Mobile Number Portability Implementation & Management, Ghana’s Experience Yaw Boamah Baafi Regulatory Administration Division National Communications Authority May 9, 2012 8-May-12 Outline Key MNP Success factors & Principles of Implementation Legal basis for MNP in Ghana MNP Implementation Processes MNP Policy Statement Highlights MNP Project Milestones Achieved Post Implementation of MNP Statistics Ongoing activities 8-May-12 2 Key Number Portability Success Factors Regulatory framework Public Awareness Recipient driven All Call Query (ACQ) method with Central Reference Database (CRDB) and local databases (DBs). No transit traffic Limited reject reasons permitted (not including debt) Per port cost low enough for recipient to cover, even for low ARPU customers Consumer Experience (Convenience & Cost) Variation in prices, QoS, Coverage & Customer Service 8-May-12 3 Principles for Successful MNP Implementation, experts’ views Stakeholders are adequately informed of benefits of MNP, in addition to providing its legal framework/basis. A Policy statement outlining the key principles under which NP will be implemented. Regulator needs to be actively involved. The Regulator needs to form an industry working group (Steering Group) to manage the implementation The regulator MUST chair the group to maintain its focus and drive Terms of Reference is essential for the Steering Group’s (SG) work SG should produce a high-level project plan to manage the implementation (maintaining progress against timescales) Decision Making Rules are key Working Groups have to be able to make (binding) collective decision 8-May-12 Decisions need to be documented and circulated 4 Legal basis for MNP Electronic communications Act, 2008 (Act 775) Section 6(1)(o), states that: “a network operator or service provider shall provide number portability when required to do so by the Authority.” Two sections of the mobile licence which refer to NP: Section 12.3 states; “When the Authority in consultation with the Industry decides to introduce number portability as an obligation for all Licensees, the Licensee shall comply.” Section 15.1 states; “The Licensee shall conform to the numbering plan approved by the Authority and any directions given by the Authority in respect of the numbering plan and any direction the Authority may give to facilitate the portability of telephone numbers between mobile cellular Operators.” 8-May-12 5 MNP Implementation Processes First MNP Workshop held on February 23 to 24, 2010 MNP Project launch in April, 2010, with formation of Steering Group & Subgroups SG meets in 6 wks Steering Group NCA + All mobile operators representatives Legal/Commercial Working Group (Pricing, Public Comm., legal docs., Business rules, issue RFP) 8-May-12 Technical Working Group (Connection with MNP service provider, maintenance, proper routing of traffic Process Working Group (Business rules, IT aspects of port ordering process) 6 Highlights of MNP Policy Statement All networks to route calls & messages by first referring to a database of ported Nos. A central NP service provider solution to be adopted MNP to be recipient operator led Porting must be concluded within 24 hrs worst case Mechanisms for tariff transparency NCA reserve the right to modify, regulate or cancel any porting fee Fair and reasonable rejection reasons, and debt owed to a network cannot be used as a refusal reason to port. 30 days lag period before a ported number can be ported again 30 days lag period before newly activated numbers can port No ‘win back’ strategy for donor operators, once the porting process has begun. 8-May-12 7 MNP Implementation Processes “Cont’d” SG published a Request for Proposal (RFP) for the central service equipment (provider) in July, 2010. Nine companies submitted proposals, from which SG evaluated and selected PortingXS of the Netherlands based on capability, pricing and experience. NCA issued MNP service provider Authorisation to PortingXS Ghana in Nov., 2010. A multilateral contract b/n all operators & PortingXS was drafted with NCA’s involvement. PortingXS charges each connected operator a fixed recurring fee, in addition to a descending fee per successful port chargeable to a recipient operator. 8-May-12 8 MNP Project Milestones Achieved Item MNP project launch Date 15/4/2010 Steering Group & Subgroups members confirmed 19/4/2010 MNP Policy Statement accepted as a working document 4/5/2010 Operators Internal Impact Assessment 21/4/2010 – 20/7/2010 30/7/2010 Issue Request for Proposal (RFP) Tender Evaluation Preferred Bidder selected (PortingXS) 6/9/2010 – 30/9/2010 4/10/2010 Initial MNP Service Provision Authorisation issued to PortingXS 12/11/2010 MNP System Specification concluded 17/12/2010 Commercial, Legal & Service Level Agreement (SLA) Negotiations 31/01/2011 8-May-12 9 MNP Project Milestones Achieved “Cont’d” Item Contracting Signing Date 10/06/2011 Preparation of Business rules 28/03/2011 Technical Specification Document 28/03/2011 MNP Regulations 20/06/11 MNP System Installation at Primary site & Testing 14/02/2011 MNP System Adjustment & Links to Operators 23/02/2011 Training Session for Operators & NCA Operator end-to-end Testing 3/03/30114/03/2011 7/03/11-17/06/11 Transfer Maintenance to Operators 1/07/11 MNP Go Live in Ghana 7/07/11 8-May-12 10 The Porting Process Recipient submits request to system: Authorisation request sent to donor as soon as customer sends validation SMS to system Donor responds within 4 hours aproving or rejecting request Recipient sends instruction request to start the actual port Donor sends confirmation that customer is terminated (or system does it within 15 minutes regardless) System sends broadcast message to all operators about the newly ported number 8-May-12 11 Post Implementation of MNP SG maintained & a Working Group established (IT, Technical, Sales & Helpdesk personnel) SG meets in 6-8 weeks intervals and WG meets as and when necessary. 8-May-12 12 No. of Ports per Months Month No. of Ports Average Time (Hrs : mins) July’ 11 21,073 5:21 August’ 11 43,593 4:16 September’ 11 41,031 3:07 October’ 11 32,772 2:53 November’ 11 20,188 3:55 December’ 11 17,892 3:10 January’ 12 23,242 3: 21 February’ 12 28,319 3: 15 March’ 12 29,424 9:10* April’ 12 29,828 2:37 Total 287,362 4:12 Fastest port in April took 31 seconds from start to finish 8-May-12 13 Cumulative Requests by Category 300,000 250,000 200,000 150,000 100,000 50,000 0 Jul-11 Aug-11 Sep-11 Oct-11 Authorisation Blocked 8-May-12 Nov-11 Dec-11 Aborted Jan-12 Feb-12 Mar-12 Apr-12 Request Completed 14 8-May-12 15 MNP Statistics for February A typical port timing in February, 2012 is as follows (28,319): 5% were completed within 15 minutes 48% were completed between 15 minutes and 1 hour 30% were completed between 1 and 3 hours 16% were completed between 3 and 24 hours 1% were completed in more than 24 hours 8-May-12 16 Time to Port in European Union Source:ICC, UK 8-May-12 17 Some Examples: Time to Port (MNP) by Country Country Australia Austria Beligum Canada Cyprus Czech Rep. Estonia Finland France Germany Greece Hong Kong Hungary Ireland Israel Italy Japan Korea Latvia Source: TMG 8-May-12 Time (in days) ~ 3 hours 3 2 ~ 3 hours 6 5 5 5 7 5 12 1-2 6 1 < 3 hours 20 depends depends 10 Country Lithuania Luxembourg Malta Netherlands Norway Oman Pakistan Poland Portugal Saudi Arabia Singapore Slovak Rep. Slovenia South Africa Spain Sweden Switzerland UK USA Ghana : Time (in days) 5 1-4 1 10 5-7 3 4-21 8 13 5 1 20 7 1 5 5 15-30 2 2 hours ≤ 24 hours 18 Time to Implement MNP in months Ghana took 15 Months to implement MNP 8-May-12 Source: ICC, UK 19 Ongoing Activities for 2012 Continue to have general oversight of the process Planning stricter enforcement of all rules, including punitive measures where necessary Tightening performance requirements to produce faster and more reliable porting processes. 8-May-12 20 Thank YOU Questions!!! Please ask 8-May-12 21