Route 79/I-195 Interchange Reconstruction Project Environmental Assessment Public Hearing July 12, 2012, 6 pm Route 79/I-195 Interchange Reconstruction Project Purpose of Tonight’s Meeting • Presentation of Rte. 79/I-195 Interchange Reconstruction Project • MassDOT compliance with Massachusetts Environmental Policy Act (MEPA) and National Environmental Policy Act (NEPA) • Identification of environmental impacts • Public questions and comments Route 79/I-195 Interchange Reconstruction Project Agenda 1. 2. 3. 4. 5. 6. 7. 8. Project Background Project Purpose and Need MassDOT Preferred Alternative Alternatives Evaluation Environmental Impacts and Mitigation Construction Overview Next Steps Questions and Answers Route 79/I-195 Interchange Reconstruction Project Where are we in the project? Getting ready for construction Currently Underway STEP 1 Value Engineering Study This study – required by FHWA – suggested investigating removing Rte. 79 Viaduct at the I-195 Interchange. April 2009 STEP 2 Feasibility Study Detailed review of Value Engineering Study to assess feasibility of removing Rte 79 Viaduct at the I-195 Interchange. July 2009 STEP 3 Planning – Alternatives Study The level of design at the end of this stage is “conceptual.” December 2009 – July 2010 STEP 4 State (MEPA) & Federal (NEPA) Environmental Review This more detailed engineering and environmental analysis will take about 12 months and the level of design will be between 15% and 20% complete. STEP 5 Preliminary Engineering This marks the first intensive design stage. This step will take about 12-14 months and the design at the end will be 25% complete. May 2011 – Oct. 2012 August 2010 – September 2012 Route 79/I-195 Interchange Reconstruction Project STEP 6 Hire DesignBuild Entity to Finish Design & Builds Project This stage will take about 48 months. Construction complete fall of 2016 Background • The interchange has numerous structurally deficient bridges and is in disrepair • Accelerated Bridge Program provides $3 billion for bridges across the Commonwealth • Deadline for completion is 2016 • Alternatives study led to 4 alternatives for environmental analysis Route 79/I-195 Interchange Reconstruction Project MassDOT Preferred Alternative Rte. 79 New Connection to Anawan Street Elevated Roadway removed; replaced at grade. Rte. 79 New Connection to Central Street New Water Street Connector at Rte. 79 4 lanes between Central and Anawan Milliken Connector Eastbound and Westbound Ramp from Central Street to I-195 eliminated Connector Street (Pocasset to Milliken) will become two-way Route 79/I-195 Interchange Reconstruction Project Project Purpose and Need • Address structural deficiencies • Reduce life-cycle costs • Address substandard roadway geometry Route 79/I-195 Interchange Reconstruction Project Project Goals • Improve system linkage connections from I-195 and Rte. 79 • Meet Legislative funding requirements • Improve project-area aesthetics • Minimize impacts to historic and cultural resources • Remain consistent with area planning Route 79/I-195 Interchange Reconstruction Project Alternatives Analysis • 12 Conceptual Alternatives developed and reviewed with public Task Force • Alternatives that were not feasible were eliminated • 4 alternatives retained for detailed study and evaluation in EA/ENF Route 79/I-195 Interchange Reconstruction Project Alternatives Evaluated in EA/ENF • No Build (emergency repairs and ramp closures) • At-Grade Alternative (Preferred Alternative) • Two-Way Single-Level Viaduct (Replacement Alternative) • Rehabilitation of Existing Two-Level Viaduct (Repair Alternative) Route 79/I-195 Interchange Reconstruction Project Evaluation of Alternatives Summary • No Build alternative Does not address deficient structures; does not improve safety; does not reduce lifecycle costs. • At-Grade alternative Fully meets the project’s purpose and need • Two-Way Single-Level Viaduct alternative Does not reduce life-cycle costs as much as the At-Grade alternative and does not improve connections from I-195 and Rte. 79 • Rehabilitation alternative Does not reduce life-cycle costs; does not address substandard geometry Route 79/I-195 Interchange Reconstruction Project At-Grade Preferred Alternative Route 79/I-195 Interchange Reconstruction Project Design Elements and Refinements of Preferred Alternative Route 79/I-195 Interchange Reconstruction Project Design Elements and Refinements Access from I-195 EB to Downtown “½ Signal”: free flow I-195 EB to Rte. 79 Make existing Connector Street 2-way for Downtown access “½ Signal”: access from Milliken to I-195 WB and EB Route 79/I-195 Interchange Reconstruction Project 2-way Water Street Connector with sidewalk and bike lanes Design Refinements and Improvements Water Street Connector Proposed So. Coast Rail platform Water Street Connector Portion of lawn area behind Gates will be taken Route 79/I-195 Interchange Reconstruction Project Environmental Review What is an Environmental Assessment? Evaluation of potential impacts from a proposed project on the existing environment What is the “Existing Environment”? The baseline environment relevant to the project. The environment includes the natural environment and the man-made environment (social and economic aspects). What are “Environmental Impacts”? Positive or negative effects of a project after it is built and impacts that may occur during construction. What are Mitigation Measures? Measures incorporated into the project that minimize impacts. Route 79/I-195 Interchange Reconstruction Project Project Area Existing Environment Transportation/Traffic Pedestrians & Bicycles Right of Way Air Quality Noise Wetlands and Waterways Stormwater Management Wild and Scenic Rivers Coastal Zone Land Use Parkland Visual Endangered Species Historic and Archeological Socio-Economic Environmental Justice Hazardous Materials Route 79/I-195 Interchange Reconstruction Project Existing Environment Route 79/I-195 Interchange Reconstruction Project Transportation/Traffic • Impacts to regional traffic – diversions to other routes – will be minimal • Intersection level of service will meet FHWA and MassDOT performance standards • Construction Phase Traffic Management Plan will be implemented Route 79/I-195 Interchange Reconstruction Project Pedestrian and Bicycle Accommodations • New and improved sidewalks • New signalized intersections will be equipped with pedestrian crossing signals • Enhanced walking environment with overhead structures removed • Bike lanes, shoulders and shared use path connecting Downtown to waterfront Route 79/I-195 Interchange Reconstruction Project Air Quality • Project is included in the Regional Transportation Plan and Transportation Improvement Program • Project is in conformance with the Clean Air Act National Ambient Air Quality Standards • Dust control plan will mitigate short-term impacts during construction Route 79/I-195 Interchange Reconstruction Project Noise • No permanent noise impacts per FHWA standards • Noise control plan will be prepared for project • Some overnight construction may be necessary • Short-term noise impacts during demolition and construction will be addressed to the maximum extent practicable • Design-Build entity will hire community liaison for noise issues Route 79/I-195 Interchange Reconstruction Project Wetlands and Waterways • No permanent impacts to state regulated wetlands • Temporary impact in Quequechan River • Protect Wild and Scenic Taunton River with improved stormwater management Route 79/I-195 Interchange Reconstruction Project Wetlands and Waterways • Permanent impact to federally regulated Bypass Channel • No adverse impacts to floodplain • Erosion controls during construction Route 79/I-195 Interchange Reconstruction Project Stormwater Management • Improvements to stormwater management • Infiltration basin, bio-swale, deep sump catch basins • Clean-out of bypass channel • In compliance with DEP Stormwater standards • Compatible with City’s Combined Sewer Overflow separation program Route 79/I-195 Interchange Reconstruction Project Historic Resources • No Adverse Effect to National Register (or eligible) properties • Visual environment of Historic District will be improved • Sensitive construction during repair of Central Street Bridge over the Quequechan River Route 79/I-195 Interchange Reconstruction Project Visual Environment Removal of elevated structure improves vistas and views from surface streets. Existing elevated Rte. 79 Elevated roadway removed; Rte. 79 at grade Route 79/I-195 Interchange Reconstruction Project Socio-economic • No measurable effects on business productivity due to change in regional travel time • Most regional-to-local travel times are reduced from I-195 to the waterfront and Downtown • No major impact on emergency response times • Improvements in access and visibility will support economic development and job creation on waterfront Route 79/I-195 Interchange Reconstruction Project Right-of-Way (ROW) Issues • Most of the project is within the existing public layout roadway ROW • No residential or business relocations anticipated • Affected abutters will be contacted about ROW impacts after the environmental process and 25% design public hearing Route 79/I-195 Interchange Reconstruction Project Right-of-Way: Heritage State Park Impacts • No permanent takings • Temporary impacts to parking lot, driveway, area next to sidewalk • Areas will be restored after construction • Access to Park and Battleship Cove maintained during construction Route 79/I-195 Interchange Reconstruction Project Right-of-Way: Gates of the City Impacts • Water Street Connector requires taking a portion of city-owned Gates of the City parcel on Ponta del Gada Boulevard • Rear lawn area will be reduced in size • Temporary use restrictions during construction • The Monument itself will not be altered Route 79/I-195 Interchange Reconstruction Project Permits Summary • NEPA/MEPA – NEPA Clearance – MEPA Certificate • Wetlands/Waterways/Tidelands – Army Corps of Engineers Section 404 Category 2 General Permit – Wetlands Protection Act Order of Conditions – DEP Waterways Chapter 91 License – DEP Section 401 Water Quality Certificate Route 79/I-195 Interchange Reconstruction Project Permits Summary, cont. • Coastal Zone Management – Concurrence on Federal Consistency • Section 106 of the National Historic Preservation Act – Finding of No Adverse Effect • National Pollution Discharge Elimination System (NPDES) – Construction Phase Permit Route 79/I-195 Interchange Reconstruction Project Summary of Propose Mitigation Measures Route 79/I-195 Interchange Reconstruction Project Construction Overview • Construction spring 2013 though fall 2016 • Regional through traffic will be diverted to Rte. 24, I-195 and Veterans Memorial Bridge • Detours for local traffic will direct motorists to alternate roadways • Access and signage for Battleship Cove area will be maintained Route 79/I-195 Interchange Reconstruction Project Next Steps 1. MEPA/NEPA environmental clearances due this summer with final permits to follow 2. Jacobs Engineering will complete 25% design for Design-Build entity this summer 3. 25% design public hearing in Fall 2012 4. MassDOT will issue Request for Proposals to Design-Build entities in fall 5. MassDOT will select Design-Build entity in early 2013 6. Design-Build entity notice-to-proceed given in early 2013 Route 79/I-195 Interchange Reconstruction Project How to Stay Involved • Read the EA/ENF and submit comments • Get on mailing list for updates • Attend future public meetings • Check website for latest news and updates: www.mass.gov/massdot/route79project Route 79/I-195 Interchange Reconstruction Project How to Comment on the EA/ENF Submit comments by Fri., July 20 OR Mail Pamela S. Stephenson, Division Administrator Federal Highway Administration 55 Broadway, 10th Floor Cambridge, MA 02142 Attention: Damaris Santiago E-mail Damaris.santiago@dot.gov Richard K. Sullivan, Jr. Commonwealth of Massachusetts Secretary of Energy and Environmental Affairs 100 Cambridge Street Boston, MA 02114 Attention: MEPA Coordinator, EEA #14917 with a copy to Thomas F. Broderick, P.E., Chief Engineer MassDOT Highway Division 10 Park Plaza Boston, MA 02116 Attention: Mary E. Hynes, Project File No. 605223 deirdre.buckley@state.ma.us Mary.E.Hynes@state.ma.us Route 79/I-195 Interchange Reconstruction Project Questions & Answers www.mass.gov/massdot/route79project Route 79/I-195 Interchange Reconstruction Project