Route 79/I-195 Interchange Reconstruction and Structural Repairs and Painting of the Braga Bridge Project Route 79/I-195 Interchange Reconstruction Project PROJECT UPDATE • The Braga Bridge Structural Steel Repairs and Painting Phase II Project has been combined with the Route 79/I-195 Interchange Reconstruction Project • Environmental permitting in final stages • Request for Qualifications released Route 79/I-195 Interchange Reconstruction Project Route 79/I-195 Interchange Project Elements • Replace 2-level elevated Rte. 79 with at-grade roadway at the level of the existing Davol Street/Rte. 138 • Add 3 signalized intersections on the new 4-lane Rte. 79 • Reconstruct ramp from I-195 EB to Milliken Blvd. as “Milliken Connector” EB & WB • Milliken Connector EB will include shared use path • Build new Water Street Connector between Rte. 79 and Water Street Route 79/I-195 Interchange Reconstruction Project MassDOT Preferred Alternative-Route 79 Route 79/I-195 Interchange Reconstruction Project Visual Environment Removal of elevated structure improves vistas and views from surface streets. Existing elevated Rte. 79 Elevated roadway removed; Rte. 79 at grade Route 79/I-195 Interchange Reconstruction Project Heritage State Park Improvements • Providing new benches, bike racks and picnic tables • Providing connections for utility upgrades Route 79/I-195 Interchange Reconstruction Project Gates of the City Improvements • Providing enhanced restoration • Providing pedestrian friendly accommodations Route 79/I-195 Interchange Reconstruction Project Gates of the City Improvements Route 79/I-195 Interchange Reconstruction Project Braga Bridge Route 79/I-195 Interchange Reconstruction Project Braga Bridge Project Scope Cleaning and painting of the structural steel on the underside of the bridge Route 79/I-195 Interchange Reconstruction Project Braga Bridge Project Scope • Structural steel repairs • General concrete repairs • Expansion joint replacement Route 79/I-195 Interchange Reconstruction Project Advantages of Combining the Two Projects • One Contractor within overall project area • One overall traffic management plan • Oversight efficiencies for District 5 construction personnel • Management of construction schedule using ABP sunset date • Ability to utilize Incentive/Disincentive provisions • Ability to use Accelerated Bridge Construction Techniques • Strict Quality Control Plans/Measures Route 79/I-195 Interchange Reconstruction Project Next Steps 1. 25% design to be completed this fall 2. 25% design public hearing in early winter 3. MassDOT will issue Request for Proposals to Design-Build entities in November 4. MassDOT will select Design-Build entity in March 5. Contractor Notice-to-Proceed issued in April 6. Project completion date of September 2016 Route 79/I-195 Interchange Reconstruction Project How to Stay Involved • Get on mailing list for updates • Attend periodic design update meetings • Check website for latest news and updates: www.mass.gov/massdot/route79project Route 79/I-195 Interchange Reconstruction Project