c d e Both fluorescent lighting fixtures and dimmer are grounded per manufacturer's recommendations. a Test each named scene ("Presentation,” "Chandelier", "Lunch", etc.) and confirm operation and naming. Named scenes will appear in the display (LCD) when the button is pressed. c d e f g Verify operation of Multizone Dimmer/Controller. h i j American University Cx Plan Functional Performance Test Only appropriate electronic dimming ballasts in use for fluorescent lamps. Controller wired with copper or copper clad wire only. If aluminum wire used, only use devices marked CO/ALR or CU/AL. Load types are not mixed on any single zone The insulation of the Class I (line voltage) field wiring must be rated no less than 75°C. No more than two (2) 12 AWG wires installed on each screw terminal. f b 7.2 Status Test MAX button and confirm that all Loads are set to maximum BRIGHT Test OFF button and confirm that all Loads are turned OFF. Test OFF button and confirm that all Loads are turned OFF. Test "Dim Scene" function. This button dims or brightens the selected scene. Test "Dim/Bright" function and confirm that manual control of light level for selected zone is enabled. Confirm that proper date and time have been programmed. If applicable, confirm timer trigger operation as expected (i.e. specific timer triggers a SCENE, MAX, OFF or Auto OFF). Confirm that Holiday schedule has been set up if applicable. Verify Auto OFF as been programmed for energy savings (if applicable). Confirm that lights automatically turn OFF at the programmed time after a warning blink to maximum. Page 5 of 6 Comments Notes/Reference Initial Date Pass? Pass? Pass? Pass? Pass? Pass? Pass? Note- this FPT developed around Leviton D3206 Multizone Controller/Dimmer. Modify based on actual dimming system provided. Required Scenes to be reviewed with Owner's representative as required. Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Lighting Control F2 FPT EXAMPLE Lighting Controls.xls 7.2 Verify operation of Multizone Dimmer/Controller. EXAMPLE LIGHTING CONTROL SYSTEM FUNCTIONAL PERFORMANCE TEST Action 7.3 Verify operation of Infrared Remote Control Expected Result Status k Verify Auto OFF override operational (if applicable). When Auto OFF occurs, press a Scene, or Zone Dim/Bright button and confirm override of Auto OFF. Confirm that the unit then sweeps the loads OFF after the user defined time interval (of up to 2 hours) has elapsed. Confirm time off interval per Owner's requirements. Pass? l Program saved or backed up per installation guide when completed. Pass? a Lighting control and programming operational from up to 40 feet (and a 100⁰ angle) Pass? Comments Notes/Reference Initial Date EXTERIOR SITE LIGHTING CONTROL 8.1 Verify the automated lighting controls of exterior lighting fixtures connected to photocells. a b Confirm that when sight light level drops below ____ fc, Exterior Lighting turns ON Confirm that when sight light level rises above ____ fc, Exterior Lighting turns OFF Pass? Pass? General Notes 1 2 3 4 5 American University Cx Plan Functional Performance Test Page 6 of 6 Lighting Control F2 FPT EXAMPLE Lighting Controls.xls EXAMPLE MEDIUM VOLTAGE SWITCH FUNCTIONAL PERFORMANCE TEST Medium Voltage Switch - Section 1 - Substation B TEST EQUIPMENT REQUIRED Test Name Voltage/Continuity Bolted Connection or Contact Resistance Bolt Torque Insulation Resistance Over-Potential/Hi-Pot Equipment Description DVM Four-probe Digital Low Resistance Ohmmeter (DLRO) Calibrated torque wrench Battery or line-powered (Hand-crank not acceptable). High voltage DC dielectric test set Action INSTALLATION INTEGRITY Safe conditions (protective gear in-place, available & 1.1 procedures observed) 1.2 Inspect the exterior of the switchgear 1.3 Verify anchoring. 1.4 Verify ratings and configuration. 1.5 Verify permanent labels and mimic bus are installed. 1.6 Verify grounding 1.7 Verify clearances. 1.8 Verify door Interlocks. Expected Result Status Comments Switch has no visible damage. Switchgear has no visible damage. View glass installed. Pass? Pass? Pass? Anchor bolts are installed. Pass? a b c d e Volts: 13.8kV (15kV class) Amps: 600A Current Limiting Fuse - 150E, 17.5kV 65kAIC Frequency: 60hZ Switch - Momentary Current 40 kA Asym Pass? Pass? Pass? Pass? Pass? f Switch - Short time Current rating 25 kA @ 2 sec Pass? g h g h i a b c d a Bus - 600A Silver plated copper Silver plated copper ground bus Main Bus Bracing: 40kA Asym, (25kA Sym) 95kV BIL Enclosure: NEMA 1 Adhesive backed. Black Letters on white background 3/16" minimum height. Mimic bus is installed. Frames and enclosures bolted to ground buss. Connection from station ground grid to equipment ground bus. Cable shields Phase to Phase 7.5 inches. Phase to ground 5.0 inches. Phase barriers installed and not damaged. Door can not open with switch closed. Switch can not close with door open. Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? a b d b c a b c a b Pass? Pass? Pass? Pass? Pass? Pass? Pass? N/A 2.2 With the switch in the CLOSED position, measure the contact resistance of each phase. Measure A phase, B phase and C phase. (Non-Fused) a Readings are within 50% of the average value. Pass? See Data Table for test results. 2.3 With the switch in the CLOSED position, measure the contact resistance of the fuse and Fuse holder. Measure A phase, B phase and C phase. resistance. (Fused) a Readings are within 50% of the average value. Pass? See Data Table for test results. 2.4 Perform an insulation resistance test at 5000 VDC phase-tophase and phase-to-ground with the switch closed and across open contacts of each phase with switch open. Test for 1 minute. a Measured values are minimum 5000 Megohms. Pass? See Data Table for test results. 2.5 Perform a DC Over Potential test on each conductor, with other phases and shield grounded. Maximum DC field test voltage for 100% cables is 56kV and 64kV for 133% cables. a Phase to ground withstand for one minute. Pass? See Data Table for test results. 2.6 Reconnect surge, arrestors, TVSS and PTs. FINAL INSPECTION Final Inspection. Initial Pass? ELECTRICAL INTEGRITY 2.1 Disconnect PTs, CPTs, surge arrestors etc. 3.1 Notes/Reference N/A a b c Hardware replaced. Tools clear. Clean. Pass? Pass? Pass? General Notes 1 2 3 4 5 American University Cx Plan Functional Performance Test Page 1 of 6 F3 FPT EXAMPLE MV Switchgear with MV Switches.xls Date EXAMPLE MEDIUM VOLTAGE SWITCH FUNCTIONAL PERFORMANCE TEST Medium Voltage Switch - Section 2 - Substation C TEST EQUIPMENT REQUIRED Test Name Voltage/Continuity Bolted Connection or Contact Resistance Bolt Torque Insulation Resistance Over-Potential/Hi-Pot Equipment Description DVM Four-probe Digital Low Resistance Ohmmeter (DLRO) Calibrated torque wrench Battery or line-powered (Hand-crank not acceptable). High voltage DC dielectric test set Action INSTALLATION INTEGRITY Safe conditions (protective gear in-place, available & 1.1 procedures observed) 1.2 Inspect the exterior of the switchgear 1.3 Verify anchoring. 1.4 Verify ratings and configuration. 1.5 Verify permanent labels and mimic bus are installed. 1.6 Verify grounding. 1.7 Verify clearances. 1.8 Verify door Interlocks. Expected Result Status Comments Switch has no visible damage. Switchgear has no visible damage. View glass installed. Pass? Pass? Pass? Anchor bolts are installed. Pass? a b c d e Volts: 13.8kV (15kV class) Amps: 600A Current Limiting Fuse - 150E, 17.5kV 65kAIC Frequency: 60hZ Switch - Momentary Current 40 kA Asym Pass? Pass? Pass? Pass? Pass? f Switch - Short time Current rating 25 kA @ 2 sec Pass? g h g h i a b c d a Bus - 600A Silver plated copper Silver plated copper ground bus Main Bus Bracing: 40kA Asym, (25kA Sym) 95kV BIL Enclosure: NEMA 1 Adhesive backed. Black Letters on white background 3/16" minimum height. Mimic bus is installed. Frames and enclosures bolted to ground buss. Connection from station ground grid to equipment ground bus. Cable shields Phase to Phase 7.5 inches. Phase to ground 5.0 inches. Phase barriers installed and not damaged. Door can not open with switch closed. Switch can not close with door open. Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? a b d b c a b c a b Pass? Pass? Pass? Pass? Pass? Pass? Pass? N/A 2.2 With the switch in the CLOSED position, measure the contact resistance of each phase. Measure A phase, B phase and C phase. (Non-Fused) a Readings are within 50% of the average value. Pass? See Data Table for test results. 2.3 With the switch in the CLOSED position, measure the contact resistance of the fuse and Fuse holder. Measure A phase, B phase and C phase. resistance. (Fused) a Readings are within 50% of the average value. Pass? See Data Table for test results. 2.4 Perform an insulation resistance test at 5000 VDC phase-tophase and phase-to-ground with the switch closed and across open contacts of each phase with switch open. Test for 1 minute. a Measured values are minimum 5000 Megohms. Pass? See Data Table for test results. 2.5 Perform a DC Over Potential test on each conductor, with other phases and shield grounded. Maximum DC field test voltage for 100% cables is 56kV and 64kV for 133% cables. a Phase to ground withstand for one minute. Pass? See Data Table for test results. 2.6 Reconnect surge, arrestors, TVSS and PTs. FINAL INSPECTION Final Inspection. Initial Pass? ELECTRICAL INTEGRITY 2.1 Disconnect PTs, CPTs, surge arrestors etc. 3.1 Notes/Reference N/A a b c Hardware replaced. Tools clear. Clean. Pass? Pass? Pass? General Notes 1 2 3 4 5 American University Cx Plan Functional Performance Test Page 2 of 6 F3 FPT EXAMPLE MV Switchgear with MV Switches.xls Date EXAMPLE MEDIUM VOLTAGE SWITCH FUNCTIONAL PERFORMANCE TEST Medium Voltage Switch - Section 10 - Main 2 Section (Main Tie Main swgr) TEST EQUIPMENT REQUIRED Test Name Voltage/Continuity Bolted Connection or Contact Resistance Bolt Torque Insulation Resistance Over-Potential/Hi-Pot Equipment Description DVM Four-probe Digital Low Resistance Ohmmeter (DLRO) Calibrated torque wrench Battery or line-powered (Hand-crank not acceptable). High voltage DC dielectric test set Action INSTALLATION INTEGRITY Safe conditions (protective gear in-place, available & 1.1 procedures observed) 1.2 Inspect the exterior of the switchgear 1.3 Verify anchoring. 1.4 Verify ratings and configuration. 1.5 Pilot lights installed and operational 1.6 Verify permanent labels and mimic bus are installed. 1.7 Verify grounding. 1.8 Verify clearances. 1.9 Verify door Interlocks. Expected Result Status Notes/Reference Initial Pass? a b d a b c d e f g h g h i j k l m a b c d a b c d a b c a b c a b Switch has no visible damage. Switchgear has no visible damage. View glass installed. Pass? Pass? Pass? Anchor bolts are installed. Pass? Type HVL, Series 2 Dual Trip 120VAC Motor Operated Volts: 13.8kV (15kV class) Amps: 600A Current Limiting Fuse - 150E, 17.5kV 65kAIC Frequency: 60hZ Switch - Momentary Current 40 kA Asym Switch - Short time Current rating 25 kA @ 2 sec Bus - 600A Silver plated copper Silver plated copper ground bus Main Bus Bracing: 40kA Asym, (25kA Sym) 95kV BIL PT: 13800:120 Surge arrestor: Type XEP, 18kV, 15.3kV MCOV Enclosure: NEMA 1 Lights operational using push to test button Lights operational with change of state - if no push to test 3/16" minimum height. Mimic bus is installed. Adhesive backed. Black Letters on white background 3/16" minimum height. Mimic bus is installed. Frames and enclosures bolted to ground buss. Connection from station ground grid to equipment ground bus. Cable shields Phase to Phase 7.5 inches. Phase to ground 5.0 inches. Phase barriers installed and not damaged. Door can not open with switch closed. Switch can not close with door open. Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? ELECTRICAL INTEGRITY 2.1 Disconnect PTs, CPTs, surge arrestors etc. Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? N/A 2.2 With the switch in the CLOSED position, measure the contact resistance of each phase. Measure A phase, B phase and C phase. (Non-Fused) a Readings are within 50% of the average value. Pass? 2.3 With the switch in the CLOSED position, measure the contact resistance of the fuse and Fuse holder. Measure A phase, B phase and C phase. resistance. (Fused) a Readings are within 50% of the average value. Pass? 2.4 Perform an insulation resistance test at 5000 VDC phase-tophase and phase-to-ground with the switch closed and across open contacts of each phase with switch open. Test for 1 minute. a Measured values are minimum 5000 Megohms. Pass? 2.5 Perform a DC Over Potential test on each conductor, with other phases and shield grounded. Maximum DC field test voltage for 100% cables is 56kV and 64kV for 133% cables. a Phase to ground withstand for one minute. Pass? 2.6 Reconnect surge, arrestors, TVSS and PTs. SWITCH OPERATION 3.1 Comments N/A a Switch opens with front mounted Trip position of selector switch b Switch closes with front mounted Closed position of Pass? selector switch a b c Hardware replaced. Tools clear. Clean. Operate Main A Switch manually with manual trip-close swtich Pass? FINAL INSPECTION 4.1 Final Inspection. Pass? Pass? Pass? General Notes 1 2 3 4 5 American University Cx Plan Functional Performance Test Page 3 of 6 F3 FPT EXAMPLE MV Switchgear with MV Switches.xls Date EXAMPLE MEDIUM VOLTAGE SWITCH FUNCTIONAL PERFORMANCE TEST Medium Voltage Switch - Section 6 - Main 1 Section (Main Tie Main swgr) TEST EQUIPMENT REQUIRED Test Name Voltage/Continuity Bolted Connection or Contact Resistance Bolt Torque Insulation Resistance Over-Potential/Hi-Pot Equipment Description DVM Four-probe Digital Low Resistance Ohmmeter (DLRO) Calibrated torque wrench Battery or line-powered (Hand-crank not acceptable). High voltage DC dielectric test set Action INSTALLATION INTEGRITY Safe conditions (protective gear in-place, available & 1.1 procedures observed) 1.2 Inspect the exterior of the switchgear 1.3 Verify anchoring. 1.4 Verify ratings and configuration. 1.5 Pilot lights installed and operational 1.6 Verify permanent labels and mimic bus are installed. 1.7 Verify grounding. 1.8 Verify clearances. 1.9 Verify door Interlocks. Expected Result Status Notes/Reference Initial Pass? a b d a b c d e f g h g h i j k l m a b c d a b c d a b c a b c a b Switch has no visible damage. Switchgear has no visible damage. View glass installed. Pass? Pass? Pass? Anchor bolts are installed. Pass? Type HVL, Series 2 Dual Trip 120VAC Motor Operated Volts: 13.8kV (15kV class) Amps: 600A Current Limiting Fuse - 150E, 17.5kV 65kAIC Frequency: 60hZ Switch - Momentary Current 40 kA Asym Switch - Short time Current rating 25 kA @ 2 sec Bus - 600A Silver plated copper Silver plated copper ground bus Main Bus Bracing: 40kA Asym, (25kA Sym) 95kV BIL PT: 13800:120 Surge arrestor: Type XEP, 18kV, 15.3kV MCOV Enclosure: NEMA 1 Lights operational using push to test button Lights operational with change of state - if no push to test 3/16" minimum height. Mimic bus is installed. Adhesive backed. Black Letters on white background 3/16" minimum height. Mimic bus is installed. Frames and enclosures bolted to ground buss. Connection from station ground grid to equipment ground bus. Cable shields Phase to Phase 7.5 inches. Phase to ground 5.0 inches. Phase barriers installed and not damaged. Door can not open with switch closed. Switch can not close with door open. Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? ELECTRICAL INTEGRITY 2.1 Disconnect PTs, CPTs, surge arrestors etc. Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? N/A 2.2 With the switch in the CLOSED position, measure the contact resistance of each phase. Measure A phase, B phase and C phase. (Non-Fused) a Readings are within 50% of the average value. Pass? 2.3 With the switch in the CLOSED position, measure the contact resistance of the fuse and Fuse holder. Measure A phase, B phase and C phase. resistance. (Fused) a Readings are within 50% of the average value. Pass? 2.4 Perform an insulation resistance test at 5000 VDC phase-tophase and phase-to-ground with the switch closed and across open contacts of each phase with switch open. Test for 1 minute. a Measured values are minimum 5000 Megohms. Pass? 2.5 Perform a DC Over Potential test on each conductor, with other phases and shield grounded. Maximum DC field test voltage for 100% cables is 56kV and 64kV for 133% cables. a Phase to ground withstand for one minute. Pass? 2.6 Reconnect surge, arrestors, TVSS and PTs. SWITCH OPERATION 3.1 Comments N/A a Switch opens with front mounted Trip position of selector switch b Switch closes with front mounted Closed position of Pass? selector switch a b c Hardware replaced. Tools clear. Clean. Operate Main B Switch manually with manual trip-close swtich Pass? FINAL INSPECTION 4.1 Final Inspection. Pass? Pass? Pass? General Notes 1 2 3 4 5 American University Cx Plan Functional Performance Test Page 4 of 6 F3 FPT EXAMPLE MV Switchgear with MV Switches.xls Date EXAMPLE MEDIUM VOLTAGE SWITCH FUNCTIONAL PERFORMANCE TEST Medium Voltage Switch - Section 8 - Tie (Main Tie Main swgr) TEST EQUIPMENT REQUIRED Test Name Voltage/Continuity Bolted Connection or Contact Resistance Bolt Torque Insulation Resistance Over-Potential/Hi-Pot Equipment Description DVM Four-probe Digital Low Resistance Ohmmeter (DLRO) Calibrated torque wrench Battery or line-powered (Hand-crank not acceptable). High voltage DC dielectric test set Action INSTALLATION INTEGRITY Safe conditions (protective gear in-place, available & 1.1 procedures observed) 1.2 Inspect the exterior of the switchgear 1.3 Verify anchoring. 1.4 Verify ratings and configuration. 1.5 Pilot lights installed and operational 1.6 Verify permanent labels and mimic bus are installed. 1.7 Verify grounding. 1.8 Verify clearances. 1.9 Verify door Interlocks. Expected Result Status Comments Initial Pass? a b d a b c d e f g h g h i j m a b c d a b c d a b c a b c a b Switch has no visible damage. Switchgear has no visible damage. View glass installed. Pass? Pass? Pass? Anchor bolts are installed. Pass? Type HVL, Series 2 Dual Trip 120VAC Motor Operated Volts: 13.8kV (15kV class) Amps: 600A Current Limiting Fuse - 150E, 17.5kV 65kAIC Frequency: 60hZ Switch - Momentary Current 40 kA Asym Switch - Short time Current rating 25 kA @ 2 sec Bus - 600A Silver plated copper Silver plated copper ground bus Main Bus Bracing: 40kA Asym, (25kA Sym) 95kV BIL Enclosure: NEMA 1 Lights operational using push to test button Lights operational with change of state - if no push to test 3/16" minimum height. Mimic bus is installed. Adhesive backed. Black Letters on white background 3/16" minimum height. Mimic bus is installed. Frames and enclosures bolted to ground buss. Connection from station ground grid to equipment ground bus. Cable shields Phase to Phase 7.5 inches. Phase to ground 5.0 inches. Phase barriers installed and not damaged. Door can not open with switch closed. Switch can not close with door open. Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? ELECTRICAL INTEGRITY 2.1 Disconnect PTs, CPTs, surge arrestors etc. Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? N/A 2.2 With the switch in the CLOSED position, measure the contact resistance of each phase. Measure A phase, B phase and C phase. (Non-Fused) a Readings are within 50% of the average value. Pass? 2.3 With the switch in the CLOSED position, measure the contact resistance of the fuse and Fuse holder. Measure A phase, B phase and C phase. resistance. (Fused) a Readings are within 50% of the average value. Pass? 2.4 Perform an insulation resistance test at 2500 VDC phase-tophase and phase-to-ground with the switch closed and across open contacts of each phase with switch open. Test for 1 minute. a Measured values are minimum 5000 Megohms. Pass? See Data Table for test results. 2.5 Perform a DC Over Potential test on each conductor, with other phases and shield grounded. Maximum DC field test voltage for 100% cables is 56kV and 64kV for 133% cables. a Phase to ground withstand for one minute. Pass? See Data Table for test results. 2.6 Reconnect surge, arrestors, TVSS and PTs. SWITCH OPERATION 3.1 Notes/Reference See Data Table for test results. N/A a Switch opens with front mounted Trip position of selector switch b Switch closes with front mounted Closed position of Pass? selector switch a b c Hardware replaced. Tools clear. Clean. Operate Tie Switch manually with manual trip-close swtich Pass? FINAL INSPECTION 4.1 Final Inspection. Pass? Pass? Pass? General Notes 1 2 3 4 5 American University Cx Plan Functional Performance Test Page 5 of 6 F3 FPT EXAMPLE MV Switchgear with MV Switches.xls Date EXAMPLE MEDIUM VOLTAGE SWITCH FUNCTIONAL PERFORMANCE TEST Medium Voltage Main-Tie-Main Switchgear. TEST EQUIPMENT REQUIRED Test Name Voltage/Continuity Bolted Connection or Contact Resistance Bolt Torque Insulation Resistance Over-Potential/Hi-Pot Protective Functions Transformer Turns Ratio Equipment Description DVM Four-probe Digital Low Resistance Ohmmeter (DLRO) Calibrated torque wrench Battery or line-powered (Hand-crank not acceptable). High voltage DC dielectric test set 3-Phase Test Set (voltage and current) Measures turns ration and polarity Action INSTALLATION INTEGRITY Safe conditions (protective gear in-place, available & 1.1 procedures observed) 1.2 Inspect the exterior of the switchgear 1.3 Verify anchoring. Expected Result Verify ratings and configuration. a b Switchgear has no visible damage. Interior is clean and dry. Pass? Pass? Anchor bolts are installed. Pass? Pass? Pass? Pass? Pass? Pass? Pass? c a b c a a b Volts: 13.8kV (15kV class) Main Bus Bracing: 40kA Asym, (25kA Sym) 95kV BIL Amps:600A, Silver Plated Copper Silver Plated Copper Ground Bus Frequency: 60hZ Controller: SEL 2411, Part # 241101A2X2X3A3A0100 Undervoltage Relay and Phase Sequence: ASEA Brown Boveri, Type 47 Enclosure: NEMA 1 Control power is supplied by customer supplied UPS Adhesive backed. Black Letters on white background 3/16" minimum height. Mimic bus is installed. Lights operational using push to test button Lights operational with change of state - if no push to test 3/16" minimum height. Mimic bus is installed. Frames and enclosures bolted to ground buss. Connection from station ground grid to equipment ground bus. Cable shields Phase to Phase 7.5 inches. Phase to ground 5.0 inches. Phase barriers installed and not damaged. Hot stick with fuse handling tool provided Door can not open with switch closed. Switch can not close with door open. a Measured values are minimum 5000 Megohms. Pass? a b c d e a b c d e Pickup voltage within tolerance. Drop-out voltage within tolerance. Time delay within tolerance. Undervoltage relay trips the lockout relay (86). Undervoltage for Main A annunciated Pickup voltage within tolerance. Drop-out voltage within tolerance. Time delay within tolerance. Undervoltage relay trips the lockout relay (86). Undervoltage for Main B annunciated Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? a Output contact picks up when voltage, frequency and phase angle match on both sides of relay. Pass? g h i j 1.5 Verify permanent labels and mimic bus are installed. 1.6 Pilot lights installed and operational a b c d a b c d a 1.7 Verify grounding. 1.8 Verify clearances. 1.9 Verify Accessories provided 1.10 Verify door Interlocks. Comments Notes/Reference Initial Date Pass? a b c d e f 1.4 Status b Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? ELECTRICAL INTEGRITY 2.1 Perform an insulation resistance test of the switchgear bus at 5000 VDC phase-to-phase and phase-to-ground.Test for 1 minute. 2.2 Using a three-phase test set, verify the operation of the under-voltage (27) function of Main A 2.3 Using a three-phase test set, verify the operation of the under-voltage (27) function of Main B Output contact drops out when voltage is raised b above high tolerance and lowered below low tolerance. Output contact drops out when frequency is raised Using a three-phase test set, verify the operation of the sync2.4 c above high tolerance and lowered below low check (25c) relay. tolerance. Output contact drops out when phase angle d difference is adjusted above the leading tolerance and above the lagging tolerance. Output contact changes state when voltage is e applied to Main A side of relay and no voltage is applied to Main B side of relay POTENTIAL TRANFORMERS (PTs) AND CURRENT TRANSFORMERS (CTs) Minimum clearances around instrument transformers a 3.1 Instrument Transformers installed per Xcel requirements 7.5" Phase to Phase 5.0" Phase to Ground 3.3 PTs installation verified Perform an insulation resistance test on each potential transformer. Measure phase A, B and C. Perform a turns ratio test on each potential transformer. 3.5 Measure phase A, B and C. Test at all tap positions. ALARMS AND CONTROL PANEL TEST 3.3 5.1 Verify connections to the building automation or other monitoring system. Pass? Pass? Pass? Pass? Pass? a ABB VIZ-75 unfused voltage transformers installed Pass? a Measured values are minimum 5000 Megohms. Pass? a b Ratio accuracies are within 0.5% of nameplate. Polarity results match transformer markings. Pass? Pass? a Values and equipment status and alarms displayed locally match values displayed on the BAS. Pass? a b c Hardware replaced. Tools clear. Clean. Pass? Pass? Pass? FINAL INSPECTION 6.1 Final Inspection. General Notes 1 2 3 4 5 American University Cx Plan Functional Performance Test Page 6 of 6 F3 FPT EXAMPLE MV Switchgear with MV Switches.xls EXAMPLE GENERATOR FUNCTIONAL PERFORMANCE TEST Generator TEST EQUIPMENT REQUIRED Test Name Voltage/Continuity Bolted Connection or Contact Resistance Insulation Resistance Primary Current Injection 2 and 4 Hour Load Bank Test Phase Rotation Volt. & Freq. Regulation Decibel Back Pressure Bolt Torque Equipment Description DVM Four-probe Digital Low Resistance Ohmmeter (DLRO) Battery or line-powered (Hand-crank not acceptable). Current Injection Test Device rated for 2X the ground fault pickup setting of the breaker Resistive load bank with capacity equal to or greater than rated load. Rated at 2% accuracy for voltage, current and KW. Verify proper phasing Computer to record voltage and frequency from the output of the generator control panel. Measure sound pressure Manometer with a scale of greater than 40” water Calibrated torque wrench Action Expected Result Status INSTALLATION INTEGRITY Safe conditions (protective gear in-place, available & 1.1 procedures observed) 1.2 Verify that the Engine, Generator, Battery, and Battery Charger nameplate data . a b c d e f g a Verify circuit breaker settings. c d a b c d e 1.4 Inspect physical and mechanical condition. f g h i j 1.5 Verify anchoring. a a b 1.6 Verify equipment grounding. c d e f American University Cx Plan Functional Performance Test Notes/Reference Initial Date Pass? b 1.3 Comments kW:______kW Rating: ____HP @ 1800RPM Freq.: 60hZ Phase/Wire: 3ph, 4W Power Factor: 0.8 Voltage Output: 480/277V Sound attenuation enclosure _____A, 3P Main Bkr Ground fault protection is disabled or ground fault indication only provided Circuit breaker is set per the coordination study and provided with selective coordination - solid state trip unit. No visible damage to circuit breaker enclosure. No visible damage to generator or enclosure. Engine generator exterior is clean and dry. Generator control panel interior is clean and dry. Generator control panel mounted at an accessible height. Vibration isolation is installed at engine and at radiator External connections are made with flexible connections. Verify remote monitoring wiring is connected and labeled. Verify control wiring is connected and labeled. Feeder cable/bus routing doesn’t obstruct access for operation or maintenance. Control wiring harness(es) does not rub against vibrating or moving parts. Anchor bolts are provided in locations shown on manufacturer's drawings. Verify ground rod is installed with connection to engine generator frame. Generator neutral is bonded to ground with conductor sized per NEC 250-20. Measured diameter of bare copper conductor corresponds to diameter of specified conductors Ground strap from engine to frame. Ground strap from generator enclosure to frame. Ground bus provided in termination cabinet with properly terminated ground conductors. Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Page 1 of 4 F4 FPT EXAMPLE Generator.xls EXAMPLE GENERATOR FUNCTIONAL PERFORMANCE TEST Action 1.7 Verify lube oil levels are within manufacturer’s recommended limits. 1.8 Verify fuel system installation and integrity. 1.9 Verify cooling system installation and integrity. Expected Result a Lube oil level is filled to proper level. Pass? a b c d a b c Tank(s) full of fuel (90% for diesel). Fuel level in fuel tank(s) matches fuel gauge. Fuel system is free of leaks. Flexible fuel lines are installed at engine. Coolant level is filled to proper level. Verify coolant system freeze protection level. Cooling system is free from leaks. Flexible coolant lines are installed between engine and radiator. Exhaust system, silencer and flexible connector installed and supported. Exhaust system expansion is not transferred to engine components such as turbocharger. Silencer is equipped with condensate drain plug and turn valve. Exhaust system is equipped with rain cap. Exhaust system has at least 9” clearance from combustible materials. Pass? Pass? Pass? Pass? Pass? Pass? Pass? d a b 1.10 Verify exhaust system installation and integrity. Status c d e Comments Notes/Reference Initial Date Pass? Pass? Pass? Pass? Pass? Pass? ELECTRICAL INTEGRITY 2.1 Prior to step 4.1 verify correct phase rotation. a b c d Phase rotation at generator matches NORMAL power source. Verify that valves to the water jacket heater are open. Verify thermostats switch at their setpoint temperatures (110°F). Verify pump runs continuously independent of heater operation. Loss of Power Alarm is operable Low Battery Volt Alarm operable. High Battery Volt Alarms operable. Power On led in on a Readings are within 50% of the average value. Pass? a Minimum insulation resistance shall be 100 Megohms. Pass? a Long delay current pick up and time delay per coordination study. Pass? a Short delay current pick up and time delay per coordination study. Pass? a Instantaneous pick up per coordination study. Pass? a a 2.2 Verify operation of coolant line heater. b c Verify operation of battery and starting system. 2.3 2.4 2.5 2.6 2.7 2.8 Record cell voltages for all cells with terminals available, total battery charging voltage and charging current. With the breaker (s) in the CLOSED position, measure the contact resistance of each phase of the primary circuit. Perform an insulation resistance test on the Generator Circuit Breaker(s) at 1000VDC, phase-to-phase and phase to ground, connected to the bus in the CLOSED position, in accordance with NETA Table 100.1. Note: Disconnect line and load side conductors. Test the Long Time Delay (seconds) and Long Time Pickup current (amperes) setting of the breaker, by using primary current injection. Test the Short Time Delay (seconds) and Short Time Pickup current (amperes) setting of the breaker, by using primary current injection. Test the Instantaneous Time Delay (seconds) and Instantaneous Time Pickup current (amperes) setting of the breaker, by using primary current injection. American University Cx Plan Functional Performance Test Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Page 2 of 4 F4 FPT EXAMPLE Generator.xls EXAMPLE GENERATOR FUNCTIONAL PERFORMANCE TEST Action ALARMS AND CONTROL PANEL TEST Verify control wiring between generator and ATS are correctly 3.1 terminated. Record all setpoints at Engine Generator Control Panel. 3.2 3.3 3.4 Verify all shutdown conditions per manufacturer’s instructions and verify operation and local annunciation at Engine Generator Control Panel. 3.5 Verify remote audible annunciation of all status, warning/prealarm, and shutdown conditions per manufacturer’s instructions. 3.6 Verify installation of remote E-Stop. LOADBANK TEST 4.2 4.3 4.4 Terminations match shop drawings. a b c d e f g h i j k l m a b c d e a b c d e f g h i a Overcrank Low Water Temp High Water Temp Low Oil Pressure Overspeed Low Coolant Level EPS Supplying Load Control switch not in Auto High Battery Voltage Low Battery Voltage Battery Charger AC Failure Lamp Test Contacts for local and remote common alarm Overcrank High Water Temp Low Oil Pressure Overspeed Low Coolant Level Overcrank Low Water Temp High Water Temp Low Oil Pressure Overspeed Low Coolant Level Control switch not in Auto Contacts for local and remote common alarm Audible alarm silencing switch E-stop pushbutton is accessible. With generator in a “cold start” condition, conduct a load performance test, by initiating a NORMAL failure and transfer of ATS’s. a b c d e f g h Exhaust system is not leaking. Pass? a Generator runs in cool down mode for 5 min. Pass? a b c a b c Engine starts and runs. Air intake louvers open fully. Exhaust damper opens fully. Fuel is not leaking. Coolant is not leaking. Lube oil is not leaking. Exhaust system expansion is not transferred to engine system components. Pass? Pass? Pass? Pass? Pass? Pass? Load generator at 50% for 15 min. Load generator at 75% for 15 min. Load generator at 100% for 3.5 hrs During test, verify exhaust, coolant, and fuel system is functioning properly. American University Cx Plan Functional Performance Test Initial Date Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Phase rotation at generator matches NORMAL power source. Engine starts and runs. Air intake louvers open fully. Exhaust damper opens fully. Fuel is not leaking. Coolant is not leaking. Lube oil is not leaking. Exhaust system expansion is not transferred to Restore NORMAL sources to ATS’s (or turn off load bank) and transfer ALL load off of generator and allow to cool down for 5 minutes With a load bank connected to the load side terminals of the generator, start generator at local control panel with engine control switch. Notes/Reference N/A a Load generator for a maximum of 2 hrs using available building load and/or a load bank During test, verify exhaust, coolant, and fuel system is functioning properly. Comments Pass? Verify correct phase rotation prior to transfer of load Conduct a load performance test utilizing a load bank to achieve 100% rated load of generator. 4.5 a Status Note: Manufacturer’s checklist can be attached to this form in lieu of recording. Verify all warning/pre-alarms per manufacturer’s instructions and verify operation and local annunciation at Engine Generator Control Panel. 4.1 Expected Result d Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Page 3 of 4 F4 FPT EXAMPLE Generator.xls EXAMPLE GENERATOR FUNCTIONAL PERFORMANCE TEST Conduct a load performance test utilizing a load bank to achieve 100% rated load of generator. Action Load generator at 50% for 15 min. Load generator at 75% for 15 min. Load generator at 100% for 3.5 hrs During test, verify exhaust, coolant, and fuel system is functioning properly. 4.5 In conjunction with step 4.4, verify voltage regulation by recording RMS voltage while increasing load on generator. 4.6 In conjunction with step 4.4, verify frequency regulation by recording frequency while increasing load on generator. In conjunction with step 4.4, measure harmonic content of 4.8 output voltage at 50 and 100 percent rated load. During step 4.4, verify engine operation is within normal 4.9 operating limits. During step 4.4 while generator is running at 100% load, 4.10 measure sound level. Measure at four locations on the property line. 4.7 While generator is running at 100% load, conduct Exhaust4.11 System Back Pressure Test. Decrease load to 0% and allow the generator to cool down for 5 minutes After the cool down, once the prime mover has reached rated 4.13 voltage and frequency, transfer full rated load onto the engine generator in a single block. Decrease load to 0% and shutdown generator with local E4.14 Stop. 4.12 Expected Result e Exhaust system is not leaking. Pass? a Voltage regulation is ±1%. Pass? a Frequency regulation is ±1%. Pass? 6.2 6.3 6.4 Turn generator control to “STOP”. Record Louver set point. Adjust the Louver set point to a setting above the enclosure temperature. Return the Louver temperature set point to the original value. 6.5 FINAL INSPECTION After testing is performed on the generator, verify tightness of 7.1 field landed feeder terminations. 7.2 Refill fuel tanks and verify 90% fuel levels. Comments Notes/Reference Initial Date Pass? Pass? a a a b a a b Pass? Maximum backpressure at full-rated load is within manufacturer’s written maximum allowable limits of 5.9 kPa or 1.7” Hg for the engine. Generator cools down No leaks from any system are found Engine continues to run without shutdown or overspeed trip and recovers to steady state voltage and frequency ranges within 5 seconds. Generator shuts down Remote annunciator alarms with E-Stop Pass? Pass? Pass? Pass? Pass? Pass? a Engine cycle cranks a minimum of three 15-second Pass? cranking cycles with 15 seconds between cycles. b At completion of third cycle engine stops cranking and “OVERCRANK” shutdown alarm is annunciated Pass? locally and remotely. a a Space heater turns on to maintain set point. Space heater turns off to maintain set point. Pass? Pass? a b a Generator starts and runs. Louvers open. Louvers remain open. Pass? Pass? Pass? N/A 4.15 Disconnect fuel solenoid and simulate START to engine. SPACE HEATER OPERATION 5.1 Adjust thermostat to 5 degrees below space temperature. 5.2 Adjust thermostat to 5 degrees above space temperature. LOUVER OPERATION Perform the following tests immediately after the load bank test. Turn generator control to “RUN” (if not already running) 6.1 Status a Louvers close. Pass? a Louvers re-open if the enclosure temp is above set point or remain closed if the enclosure temp is below the set point. Pass? a Feeder cable connections properly torqued and marked. Pass? a Fuel level indicator verifies 90% fuel level in tank. Pass? General Notes 1 2 3 American University Cx Plan Functional Performance Test Page 4 of 4 F4 FPT EXAMPLE Generator.xls EXAMPLE CLOSED TRANSITION AUTOMATIC TRANSFER SWITCH W ISOLATION BYPASS FUNCTIONAL PERFORMANCE TEST Automatic Transfer Switch (ATS), Closed Transition with Isolation Bypass TEST EQUIPMENT REQUIRED (TO BE PROVIDED BY CONTRACTOR OR TEST AGENCY) Test Name Equipment Description Bolt Torque Calibrated torque wrench Bolted Connection or Contact Resistance Four-probe Digital Low Resistance Ohmmeter (DLRO) Voltage/Continuity DVM Insulation Resistance Battery or line-powered (Hand-crank not acceptable). Action INSTALLATION INTEGRITY Safe conditions (protective gear in-place, available & 1.1 procedures observed) Confirm that NORMAL and EMERGENCY sources match 1.2 final design drawings. 1.3 Verify nameplate data matches one-line drawings, specifications, and shop drawings. 1.4 Verify permanent labels for transfer switch is installed. 1.5 Verify accessibility for maintenance. Expected Result 1.7 Inspect physical and mechanical conditions. Verify anchoring. a b a b c d e f a b c a b a b Normal: Emergency: Volts: ______VAC Amps: _____A __4 pole, ___W Frequency: 60hZ Interrupting Rating: Enclosure: NEMA 1 Adhesive backed. White letters on dark gray background. 3/8 in minimum height. Door opens freely and swings fully open. 3’-6” minimum clearance in front of switch. Cables do not block access to indicators or adjustable components. Cables do not block access to manual transfer switch operator. No visible signs of damage. No visible dirt, metal chips or contamination. c Appropriate source indicating lights are illuminated. Pass? c a a 1.8 Verify ATS is properly grounded. b c 1.9 Confirm that components of control system including terminal block, wiring, and Ni-Cad batteries are complete. Anchor bolts are provided in locations shown on manufacturer's drawings. Enclosure bonded to ground bus. Incoming (normal and emergency) and outgoing (load) feeder grounding conductors bonded to ground bus. Neutral bus/pole isolated from ground. a Perform manual transfer operation with both NORMAL and EMERGENCY sources de-energized. Use detachable 1.10 manual operator to transfer from NORMAL to EMERGENCY and back. a 1.11 Perform manual bypass transfer operation to each source. a American University Cx Plan Functional Performance Test Comments Notes/Reference Initial Date Pass? d 1.6 Status b Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Switch should transfer smoothly and with full contact travel speed. Mechanical interlocking should prevent simultaneous closure of NORMAL and EMERGENCY sources. Switch should transfer smoothly and with full contact travel speed. Pass? Pass? Pass? Page 1 of 3 F5 FPT ATS.xls EXAMPLE CLOSED TRANSITION AUTOMATIC TRANSFER SWITCH W ISOLATION BYPASS FUNCTIONAL PERFORMANCE TEST Action ELECTRICAL INTEGRITY Measure contact resistance on all poles in all closed 2.1 positions (Normal, Emergency, Bypass to Normal, Bypass to Emergency) Perform an insulation resistance test at 500VDC (or at test 2.2 voltage per mfgr recommendations) on each bus section, phase-to-phase and phase to ground. Perform insulation resistance test at 500 VDC (or at test 2.3 voltage per mfgr recommendations) to verify Automatic Transfer Switch is isolated from load when bypassed. Verify the operation of four-line LCD display and character 2.4 keyboard. 2.5 Verify “In Phase Monitoring” setting. 2.6 Verify all voltage, frequency, and time delay settings. 2.7 Verify all applicable local and remote annunciation by the monitoring system for various operating conditions. 2.8 Verify proper phase rotation TRANSFER OPERATION TESTS 3.1 Disconnect NORMAL power source to transfer switch. Expected Result a Readings are within 50% of the average value, including the neutral pole. Pass? a Minimum insulation resistance shall be 100 megohms. Pass? a Insulation resistance shall equal or exceed 100 Megohms. Pass? a b a a b a b c d e f g h i j k a All data displays operate. All program parameters accessible. In phase monitoring is enabled/disabled. Use ATS microprocessor control system. Device pick-up (PU) and drop-out (DO). NORMAL power available EMERGENCY power avail. ATS in NORMAL position. ATS in EMERGENCY position. LED indicating lights are operating Test light button operational Bypass Switch Bypassed to Normal Bypass Switch Bypassed to Emergency ATS Connected ATS in Test Position ATS Isolated Emergency source matches utility source. Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? Pass? a b c d Pass? Pass? Pass? Pass? d Time delay on engine start equals setpoint. Start signal sent to engine generator. Transfer time delay equals setpoint. ATS transfers to Emergency source position. Total time to connect to Emergency source is no more than ____ - seconds Re-transfer time delay equals setpoint. ATS transfers to Normal source position. Closed transition switching (if applicable) occurs. No loss to load detected as applicable Engine cool down time delay equals setpoint. e Engine shuts off after cool down delay times out. Pass? a b c d a b Pass? Pass? Pass? Pass? Pass? Pass? d Time delay on engine start equals setpoint. Start signal sent to engine generator. Transfer time delay equals set point. ATS transfers to Emergency source position. Re-transfer time delay equals setpoint. ATS transfers to Normal source position. Closed transition (if applicable) switching occurs. No loss to load detected as applicable Engine cool down time delay equals setpoint. e Engine shuts off after cool down delay times out. Pass? a Switch should re-transfer (closed transition if applicable) to Normal without delay on engine shutdown. Pass? a Simulates failure of normal source. Pass? a No interruption to the load during closed transition. Pass? e a b 3.2 Restore Normal power source to Automatic Transfer Switch to verify setpoints. 3.3 Simulate loss of phase to ground voltage for each phase of the NORMAL source. 3.4 Restore each phase (Normal) voltage to Automatic Transfer Switch to verify setpoints. 3.6 Repeat steps 3.1 and 3.2 except manually disconnect EMERGENCY source, to simulate failure of the engine, after restoration of NORMAL power and before the re-transfer delay has expired. Verify operation of ATS TEST switch. 3.7 Confirm closed transition. 3.5 American University Cx Plan Functional Performance Test Status c c Comments Notes/Reference Initial Date Pass? Pass? Pass? Pass? Pass? Pass? Pass? Page 2 of 3 F5 FPT ATS.xls EXAMPLE CLOSED TRANSITION AUTOMATIC TRANSFER SWITCH W ISOLATION BYPASS FUNCTIONAL PERFORMANCE TEST Action EXTENDED PARALLEL/SHUNT TRIP 4.1 Simulate an extended parallel between the normal (utility) and emergency source. Expected Result Status a Normal circuit breaker feeding the ATS shunt trips. Pass? b Generator continues to serve the load (no interruption to load) Pass? 4.2 Attempt to reset the ATS feeder circuit breaker without resetting the lock out relay. a ATS normal Circuit breaker will not reset, Pass? 4.3 Reset the lock out relay and reset the normal circuit breaker. a ATS normal Circuit breaker resets. Pass? a No interruption to the load during closed transition back to normal source Pass? a ATS mechanism is de-energized and power passes Pass? through the bypass/isolation switch path. a ATS mechanism is energized and the bypass/isolation switch path is de-energized. Pass? Pass? Confirm that ATS transfers back to Normal source by closed transition BYPASS AND ISOLATION SWITCH OPERATION 4.4 5.1 Verify Automatic Transfer Switch manual bypass (to Normal and Emergency sources) and isolation switch operation with NORMAL source energized and load on ATS. Restore the Automatic Transfer Switch to its automatic mode by manually reversing the bypass and isolation switch operation. ATS REMOTE ANNUNCIATOR 5.2 6.1 Verify installation of remote annunciator. a Display mounted at reasonable height. (easily viewable from the floor) 6.2 Verify interface to each transfer switch. a Correct status of each transfer switch is displayed. Pass? a Feeder cable connections properly torque and marked. a Prior to energization, inspect interior hardware and Pass? electrical terminations. FINAL INSPECTION After testing is performed on the ATS, verify tightness of field 7.1 landed feeder terminations (NORMAL, EMERGENCY, and LOAD feeders). Prior to energization, inspect interior hardware and electrical 7.2 terminations. Comments Notes/Reference Initial Date Pass? General Notes 1 2 3 4 5 American University Cx Plan Functional Performance Test Page 3 of 3 F5 FPT ATS.xls