4. EXISTING ENVIRONMENT 4.1 Introduction

advertisement
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
4.
EXISTING ENVIRONMENT
4.1
Introduction
PART 1
NEPA
Environmental Assessment
Terminology: The existing interchange is a complex system of roads and ramps. Readers
are directed to Section 4.3 for a detailed description of the existing interchange and
roadway network. In Section 4.3, photos, figures, and text explain the roadways, bridges,
and ramp system, as well as roadway and ramp nomenclature. The terms at-grade and
grade-separated are discussed in Section 1.1.
FHWA NEPA guidance documents, the MassGIS database, literature searches, and site
investigations were used to identify environmental elements within the project area.
Some categories of potential environmental effect are not present within the project area.
The project area does not contain farmland, state or federal rare and endangered species,
or drinking water resources. Additionally, since the natural soils and geology have been
highly modified during the development of the mills, railroad, and highway system, soils
and geology are not discussed as part of the existing environment except relative to oil
and hazardous material contamination.
4.2
Land Use
4.2.1
History and Geography
The City of Fall River is located in southeastern Massachusetts in Bristol County. The
city was built on a series of terraces down to the Taunton River. Geography can often
influence, if not determine, a city’s future. In the case of Fall River, it can be said that
geography not only determined the city’s future development but gave it its name. The
Quequechan River (discussed separately in Section 4.8) is a Wampanoag word meaning
Falling River. The river gave both its name and water power to the city. The Quequechan
River flows westerly through the city, historically dropping steeply through a series of
falls west of Plymouth Avenue to the Taunton River and Mount Hope Bay. That water
power, combined with the navigation and port facilities on the Taunton River, made Fall
River an industrial giant and the leading textile manufacturing center in the United States
in the 19th and early 20th centuries. The water power of Quequechan River was harnessed
as mills were built next to and even over the river. Although textile manufacturing is no
longer the dominant industry, its impact on the city's landscape and culture is still evident
with the many brick mill buildings near the waterfront.
In the early 1960s, I-195 was completed during the period of extensive construction for
the interstate highway system. To accommodate the I-195 roadway, the open water
_______________________________________________________________
Existing Environment
4-1
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
section of the Quequechan River west of Plymouth Avenue was realigned in a series of
underground culverts and control structures which connected to the existing control
structures and underground culverts under the mill buildings. West of the mill buildings,
the Quequechan River was put in an open channel which flows under the Braga Bridge.
The river continues in an open channel under the Central Street Bridge and into
Battleship Cove. The alignment of the Quequechan River can be seen on Figure 4-16.
East of Plymouth Avenue, a portion of the Quequechan River was filled for the
construction of I-195. Mills and other buildings, including the old city hall, were
demolished to construct I-195 through the center of the city.
The Route 79/I-195 Interchange is within the city’s working waterfront and recreational
area, an area that also includes manufacturing and mixed residential and commercial
areas.
Fall River is host to many ethnic festivals which celebrate its heritage as well as the
diversity of the city. Today, the city strives to diversify and strengthen its economy by
maintaining long standing historical industries such as chemicals, while encouraging new
industries, such as wind turbine blades.
4.2.2
Zoning and the Central Business District
The project area is mainly zoned for business and industry with some mixed residential
areas. Business districts are further subdivided, such as the Marine Business District
(MBD) which is along the waterfront, and the Central Business District (CBD). The city
is currently exploring zoning revisions for the waterfront area such as the Transit
Oriented District (TOD). Figure 4-1 identifies the zoning within the project area. In this
document, the CBD refers to the geographical area near or around City Hall.
4.2.3 Utilities
Underground utilities within the project area include water mains, a Combined Sewer
Overflow (CSO) system, gas lines, National Grid power lines, telephone ducts, and street
lighting and signal conduit. CSO is the discharge of combined sewage into a water body
such as a river, lake or stream. Combined sewage is a combination of untreated sewage
and stormwater. The combined sanitary and stormwater system is discussed in Section
4.10. According to the city’s website, public drinking water is supplied by the North
Watuppa Pond and the Copicut Reservoir. These water bodies are well east of the project
area.
Most utilities are underground within the project area. There are utility poles along the
south side of Central Street approaching Davol Street. These poles will be removed and
utilities will be put underground under any Build alternative. Existing utility poles along
Anawan Street will remain under any alternative.
_______________________________________________________________
Existing Environment
4-2
HATH
Central Business District (CBD)
TAY LO
R
Residential
Zoning: August 2007
AW AY
PE AR
C
STR E
ET
E S TR
EET
S TRE E
T
Business
BAYL IE
S ST RE
ET
BA
RN
AB
Industrial
ET
City Zoning Districts Boundary
TR
E
Legend:
YS
Data compiled from the following source:
Office of Geographic Information (MassGIS),
Commonwealth of Massachusetts, Information
Technology Division
VE NUE
DYE
Source Data:
E NT A
RS
TR
EE T
PRE S ID
TURN
ER S
TRE E
138
T
FRE N
C
ODD ST
RE ET
H S TR
T
EET
PRO S
PE CT
ST RE
E
EET
SCHO
O
L S TR
79
CHAL
O NE R
S TRE
STR EE
T
EE T
T
ET
S TRE
TH
TROY
TN
OR
TR
EE
REE
T
ST
ON
D
ET
TR
E
ET
TR
E
CBD
TH
S
T
FO
UR
NS
TR E
ET
TR
EE
FIF
TH
S
Area Zoning
TH
IR
DS
ET
ST
RE
IN
MA
TH
SO
U
SE
C
RL
PE A
UNIO
NS
TRE
E
T
T
S TRE E
GRAN T
TREE T
ERRY
S
M U LB
OD
MA
Route 79 / I-195
Interchange Reconstruction Project
Fall River, MA
AD
S TRE ET
ET
Approx. Scale: 1 " = 750 '
HOP E
RO
EET
SP
R IN
GS
TR E
M S TR
CD
BIA ST
REE T
ST .
W AY
CBD
Central Business Distric
t
B
BROA D
CANA
L ST R
ET
D S TRE
NS
T RE
ET
5W
ALMO N
WA
E LL S
WILLI A
EET
ANA
19
T
COLU M
UL
EV
N
SIO
BO
EN
E XT
Cit
y
Hall
STR E
ET
PO CAS S
E T STREE
T
EN
AY
A DW
BRO
NORT H MAIN
STR
EE T
D
ST R
AR
AN
MI
LL
IK
REE T
EE T
FER RY
ST
ROCK
T.
AW
T
CBD
DS
PO
N
AN
JUN E
DURFEE STREET
S TR EE
AS E S
T REE
BANK
ET
PURC
H
TR
EE
T
ET
DANFORTH STR
EET
E ET
N S TR
G REE
ST.
LS
REE T
TW
HAR
N S TR
ELM S
TRE
EE T
E
AT
ST
P:\MHD\2009\E2X45204\600 Discipline Files\607 Gis\EA-ENF_Figure 4-01_Zoning.mxd
WA
T ER
MIL
LS
T.
NT
RA
R
DIV IS IO
CHER RY STREET
PINE STREET
CE
UT ST
E ST R
R
TE
IN
BAY
LOCU ST STREET
i ver
138
RE E
B ST
C LU
E ET
R
T
S
WALN
MAY STREET
to n
Tau
n
qu e
c ha
nR
DOCT OR ST RE
ET
DAV O
L STR E
ET
R iv
er
Q ue
195
MAPL
Figure 4-1
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
4.3
PART 1
NEPA
Environmental Assessment
Transportation Network
4.3.1 Introduction and Terminology
Introduction
The transportation network within the project area includes interstate, regional, and local
roadway facilities, as well as transit facilities and non-vehicular modes of transportation
facilities for cyclists and pedestrians.
Roadways include Interstate 195 in the east-west direction, state Routes 79 and 138 in the
north-south direction and Route 24 in the north-south direction east of the project area.
These and other local roadways in the region are discussed below and can be located on
Figures 4-2, 4-3, 4-4, and 4-5. Transit facilities are discussed in Section 4.3.7 and bicycle
and pedestrian accommodations are discussed in Section 4.5.
Roadway and Traffic Terminology
Although we all use the transportation network everyday as drivers, pedestrians, or
cyclists, the terms used to describe roadway geometry, traffic operations and the various
parts of the roadway system may not be familiar. Some roadway terms used in this
document are defined below. Other terms are defined throughout the document.
Acceleration lane: An auxiliary lane at the end of an entrance ramp that allows entering
traffic to increase speed before merging into the main travel lanes, at which point the
auxiliary lane terminates.
At-grade roadway: Roadway which intersects with other roadways requiring traffic
control (traffic signals or stop signs etc.).
Auxiliary lane: A lane with a relatively short length that can be used to both enter and
exit the highway.
Deceleration lane: An auxiliary lane at the beginning of an exit ramp with enough length
for a vehicle to reduce travel speed in order to safely maneuver along ramp curvature.
Diverge junction: An exit ramp diverging from the mainline along the same general
direction.
Grade-separated: Two roadways in the vicinity of each other that do not intersect because
of different roadway elevations.
Horizontal alignment: A description of the roadway horizontal curvature connecting the
straight sections of road, known as tangents. If a horizontal curve has a high speed and a
_______________________________________________________________
Existing Environment
4-4
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
small radius of curvature, an increased superelevation (bank) is needed in order to aid in
safe steering of motor vehicles on curved roadways.
Interchange: A grade-separated junction of two roadways with full or partial access
between them. The term "interchange" can refer to a junction between a freeway and a
surface street or a junction between a freeway and another freeway.
Merge junction: An entrance ramp and a mainline merging together in the same general
direction.
Ramp: A short section of road (either for an on-ramp and off-ramp) which allows
vehicles to enter or exit a freeway or arterial.
Roadway geometry: Road design features related to the curvature of the roadway
(horizontal and vertical alignment) and the roadway cross section (number of lanes and
lane width, presence of shoulders and curbs) that relate to the roadway’s operation and
safety.
Ramp junction: The point of connection of a ramp with a roadway.
Terminus: Either end of a transportation route.
Tangent section: Straight section of road.
Vertical alignment: A description of the roadway vertical curvature which is used to
provide a gradual change so that vehicles may smoothly navigate uphill and downhill.
Weave lane: A lane used to both enter and exit the highway.
Weaving: A situation in which vehicles maneuvering right to take an off-ramp, and
vehicles maneuvering left from an on-ramp must cross paths within a limited distance. In
highly urban areas, there frequently is not enough space to locate the ramps further apart
or provide frontage roads to avoid weaving sections.
4.3.2 Regional Roadways
Interstate 195
I-195 runs east-west from Providence, Rhode Island, through Fall River and New
Bedford, ending at I-495 in Wareham, MA. It was constructed between the late 1950s
and the early 1970s. Parts of the then-called "Cape Cod Expressway" and the "Providence
Connection" were included in the Interstate Highway System. The route received a
preliminary designation of I-95E, as a spur off the mainline I-95 and was soon after
designated as I-195.
_______________________________________________________________
Existing Environment
4-5
Legend:
Source Data:
Data compiled from the following source:
Office of Geographic Information (MassGIS), Commonwealth
of Massachusetts, Information Technology Division
Interstate - Limited Access Highway
U.S. Highway
State Route
Major Road
138
79
Veterans Memorial Bridge
24
6
Somerset
103
6
79
Fall River
Braga
Bridge
Route 79
Interchange
Exit 5
138
81
Plymouth Ave.
Interchange
Exits 6/7
tpo
rt
195
24
Wes
P:\MHD\2009\E2X45204\600 Discipline Files\607 Gis\EA-ENF_Figure 4-02_Roadway Network.mxd
138
6
Regional Roadway Network
Approx. Scale: 1 " = 3,000 '
Route 79 / I-195
Interchange Reconstruction Project
Fall River, MA
Figure 4-2
PRE SID
HATH
AWAY
ST
Data compiled from the following source:
Office of Geographic Information (MassGIS), Commonwealth
of Massachusetts, Information Technology Division
TAYLO
R
PEAR
CE ST
REET
REET
STREE
VE N U E
T
TUR
NE
138
U
V
79
!
(
.B.
DANFORTH ST.
CHERRY STREET
I
Approx. Scale: 1 " = 750 '
1"=750'
ROCK
ST
TROY
ST
NOR
TR
E
ET
T.
DS
CONNECTOR
STREET
EE
T
MA
IN
ON
MA
SE
C
OD
DS
TR
SO
UT
H
PEA
RL
S
T.
ST
.
TH
IR
BO
UL
EV
AR
D
ANA
WA
NS
REET
TH
SET ST.
MI
LL
IK
EN
ST.
UNI
ON
HOPE
STREE
T
PURC
HASE
STRE
ET
S T.
GREE
N
HA
T.
PO
ND
S
CANAL
STREE
T
T
GRANT
ST
RY S T
.
MULB
ER
FOUNT
AIN ST
.
STREE
DURFEE
STREET
TE
RB
OR
ST.
WA
T ER
LV D
.
AD
AB
DE
LG
PO
NT
A
IO N
NS
XTE
E
SPRING
Y
ST.
WA
AD
BRO
FERRY
ST.
Y
BROAD
WA
TREET
POCAS
138
U
V
COLUM
BIA
WILLIA
MS
79
!
(
N ST
REE
T
SP
Area Street Names
RIN
GS
TR
EE
T
Route 79 / I-195
Interchange Reconstruction Project
Fall River, MA
T
P:\MHD\2009\E2X45204\600 Discipline Files\607 Gis\EA-ENF_Figure 4-03_Street Locus Map.mxd
STREE
T
TRE
ET
ST
RE
ET
EE
STR
EL L
E ET
AN
AW
AN
S
RA
L
W
HART
S TR
FERRY
ST.
NT
REET
PINE STREET
R
BAY
MIL
L
CE
NORTH MAIN ST
REET
S TRE
LOCUST STREET
RR
.
195
DAVO
L
¦
¨
§
WALNUT STRE
ET
ET N
T S.B.
GE
DAV O
L S TREE
RID
T.
SCHO
O
i ve
nR
MAPLE STREET
n to
AB
ECT S
L ST .
r
PROS
P
CEDAR STREET
Tau
AG
.
ODD ST
.
DAVOL STREET
TURNAROUND
BR
R ST
BA
RN
AB
YS
BAYLIES
STREET
T.
Source Data:
EN T A
Figure 4-3
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
From west to east in Fall River, I-195 has interchanges with Route 79 (Exit 5), Route
81/Plymouth Avenue (Exit 6/7), and Route 24 (Exit 8).
Route 79
Within the project area, Route 79 is a four-lane, limited-access highway with two
northbound and two southbound lanes. It is classified as a principal urban arterial and has
an Average Daily Traffic (ADT) of approximately 40,000 vehicles within the project
area.
The southern terminus of Route 79 is south of the Braga Bridge at Broadway Extension.
Ramps connect Broadway Extension with the two-level viaduct. The northbound ramp
connection to Route 79 can be seen on the right in Photo 4-1. At this point northward
Broadway Extension becomes Davol Street which is below the Route 79 viaduct. Route
79 is carried on the two-level viaduct directly over Davol Street between the historic mill
buildings as shown in Photos 4-2 and 4-3. The viaduct structure extends north for
approximately 1,400 feet over Central Street as shown in Photo 4-4 and Figures 4-8 and
4-9. Route 79 then continues on an embankment between the northbound and southbound
lanes of Davol Street.
Photo 4-1 View of southern limit of Route 79 at Broadway Extension. Arrow indicates ramp from Route 79 southbound. Ramp to Route 79 northbound is on the right.
_______________________________________________________________
Existing Environment
4-8
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Photo 4-2 View of Route 79 Viaduct at Braga Bridge, looking west.
NB and SB viaduct structure in the vicinity of the mill buildings
Photo 4-3 Route 79 Viaduct at Mill Building.
The Route 79 viaduct above the Davol Street
Bridge is an intrusive element within the
American Printing Company-Metacomet Mill
Historic District.
_______________________________________________________________
Existing Environment
4-9
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Photo 4-4 Davol Street & Route 79 Viaduct.
The view is at the Davol Street intersection with Central Street, looking north. Further north of Central Street, at the Davol Street turn-around, Route 79 continues on an
embankment between the NB and SB barrels of Davol Street. From that point, Route 79
travels concurrently with Route 138 until the Veterans Memorial Bridge. Route 138 then
turns westward and Route 79 continues north, merging with Route 24.
Route 24
Route 24 is a north-south state highway which links Fall River with the Boston
metropolitan area to the north. The highway starts at the Rhode Island border as a
continuation of Rhode Island Route 24 and meets I-195 in Fall River at Exit 8. Route 24
continues north, intersecting with I-495. The highway continues north through the City of
Brockton and ends at Interstate 93 in Randolph, MA.
Route 81 Route 81 is a north-south state highway located entirely within the City of Fall River. Route 81/Plymouth Avenue has an interchange (Exit 6/7) with I-195 east of the Route 79 Interchange. 4.3.3 Project Area Roadways
Other roadways within the project area are described below and can be located on Figures
4-3, 4-4, and 4-5.
_______________________________________________________________
Existing Environment
4-10
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Route 138/Broadway Extension is a two-way north-south arterial with its northern
terminus at Anawan/Pocasset Street. Its southern terminus is at the Rhode Island state
line where it becomes RI Route 138. The facility primarily services low density
commercial and retail. North of Anawan Street, Route 138/Broadway Extension becomes
Davol Street. At that point Route 138 runs concurrently with Route 79. It then turns
westward and Route 79 continues north, merging with Route 24.
Davol Street is a local two-way north-south road with its southern terminus at
Anawan/Pocasset Street. Davol Street handles on- and off-ramp traffic for Route 79. It
also carries local traffic from intersecting streets and provides access to Fall River
Heritage State Park (Heritage Park). The section of Davol Street between
Anawan/Pocasset Streets and Central Street is also referred to as “Viaduct Street” on
various maps and plans because Davol Street is on a bridge above the level of the railroad
as shown in the cross section in Figure 4-6. It was called Viaduct Street prior to the
construction of the Braga Bridge and the Route 79 interchange. This document calls this
section of road Davol Street. At Central Street, Davol Street just begins to separate as
shown on Photo 4-4 and Figure 4-7. North of Central Street, Davol Street northbound and
southbound lanes are separated by the Route 79 viaduct as shown in cross section in
Figure 4-8.
Central Street is one-way in the westerly direction (see Photo 4-5). It provides access
from the CBD (City Hall area) to businesses and other attractions along the waterfront
area. It intersects with Davol Street and is carried over the railroad and the Quequechan
River on historic bridges.
Connector Street
Connector Street is a one-way street, approximately 23 feet in width. The street is
approximately 300 feet in length, located just south of the Milliken Boulevard Bridge
over I-195. This short street segment provides access from Milliken Boulevard to
Pocasset Street.
_______________________________________________________________
Existing Environment
4-11
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Photo 4-5 Central Street approach to its intersection with Davol Street.
Anawan and Pocasset Streets are local two-way streets that run east-west and intersect
with Broadway Extension/Davol Street. They provide access from the CBD to businesses
along the waterfront area. West of Davol Street, the road is Anawan Street. East of Davol
Street, it is Pocasset Street.
Milliken Boulevard is a local two-way street in the north-south direction that provides
access between Columbia Street and Central Street/City Hall.
Water Street/Ponta Delgada Boulevard is a local two-way street in the north-south
direction adjacent to the waterfront. This street primarily serves low density commercial
and industrial uses and connects, at its northerly end, with Central Street at Battleship
Cove. It intersects with Columbia Street to the south. South of its intersection with
Anawan Street, Water Street becomes Ponta Delgada Boulevard.
Canal Street is a two-way local street in the north-south direction between Columbia
Street and Broadway Extension. It primarily serves a low to medium density residential
neighborhood.
Harbor Terrace is a local two-way street that connects Central Street to Pine Street. It
primarily serves traffic for the adjacent Fall River Housing Authority Development.
_______________________________________________________________
Existing Environment
4-12
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
4.3.4 Interchange and Ramps
The Route 79/I-195 Interchange (Exit 5) connects I-195 with the southern terminus of
Route 79. "Spaghetti Junction" is a nickname sometimes given to an intertwined, multi­
level roadway interchange that resembles a plate of spaghetti. The ramps for the I-195,
Route 79, and Davol Street connections are often called the spaghetti ramps. The ramps
are either on structures or filled embankments. The ramps (and ramp directions) are
discussed below and identified on Figures 4-4 and 4-5, as well as on the project plans at
the end of the document. Table 4.1 lists the existing ramp connections.
I-195 Off-ramps
At Exit 5, drivers traveling eastbound on I-195 can take Ramp A which connects to Route
79 northbound. Drivers can also connect to Milliken Boulevard by taking Ramp Y which
splits off Ramp A.
Drivers traveling westbound on I-195 take Ramp G which connects to Route 79
northbound. Drivers can also connect to Route 79 southbound by taking Ramp F which
splits off Ramp G.
I-195 On-ramps
Drivers traveling southbound on Route 79 can take Ramp D to connect to I-195. Ramp D
merges with Ramp C. To connect with I-195 westbound, drivers stay on Ramp C. Drivers
heading to I-195 westbound get off Ramp C onto Ramp E.
Drivers traveling north on Broadway Extension can easily take the ramp for Route 79
northbound and then take Ramp C to connect with I-195. However, drivers traveling
south on Broadway Extension must make a potentially dangerous U-turn to connect with
I-195 as illustrated in Photo 4-5.
Drivers traveling west on Central Street can take Ramp L and merge with Ramp C to
connect with I-195 westbound.
Route 79 Ramp Connections with Davol Street
Drivers on Route 79 northbound take Ramp R to connect with Davol Street northbound.
Driver traveling southbound on Davol Street can take Ramp P to connect with Route 79
southbound.
_______________________________________________________________
Existing Environment
4-13
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Table 4-1 Existing Interchange Ramps
Ramp Name
Connects from
Connects To
A
I-195 EB
Route 79 NB
C
Broadway Extension NB
I-195 WB or EB
D
Route 79 SB
I-195 WB or EB
E
Via Ramps C and D
I-195 EB
F
I-195 WB via Ramp G
Route 79 SB
G
I-195 WB
Route 79 NB
L
Bedford Street/Central Street I-195 WB
P
Davol Street SB
Route 79 SB
R
Route 79 NB
Davol Street NB
Y
I-195 EB via Ramp A
Milliken Blvd NB or
SB
_______________________________________________________________
Existing Environment
4-14
Col
um
bia
St.
Crab
Pond
Pont
a De
lgada
Blvd
Gates of the
City Monument
P
Durfee St.
Walnut St.
Con
St. nector
Locust St.
Blv
d
Cherry St.
Pine St.
Blv
d
Ramp ID
NOT TO SCALE
Route 79 / I-195 Interchange Reconstruction
Project
Fall River, MA
Existing Project Area
Roadways & Ramps
Figure 4-4
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
_______________________________________________________________
Existing Environment
4-16
Ramp F onto Route 79 SB
I-1
95
W
W ater
te 7
Rou
B
te 7
Rou
I-1
95
EB
Street
Ramp G
Ram
pG
pC
Ram
Ramp A
D
nd
Ram
pL
Po
cas
set
Str
eet
Ram
p
u
hbo
out
Central Street
l
Davoet
e
Str
Ramp C
9S
9
d
oun
b
h
t
Nor
Ramp E
rd
leva
u
o
B
ken
Milli
Y
mp
a
R
NOT TO SCALE
Route 79 / I-195 Interchange Reconstruction Project
Fall River, MA
Interchange Area Existing
Roadways and
Figure 4-5
Ramps
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
_______________________________________________________________
Existing Environment
4-18
Note: Looking Northbound
Existing Cross Section at Mill Complex
NOT TO SCALE
Route 79 / I-195 Interchange Reconstruction Project
Fall River, MA
Figure 4-6
Note: Looking Northbound
Existing Cross Section at Central Street
NOT TO SCALE
Route 79 / I-195 Interchange Reconstruction Project
Fall River, MA
Figure 4-7
HERITAGE
PARK
Note: Looking Northbound
Existing Cross Section Opposite Heritage Park
NOT TO SCALE
Route 79 / I-195 Interchange Reconstruction Project
Fall River, MA
Figure 4-8
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
4.3.5 Bridges
Portions of the roadways and ramps for the interchange are carried on structures. These
structures are also referred to as bridges or viaducts. The largest structure within the
project area is the Braga Bridge which carries I-195 over the Taunton River and the
Route 79 Viaduct. Although the proposed project includes reconstruction of ramps
connecting to the Braga Bridge, the project does not involve any work on the Braga
Bridge.
The Route 79 viaduct and ramp system consists of 11 structures. Throughout this
document, the term viaduct refers to the two level structure that carries Route 79
northbound (upper level) and southbound (lower level) lanes. The connecting ramps are
referred to by the letter designation given to each ramp (Ramp A, C, etc.) as listed in
Table 4-1 and illustrated in Figures 4-4 and 4-5.
Directly under the Route 79 viaduct, Davol Street is carried on a structure over the
railroad. For this reason, many maps and plans refer to Davol Street as “Viaduct Street.”
Throughout this document, this stretch of road is called Davol Street. A cross section of
the existing roadways between the mill buildings is provided in Figure 4-6. Cross
sections of the proposed roadway with the existing viaduct and ramps in the background
are provided in Section 3 on Figures 3-6, 3-7, and 3-8.
Other bridges within the project area include the two historic stone arch bridges which
carry Central Street over the railroad and over the Quequechan River. The Anawan Street
Bridge carries Anawan Street over the railroad. Milliken Boulevard crosses over I-195
eastbound and westbound, as well as over Pocasset Street and Ramp E, on a bridge
structure. The proposed project does not involve any work on the Milliken Boulevard
Bridge.
Table 4-2 lists the existing bridges in the project area.
Table 4-2 Existing Bridges
Bridge Name/Location
Charles M. Braga, Jr. Memorial Bridge
Route 79 Viaduct and ramps
Davol Street over the railroad
Central Street Bridge over the Quequechan River
Central Street Bridge over the railroad
Anawan Street Bridge over the railroad
Milliken Boulevard over I-195
MassDOT Bridge Number*
F-02-058=S-16-008
F-02-059
F-02-014
F-02-093
F-02-016
F-02-013
F-02-056
*The letter and first number in the bridge number corresponds to the city or town where the bridge is
located. Fall River is the second MA municipality that begins with “F”. The Braga Bridge is in Somerset
and Fall River.
_______________________________________________________________
Existing Environment
4-22
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
4.3.6 Existing Vehicular Connectivity
This section describes the existing vehicular connectivity of Interstate 195 and Route 79
with local roads and the waterfront area. Route 79 was planned in the late 1940s to
handle traffic along the Taunton River waterfront and serve as a regional highway
connection on the western side of Fall River to the regional roadway network such as
Route 24. The road was built over a period of 15 years and the elevated section was
opened in 1965 along with I-195 and the Braga Bridge.
Connectivity to I-195
To I-195 from CBD
As shown on Figure 4-9, drivers coming from the CBD/City Hall area can directly access
I-195 westbound by way of Ramp L onto Ramp C. However, access from CBD/City Hall
to I-195 eastbound now requires a circuitous route on local streets or access to the
Plymouth Avenue Interchange.
To I-195 from Waterfront
There is no direct access from the waterfront area to I-195, either eastbound or
westbound, without making a potentially dangerous U-turn from Broadway Extension as
shown on Photo 4-6.
Photo 4-6 U-turn required on Broadway Extension to access I-195 via Route 79.
Connectivity from I-195
_______________________________________________________________
Existing Environment
4-23
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
From I-195 Eastbound
As shown on Figure 4-10, drivers on I-195 eastbound can go north on Route 79 by way
of Ramp A. However, drivers wishing to access the waterfront and Heritage Park need to
continue north on Route 79 well past the area and loop backwards to the waterfront via
Davol Street. Another option to reach the waterfront area from I-195 eastbound is to take
Ramp Y, off Ramp A, to Milliken Boulevard, if drivers are familiar with local streets.
From I-195 Westbound
Drivers traveling west on I-195 westbound can directly connect to Route 79 northbound
by way of Ramp G. Drivers wishing to go south can take Ramp F off Ramp G and access
Davol Street.
Route 79 Connectivity
Successful navigation from Route 79 to local Fall River destinations such as Battleship
Cove and Heritage Park requires drivers to be alert to the limited signage and visual aids.
Drivers approaching the area on Route 79 southbound must exit 1.5 miles north of the
area at Brightman Street / Route 6 in order to get onto Davol Street.
4.3.7 Transit and Mass Coastal Railroad
Southeastern Regional Transit Authority (SRTA)
The Southeastern Regional Transit Authority (SRTA) was established in 1974 in
response to state legislation which authorized the establishment of regional transit
authorities. SRTA serves Acushnet, Dartmouth, Fairhaven, Fall River, Freetown,
Mattapoisett, New Bedford, Somerset, Swansea, and Westport.
Several bus routes run from the Fall River bus terminal that serve Fall River and other
destinations. Some bus routes travel along Milliken Boulevard and across the Braga
Bridge to Somerset and the Swansea Mall.
Mass Coastal Railroad
The Mass Coastal Railroad runs on north-south tracks through the project area under
Anawan Street, Davol Street and Central Street. Mass Coastal is a Massachusetts-based
freight railroad company which, since January 2008, has had a contract to operate on
MassDOT rail lines. Mass Coastal provides freight service to the Borden & Remington
Corporation facility on the waterfront near the state pier (tracks on right in Photo 4-7).
The two tracks on the left of Photo 4-7 continue south under the Anawan Street Bridge.
_______________________________________________________________
Existing Environment
4-24
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Photo 4-7 Railroad seen from Central Street Bridge
View of the railroad looking south from the Central Street Bridge over the railroad. Track to Borden
& Remington facility is on right.
_______________________________________________________________
Existing Environment
4-25
adw
ay
E
I-195
Bro
xte
From Ramp C
To I-195 WB
nsi
on
Rte. 79 SB
(Lower Level)
mp
Ra
C
Ramp D
(Lower Level)
Ramp L
From Ramp E
To I-195 EB
Legend
Traffic Flow
To I-195 EB & WB
Existing Connectivity To I-195 EB and WB
NOT TO SCALE
Route 79 / I-195 Interchange Reconstruction Project
Fall River, MA
Figure 4-9
I-195
Bro
adw
ay
E
xte
nsi
on
From I-195 EB
9 NB
Rte. 7 Level)
er
(Upp
Ramp G
Central St.
Ramp F
pA
m
Ra
pY
m
Ra
Milliken Blvd.
To Ramp G
From I-195 WB
Legend
Traffic Flow
From I-195 EB & WB
Existing Connectivity From I-195 EB and WB to Route 79
and Local Streets
NOT TO SCALE
Route 79 / I-195 Interchange Reconstruction Project
Fall River, MA
Figure 4-10
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
4.4
Traffic Operations
4.4.1
Existing (2009) Traffic Operations
PART 1
NEPA
Environmental Assessment
Existing traffic operations (Level of Service) for the I-195 freeway sections, weave
sections, ramp junctions and local intersections have been evaluated and are discussed
below in terms of Level of Service (LOS) for the AM and PM peak hour. Additional
information can be found in the Traffic Study in Appendix 1.
Level of Service (LOS) is a measure that reflects the relative ease of traffic flow. This
scale denotes different operating conditions that occur under various traffic volume loads.
It is a qualitative measure of the effect of factors such as roadway configuration, speed,
travel delay, freedom to maneuver, and safety. LOS is divided into a range of six letter
grades, ranging from A to F, with A being the best and F the worst.
FHWA uses the American Association of State Highway Transportation Officials
(AASHTO) guidelines for determining which criteria apply to the performance of an
intersection. MassDOT uses its Design Guide for the same purpose. In urban areas, traffic
operations of LOS D are generally considered adequate according to AASHTO and
MassDOT guidance, while LOS E or F is considered inadequate.
In summary, in the project area, I-195 freeway, weave and ramp junctions operate with
adequate conditions in the AM and PM peak hour. Four intersections (listed in Table 4-3)
have some turning movements that are inadequate but, for the most part, the intersections
currently operate with adequate “overall” conditions.
Existing Freeway LOS
LOS analysis for traffic on freeway sections is based upon density of vehicles. Density is
measured in passenger cars per mile per lane (pc/mi/ln). The freeway sections of I-195 in
the study area were evaluated and all sections currently operate with adequate levels of
service in both the AM and PM peak hour, as illustrated in Figure 4-11.
Existing Weave LOS
A weave section of a highway is the length of the highway where vehicles in two lanes
traveling in the same direction are changing lanes in order to either exit the roadway or
enter the highway from an on-ramp. Weaving areas form along a roadway when a merge
area (on-ramp) is closely followed by a diverge area (off-ramp).
Similar to Freeway LOS analysis, weave section LOS is based upon density of vehicles,
measured in passenger cars per mile per lane (pc/mi/ln). The weave sections of I-195 in
the study area were evaluated and all sections currently operate with adequate levels of
service in both the AM and PM peak hour as illustrated in Figure 4-11.
_______________________________________________________________
Existing Environment
4-28
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Existing Ramp LOS
Vehicles entering a highway must merge with the existing traffic flow from an on-ramp.
Vehicles exiting a highway must change lanes to diverge from the existing traffic flow
onto an off-ramp. The LOS for on- and off-ramp junctions (merge and diverge points) are
based upon the density of vehicles prior to the merge point and after the diverge point.
The interchange ramp junctions in the project area were analyzed and found to operate
with adequate levels of service in the AM and PM peak hour existing conditions as
illustrated in Figure 4-11.
Existing Intersection LOS
LOS designation is defined by average seconds of delay. The average vehicle delay
thresholds for LOS are slightly different between signalized and unsignalized
intersections.
Five intersections within the project interchange, two of which are currently signalized,
were evaluated. Existing traffic operations during the AM and PM peak hours for these
intersections are discussed below and summarized in Table 4-3 and on Figures 4-12 and
4-13 respectively.
Table 4-3 Existing (2009) Intersection Operations
Intersection
Traffic
Overall Level
Locations are shown on Control
Service (LOS)
Of
Notes
Figures 4-11 & 4-12
Broadway Extension at
Columbia Street
Signalized
Adequate operations.
Milliken Blvd / Durfee
Street and Central Street
Davol Street and Anawan
Street/Pocasset Street
Signalized
Adequate operations.
Overall LOS is not
calculated for
unsignalized
intersections.
Davol Street and Central Unsignalized Overall LOS is not
calculated for
Street
unsignalized
intersections.
Milliken Blvd and Ramp Unsignalized Overall LOS is not
calculated for
Y (195 EB off-ramp)
unsignalized
intersections.
Source: Route 79/I-195 Interchange Traffic Study, July 2011, Jacobs.
Unsignalized
4-Way Stop
In PM peak hour, the SB left turn
movement is inadequate. WB
approach is also inadequate.
Adequate operations. LOS D or
better in peak hour.
In AM and PM peak hour, some
movements are inadequate.
In PM peak hour, westbound
movements are inadequate.
Adequate operations.
Broadway Extension at Columbia Street
The overall LOS for the intersection during the AM and PM peak hour is considered
adequate. During the PM peak, however, the southbound left turn on Broadway
Extension operates with a LOS of F and the westbound approach on Columbia Street
currently operates with a LOS of E, both considered inadequate levels of service.
_______________________________________________________________
Existing Environment
4-29
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Milliken Blvd/Durfee Street and Central Street
The intersection operates with adequate levels of service of A and B during both peak
hours.
Davol Street at Anawan Street/Pocasset Street
The southbound lane on Davol Street operates with inadequate LOS of F during the
morning and evening peak hour. The eastbound lane on Anawan Street at the intersection
currently operates with inadequate LOS E during the evening peak hour.
Davol Street at Central Street
In the evening peak hour, all three westbound lanes on Central Street at Davol Street
currently operate with inadequate LOS of E and F.
Milliken Blvd and Ramp Y (I-195 EB off-ramp)
The intersection operates with adequate LOS C during both peak hours. _______________________________________________________________
Existing Environment
4-30
vol S
t
ac
er r
F
lS
t
St
vo
l
vd
Ha
ll
St
St
ke
n
ill
i
Ro
dm
an
S
Legend
Roadway
Viaduct
Ramp
t
Hart
well
St
4 th
St
S
M
ai
n
M
l St
Cana
Colum
bia St
Ci
ty
Bl
Ramp Y
ay
et St
Bedfo
rd St
St
Pocas
s
Ramp C
Tu
nn
el
Tro
y
pC
Ra
m
on
n si
m
p A
Ramp E
3 rd
79
Da
R te
Bl v
d
De
l ga
da
t
Ra
Bank S
t
pF
&G
Ramp L
A
Po
nta
t
D
dw
oa
r
B
en
an
S
t
t
p
Mo
nu
m
NB
(
top
)
m
Elm S
m
Ra
An
aw
N Main St
rT
)
ter
Wa
Ce
nt
ra
lS
Ra
G
Mil
Pine St
Ha
rbo
79
SB
al S
t
R te
St
(bo
tto
m
r
Cen
tr
p
m
Ra
e
E xt
Durfee St
E
Ri
ve
Ta
un
t
NB D
a
DG
e
BR
I
SB Da
vol St
Fronta
g
AG
A
on
BR
Fron
tage
Rd
e Rd
Cedar St
Freeway & Arterial LOS A or B
Freeway & Arterial LOS C or D
Merge/Diverge LOS C or D
Weave LOS C or D
Existing Level of Service (LOS)
NOT TO SCALE
Route 79/I-195 Interchange Reconstruction Project
Fall River, MA
Figure 4-11
Broadway Extension and Columbia St.
Davol St. and Anawan/Pocasset St.
Davol St. and Central St.
Milliken Blvd/Durfee St. and Central St.
Milliken Blvd and Ramp Y
Fron
tage
Rd
e Rd
vol S
t
184 (341)
St
vo
l
Pocas
s
vd
Ha
ll
Ro
dm
an
S
Legend
t
Hart
well
St
4 th
St
5
S
M
ai
n
M
St
St
ke
n
ill
i
l St
Cana
Colum
bia St
1
Ci
ty
Bl
Ramp Y
ay
et St
Bedfo
rd St
St
m
p A
Ramp C
Tu
nn
el
Tro
y
pC
Ra
m
io n
Ramp E
3 rd
79
Da
R te
Bl v
d
De
l ga
da
Po
nta
t
Ra
Bank S
t
pF
&G
Ramp L
A
t
D
dw
oa
Br
en
an
S
t
4
t
p
Mo
nu
m
NB
(
top
)
m
Elm S
m
Ra
An
aw
p
m
Ra
e ns
E xt
Durfee St
ac
er r
rT
)
ter
Wa
F
lS
t
Pine St
Ce
nt
ra
lS
Ra
G
Mil
3
Ha
rbo
(bo
tto
m
79
SB
al S
t
R te
St
Cen
tr
N Main St
NB D
a
E
e
DG
SB Da
vol St
Fronta
g
BR
I
r
Ta
un
t
2
AG
A
Cedar St
on
BR
Ri
ve
1.
2.
3.
4.
5.
Roadway
Viaduct
Ramp
Signalized Intersection – Overall intersection
LOS shown by color of circle
LOS A - B
LOS C - D
LOS E
LOS F
Un-Signalized Intersection
Existing AM Intersection Level of Service
(LOS)
NOT TO SCALE
Route 79/I-195 Interchange Reconstruction Project
Fall River, MA
Figure 4-12
Broadway Extension and Columbia St.
Davol St. and Anawan/Pocasset St.
Davol St. and Central St.
Milliken Blvd/Durfee St. and Central St.
Milliken Blvd and Ramp Y
vol S
t
St
Pocas
s
N Main St
vd
Ha
ll
M
ai
n
M
St
St
ke
n
ill
i
l St
Ci
ty
Bl
Ramp Y
Cana
et St
Bedfo
rd St
St
m
p A
Ramp C
Tu
nn
el
Tro
y
pC
io n
ay
5
Colum
bia St
Ro
dm
an
S
Legend
Roadway
Viaduct
Ramp
t
Hart
well
St
4 th
St
1
Ramp E
Ra
m
t
Ra
Bank S
t
pF
&G
Ramp L
3 rd
79
vo
l
Da
R te
Bl v
d
De
l ga
da
Po
nta
t
D
dw
oa
Br
en
an
S
t
4
t
pA
Mo
nu
m
NB
(
top
)
m
Elm S
m
Ra
An
aw
p
m
Ra
e ns
E xt
Durfee St
ac
rT
)
ter
Wa
F
lS
t
184 (341)
Ce
nt
ra
lS
Ra
G
Mil
Pine St
Ha
rbo
79
SB
al S
t
R te
St
(bo
tto
m
r
Ri
ve
Cen
tr
3
er r
2
Ta
un
t
Fron
tage
Rd
e Rd
E
S
DG
NB D
a
BR
I
e
AG
A
on
BR
Cedar St
SB Da
vol St
Fronta
g
1.
2.
3.
4.
5.
Signalized Intersection – Overall intersection
LOS shown by color of circle
LOS A - B
LOS C - D
LOS E
LOS F
Un-Signalized Intersection
Existing PM Intersection Level of Service
(LOS)
NOT TO SCALE
Route 79/I-195 Interchange Reconstruction Project
Fall River, MA
Figure 4-13
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
4.4.2 Existing Safety Conditions (Crash Analysis)
Safety has been evaluated in terms of crash rates (number of crashes weighted by traffic
volume and length of roadway) for the project area including three specific areas within
the Route 79/I-195 interchange itself that exceed state average rates for similar areas.
Databases were reviewed from the years 2006, 2007 and 2008, the latest available at the
time of analysis. Two areas are weave sections, and the third area is the merge junction of
Ramp E with eastbound I-195. Areas where drivers are either leaving or entering a
roadway require intense lane changing maneuvers. Four local intersections within the
project area exceed the state average crash rates for intersections. These intersections are
discussed below and shown on Figure 4-14.
Interchange Safety Concerns
Ramps D and C have a weave section within the interchange (shown on Figure 4-14 as
Weave Section #1) that has a crash rate of 2.51 crashes per Million Vehicle Miles
Traveled (MVMT), slightly higher than the state average of 2.3 MVMT.
The section of Route 79 southbound from the entrance of Ramp F to the location of the
Ramp D off-ramp and continuing to Broadway Extension also has a weave area (shown
on Figure 4-14 as Weave Section #2) with a higher than average crash rate of 4.17 per
MVMT, compared to the state average of 2.3 MVMT.
The Ramp E merge with I-195 eastbound (shown on Figure 4-14 as Merge Section #3)
has a crash rate of 1.84 per Million Entering Vehicles (MEV). The state average for
unsignalized intersections of 0.62 has been used as a substitute for the analysis of the
ramp since the state does not have historical crash averages for merge junctions.
Factors that may be contributing to the high crash rates include lack of pavement
markings and insufficient weave length. Since the time of analysis, new pavement
markings have been provided.
Local Intersection Safety Concerns
Four intersections (located on Figure 4-12) within the project area have higher than
average crash rates compared with the state average. These intersections are:
• Broadway Extension and Columbia Street
• Milliken Blvd/Durfee Street and Central Street
• Central Street and Davol Street
• Davol Street at Anawan/Pocasset Streets
As shown in Table 4-4, the signalized intersection of Broadway Extension with Columbia
Street has an average of 12 crashes per year and a crash rate of 1.47 MEV which is
_______________________________________________________________
Existing Environment
4-34
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
almost twice the statewide average of 0.82 for signalized intersections. This high rate
may be due to traffic congestion and inadequate signal timing.
Another signalized intersection within the project area that has a higher than average
crash rate is the Central Street intersection with Milliken Boulevard and Durfee Street. It
has a crash rate of 1.19 MEV which is slightly higher than the statewide average. This
may be due to outdated signal equipment and poor intersection operations.
The unsignalized Central Street intersection with Davol Street has a crash rate that is
more than 5 times the statewide average for unsignalized intersections. The crash rate is
3.35 compared to an average of 0.62 for the state. There are several factors that contribute
to driver confusion and the high crash rate at this location. The geometry of the
intersection and the steep grade on Central Street as it approaches Davol Street affect the
line of sight and visibility of oncoming cars. Central Street westbound approaching the
intersection is a wide approach that has no pavement markings which may cause
confusion as drivers must weave as they decide to turn left or right or continue straight,
while at the same time judging when to proceed through the unsignalized intersection.
Meanwhile, drivers on Davol Street northbound approaching the intersection are faced
with the change in road alignment as the NB and SB lanes of Davol Street transition and
shift to either side of the Route 79 viaduct structure as shown in Photo 4-5 in Section
4.3.2.
The intersection of Anawan /Pocasset Streets at Davol Street has an average of 3 crashes
per year for the years 2005 through 2008 and a crash rate a little higher than the statewide
average.
Table 4-4 Intersection Crash Rates
Signalized Intersections
Intersection
Broadway
Extension
and
Columbia Street
Milliken Blvd/Durfee Street and
Central Street
Crash Rate
per Million Entering
Vehicles (MEV)
1.47
Average Rate
Statewide
Compared to Average
Rate
0.82
Moderately higher
1.19
0.82
Moderately higher
Unsignalized Intersections
Intersection
Central Street and Davol Street
Davol Street at Anawan/Pocasset
Crash Rate
per Million Entering
Vehicles (MEV)
3.35
0.63
Average Rate
Statewide
Compared to Average
Rate
0.62
0.62
Substantially higher
Slightly higher
Source: MassDOT, 2006-2008
_______________________________________________________________
Existing Environment
4-35
Ramp G
Ce
nt
ra
2-L
e
et
St
Ramp E
Tu
nn
el
Bl
vd
D
x
yE
wa
d
a
o
n
sio
te n
cas
s
C
Ramp F
G
et
Ramp L
p
Ram
Br
Po
tre
t
p
m
Ra
New
S
lS
iad
ve
lV
An
aw
an
St
p A
Ram
Po
nta
De
lag
ad
aB
lvd
.
uc
t
Weave Section
#2
Ra
mp
Wa
ter
St
Ri
ve
r
Ta
un
to
n
Braga
Bridge
Exceeds Average Statewide
Crash Rate
ke
n
Mi
lli
Ramp Y
Ramp C
Ramp E
Merge Junction #3
Weave Section # 1
Note: Based on 2007 & 2008 State Police Records
NORTH n.t.s
Interchange Areas of Safety Concern
NOT TO SCALE
Route 79/I-195 Interchange Reconstruction Project
Fall River, MA
Figure 4-14
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
4.5
PART 1
NEPA
Environmental Assessment
Pedestrian / Bicycle Accommodations
Existing accommodations for pedestrians and cyclists within the project area are limited.
Although most of the local roadways have sidewalks, they are narrow, in poor condition,
and many do not meet the Americans with Disabilities Act (ADA) standards for width,
surface texture (firm, stable & slip-resistant), slope (steepness), curb ramps, and
obstructions (such as telephone poles). Most intersections are not signalized and therefore
do not have signal protected pedestrian movements. There are no bicycle lanes or paths in
the project area.
4.6
Air Quality
4.6.1
Introduction
Clean Air Act National Ambient Air Quality Standards
The federal Clean Air Act (CAA) of 1963 established funding for the study and the
reduction of air pollution. In 1970, Congress passed a stronger CAA and created the U.S.
Environmental Protection Agency (EPA) to carry out the law. The 1970 CAA, amended
in 1990, required EPA to establish the National Ambient Air Quality Standards
(NAAQS) and to conduct periodic review of the standards. The Clean Air Act established
two types of national air quality standards. Primary standards set limits to protect public
health, including the health of "sensitive" populations such as people with asthma,
children, and the elderly. Secondary standards set limits to protect public welfare,
including protection against decreased visibility and damage to animals, crops,
vegetation, and buildings.
Criteria pollutants are those pollutants that are common and found all over the United
States. EPA uses these "criteria pollutants" as indicators of air quality. The six criteria
pollutants are:
Carbon Monoxide
Sulfur Dioxide
Nitrogen Dioxide
Lead
Ozone
Particulate Matter (PM10 and PM2.5-particle size)
Mobile Source Air Toxics
Mobile source air toxics (MSATs) are compounds emitted from highway vehicles and
non-road equipment which are known or suspected to cause cancer or other serious health
and environmental effects. In February 2007, EPA finalized a rule to reduce hazardous
air pollutants from mobile sources (Control of Hazardous Air Pollutants from Mobile
Sources, February 9, 2007). The rule limits the benzene content of gasoline and reduces
toxic emissions from passenger vehicles and gas cans. EPA estimates that in 2030 this
rule would reduce total emissions of mobile source air toxics by 330,000 tons and VOC
emissions (precursors to ozone and can be precursors to PM2.5) by over 1 million tons.
_______________________________________________________________
Existing Environment
4-37
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
4.6.2 Air Quality Monitoring
The Massachusetts Department of Environmental Protection (MassDEP) operates air
quality monitoring stations across the state and prepares annual reports on air quality.
During 2009 (latest data available at the time of writing), MassDEP operated a network
of 29 monitoring stations located in 21 cities and towns. Not all pollutants are monitored
at each station. The nearest stations that monitor the criteria pollutants are located in:
•
•
•
•
Fall River, Bristol County, at Globe Street
Fairhaven, Bristol County, at Leroy Wood
Milton, Norfolk County, at Blue Hill
Boston, Suffolk County, at Harrison Avenue
With the exception of ozone, Massachusetts is in attainment (meets the standards) for all
criteria pollutants including carbon monoxide, lead, nitrogen dioxide, sulfur dioxide, and
particulate matter (including PM10 and PM2.5). Eastern Massachusetts is classified as a
serious non-attainment area for ozone. The Eastern Massachusetts ozone non-attainment
area includes Barnstable, Bristol, Dukes, Essex, Middlesex, Nantucket, Norfolk, Suffolk,
and Worcester counties.
Once an area is designated a non-attainment area, a “State Implementation Plan” (SIP) is
developed and must include strategies and methods to demonstrate how the state is going
to meet the NAAQS. The CAA requires Metropolitan Planning Organizations (MPOs)
within non-attainment areas to perform conformity determinations prior to the approval
of their Regional Transportation Plans (RTPs) and Transportation Improvement
Programs (TIPs). Conformity to a SIP means that a proposed transportation project would
not cause or contribute to any new violations of the NAAQS; increase the frequency or
severity of NAAQS violations; or delay timely attainment of the NAAQS or any required
interim milestone.
4.6.3
Conformity Determination
The conformity determination analysis for the 2012 Regional Transportation Plan and the
FFY 2012 Transportation Improvement Program (TIP) was prepared by the Southeastern
Massachusetts MPO (SMMPO) in accordance with EPA’s final conformity regulations.
The air quality analysis demonstrated that the implementation of the TIP satisfies the
conformity criteria where applicable and is consistent with the air quality goals in the
Massachusetts SIP. Specifically, the SMMPO has found the emission levels from the FY
2012-2015 TIP, in combination with the emission levels from the other MPOs in its nonattainment area, demonstrate conformity with the SIP. Therefore, the FFY 2012–2015
Transportation Improvement Program (TIP) is in conformity with the SIP.
The Route 79/I-195 Interchange Reconstruction Project has been included in the 2012
RTP and Air Quality Conformity Determination, the TIP for FY 2012-2015, as well as
_______________________________________________________________
Existing Environment
4-38
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
the Massachusetts SIP and STIP. Therefore, this project does not require an air quality
conformity determination.
4.7
Noise
4.7.1
Introduction
A traffic noise analysis was completed to establish existing noise levels in the vicinity of
the Route 79/I-195 Interchange and to set the baseline for the evaluation of potential
impacts from the various alternatives. The project is located within an area that includes
residential areas, schools, manufacturing facilities, commercial properties, recreational
parkland, and multilevel highways and bridges.
Consistent with FHWA Policy and Guidance and 23 CFR 772, the MassDOT Type I
Noise Abatement Program allows for the construction of a noise barrier with the physical
alteration of an existing highway if noise sensitive receptors would be impacted by the
project and a noise barrier is determined to be feasible and reasonable to construct.
Because the proposed improvements would alter existing travel patterns through the
interchange as well as the geometric relationship between the roadways and receptors—
thereby potentially increasing their exposure to localized traffic noise—the project
qualifies as a Type I project.
The tasks involved in the noise study included short-term field measurements
accompanied by traffic counts, model validation to compare the predicted sound levels
with the field-measured levels, and computer modeling of existing and future conditions
for sensitive noise receptors to predict the change in sound levels associated with the
project and to determine potential noise impacts. Computer modeling was performed
using FHWA’s Traffic Noise Model (TNM) program, Version 2.5.
The analysis was performed following the guidelines of the MassDOT Type I and Type II
Noise Abatement Policies and Procedures, effective July 13, 2011, and the recently
revised Federal Highway Administration’s (FHWA) Highway Traffic Noise: Analysis
and Abatement Guidance, dated July 2010, revised January 2011.
_______________________________________________________________
Existing Environment
4-39
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Table 4-5 Common Sound Levels
Table 4-5 Common Outdoor and Indoor Sound Levels
4.7.2 Principles of Highway
Noise
Environmental noise is defined as
the sound in a community emanating
from man-made sources such as
automobiles, trucks, buses, aircraft,
trains, and fixed industrial sources,
or from natural sources such as
animals and wind. Sound levels are
measured in logarithmic units called
decibels (dB).
An overall measurement of sound
results in a single decibel value that
describes the sound environment,
taking all frequencies (pitches) into
account. The human ear, however,
does not sense all frequencies in the
same manner. The “A”-weighted
scale (expressed in dBA units) was
developed to closely approximate the
human sensory response from
highway-related noise. A list of
common noise sources and their
associated sound levels are shown in
Table 4-5.
Since an instantaneous noise
measurement (measured in dBA)
describes noise levels at just one
moment of time, and since very few
noises in a community area are
constant, other descriptors are used
to represent varying sound levels
over extended periods of time. The
noise level descriptor used for highway projects is the hourly equivalent sound level
(Leq). Leq is the steady-state, A-weighted sound level, which contains the same amount
of acoustic energy as the actual time-varying, A-weighted sound level over a one-hour
period.
Usually, public reaction to noise levels is a function of location (urban, suburban, rural),
time of day, fluctuation of noise levels, duration, and individual perception of the listener.
Under normal conditions, a change in noise level of 3 dBA is required for the average
_______________________________________________________________
Existing Environment
4-40
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
person to perceive a difference. A decrease of 10 dBA appears to the listener to be a
halving of noise levels, while an increase of 10 dBA appears to be a doubling of the
noise.
4.7.3
FHWA Noise Abatement Criteria
The FHWA has established Noise Abatement Criteria (NAC) for various land uses, listed
in Table 4-6, to identify noise impacts from roadway projects. Federal regulation 23 CFR
772 states that: “Noise impacts occur when the predicted traffic noise levels approach or
exceed the noise abatement criteria levels, or when the predicted traffic noise levels
substantially exceed the existing noise levels.” If a project causes a noise impact, noise
abatement must be evaluated for mitigation. Noise levels from traffic may increase with a
project but not be considered an impact if the noise abatement criteria levels are not
reached or exceeded.
Adverse noise impacts are defined by MassDOT in two ways. A noise impact occurs
when the computed existing or future sound levels approach (within 1 decibel) or exceed
the FHWA NAC. For example, the NAC for residential areas (Activity Category B) is 67
decibels. MassDOT defines an impact for residential areas when sound levels reach or
exceed 66 decibels (i.e., within 1 decibel of the NAC). A noise impact also occurs when
the computed future sound levels exceed the loudest existing sound levels by 10 decibels
or greater. If adverse noise impacts are predicted, noise reduction measures must be
evaluated to determine if construction of a noise barrier is feasible and reasonable in
accordance with the MassDOT Type I and Type II Noise Abatement Policies and
Procedures.
_______________________________________________________________
Existing Environment
4-41
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Table 4-6 FHWA Noise Abatement Criteria
One-Hour, A-Weighted Noise Levels in Decibels (dB(A))
Leq (h)*
Activity
Activity Description
Category
A
57
Lands on which serenity and quiet are of extraordinary significance and serve an important
(exterior) public need and where the preservation of those qualities is essential if the area is to
continue to serve its intended purpose.
B**
67
Residential
(exterior)
C**
67
Active sport areas, amphitheaters, auditoriums, campgrounds, cemeteries, day care centers,
(exterior) hospitals, libraries, medical facilities, parks, picnic areas, places of worship, playgrounds,
public meeting rooms, public or nonprofit institutional structures, radio studios, recording
studios, recreation areas, Section 4(f) sites, schools, television studios, trails and trail
crossings.
D
52
Auditoriums, day care centers, hospitals, libraries, medical facilities, places of worship,
(interior) public meeting rooms, public or nonprofit institutional structures, radio studios, recording
studios, schools, and television studios.
E**
72
Hotels, motels, offices, restaurant/bars, and other developed lands, properties or activities
(exterior) not included in A-D or F.
F
-Agriculture, airports, bus yards, emergency services, industrial, logging, maintenance
facilities, manufacturing, mining, rail yards, retail facilities, shipyards, utilities (water
resources, water treatment, electrical), and warehousing.
G
-Undeveloped lands.
Source: 23 CFR 772, FHWA Procedures for Abatement of Highway Traffic Noise and Construction Noise.
** Includes undeveloped lands permitted for this Activity Category
* Leq (h) is an energy-averaged, one-hour, A-weighted noise level in decibels (dB(A)). The Leq (h) Activity Criteria
values are for impact determination only, and are not design standards for noise abatement measures.
4.7.4
Noise Monitoring and Development of Model
For this project, noise monitoring was conducted at five locations to determine the
existing sound levels in the project area and to validate the accuracy of the noise model in
predicting traffic noise levels within the noise assessment area. Accessible locations
which are representative of noise sensitive areas were chosen for noise monitoring.
Figure 4-15 identifies the location of the noise receptors. Traffic volume, speed, and
composition data were collected simultaneously with noise monitoring. This data, as well
as roadway and adjacent terrain elevations were used to develop a model of the area
using FHWA’s Traffic Noise Model (TNM) noise prediction software, Version 2.5.
The resulting modeled traffic noise levels were compared with the monitored traffic noise
levels for validation. Once the noise model was validated through comparison with the
monitored traffic noise levels collected at the site, additional receptors were added to the
model to refine the existing noise environment. Validation of the noise model is done to
ensure that changes between future and existing conditions were due solely to changes in
conditions and did not erroneously reflect discrepancies due to modeling and monitoring
techniques. For all of the monitored sites, the model-predicted traffic noise levels were
within 3 dBA of the monitored traffic noise levels, indicating that the model may be used
to accurately calculate traffic noise levels within the study area. Additional information is
provided in the Noise Technical Report in Appendix 2.
_______________________________________________________________
Existing Environment
4-42
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
4.7.5
PART 1
NEPA
Environmental Assessment
Existing Noise Conditions
As shown in Table 4-7, sound levels at all receptors within the noise assessment area are
currently below the applicable NAC for their activity category and are therefore
considered properties that are not impacted. The existing sound levels range between 56
and 64 dBA for Categories B and C properties such as residential, schools and
playgrounds, which is below the 66 dBA approach threshold for this category. Existing
commercial properties (Category E) ranged between 60 and 67 dBA, also well below the
approach threshold of 71 dBA for this category.
Of the 14 receptors which were evaluated against the residential/park NAC of 67 dBA:
• Eight receptor locations were chosen to represent residences near Central Street
and Canal Street;
• Five receptors were chosen to represent parklands at Heritage Park, neighborhood
parks near Central Street and Canal Street, as well as the Gates of the City
monument near Firestone Pond on Water Street;
• One receptor was chosen to predict traffic noise exposure at the John J. Doran
Elementary School on Fountain Street.
Of the four receptors at Anawan Street and Pocasset Street which were evaluated against
the commercial NAC of 72 dBA:
• two were placed on ground level (R9-a and R10-a);
• two others were stacked on top at the same locations but at approximately the
height of the top floor (R9-b and R10-b, 42 feet above ground) of each
commercial building.
The purpose of this arrangement was to sample traffic noise exposure at various heights
of each building relative to the elevated viaduct structure with multiple roadway decks
and associated ramps.
The existing noise levels were used to evaluate the alternatives in terms of noise impacts
for the 2030 Build Condition as discussed in Section 6.
_______________________________________________________________
Existing Environment
4-43
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Table 4-7 Existing Noise Levels
Noise levels are compared with Noise Abatement criteria (NAC)
Location/ Units Represented
Activity Category/
Receptor
Noise Abatement
Criteria
Approach
NAC
Existing
(Leq(h), dBA)
R1
C / 67
Heritage Park-Boardwalk / 1
66
63
R2
C / 67
Heritage Park-Boardwalk / 1
66
63
R3
C / 67
66
61
R4
B / 67
Turner Playground- basketball court
/1
Residential-Front yard / ~10
66
59
R5
B / 67
Residential-Backyard / ~14
66
63
R6
B / 67
66
64
R7
B / 67
66
64
R8
C / 67
Residential-Heritage Heights City
Housing-off Harbor Terrace / 84
Apts.
Residential-Heritage Heights City
Housing-Central Street sidewalk
Terrace / 84 Apts.
Gates of the City Monument / 1
66
58
R9-a
E / 72
71
66
R9-b
E / 72
71
67
R10-a
E / 72
71
60
R10-b
E / 72
71
65
R11
C / 67
66
60
R12
B / 67
66
59
R13
B / 67
66
61
R14
B / 67
66
63
R15
B / 67
Residential-sidewalk near backyard /
~10
Residential-side / ~4
66
62
R16
C / 67
John J. Doran Elementary School / 1
66
56
Commercial-ground level at 132
Anawan Street Mill Complex / ~2
Commercial-top floor at 132 Anawan
Street Mill complex / ~2
Commercial- ground level at 36
Pocasset Street Mill Complex / ~5
Commercial--top floor at 36 Pocasset
Street Mill Complex / ~5
Apartment building playground / 1
Residential-side of building / ~432
Apts.
Residential-front of unit / ~10
Notes: See Figure 4-15 for locations. See Table 4-6 for an explanation of activity categories.
All sound levels are expressed in dBA. (Leq(h), dBA). Leq(h) is an energy-averaged, one-hour, A-weighted
noise level in decibels (dB(A)).
_______________________________________________________________
Existing Environment
4-44
CEDA R STREET
Source Data:
R iv
to n
R1
DAVO
L ST RE
ET
R3
LOCU ST STREET
R4
R2
ch a
nR
CHER RY STREET
R5
i ve
r
PINE STREET
R6
R9-a
R9-b
EE T
DS
PO
N
AY
ADW
BRO
N
R14
POCA
SSET
R13
R15
STRE E T
R11
ANA
WA
NS
T RE
ET
R12
TH
SO
U
ST R
RL
T
ST R
EE
T
PE A
BIA ST
REE
T
TH
DM
AN
S TR
E ET
Noise Modeling Receptors
Approx. Scale: 1 " = 500 '
TR
EE
FO
UR
T
TRE
E
S TRE ET
NS
HOP E
O
ING
S
UNIO
T
S TRE E
GRAN T
TREET
ERRY
S
MULB
FOUN TA
IN
S TRE ET
SP
R
SE
BROA D
CO
ND
W AY
COLU M
EE T
CANA
MA
IN
L ST R
ST
RE
EE T
R16
E
N SIO
XTE
R10-a
R10-b
ET
REE T
T
R
P:\MHD\2009\E2X45204\600 Discipline Files\607 Gis\EA-ENF_Figure 4-15_Noise.mxd
FER RY
ST
S TR EE
D
138
ET
AR
R8
BANK
UL
EV
ST R
ET
BO
AN
TR
E
EN
AW
T.
WA
T ER
AN
LS
MI
LL
IK
ST.
MIL
LS
T.
STREE
T
NT
RA
ELM S
TRE
GREE
N
CE
R7
EE T
que
NORT H MAIN
STR
Q ue
MAY STREET
195
DURFEE STREET
Noise Modeling Receptor Locations
DANFORTH STR
EET
Tau
n
Legend:
79
er
Data compiled from the following source:
Office of Geographic Information (MassGIS), Commonwealth
of Massachusetts, Information Technology Division
Route 79 / I-195
Interchange Reconstruction Project
Fall River, MA
Figure 4-15
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
4.8
PART 1
NEPA
Environmental Assessment
Wetland and Floodplain Resources
The wetland resources in the project area are associated with the Taunton River, the
Quequechan River, and Crab Pond. The Taunton River is discussed separately as a
designated Wild and Scenic River in Section 4.11. Figure 4-16 gives an overview of the
wetlands within the project area.
An Abbreviated Notice of Resource Area Delineation (ANRAD) was submitted to the
Fall River Conservation Commission in order to establish the wetland resource area
boundaries and state jurisdictional determinations pursuant to the Wetlands Protection
Act (WPA) in advance of the final design. The Commission issued an Order of Resource
Determination (ORAD DEP File No. SE-24-0607) in April 2011, which is included in
Section 10.3.
Coordination was also carried out with the US Army Corps of Engineers in order to
obtain the federal jurisdictional status of the Quequechan River Bypass Channel pursuant
to the Clean Water Act (CWA). This is discussed further in Section 4.8.2.
4.8.1
Quequechan River
As shown on Figure 4-16, the Quequechan River (federal riverine system) begins east of
the project area and runs through most of the project site underground in a series of arch
culverts (pipes) that follow the old riverbed to Battleship Cove. The culverts are located
beneath the mill buildings and the mill parking area. There are two control structures
along the culverted portion of the river which were built as part of historic mill operation
to control the flow of water. The two structures (Ironworks #7 and Mill Complex) are
shown in Photos 4-8 and Photo 4-9 respectively. The structures are also located on Sheet
5 of the Existing Conditions Plan Sheets.
_______________________________________________________________
Existing Environment
4-46
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Photo 4-8 Control Structure (Iron Works #7).
The portion of the Quequechan River contained within a culvert underground ends just
west of the railroad track as shown in Photo 4-10. The river then flows within a stone
channel between the piers for the Braga Bridge towards the Central Street Bridge as
shown in Photo 4-11. The river then continues in this open stone lined channel to
Battleship Cove, and ultimately to the Taunton River as shown in Photos 4-12 and 4-13.
The open channel portion of the Quequechan River is tidal. The state wetland resources
associated with the open (tidal) portion of the Quequechan River are Bank (defined by
concrete walls), Land Under Ocean, and Riverfront Area (RA). The RA is a state
regulated resource that is discussed below in Section 4.8.4.
_______________________________________________________________
Existing Environment
4-47
Source Data:
138
Data compiled from the following source:
Office of Geographic Information (MassGIS), Commonwealth
of Massachusetts, Information Technology Division
6
FEMA Flood Data: July 1997
Legend:
Quequechan River in culvert
79
NORT H MAIN ST
RE ET
T
Ri v
e
Davol St.
Wetlands
ROBE
S
r
ON S
n
a
T RE E
ch
Firest
one
Pond
DAV OL
S
Q ueq u e
T. NB
Tau
195
DURFEE STRE
ET
n to
nR
ive
r
Bypass channel and culvert
Central St. Bridge
Control Structures
Over Quequechan River
T
ST
RE
E
PL E A
S
M
AI
N
MI
LL
IK E
TH
IA S T R
EET
SO
U
Crab
Pond
COLU M
B
RD S T
R
RO
DM
AN
S
T
OU
H
EN
AV
T
UE
Wetland Resources
Approx. Scale: 1 " = 1,000 '
195
Qu
eq
ue
ch
r
YM
PL
TR
EE
AN T S
TRE E
T
ve
Ri
SECOND STREET
138
EET
an
P:\MHD\2009\E2X45204\600 Discipline Files\607 Gis\EA-ENF_Figure 4-16_Wetland Resources.mxd
NB
LV
D.
BE DF
O
Route 79 / I-195
Interchange Reconstruction Project
Fall River, MA
Figure 4-16
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Photo 4-9 Mill Complex Outlet Control Structure
Photo 4-10 The Quequechan River culvert ends past the railroad track. Note that the culvert has collapsed. Looking southeast, upstream. Concrete pier on left is for the Davol
Street Bridge. _______________________________________________________________
Existing Environment
4-49
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Photo 4-11 Quequechan River beneath Route 79 Viaduct & I-195 Braga Bridge.
Looking West, Downstream.
Photo 4-12 Quequechan River upstream of Battleship Cove and the Taunton River.
Central Street Bridge is in background.
_______________________________________________________________
Existing Environment
4-50
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Photo 4-13 View of Battleship Cove from Central Street Bridge over the Quequechan River.
4.8.2 Quequechan River Bypass Channel
The Mill Complex Control Structure, discussed above, is designed to divert flow from the
Quequechan River to Crab Pond by way of the Quequechan River Bypass culvert and
Bypass Channel during periods of high flow. Historically, the diverted water was used for
mill operations. From the Mill Complex Control Structure, water flows into an 8-foot
masonry culvert which outlets (Photo 4-14) to an open channel called the Quequechan
Bypass Channel. The concrete bottom channel has a section with masonry walls and a
section with rock armored slopes composed of cut granite block stones. Sediment build­
up within the channel and culvert has impeded flows to this system. The Bypass Channel
flows in a southerly direction and outlets to Crab Pond (described below).
As a result of the Abbreviated Notice of Resource Area Delineation (ANRAD) review by
the Fall River Conservation Commission, the Bypass Channel has been determined to be
non-jurisdictional (i.e. not subject to the WPA regulations) because: a) it was created
through what would otherwise be an upland area; b) it was constructed for stormwater
control and mill operations; c) the flow through the channel is intermittent; and d) there
are no Bordering Vegetated Wetlands upstream. The Order of Resource Area Delineation
issued by the Fall River Conservation Commission on April 12, 2011 is included in
Section 10.3. The New England District, Army Corps of Engineers has determined,
however, that the channel is subject to jurisdiction under Section 404 of the Clean Water
_______________________________________________________________
Existing Environment
4-51
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Act (CWA). The Preliminary Jurisdictional Determination Form issued by the Corps is
included in Section 10.9.
Photo 4-14 Bypass Culvert and Channel
Looking towards the north, the culvert can be seen in lower left as it meets the Bypass Channel. Pier in
foreground supports the Route 79 SB Ramp. Stone armored slopes of Bypass Channel in foreground.
4.8.3
Crab Pond
Crab Pond (federal emergent wetland) is located on a city-owned parcel along Ponta
Delgada Boulevard and Water Street. The northern limit of the Bordering Vegetated
Wetland (containing greater than 50% hydrophytic vegetation) associated with the pond
is defined by a sheet pile wall system (Photo 4-15).
The water level in the pond is variable. The pond receives flow from the Quequechan
Bypass Channel and from the city’s Combined Sewer Overflow (CSO) connection to the
Quequechan River Bypass Channel. Flow to the pond has been restricted over the years
due to siltation within the Channel. Crab Pond is connected to Firestone Pond by way of
pipes under Ponta Delgada Boulevard (Photo 4-16).
_______________________________________________________________
Existing Environment
4-52
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Photo 4-15 Crab Pond, looking northwest toward sheet pile wall.
Photo 4-16 Crab Pond Outlet. Pipes under Ponta Delgada Boulevard carry flow to Firestone Pond. _______________________________________________________________
Existing Environment
4-53
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
4.8.4
PART 1
NEPA
Environmental Assessment
Riverfront Area
The Massachusetts Riverfront Protection Act established the Riverfront Area (RA) as a
wetland resource, subject to the WPA regulations. The RA is an area measured from the
mean annual high water line outward horizontally and parallel to the river. Typically this
distance is 200 feet except in specific large, densely developed cities such as Fall River
where the regulated Riverfront Area is 25 feet. The Riverfront Area does not apply where
a river runs through a culvert 200 feet or more in length. Therefore, along the section of
the Quequechan River that is contained within culverts, there is no Riverfront Area.
Additionally, activities on land occupied by historic mill complexes, as well as projects
that will obtain a Chapter 91 License, are grandfathered or exempted from requirements
for Riverfront Area.
The lower portion of the Quequechan River is open and has an associated 25 foot
Riverfront Area. The Taunton River also has a 25 foot Riverfront Area.
4.8.5
Davol Street Wetland Areas
Adjacent to Davol Street northbound, just north
of Central Street, there are two wetland areas
(federal emergent wetlands).
A small area of Bordering Vegetated Wetlands
(BVW) is located between the railroad
retaining wall and the curb of Davol Street
(Photo 4-17). The area has a hydraulic
connection via drainage culverts to the Taunton
River and is dominated by wetland plants,
including duckweed (Lemna sp). This resource
has been observed on several occasions to hold
several inches of standing water. This small
vegetated wetland is classified as BVW under
the WPA.
A second small area, north of the BVW, is
isolated with no hydraulic connection to any
stream. It is therefore non-jurisdictional
pursuant to the WPA and jurisdictional
pursuant to the CWA.
Photo 4-17 BVW located along Davol Street NB,
looking north. Railroad retaining wall is to the right.
4.8.7
100 Year Floodplain
The Taunton River (federal riverine system) is tidal within the vicinity of the project area.
It has a mapped 100-year flood zone associated with it, as shown in Figure 4-17. Under
_______________________________________________________________
Existing Environment
4-54
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
the WPA, this area is defined as Land Subject to Coastal Storm Flowage (LSCSF). Land
Subject to Coastal Storm Flowage is defined at 310 CMR 10.04 as: "land subject to any
inundation caused by coastal storms up to and including that caused by the 100-year
storm, surge of record or storm of record, whichever is greater".
The two primary types of flood zones (or special flood hazard areas) included in the
Massachusetts Wetlands Protection Act regulations as Land Subject to Coastal Storm
Flowage are velocity zones and A-zones. Velocity flood zones, also known as V-zones or
coastal high hazard areas, have been identified by the Federal Emergency Management
Agency (FEMA) as areas "where wave action and/or high velocity water can cause
structural damage in the 100-year flood," a flood with a 1-percent chance of occurring or
being exceeded in a given year. A-zones are areas inundated in a 100-year storm event
that experience conditions of less severity than conditions experienced in V-zones. Since
FEMA flood zones may experience dangerous storm-generated wave action and surges,
an accurate determination of the spatial extent of these zones is vital to understanding the
level of risk for a particular property or activity.
MassDEP uses the 100-year coastal flooding event as defined and mapped by FEMA,
unless recorded storm data reveals a higher flood elevation. Within the project area the
flood zone is highly urbanized and includes roadways and railroad rights of way. Natural
coastal wetlands, such as salt marsh or coastal dunes are absent from the project area.
Areas defined as subject to flooding within the project vicinity include mill buildings
along Pocasset Street, all of Mill Street (north of Anawan Street), Heritage Park and
almost all of Davol Street.
According to the FEMA mapping, a short segment of the proposed reconstruction of
existing Route 79 roadway along the west edge of the corridor and immediately north of
the Central Street intersection falls within the 100-year Flood Velocity Hazard Zone on
plan view. However, the V Zone flood surge elevation is 19. The existing and proposed
roadway is above this elevation. Additionally, the elevation of the roadway in this
segment is about 30+ feet higher in vertical elevation than water’s edge of the
Quequechan River and about 80 feet east of the river. The Quequechan River is defined
and contained by an existing granite block seawall that provides approximately 3 feet of
reveal height above normal high water.
The majority of the critical storm surge wave action during a 100 year flood under VZone condition will occur further west, about 600 feet away from the limits of the
proposed roadway improvements. This is primarily due to the unique configuration of the
Quequechan River at Battleship Cove which provides a sheltered waterway area within
this zone of the coastline that is not directly impacted by the wave action occurring in
greater Mount Hope Bay and the Taunton River.
_______________________________________________________________
Existing Environment
4-55
Source Data:
TURN
E
Data compiled from the following source:
Office of Geographic Information (MassGIS), Commonwealth
of Massachusetts, Information Technology Division
R S T.
138
FEMA Flood data: July 1997
79
ODD ST
RE ET
R iv
er
Legend:
FEMA Flood Data
to n
100 year floodplain
Tau
n
500 year floodplain
100 yr floodplain Zone V (velocity hazard)
CEDA R STREET
Quequechan River (in culvert)
DANFORTH STR
EET
Bypass channel and culvert
DOCT OR ST RE
ET
PINE STREET
CE
NT
RA
EE T
ELM S
TRE
LS
TR
EE T
iv e
r
NORT H MAIN
STR
nR
S TRE
ET
c ha
EE
T
BANK
ET
S TR EE
T
PO
N
DS
TR
EE T
MIL
LS
TR
q ue
CHER RY STREET
G RE EN
Q ue
T RE
ET
AN
RS
Firestone
Pond
AW
AN
ST .
GRAN ITE STRE ET
WA
TE
BEDFO
RD
WA
NS
T RE
ET
TH
MA
IN
Route 79 / I-195
Interchange Reconstruction Project
Fall River, MA
Figure 4-17
SO
U
L ST R
Approx. Scale: 1 " = 500 '
Floodplain Map
ANA
ET
BO
N
ST
RE
UL
EV
AR
D
STRE E T
EN
IO
NS
EE T
X TE
AY E
AD W
BR O
138
POCA
SSET
MI
LL
IK
Crab
Pond
79
CANA
P:\MHD\2009\E2X45204\600 Discipline Files\607 Gis\EA-ENF_Figure 4-17_FEMA.mxd
DURFEE STREET
LOCU ST STREET
DAV
195
MAY STREET
OL S T
RE
ET
WALNUT S
TR E
S TRE
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
4.9
PART 1
NEPA
Environmental Assessment
Wildlife and Fisheries
The project area is located within a highly urbanized area. Most of the upland areas
consist of industrial facilities, commercial businesses, roadways, and railroads, except for
Heritage Park and the areas around the Gates of the City and Claudio Monuments. Given
the nature and small size of any open areas, their isolation from other larger habitat, and
their proximity to human activity, their potential for wildlife habitat is limited to a few
species common to urban environments.
The Taunton River and the lower portion of the Quequechan River are tidal, although
most of the Quequechan River within the project area is within culverts as discussed in
Section 4.8. Fisheries data discussed in the Taunton River Watershed 2001 Water Quality
Assessment Report identified several coastal fish species including Alewife, Atlantic
Silverside, Cunner, Tautog, and Winter Flounder as some of the fish species found in the
Taunton River. The Taunton River is also a fish run for anadromous fish, including the
state-listed Atlantic Salmon.
The USFWS Federally Listed Endangered and Threatened Species list for Bristol County
Massachusetts (revised 6/22/2009) was reviewed. Effective April 6, 2012, Atlantic
Sturgeon has been listed as a federally endangered species. This species may occur within
the Taunton River, but since there is no work proposed in the river, there is no adverse
effect anticipated. MassDOT has been authorized by FHWA to consult directly with the
National Marine Fisheries Service (NMFS) as the non-federal representative for the
project in a letter from FHWA to NMFS dated April 4, 2012. A Section 7 Consultation
letter, dated April 5, 2012, was sent by MassDOT to the Northeast Regional Office of
NMFS to solicit comments. In a letter dated April 12, 2012, the NMFS stated that no
federally listed or proposed threatened or endangered species and/or designated critical
habitat are known to exist within the project area. No further coordination is required.
The letters are included in Section 10.10.
According to the 2008 Natural Heritage & Endangered Species Program (NHESP), and
confirmed in a letter from NHESP (provided in Section 10.8), the project area is not
within any mapped Priority or Estimated Habitat.
4.10 Stormwater Management System and Combined Sewer
Overflow
The existing drainage from the viaduct and other roadways within the project area
discharges either directly or indirectly into the Quequechan River, Crab Pond, and the
Taunton River. Downspouts from the existing overhead viaduct structure either discharge
directly to the ground and flow overland into the waterways, or connect into the existing
ground level roadway drainage outlets. Sedimentation that has built up at the discharge
_______________________________________________________________
Existing Environment
4-57
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
outlets and within the catch basins compromises the efficiency of the existing drainage
system.
The Quequechan River Bypass Channel, discussed in Section 4.8.2, conveys overflow
during storm events towards Crab Pond from the Canal Street Combined Sewer Overflow
(CSO), identified as wet weather sewage discharge outfall #0019. Fall River has
developed a CSO Abatement Program which includes expansion of the Regional
Wastewater Treatment Plant on Bay Street approximately 3 miles south of the project and
separation of the CSO system. Wastewater collection systems can be "separate" and
"combined" sewers. Separate systems are comprised of two independent piping systems:
one system for "sanitary" sewage (i.e., sewage from homes and businesses) and one
system for stormwater (runoff from roads and other paved surfaces during storms). A
combined sewer system conveys both sanitary sewage and stormwater in one piping
system.
During normal dry weather conditions, sanitary wastes collected in the combined sewer
system are diverted to the Wastewater Treatment Plant. During periods of heavy rainfall,
the capacity of a combined sewer may be exceeded. When this occurs, the excess flow,
which is a mixture of storm water and sanitary wastes, is discharged directly into the
tributary waters. This excess flow is called Combined Sewer Overflow (CSO). Release of
this excess flow is necessary to prevent flooding in homes, basements, businesses, and
streets.
The Taunton and Quequechan Rivers are considered impaired waters by MassDEP and
have Total Maximum Daily Loads (TMDLs) established for pathogens and waterborne
bacteria.
4.11 Wild and Scenic Rivers
The Taunton River is located to the west of the project site and is defined by a concrete
bank. In March 2009, the Taunton River, from its headwaters in Bridgewater to the Braga
Bridge in Fall River, was officially designated as a Wild and Scenic River and was
incorporated into the National Park Service's Wild and Scenic River management
program. Wild and Scenic River designation includes protection of water quality,
historic, cultural, and recreational values.
As part of the process to designate the river a Wild and Scenic River, a Stewardship
Management Plan was developed. The Taunton River Stewardship Plan presents a vision
and action strategies for management and protection of approximately 40 miles of the
River. The major resources for management and protection include agriculture, ecology
and biological diversity, the estuary, fisheries, history and archaeology, recreation and
scenery. The Plan outlines the resources, objectives and action strategies.
Effective April 6, 2012, Atlantic Sturgeon has been listed as a federally endangered
species. This species may occur within the Taunton River, but since there is no work
_______________________________________________________________
Existing Environment
4-58
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
proposed in the river, there is no adverse effect anticipated. Consultation has been
initiated with NMFS as discussed in Section 4.9.
4.12 Massachusetts Coastal Zone
The federal Coastal Zone Management Act of 1972 gave states with marine or Great
Lakes shorelines the opportunity to develop management plans for coastal resources
within the coastal zone and the authority to implement those plans. The project area is
within the Massachusetts Coastal Zone as shown on Figure 4-18.
The Massachusetts Coastal Zone Management Office (MCZM) implements the 2011
Massachusetts Coastal Zone Management Policy Guide (Policy Guide) which is a
component of the federally approved Massachusetts coastal program and replaces the
2002 Massachusetts Coastal Zone Management Plan. The Policy Guide includes the
coastal program polices. MCZM established the Designated Port Area (DPA) program
for the purposes of promoting and protecting marine industrial activities and other
supporting uses. MCZM ensures consistency with its policies by the federal consistency
review process through several laws and regulations such as the Massachusetts
Environmental Policy Act (MEPA), the Massachusetts Wetlands Protection Act, and the
Massachusetts Public Waterfront Act (Chapter 91).
The Massachusetts coastal zone is the area bounded by the seaward limit of the state’s
territorial sea, generally 3 miles from shore to 100 feet landward of major roads, railroads
or other visible right-of-way. The South Coastal Region of MCZM includes the coastal
communities which border on Buzzard’s Bay, Mount Hope Bay and the Taunton River,
including Fall River. The South Coastal Region has two major industrial ports, New
Bedford and Fall River (Mount Hope Bay Designated Port Area).
4.12.1 MA Office of Coastal Zone Management’s Coastal Policies
The Massachusetts Office of Coastal Zone Management has established the following
program policies that address natural, cultural, social, and economic resources.
Water Quality
Water Quality Policy #1 - Ensure that point-source discharges in or affecting the coastal
zone are consistent with federally approved state effluent limitations and water quality
standards.
Water Quality Policy #2 - Ensure that nonpoint source (NPS) pollution controls promote
the attainment of state surface water quality standards in the coastal zone.
Water Quality Policy #3 - Ensure that activities in or affecting the coastal zone conform
to applicable state and federal requirements governing subsurface waste discharges.
_______________________________________________________________
Existing Environment
4-59
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Habitat
Habitat Policy #1 - Protect coastal resource areas including salt marshes, shellfish beds,
dunes, beaches, barrier beaches, salt ponds, eelgrass beds, and fresh water wetlands for
critical wildlife habitat functions as well as other including nutrient and sediment
attenuation, wave and storm damage protection, and landform movement and processes.
Habitat Policy #2 - Restore degraded or former wetland resources in coastal areas and
ensure that activities in coastal areas do not further wetland degradation but instead take
advantage of opportunities to engage in wetland restoration.
Protected Areas
Protected Areas Policy #1 - Preserve, restore, and enhance complexes of coastal
resources of regional or statewide significance through the Areas of Critical
Environmental Concern (ACEC) program.
Protected Areas Policy #2 - Protect state and locally designated scenic rivers and stateclassified scenic rivers in the coastal zone.
Protected Areas Policy #3 - Ensure that proposed developments in or near designated or
registered historic districts or sites respect the preservation intent of the designation and
that potential adverse effects are minimized.
Coastal Hazard
Coastal Hazard Policy #1 - Preserve, protect, restore, and enhance the beneficial
functions of storm damage prevention and flood control provided by natural coastal
landforms, such as dunes, beaches, barrier beaches, coastal banks, land subject to coastal
storm flowage, salt marshes, and land under the ocean.
Coastal Hazard Policy #2 - Ensure construction in water bodies and contiguous land areas
will minimize interference with water circulation and sediment transport. Approve
permits for flood or erosion control projects only when it has been determined that there
will be no significant adverse effects on the project site or adjacent or down coast areas.
Coastal Hazard Policy #3 - Ensure that state and federally funded public works projects
proposed for location within the coastal zone will:
• Not exacerbate existing hazards or damage natural buffers or other natural
resources.
• Be reasonably safe from flood and erosion related damage.
• Not promote growth and development in hazard-prone or buffer areas, especially
in Velocity zones and ACECs.
• Not be used on Coastal Barrier Resource Units for new or substantial
reconstruction of structures in a manner inconsistent with the Coastal Barrier
Resource/ Improvement Acts.
_______________________________________________________________
Existing Environment
4-60
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Coastal Hazard Policy #4 - Prioritize hazard mitigation funds for acquisition of hazardous
coastal areas for conservation or recreation use, and relocation of structures out of coastal
high hazard areas, giving due consideration to the effects of coastal hazards at the
location to the use and manageability of the area.
Ports
Ports Policy #1 - Ensure that dredging and disposal of dredged material minimize adverse
effects on water quality, physical processes, marine productivity and public health.
Ports Policy #2 - Obtain the widest possible public benefit from channel dredging,
ensuring that designated ports and developed harbors are given highest priority in the
allocation of federal and state dredging funds. Ensure that this dredging is consistent with
marine environment policies.
Ports Policy #3 - Preserve and enhance the capacity of Designated Port Areas (DPAs) to
accommodate water-dependent industrial uses, and prevent the exclusion of such uses
from tidelands and any other DPA lands over which a state agency exerts control by
virtue of ownership, regulatory authority, or other legal jurisdiction.
Ports Management Principle #1 - Encourage, through technical and financial assistance,
expansion of water dependent uses in designated ports and developed harbors, re­
development of urban waterfronts, and expansion of visual access.
Public Access
Public Access Policy #1 - Ensure that the adverse impacts of developments proposed near
existing public recreation sites are minimized.
Public Access Management Principle #1 - Improve public access to coastal recreation
facilities and alleviate auto traffic and parking problems through improvements in public
transportation. Link existing coastal recreation sites to each other or to nearby coastal
inland facilities via trails for cyclists, hikers, and equestrians, and via rivers for boaters.
Public Access Management Principle #2 - Increase capacity of existing recreation areas
by facilitating multiple use and by improving management, maintenance and public
support facilities. Resolve conflicting uses whenever possible through improved
management rather than through exclusion of uses.
Public Access Management Principle #3 - Provide technical assistance to developers of
private recreational facilities and sites that increase public access to the shoreline.
Public Access Management Principle #4 - Expand existing recreation facilities and
acquire and develop new public areas for coastal recreational activities. Give highest
priority to expansions or new acquisitions in regions of high need or limited site
availability. Assure that both transportation access and the recreational facilities are
compatible with social and environmental characteristics of surrounding communities.
_______________________________________________________________
Existing Environment
4-61
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Energy
Energy Policy #1 - For coastally dependent energy facilities, assess siting in alternative
coastal locations. For non-coastally dependent energy facilities, assess siting in areas
outside of the coastal zone. Weigh the environmental and safety impacts of locating
proposed energy facilities at alternative sites.
Energy Management Principle #1 - Encourage energy conservation and the use of
alternative sources such as solar and wind power in order to assist in meeting the energy
needs of the Commonwealth.
Ocean Resources
Ocean Resources Policy #1 - Support the development of environmentally sustainable
aquaculture, both for commercial and enhancement (public shellfish stocking) purposes.
Ensure that the review process regulating aquaculture facility sites (and access routes to
those areas) protects ecologically significant resources (salt marshes, dunes, beaches,
barrier beaches, and salt ponds) and minimizes adverse impacts upon the coastal and
marine environment.
Ocean Resources Policy #2 - Extraction of marine minerals (other than sand and gravel)
will be considered in areas of state jurisdiction, except where prohibited by the
Massachusetts Ocean Sanctuaries Act, where and when the protection of fisheries, air and
marine water quality, marine resources, navigation and recreation can be assured.
Ocean Resources Policy #3 - Accommodate offshore sand and gravel mining needs in
areas and in ways that will not adversely affect shorelines areas due to alteration of wave
direction and dynamics, marine resources and navigation. Mining of sand and gravel,
when and where permitted, will be primarily for the purpose of beach nourishment.
Growth Management
Growth Management Principle #1 - Encourage, through technical assistance and review
of publicly funded development, compatibility of proposed development with local
community character.
Growth Management Principle #2 - Ensure that state and federally funded infrastructure
projects primarily serve existing developed areas, assigning highest priority to projects
that meet the needs of urban and community development centers.
Growth Management Principle #3 - Encourage the revitalization and enhancement of
existing development centers in the coastal zone through technical assistance and federal
and state financial support for residential, commercial and industrial development.
4.12.2 MCZM Applicability
The project is within the Massachusetts Coastal Zone Management area (MCZM) and a
portion of it is within the draft Fall River/Mt. Hope Bay Designated Port Area (DPA).
_______________________________________________________________
Existing Environment
4-62
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Table 4-8 identifies which MCZM policies apply to the project. The project’s consistency
with MCZM policies is provided in the CZM Federal Consistency Certification provided
in Section 10.1.
Table 4-8 MCZM Policies and Applicability to Project
MCZM
Policies
and Applicability
Consistency with MCZM
Principles
to Project
Water Quality Policy #1
Yes
All point source discharges will be in compliance
with the DEP Stormwater Regulations.
Water Quality Policy #2
Yes
All disturbed areas will be stabilized.
Water Quality Policy #3
No
Subsurface waste discharges are not part of the
project.
Habitat Policy #1
No
Coastal resources such as dunes and salt marsh are
not present within the project area.
Habitat Policy #2
No
The project is not within an area with potential for
restoration of coastal wetland resources.
Protected Areas Policy #1
No
The project is not within an Area of Critical
Environmental Concern (ACEC).
Protected Areas Policy #2
No
The project will support the Stewardship Plan for the
Taunton River, a federal Wild and Scenic River.
Protected Areas Policy #3
Yes
The project will minimize adverse effects to historic
districts and sites.
Coastal Hazard Policy #1
No
The project area does not include areas of natural
coastal wetlands that would function as flood
control. The land subject to coastal storm flowage
within the project area consists of mill buildings and
roadways.
Coastal Hazard Policy #2
No
The project does not include any work within coastal
water bodies and there will be no interference to
water circulation.
Coastal Hazard Policy #3
No
There are no existing hazards or natural buffers
within the project area. The roadways will be safe
from flood and erosion related damage and will not
promote growth in hazard-prone areas.
Coastal Hazard Policy #4
No
The project does not include acquisition of hazardous
coastal area for conservation.
Ports Policy #1
No
The project does not include dredging in a navigation
channel or open water disposal.
Ports Policy #2
No
The project does not include navigational channel
dredging.
Ports Policy #3
Yes
The project will preserve and enhance vehicular
access to the DPA to support existing industrial and
commercial uses.
Ports Management Principle
No
The project does not directly involve financial
#1
support of water dependent uses within the port.
Public Access Policy #1
Yes
The project will not adversely affect Heritage Park
and will indirectly support awareness of this public
recreational resource.
Public Access Management
Yes
The project will improve public access to the
Principle #1
waterfront and Heritage Park.
Public Access Management
No
The project does not involve increasing (or
Principle #2
decreasing) the capacity of Heritage Park. Visibility
_______________________________________________________________
Existing Environment
4-63
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Table 4-8 MCZM Policies and Applicability to Project
MCZM
Policies
and Applicability
Consistency with MCZM
Principles
to Project
of, and access to, the Park will be improved.
Public Access Management
No
The project does not involve technical assistance to
Principle #3
private recreational facilities.
Public Access Management
No
The project does not involve expansion of
Principle #4
recreational areas.
Energy Policy #1
No
The project does not involve energy facilities.
Energy Management
No
The project does not involve alternative energy
Principle #1
sources such as solar. However, the project will not
preclude any other energy initiatives in the area.
Ocean Resources Policy #1
No
The project does not involve aquaculture.
Ocean Resources Policy #2
No
The project does not involve extraction of marine
minerals.
Ocean Resources Policy #3
No
The project does not involve offshore sand and
gravel mining.
Growth Management
Yes
The project is compatible with other proposed
Principle #1
development in the area.
Growth Management
Yes
The project serves an existing developed area.
Principle #2
Growth Management
Yes
The project is supported by federal and state
Principle #3
resources and will encourage the revitalization and
enhancement of existing development centers in the
coastal zone.
_______________________________________________________________
Existing Environment
4-64
Source Data:
TURN
E
Data compiled from the following source:
Office of Geographic Information (MassGIS), Commonwealth
of Massachusetts, Information Technology Division
138
The Massachusetts Coastal Zone: December 2007
79
ODD ST
RE ET
R iv
er
Legend:
Massachusetts Coastal Zone
Tau
n
to n
Quequechan River (in culvert)
R S T.
DANFORTH STR
EET
CEDA R STREET
TREE
CHER RY STREET
iv e
r
PINE STREET
STRE
ET
NT
RA
ELM S
TRE
TR
E
ET
BANK
S TR EE
T
PO
N
AN
ST
REE
T
DS
TR
EE T
LS
ET
G RE EN
ha
nR
EE T
AW
AN
ST R
GRAN ITE STRE ET
EE T
BE DFO
PO CASS
ET S TRE
ET
TH
Route 79 / I-195
Interchange Reconstruction Project
Fall River, MA
ST
RE
ET
NS
T RE
ET
IN
WA
SO
U
L ST R
Approx. Scale: 1 " = 500 '
Coastal Zone
ANA
MA
EN
BO
ION
EN S
EXT
EE T
AY
AD W
BRO
MI
LL
IK
REE T
UL
EV
AR
D
138
CANA
FER RY
ST
MIL
LS
TR
uec
CE
WA
T ER
P:\MHD\2009\E2X45204\600 Discipline Files\607 Gis\EA-ENF_Figure 4-20_Coastal.mxd
Qu e
q
DURFEE STREET
LOCU ST STREET
DOCT OR ST RE
ET
195
MAY STREET
DAVO
L S TR
EET
WALNUT S
Figure 4-18
RD S TR
EE
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
4.13 Existing Project Area Parks and Monuments
Parks and monuments within the immediate vicinity of the project are discussed below.
These and other parks and monuments within the general vicinity of the project are
identified on Figure 4-19.
Fall River Heritage State Park
The 8.5-acre Fall River Heritage State Park, managed by the Massachusetts Department
of Conservation and Recreation, is located along the Taunton River and Davol Street
overlooking Battleship Cove. Heritage Park is the site of former maritime facilities and
has a Visitors Center, boardwalk, benches, open areas, an antique carousel, and public
sailing program. Outside of the limits of Heritage Park, the boardwalk extends north
along the shore of the Taunton River to Bicentennial Park.
Gates of the City Monument
The Gates of the City Monument, shown in Photos 4-18 and 4-19, is located on a 4-acre
parcel owned by the city off Ponta Delgada Boulevard. It is a replica of the 18th Century
“Gates of the City” of Ponta Delgada on the Portuguese island of San Miguel, Azores.
The monument is constructed of stone from San Miguel. It was sent to Fall River as a gift
from the people of Ponta Delgada to the people of Fall River as part of its “Sister City”
cultural exchange and serves to commemorate the immigration by many PortugueseAzorean people to the Fall River area. The city has confirmed that this is classified as a
monument, not a park (see letter in Section 10.4).
Photo 4-18 Gates of the City
Monument
View looking west.
_______________________________________________________________
Existing Environment
4-66
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Photo 4-19 Gates of the City Monument viewed from Water Street looking northeast.
Claudio War Monument
Completed in 1955, this obelisk-shaped monument, shown in Photo 4-20, honors Private
Manuel F. Claudio who was killed in action during WWII. The monument is located on
approximately 0.13 acres of city-owned land adjacent to Broadway Extension and Canal
Street. Originally erected on Pocasset Street, it was put in storage during the construction
of the Braga Bridge and relocated to its present location in the 1970s.
Photo 4-20 Claudio War Monument.
_______________________________________________________________
Existing Environment
4-67
6
Bicentennial
State Park
Legend:
AW AY
TAY LO
R
Monuments
PE AR
C
STR E
ET
BAYL IE
RN
R S TR
EET
TURN
138
ER S
n to
nR
ODD ST
RE ET
Tau
T
ET
ET
S TRE
CHAL
O NE R
ET
TRE E T
S TRE
HIG H S
ROCK
ET
TR
E
TR
EE
FIF
TH
S
SE
STR E
ET
TROY
TR
EET
RD
S
TH I
TR
E
TH
S
SP
R IN
GS
Parks and Monuments
Approx. Scale: 1 " = 800 '
L S TR
STR EE
T
JUN E
T
AS E S
T REE
RT H
NO
ET
IN
MA
TH
SO
U
ST.
FO
UR
MA
N
TR
EE
T
OD
CO
ND
S
T
TRE
E
NS
UNIO
T
S TRE E
EE T
D
AR
ST
RL
PE A
CANA
TREE T
MULBE
RRY S
GRAN T
T
Route 79 / I-195
Interchange Reconstruction Project
Fall River, MA
AD
FOUN TA
IN
Manuel F. Claudio
Monument
RO
S TRE ET
T
S TRE E
NS
T RE
ET
CD
EAG LE
WA
B
W AY
ANA
T
S TRE ET
S TRE
ET
5W
BROA D
BEDFO
RD
UL
EV
S TREE T
EE
STR
HOP E
T
EE
T
W E LL
BIA ST
REE
PURC
H
GRE EN
T
RE
E
ST
OL
POCAS
S ET
138
COLU M
S TR EE
GRAN ITE STRE ET
EE T
L ST R
ET
D S TRE
TR
19
ALMO N
BANK
LS
H ART
EET
NT
RA
ET
E
AT
ST
N S TR
ST R
BO
N
AN
EN
S IO
D AV
DS
PO
N
EN
EXT
AW
MI
LL
IK
WA Y
CE
EE T
D
B RO A
AN
ELM S
TRE
EE T
NORT H MAIN
STR
PINE STREET
MAY STREET
iv e r
EE T
TR
EE T
ET
T RE
RS
WA
TE
REE T
T
R
TE
IN
P:\MHD\2009\E2X45204\600 Discipline Files\607 Gis\EA-ENF_Figure 4-19_Parks.mxd
MIL
LS
TR
DURFEE STREET
L STR
DAVO
CHER RY STREET
ST
RE
ha
nR
LOCU ST STREET
STR E
ET
u ec
E ST R
Turner
Playground
E ET
Qu e
q
EET
SCHO
O
MAPL
DANFORTH ST
Fall River
Heritage State Park
R
DIV IS IO
H S TR
EET
CEDA R STREET
Gates of the
City Monument
EET
T
PRO S
PE CT
ST RE
E
Fall River
Heritage State Park
M S TR
TRE E
FRE N
C
79
ive
r
Heritage Park
Boardwalk
Battleship Cove
Museum
WILLI A
ET
BA
TURN
E
195
BAY
S ST RE
AB
Quequechan River (in culvert)
REE T
B ST
C LU
E ET
S TR
EET
S TRE E
T
Parks
FER RY
ST
E S TR
ET
HATH
VE NUE
TR
E
Protected and Recreational OpenSpace: February 2010
E NT A
RS
TR
EE T
PRE S ID
DYE
Data compiled from the following source:
Office of Geographic Information (MassGIS), Commonwealth
of Massachusetts, Information Technology Division
YS
Source Data:
Figure 4-19
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
4.14 Cultural Resources (Section 106)
The regulations implementing Section 106 of the National Historic Preservation Act of
1966, as amended, require the lead federal agency for a federal undertaking to identify
historic properties that might be affected by that undertaking [36 CFR 800.4]. The lead
federal agency first must establish the undertaking’s Area of Potential Effect (APE),
which is defined as “the geographic area within which the undertaking may cause
changes in the character or use of historic properties, if any such properties exist” [36
CFR 800.16(d)]. The federal agency then must identify any properties within the APE
that are included in or have previously been determined eligible for inclusion in the
National Register of Historic Places. The agency also must apply the National Register
criteria to other properties within the APE to determine if any additional buildings,
structures, objects, districts, or sites are eligible for inclusion in the National Register.
The regulations require the federal agency to seek information about historic properties
from the State Historic Preservation Officer (SHPO), the tribal historic preservation
officer (THPO) of any American Indian tribe that might attach religious or cultural
significance to properties within the APE, and other consulting parties (i.e. individuals,
organizations, or local governments) that are likely to have knowledge of or concerns
with historic properties in the APE.
MassDOT, acting on behalf of the Federal Highway Administration, established an APE
for the Section 106 review of the Route 79/I-195 Interchange Improvement Project and
identified historic properties within that APE. MassDOT determined that the APE
includes the following locations: 1) the entire length of the Route 79 Viaduct; 2) the
Davol Street Viaduct under the Route 79 Viaduct south of Central Street; 3) Davol Street
northbound and southbound as it extends parallel to the Route 79 Viaduct north of
Central Street; 4) Central Street between Water Street and Durfee Street, Anawan and
Pocasset Streets between Water Street and Milliken Boulevard, and all of Water Street;
and 5) Battleship Cove on the Taunton River. On behalf of MassDOT, the project's
design consultant, Jacobs Engineering Group, Inc., solicited comments regarding this
project and its potential effects on cultural resources from the Fall River Historical
Commission (with a copy of that solicitation sent to the State Historic Preservation
Officer), the Wampanoag Tribe of Gay Head (Aquinnah), and the Mashpee Wampanoag
Tribe in letters dated March 28, 2011. None of those entities has responded to
MassDOT's request for comments.
MassDOT’s Cultural Resources Unit (CRU) staff has determined that a portion of the
project area is located within the National Register-listed American Printing Company–
Metacomet Mill Historic District, which is comprised of several large mid- to late 19th
century and early 20th century industrial buildings along the northerly sides of Anawan
and Pocasset Streets as shown on Figure 4-20. The double-decked Route 79 Viaduct and
the single deck of the Davol Street Viaduct below, pass between two contributing
buildings within the National Register-listed historic district: the Metacomet Mill #6
Building east of the viaducts and the Packing and Storage Building of the American
Printing Company (APC) west of the viaducts. The granite Metacomet Mill #6 Building,
_______________________________________________________________
Existing Environment
4-69
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
constructed in 1847, is the oldest textile mill building in Fall River. The APC Packing
and Storage Building is a larger but more utilitarian brick building constructed c. 1895.
Figure 4-20 American Printing Co. Historic Buildings.
(Source: Massachusetts Historical Commission)
The project area is in view of three decommissioned National Historic Landmark (NHL)
World War II-era U. S. Navy vessels that are docked in Battleship Cove at the Fall River
Heritage Park on the Taunton River. These include the battleship USS Massachusetts, the
destroyer USS Joseph P. Kennedy, Jr., and the submarine USS Lionfish.
The project area is adjacent to two single-span stone arch bridges on Central Street that
are eligible for individual listing in the National Register of Historic Places. Figure 4-21
identifies cultural resources within the APE. The two National Register-eligible singlespan stone arch bridges are discussed below.
The Central Street Bridge (F-02-093) over the Quequechan River, constructed in 1903, is
comprised of a single-span, mortared stone arch with large-block, cut granite voussoirs,
which are wedge-shaped stones forming the curved parts of an arch. The face-ring
voussoirs have rock faced ends. The arch barrel is composed of coursed ashlar sheeting
stones. The arch profile appears to be segmental but is very close to half-round. The
Quequechan River flows through a stone-lined channel at the crossing, which is located
under a welter of elevated modern highways and ramps at the junction of I-195 and Route
79. The bridge is part of an approximately 350'-long stone-faced causeway that carries
Central Street as it descends at a relatively steep 7% grade from Davol Street on the east
toward Water Street on the west near the Taunton River. The spandrel walls on the bridge
and causeway are constructed of random large-block granite rubble. These walls rise
above the roadway to form 4'-high parapets capped by a single course of rock-faced
granite coping stones with drafted margins. The SHPO, in a letter dated August 28, 2003,
concurred with a determination by MassHighway (now MassDOT) that the Central Street
_______________________________________________________________
Existing Environment
4-70
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Bridge over the Quequechan River is eligible for individual listing in the National
Register. Photos 4-21 and 4-22 show the bridge.
The Central Street Bridge was damaged in January 2000 when a gas line buried within
the fill of the causeway exploded and burned, causing a crack in the arch ring and
damage to the spandrel wall on the northerly side of the bridge. The spandrel wall was
subsequently repaired using mortar with high cement content; the repaired areas are
marked by heavily tooled joints, similar to but more boldly scaled than the tooling of the
original mortar joints. A separate major alteration to the bridge, unrelated to the gas line
explosion repairs, involves the inappropriate reconstruction of a 40 foot segment of the
parapet and spandrel wall at the easterly end of the north elevation of the causeway,
including the removal of the original parapet coping stones and the reconstruction of a
corner return at the parapet’s end. This reconstruction was undertaken at an unknown
date using a variety of granite paving stones, cobblestones, curb stones, and small rubble
stones with an apparent disregard for the design of the original structure.
Photo 4-21 Central Street Bridge over the Quequechan River.
View downstream of bridge looking east. Route 79 viaduct is above. Parking lot for the Heritage Park Carousel is in foreground edged by steel guardrail.
_______________________________________________________________
Existing Environment
4-71
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Photo 4-22 Central Street Bridge over the Quequechan River. I-195 Pier in Foreground. Route 79 viaduct in background. View looking north. The Central Street Bridge (F-02-016) over the Mass Coastal Railroad right of way is
comprised of a single-span mortared stone arch with cut granite voussoirs, spandrels, and
parapets as shown in Photo 4-23. The bridge was constructed in 1904 to carry Central
Street over the expanded right of way of the former Old Colony Railroad (now the Mass
Coastal Railroad). Date stones are included in the spandrel walls. Prior to construction of
the existing bridge, the railroad passed through a single-track tunnel that had been cut
through ledge at this location. That tunnel was removed in 1904 and the railroad right of
way was widened to accommodate three tracks. The existing bridge then was constructed
to carry Central Street over the right of way. MassDOT’s Cultural Resources Unit (CRU)
staff has recommended that Bridge F-02-016 be found eligible for individual listing in the
National Register under Criterion C as a good local example of the stone arch structural
type (FHWA and SHPO have concurred). Vehicular collision damage has misaligned
several stone blocks in the north parapet of the bridge and in the adjacent retaining wall
above the railroad cut along Davol Street.
_______________________________________________________________
Existing Environment
4-72
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Photo 4-23 Central Street Bridge over the Railroad, looking south
The project area also includes three other bridges that have been reviewed by
MassDOT’s historic bridge specialists and have been determined not to be eligible for
listing in the National Register as discussed below.
The Route 79 Viaduct (F-02-059), constructed in 1965, is a multi-level complex of
eleven separate bridge and ramp structures that connects Route 79 and I-195 to one
another and to local streets at Interchange #5 at the easterly end of the Braga Bridge. The
mainline Route 79 Viaduct is approximately 2,400 feet long, extending north-south from
its concrete abutments north of I-195 to ramps connecting the viaduct to the at-grade
Broadway Extension south of I-195. The massive double-deck mainline Route 79
Viaduct is comprised primarily of steel stringer spans framed into steel bent piers, but
also includes a two-level, two-span riveted steel Warren truss superstructure that carries
Route 79 over the Quequechan River and the Mass Coastal Railroad right of way just
south of I-195. The entire viaduct structure has been reviewed previously for National
Register eligibility by MassDOT’s Cultural Resources Unit (CRU) staff, under FHWA’s
Amended Section 106 Programmatic Agreement, and the viaduct was determined to be
not eligible on February 14, 2006, because it is less than 50 years old and is comprised of
undistinguished examples of its various structural types.
The existing Davol Street Viaduct was constructed in 1985 to replace an earlier viaduct
that had been constructed at this crossing in 1905. No roadway or bridge existed on this
alignment prior to 1905. The viaduct constructed in 1905 was a 17-span steel plate girder
bridge carried on stone abutments and steel H-beam column piers that connected Davol
Street on the north to Canal Street on the south. At a later date, Broadway was extended
north to connect to the southerly end of the Davol Street Viaduct. The double-deck Route
_______________________________________________________________
Existing Environment
4-73
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
79 Viaduct was constructed in 1965 on a similar alignment directly above the Davol
Street Viaduct. The Massachusetts State Historic Preservation Officer, in a letter dated
August 30, 1984, concurred with the finding of the Massachusetts Department of Public
Works (now MassDOT) that the 1905 Davol Street Viaduct was an undistinguished
example of a common structural type and was not eligible for individual listing in the
National Register of Historic Places.
The existing Davol Street Viaduct is comprised of a 12-span steel stringer superstructure
carried on the cut granite abutments and three steel H-beam column piers from the earlier
viaduct, supplemented by eight reinforced concrete piers constructed in 1985.
MassDOT’s Cultural Resources Unit (CRU) staff has recommended that the 1985 viaduct
be found not eligible for individual listing in the National Register based on its recent
date of construction and common structural type (FHWA and SHPO have concurred).
Bridge F-02-013, which carries Anawan Street over the Mass Coastal Railroad right of
way, was constructed in 1977. The bridge is comprised of a single-span, voided concrete
deck beam superstructure carried on earlier stone abutments with concrete bridge seats.
The stone abutments are part of the massive cut granite retaining walls along the railroad
right of way. The present bridge replaced a 1904 single-span metal pony truss, which is
shown at this crossing on the 1905 Sanborn Fire Insurance Company map. MassDOT’s
Cultural Resources Unit (CRU) staff has recommended that Bridge F-02-013 be found
not eligible for listing in the National Register because it is less than 50 years old and is
an undistinguished example of this common structural type (FHWA and SHPO have
concurred).
The project area also is adjacent to two previously un-inventoried late 19th century/early
20th century industrial complexes on Anawan Street: the Fall River Gas Works and the
Borden & Remington Co. Each of these properties holds some apparent historical
interest. MassDOT’s Cultural Resources Unit staff has prepared Massachusetts Historical
Commission (MHC) inventory forms for both properties and has submitted those forms
to the SHPO.
The Fall River Gas Works Area is comprised of four buildings located on a two acre
parcel bounded by Anawan Street on the north, Water Street on the west, Pond Street and
the Mass Coastal Railroad right of way on the east, and municipal property containing the
c. 2008 Gates of the City Monument on the south. The four buildings include an
Office/Storage Building, an Engine Room Building, a Coal House, and a round,
reinforced concrete Fuel Storage Tank Building along the railroad right of way, shown in
Photo 4-24. The inventoried area is associated with the Fall River Gas Works from the
1880s through the 1920s when that company was involved in the production of coal gas
at this location. One of the buildings, the Coal House, may date to the 1870s, when the
Fall River Iron Works also appears to have manufactured coal gas at this location. The
buildings' functions have been determined by examining Sanborn Fire Insurance maps
from 1888, 1893, 1905, and 1933. The area also includes three infill buildings that appear
to have been constructed during the second half of the 20th century when the site was
operated by the Fall River Gas Co., which was a natural gas distribution company rather
than a coal gas production company.
_______________________________________________________________
Existing Environment
4-74
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Photo 4-24 Former Storage Building for Oil Tank off Anawan Street.
The SHPO has concurred with MassDOT’s opinion that the Fall River Gas Works
complex has lost historic integrity through demolition, alteration, and infill construction
and that the remnants of the complex are not eligible for listing as a district in the
National Register of Historic Places. The SHPO also has concurred with MassDOT’s
opinion that the Fuel Oil Storage Tank Building is not eligible for individual listing in the
National Register. The building has lost integrity through substantial alterations and,
more importantly, appears to have had little direct relationship to the coal gas production
process. The SHPO’s concurrence is dated October 24, 2011 and provided in Section
10.2.
The Borden and Remington Co. Building at 105-115 Anawan Street, is situated on the
southerly side of Anawan Street west of Bridge F-02-013 and directly across the street
from the long southerly elevation of the APC Packing and Storage Building. Constructed
c. 1893, the Borden and Remington Co. Building is a large three-story flat-roofed brick
industrial block that is eight bays wide and eight bays deep. The building is unadorned
except for arched window and door openings, and two rudimentary entablatures across
the main façade (the upper one including a brick dentil course and developed as the
building’s cornice), and simple granite detailing. The building's foundation is constructed
of granite blocks. All window openings have granite sills. A single course of narrow
granite blocks forms the “cornice” of the simple entablature/belt course across the front
facade between the first and second stories. The arched window openings have been
altered with wooden inserts that create rectangular rather than arched openings.
Replacement wooden window sash have been installed throughout the building in a
_______________________________________________________________
Existing Environment
4-75
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
variety of unmatched configurations. The most distinctive feature of the building is a
vertical tier of wide arched loading bays that extends up the three stories of the front
elevation. The projecting metal support for a (now missing) pulley remains attached to
the building directly above the loading bays.
A small one-story rectangular brick out-building is located at the northeast corner of the
property along Anawan Street. The building is identified on the 1933 Sanborn map as
then being used for storage, but may have originally been erected to serve some higher
purpose. A building of similar size is shown at this location on the 1905 Sanborn map,
but the 1905 map indicates that the earlier building was constructed of wood. The
existing brick building is characterized by a hip roof, a wide front window (now boarded
up) and deep eaves exposing jig-sawn rafter ends, giving a Craftsman-style flavor to the
building's otherwise utilitarian design.
The Borden and Remington Co. Building may be eligible for listing in the National
Register of Historic Places under Criterion A for its association with an important local
chemical firm that is still in business at another location in Fall River and under Criterion
C as a good, intact local example of a late-19th century industrial building.
Archaeological Assessment
A review of the MHC archaeological base maps disclosed no recorded pre-contact or
historic archaeological sites in the vicinity of the project area. CRU staff, based on a
review of project plans and historic maps supplemented by a February 11, 2011 site visit,
has assessed the entire project area as having little or no archaeological sensitivity. The
areas to be impacted by the new roadway and ramp construction variously include
existing paved roadway, ramp and parking lot surfaces; an abandoned multi-track railroad
bed, made land associated with the filling of Crab Pond and steep highway embankments.
Many of these areas have been further disturbed by the installation of underground gas,
electrical, water and sewer utilities and drainage structures. The likelihood that
archaeological resources have survived, intact, in the project area, having escaped the
destructive effects of historic and modern development, is extremely low.
MassDOT also has notified the Board of Underwater Archaeology (BUAR) about the
project. The director of the BUAR responded by email to MassDOT on October 18,
2011. The email is provided in Section 10.2 of the EA and includes the following
comments:
“The BUAR conducted a preliminary review of its files and secondary literature sources to identify known and potential submerged cultural resources in the proposed project area. No record of any underwater archaeological resources was found within the specific project area. Based on the results of this review and the very limited nature of bottom lands (Quequechan River) disturbance by the proposed project, the Board expects that this project is unlikely to impact submerged cultural resources.”
As requested by the director of the BUAR in his email, MassDOT agrees to notify the
BUAR if any “heretofore-unknown submerged cultural resources” are encountered
during the course of the project and will take steps to limit adverse effects to those
resources.
_______________________________________________________________
Existing Environment
4-76
ODD ST
RE ET
Source Data:
Data compiled from the following source:
Office of Geographic Information (MassGIS), Commonwealth
of Massachusetts, Information Technology Division
CEDA R STREET
138
Battleship Cove:
USS Massachusetts
USS Lionfish
USS Joseph P. Kennedy
PT Boat 617 (inside Museum)
PT Boat 796 (inside Museum)
OL ST
RE ET
DANFORTH STR
EET
79
DURFEE STREET
LOCU ST STREET
DAV
195
WALNUT S
TRE ET
EE T
T
EE
ST R
ST
RE
AW
AN
ST R
TR
E
S TR EE
T
ET
EE T
PO CA
BEDFO
R
SSET S
TREET
D STR
EET
AR
UL
EV
EN
BO
N
NS IO
ANA
NS
T
STREE
T
IN
MA
TH
SO
U
ST
RL
PE A
CANA
L ST R
WA
ST
MI
LL
IK
Quequechan River
(in culvert)
EE T
TE
EX
W AY
GRAN T
Approx. Scale: 1 " = 500 '
O
DM
Route 79 / I-195
Interchange Reconstruction Project
Fall River, MA
AN
S
T.
SP
R IN
GS
TR
E
Cultural Resources
ET
T
TR
EE
TH
S
BIA ST
REE
R
S TRE E
T
COLU M
T
FO
UR
M ULB
E RRY
FOUN TA
IN
S TRE ET
T
S TRE E
EAG LE
BANK
LS
D
WA
TE
R
AD
BR O
W AY
NT
RA
OL
AN
138
REE T
BROA D
CE
D AV
T.
DS
PO
N
ET
P:\MHD\2009\E2X45204\600 Discipline Files\607 Gis\EA-ENF_Figure 4-21_Historic.mxd
Fall River
Gas Works
EE T
GRE EN
MIL
LS
TR
Borden and
Remington Co.
FER RY
ST
ELM S
TRE ET
STRE
ET
American Printing Metacomet Mill Historic District
Central Street
PINE STREET
Bridge over
Railroad
NORTH MAIN
STR
Central Street
Bridge over
Quequechan River
MAY STREET
CHER RY STREET
Figure 4-21
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
4.15 Socio-Economic
4.15.1 Introduction
This section provides a demographic profile of Fall River, using several factors including
population, households, employment, and income. This section discusses key population,
business and employment characteristics and trends affecting economic development
potential in the project area and the city. The geographic area included in the project area
for the socio-economic discussion extends from the Taunton River on the east to Milliken
Boulevard on the west and from Cedar Street on the north to Ferry Street on the south.
These streets are identified on Figure 1-2 in Section 1. Information was obtained from the
US Census Bureau, SRPEDD, and Claritas Site Reports. The 2000 and estimated 2009
census data is the information currently available. Estimates for 2009 population,
households, businesses and jobs within the project area are based on information obtained
from Claritas Site Reports, a data base that uses baseline US population and economic
census data as well as private data sources and proprietary software to produce annually
updated estimates of demographic and economic characteristics within any specified
geographic area. Claritas Reports provide estimates of demographic and economic
characteristics within small geographic areas, such as the project area. It is widely used
by professional analysts for transportation, economic development, real estate, and
marketing research. Tables 4-9 and 4-10 summarize the information discussed below
4.15.2 Population
The 2000 U.S. Census reported a population of 91,938 residents in the City of Fall River,
with 1,901 residents in the project area. In 2009, the estimated population of Fall River
was 90,885, with 1,798 residents in the project area, representing an estimated decline of
1.2% and 5.4% respectively since 2000. Statewide, Massachusetts experienced a modest
growth rate of 1.7 % from 2000 to 2009, and the population is projected to grow 0.98 %
to 6,522,101 residents by 2014. SRPEDD has projected an increase in the city’s
population to 99,831 by 2030.
Table 4-9 Population Trends 2000-2014
2000
Fall River
Bristol
County
Massachusetts
2009
91,938
534,678
90,885
542,968
2014
Projection
89,830
547,043
6,349,097
6,459,022
6,522,101
Change
2009-2014­
-0.80%1
0.75%
0.98%
Source: US Census, Claritas Site Reports.
In 2009, the average age of the population in Fall River was 37.6 years overall with an
average of 39.7 years in the project area, similar to the statewide average of 36 years. The
project area has a larger percentage of residents aged 65 and older (19.4%) compared to
the city-wide average (17.7%), as well as residents under 18 years old (25%) compared to
city-wide (22.6%). The city’s racial composition was reported as 86.4% white, 4.1%
_______________________________________________________________
Existing Environment
4-78
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
black, and 6% of Hispanic or Latino origin in 2009. Residents in the project area were
76% white, 10% black, and 15.2% of Hispanic or Latino origin.
4.15.3 Households
In 2000, there were 38,759 households in Fall River, increasing to 38,988 in 2009.
Projections estimate a further modest increase to 38,996 in 2014. The project area
reported 958 households in 2000, with an estimated 913 households in 2009, and the
number of households is projected to total 934 household by 2014. Project area
households are slightly smaller (1.96 people per household) than the city-wide average of
2.30 people per household.
There were an average of 1.2 vehicles per Fall River household in 2009, and 0.8 vehicles
per household in the project area in 2009. More than one-third of project area households
are transit-dependent (34.8% have no vehicle), compared to 20.4% of all city households.
The vast majority (88%) of housing units in the project area were renter occupied in 2009
compared with 65% in the City of Fall River. The median value of owner-occupied
housing in the project area ($176,200) was about 70% that of all owner-occupied housing
in the city ($249,728). Almost half (46.5%) of the project area households live in
apartment buildings compared to less than 10% of households in the city overall. One
large residential development in the area is the Heritage Heights city-owned housing
development that is located on Central Street between Milliken Boulevard and Davol
Street.
_______________________________________________________________
Existing Environment
4-79
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Table 4-10 Selected Project Area Demographic Characteristics
Description
2009 Estimated Population
2009 Estimated Households
Persons per Household
Educational Attainment (Age 25+)
Less than 9th grade
Some high school, no diploma
High school graduate
College
Income
Median Household Income
Per Capita Income
Families Below Poverty Level
Race & Ethnicity
Non-Hispanic White
Black
Portuguese Ancestry
Hispanic or Latino Origin
Speak language other than English at home
Age
Age 65 or older
Under 18
Transportation
Average number of vehicles per household
No vehicles in household
Housing Tenure & Value
Owner Occupied
Renter Occupied
Median Value Owner-Occupied Housing
Housing Units by Units in Structure
1 unit attached
1 unit detached
2 units
3 to 19 units
20 to 49 units
50 or more units
Project Area 1.
1,901
913
2.08
City of Fall River
90,885
38,759
2.34
29%
20%
25%
27%
24%
20%
26%
30%
$20,545
$14,805
28%
$35,207
$19,901
14%
76%
10%
49%
15%
32%
86%
4%
43%
6%
36%
19%
25%
18%
23%
0.8
35%
1.2
20%
13%
88%
$176,220
35%
65%
$249,728
0%
2%
5%
45%
3%
47%
1%
20%
12%
57%
3%
7%
Source: U.S. Census data, Claritas Site Reports, 2009, FXM Associates
Totals may not add to 100% due to rounding. 1 Project Area is defined in Section 4.15.
_______________________________________________________________
Existing Environment
4-80
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
4.15.4 Income and Education
In 2009, per capita household incomes in Fall River ($35,200), and the project area
($14,805) were significantly lower than the statewide average ($63,400). The Fall River
per capita income was only 55% of the state average, and 27.7% of project area family
households had incomes below the poverty level compared to 14% in the city overall.
The city’s median household income was approximately 39% of statewide median
household income and the project area median household income was 33% of the
statewide median household income.
Nearly half (48%) of project area residents aged 25+ have not attained a high school level
education compared to 43% in the city overall, and 15.4% statewide. Slightly more than
one-quarter of project area residents had less than a 9th grade education (28.5%),
compared to 23.9% at this level in the city overall. In the project area, 7.7% of residents
had earned a bachelor’s degree or higher, compared to 10.6% in the city and 40% in
Massachusetts.
4.15.5 Employment
In the midst of the national recession in 2009, the City of Fall River had an
unemployment rate of over 14% compared to the statewide rate of 9.2% unemployment.
As shown in Table 4-11, the major sectors of employment in Fall River were
Manufacturing, Health Care and Social Services, and Retail Trade. Since 2001,
Manufacturing and Retail Trade sectors declined by approximately 60% and 10%
respectively, and the Health Care sector grew by 10%. There were an estimated 132
business establishments within the project area which employed more than 900 workers,
and generated approximately $119 million in 2009 business sales. The project area
accounted for about 2% of total jobs and 3% of total business sales in the City of Fall
River. The estimated 21 manufacturers within the project area comprise 11% of all
manufacturing establishments in Fall River overall and most are small businesses
compared to city-wide averages in the manufacturing sector. Relative to all business
types, retail was the smallest industry sector represented in the project area, accounting
for less than 1% of city-wide retail jobs and business sales. Insurance companies were the
leading generator of business sales with 25% of all project area sales, representing 27%
of overall Fall River insurance industry sales.
_______________________________________________________________
Existing Environment
4-81
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Table 4-11 Project Area Employment for Selected Industries
Business Description
Insurance
Wholesale Trade
Health Services
Social Services
Chemical Manufacturing
Recreational Services
Eating and Drinking Places
Rubber/Plastic Products
Museums, Etc.
Professional Services
Instrument Manufacturing
Real Estate
ALL INDUSTRIES
Project Area
Establishments Employees
6
128
18
98
12
52
5
52
1
50
5
43
3
41
3
38
4
38
6
31
2
29
5
22
132
903
Percent of
Project
Area Total
Employees
14.2%
10.9%
5.8%
5.8%
5.5%
4.8%
4.5%
4.2%
4.2%
3.4%
3.2%
2.4%
100.0%
Percent of
Fall River
Category
Employees
27.1%
3.5%
0.8%
1.9%
31.3%
16.7%
1.5%
24.5%
73.1%
8.2%
4.0%
4.4%
2.2%
Source: Claritas Site Reports, 2009, and FXM Associates
4.16 Environmental Justice Populations
Federal Executive Order 12898 (1994) requires federal agencies to identify and address
disproportionately high and adverse human health or environmental effects of federal
actions (such as federally-funded roadway projects) on minority and low-income
populations. If such impacts would result, mitigation measures or alternatives must be
developed to avoid or reduce the impacts.
• Environmental Justice (EJ) populations in Massachusetts are determined when:
households earn 65% or less of the statewide median household income, or
• 25% or more of the residents are members of a minority group, or
• 25% or more of the residents are foreign-born, or
• 25% of the residents are lacking English language proficiency.
Based on the 2000 U.S. Census, Fall River meets all four EJ population criteria. Over
57% of Fall River’s population is living within designated Environmental Justice (EJ)
areas. The project area includes EJ populations.
_______________________________________________________________
Existing Environment
4-82
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
4.17 Oil and Hazardous Materials (OHM)
The project area includes residential, commercial and industrial properties and has a long
history of industrial and transportation land use. Given the current and historical land use,
contaminated soils or groundwater may be encountered during construction and/or
demolition. The project area has been reviewed for the presence of oil and hazardous
material (OHM) in the environment that could be encountered during construction.
Historical industrial operations and waste generation/disposal practices were considered
and searches were done of environmental databases maintained by Federal and State
Environmental Agencies for records of industrial and transportation related spills and
releases of OHM. The project does not involve work within or adjacent to any known
Superfund site. However, several sites adjacent to the interchange are listed on various
databases maintained by the U.S. Environmental Protection Agency and MassDEP.
Remedial action has been completed on many of these sites.
A review of documented spills, releases and Federal and State listed hazardous waste
sites was completed to determine potential impacts to design and construction phases of
the project. A search of environmental information maintained within 47 Federal, 15
State and Local, and 5 Tribal databases, as well as propriety databases, was carried out to
identify records indicating where historic releases of Oil and/or Hazardous Material
(OHM) has occurred.
Two separate electronic records searches were conducted. One search included records
for locations within a one mile radius of the project. To further refine the search and
separate out site data, a second search considered only records within the more immediate
project area. Over 300 records were identified. These records were reviewed and various
types of records were selected to characterize the area. As a result, 11 “sites of interest”
that have the potential to impact the project during construction were identified. These
records include:
• Emergency Response Notification System (ERNS)
• DEP Listed Sites (SHWS)
• Leaking Underground Storage Tanks (LUST)
• Underground Storage Tanks (UST)
• Leaking Above Ground Storage Tank (LAST)
• Above ground Storage Tank (AST)
• DEP MA Release Tracking (RELEASE)
• Spills Reported to MassDEP (SPILLS)
• Manufactured Gas Plants (EDR Proprietary Record)
DEP Listed Sites (SHWS) can have a Response Action Outcome (RAO) which is a
site/release where an RAO Statement was submitted. An RAO Statement asserts that
response actions were sufficient to achieve a level of no significant risk or at least ensure
that all substantial hazards were eliminated. The classes of Remedial Action Outcome
Statement that can be submitted include:
_______________________________________________________________
Existing Environment
4-83
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
Class A RAO- Remedial work was completed and a level of "no significant risk" has
been achieved.
A1: A permanent solution has been achieved. Contamination has been reduced to
background or a threat of release has been eliminated.
A2: A permanent solution has been achieved. Contamination has not been
reduced to background.
A3: A permanent solution has been achieved. Contamination has not been
reduced to background and an Activity and Use Limitation (AUL) has been
implemented.
A4: A permanent solution has been achieved. Contamination has not been
reduced to background and an Activity and Use Limitation (AUL) has been
implemented. Contamination is located at a depth of >15 feet but evaluation has
determined that it is not feasible to reduce it.
Class B RAO- Site assessment indicates that "no significant risk" exists. No remedial work was necessary.
B1: Remedial actions have not been conducted because a level of No Significant Risk exists. B2: Remedial actions have not been conducted because a level of No
Significant Risk exists, but that level is contingent upon one or more Activity
and Use Limitations (AULs) that have been implemented.
B3: Remedial actions have not been conducted because a level of No
Significant Risk exists, but that level is contingent upon one or more Activity
and Use Limitations (AULs) that have been implemented, and contamination is
located at a depth of >15 feet but evaluation has determined that it is not
feasible to reduce it.
Class C RAO- A temporary cleanup. Although the site does not present a "substantial
hazard", it has not reached a level of no significant risk. The site must be evaluated every
five years to determine whether a Class A or Class B RAO is possible. All sites are
expected eventually to receive a Class A or B RAO.
Table 4-12 lists records of the 11 sites. Figure 4-22 identifies the selected sites of interest
within the project area. The complete reports for both searches are provided in Appendix
3.
_______________________________________________________________
Existing Environment
4-84
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
Environmental Assessment
Table 4-12 DEP Listed Sites
Table 4-12
Type of
Site
Record
SHWS
RELEASE
MGP
Source
Figure 4-22
FALL RIVER
GAS CO
FALL RIVER
GAS CO
Address
Contaminate
ID Number
of Release
45 ANAWAN ST
4
Hazardous Material
Not Reported
45 ANAWAN ST
4
Hazardous Material
Not Reported
8
Not Available
Not Available
FALL RIVER
POND & ANAWAN
GAS WORKS CO
STREETS
MANUFACTURE
UST
RS REALTY
18 POCASSET ST
10
Not Available
Not Available
COMPANY
SHWS
RELEASE
UST
UST
SHWS
LUST
RELEASE
NO LOCATION
175 MILLIKEN
AID
BLVD
NO LOCATION
175 MILLIKEN
AID
BLVD
HESS #21513
175 MILLIKEN
POSTAL
SERVICE
Benzene
12/22/2009
No
12/22/2009
No
Phase II
DEP/Tier IIPhase II
No
UST's Removed
Not Reported
DEP/RAO - C1
Not Reported
DEP/RAO - C1
21
Not Available
Not Available
UST's In Use
17 BANK ST
26
OIL
Not Reported
DEP/RAO - A3
17 BANK ST
26
GASOLINE
UST
DEP/RAO - A2
17 BANK ST
26
(1) Not Reported
(2) UST
BLVD
(Release 1) OIL
(Release 2) GASOLINE
No
UST's Filled
UST's In Use
BLVD
SERVICE
Hazardous Material:
DEP/Tier II-
Not Available
#32472
POSTAL
Benzene
AUL
Not Available NEPA
340 MILLIKEN
SERVICE
15
Hazardous Material:
Date
15
7-ELEVEN
POSTAL
15
Regulatory Agency/Status
10/18/2002
No
10/18/2002
No
3/26/2007
No
No
12/15/2004
Yes
12/15/2004
Yes
(1) DEP/RAO - A3
(1) 12/15/2004
Yes
(2) DEP/RAO - A2
(2) 12/15/2004
Shaded area indicates records from the corridor study area.
See Section 4.17 for additional discussion of terms.
RAO: Response Action Outcome
SHWS: DEP listed Hazardous Waste Site MGP: Manufactured Gas Plants AUL: Activity and Use Limitation
RELEASE: DEP MA Release Tracking UST: Underground Storage Tank LUST: Leaking Underground Storage Tank
________________________________________________________________
Existing Environment
Route 79/I-195
Interchange Reconstruction Project
Fall River, MA
PART 1
NEPA
Environmental Assessment
_______________________________________________________________
Existing Environment
4-86
CEDA R STREET
Source Data:
79
to n
R iv
er
Data compiled from the following source:
Office of Geographic Information (MassGIS), Commonwealth
of Massachusetts, Information Technology Division
Tau
n
Legend:
Listed Oil and Hazmat Sites
DANFORTH STR
EET
Sites with Records
DAVO
L ST RE
ET
195
uec
ha
nR
CHER RY STREET
ive
r
PINE STREET
G REE
N S TR
EE T
Qu e
q
DURFEE STREET
DOCT OR ST RE
ET
LOCU ST STREET
MAY STREET
Sites of Interest
See Table 4-12 for site information
CE
MIL
LS
T.
4
ST.
LS
TR
E
26
ET
BANK
S TR EE
ET
T
DS
T.
8
PO
N
WA
T ER
NT
RA
ELM S
TRE
AN
AW
AN
ST R
EE T
10
POCA
SSET
STRE E T
NS
T RE
ET
UL
EV
ST
RE
MA
IN
L ST R
ET
15
SO
U
ST R
ST R
EE
T
PE A
RL
21
T
TH
EE T
CANA
BIA ST
REE
WA
T
TH
TR
EE
DM
AN
FO
UR
T
TRE
E
S TRE ET
NS
HOP E
O
ING
S
S TR
E ET
UNIO
T
S TRE E
GRAN T
TREET
ERRY
S
MULB
FOUN TA
IN
S TRE ET
SP
R
SE
BROA D
CO
ND
W AY
COLU M
ANA
BO
N
EN
SIO
TEN
EX
EE T
AY
ADW
BRO
MI
LL
IK
REE T
R
P:\MHD\2009\E2X45204\600 Discipline Files\607 Gis\EA-ENF_Figure 4-22_Hazmat.mxd
FER RY
ST
AR
D
138
Oil and Hazardous Material Sites
Approx. Scale: 1 " = 500 '
Route 79 / I-195
Interchange Reconstruction Project
Fall River, MA
Figure 4-22
Download