67 AGENDA ITEM BACKGROUND TO: GOVERNING BOARD DATE FROM: PRESIDENT SUBJECT: September 17, 2012 Facilities Master Plan (FMP) as of June 30, 2012 Semi-Annual Update, Revision and Project Status REASON FOR BOARD CONSIDERATION ACTION ITEM NUMBER C.1 ENCLOSURE(S) Page 1 of 6 BACKGROUND: This report provides a detailed summary of Facilities Master Plan (FMP) projects recently completed, projects under construction or active planning, projects approved for future construction as well as recommendations for changes to FMP projects, scope, budget or schedule. The FMP is officially revised monthly and was last presented in January 2012. RECOMMENDATION: It is recommended that the Governing Board approve the Facilities Master Plan as presented in this report. Administrator Initiating Item: Joe Nugent Victoria Lewis Academic and Professional Matter If yes, Faculty Senate Agreement Senate President Signature Yes No Yes No Final Disposition Approved 68 June, 2012 – Cabrillo College Facilities Master Plan Summary of Revisions and New Activities to the Approved March 2012 FMP Arts Education Classrooms Project Final Certification by DSA received and closed. Arts Education Remediation Project. Staff is working to identify alternative corrective measures in order to resolve deficiencies such as HVAC (Heating, Ventilation & Air Conditioning) throughout the five buildings and water leaks in the Theater and Music buildings. Health and Wellness Project Nursing, Radiology Technology, Medical Assisting, Dental Hygiene, Health and Wellness, and the Stroke Center are fully operational. Final Certification by DSA received and closed. Equipment is in the process of being purchased by Cabrillo Purchasing department. Building 300 Renovation Final Certification by DSA received and closed. Equipment is in the process of being purchased by Cabrillo Purchasing department. Watsonville Green Technology Center This project was developed in collaboration with staff and faculty in order to construct a 14,000 square foot LEED Platinum Level certified “green” community education center. The District received a grant for $2.5 million from Economic Development Agency for the project, and the grant was augmented by $865,000 to help fund the upgrade to a LEED Platinum Level certified “green” building. The Division of State Architect (DSA) approved the plans in June of 2010 and EDA approved the plans and specifications in July 2010. The project went to bid in August 2010. In October, the Board approved Dilbeck and Sons as well as an augmentation to the budget of $517,000. A deductive change order for the value engineering items discussed at the October Board meeting was approved at the November Board Meeting. The District has received a generous donation from the Ley Family of $100,000 for construction which allowed us to add back some of the items that were value engineered out. Staff worked with the Architect, Contractor and Faculty to add back items as necessary throughout the course of the project. This project is substantially complete and the process of close out with EDA and DSA is underway. Equipment is in the process of being purchased by Cabrillo Purchasing department. 800 Bldg. STEM Grant Project Cabrillo College has been awarded a $4,339,878 million federal five-year Title III grant for the STEM fields (Science, Technology, Engineering, and Mathematics). The grant will fund the renovation of classrooms and laboratory space in the 800 building in the amount of $1,952,530. Additional renovations to the 800 building will be required and include repairs to the heating and ventilation systems, office space and restrooms. Administrative Services and student service programs within the 800 building have been relocated. Bond funds will be needed to accomplish the additional required renovations and relocation of functions which are not covered by the grant. The Cabrillo College Foundation received a generous gift of $894,495 from the Peggy and Jack Baskin Foundation. 69 800 Bldg. STEM Grant Project, con’t 800 Bldg. Moves Phase I: Project #9276 (This phase includes renovations and relocation to buildings SAC, 100, 900 bldg.) The 800 building moves were initiated in December and substantially complete by the end of January with the exception of phase II work. Administrative offices and Student Services (Fast track to Work and Student Job Placement) located in the 800 building are now relocated to the SAC, 100 and 900 buildings. Contracts for construction services include Michael Wolcott Construction in the amount of $29,274; Epico Systems Inc. in the amount of $13,322; Carpet King in the amount of $6,442. Other services include project management, furniture and equipment, as well as moving services. The initial Measure D budget for this phase of the project is $248,283 and was completed in the amount of $112,422 and the remaining funds $126,679 will be used for 800 Bldg. Phase II Moves. Phase I was substantially complete in January, 2012. 800 Bldg. Moves Phase II: Project #9276 (This phase includes additional punch list, renovation, relocation and equipment needs to SAC/100/900/HW bldg.) Signage was needed to facilitate way finding for the programs that have been relocated in phase I of this project and is approximately 70% complete. Additional renovation work has been identified to facilitate the needs of the programs (President’s component and Student Assessment) located in the upper SAC west and is nearing completion. Furniture and equipment also remains on the list to complete the transition for the moves. Disabled Student Program & Services (DSP&S) space has been identified as part of the program needs for the 800 building STEM project. This will require relocation of DSPS to the Health & Wellness building where it will share space with Stroke Center Program. 800 Bldg. Construction / Renovation: Project #4675 (This phase includes all design and construction elements of the project) As authorized in the December Board meeting, the District is in contract with RMW for architectural services and submitted drawings to the Division of the State Architect (DSA) in June, 2012. Efforts to identify total funding needs are in process and the scope development and bidding process for the hazardous abatement work is underway. Building 600 Renovation The west end of building 600 has been identified to be renovated in order to provide the much needed space for the Chemistry and Biology laboratory and classrooms. VBN Architects have been selected to provide the design services and program development is expected to occur over the next few months. The current target completion timeline for construction is scheduled for the Fall 2013. Smart Classrooms 11-12 The Smart Classrooms projects were developed several years ago in order to provide the much needed upgrades in technology and equipment to improve access and the learning environment. The 2011/12 classrooms identified by the divisions were rooms 352, 355, 410, 411, and 1091. The target date for completion of these rooms are for the start of the fall semester and a majority of the work is expected to be complete and spaces will be ready to use by instruction. Additional smart classrooms were renovated using Title V grant funds which included rooms 512, 716 and 1071. Smart Classrooms 12-13 A project budget of $80,000 has been established and classrooms in need of improvements will be identified and upgraded this fiscal year. 70 Campus Signage Project The Campus signage project was established to address the way finding needs of students and visitors arriving to Cabrillo College. As new building and facilities use changes, the need to identify and direct people continues. Most recently signs have been added and/or change to accommodate the relocation of programs such as Physics, Fast Track to Work, Disabled Students Program and Services and others associated with the 800 building renovation project. DSA Closeout Despite the Certification and final closure of several large projects, numerous small and older projects under the jurisdiction of the Division of State Architect (DSA) require processing in order to be complete and closed. Staff will continue to work with DSA to identify the required documentation and close out all nine remaining projects. June, 2012 – Cabrillo College Facilities Master Plan FMP Projects Closed in 2011/12 AEC/VAPA Complex June, 2012 – Cabrillo College Facilities Master Plan FMP Projects in Active Planning, Construction or Substantial Completion 800 Bldg. STEM Grant Project Building 600 Renovation Smart Classrooms 12-13 This section includes projects in active planning as of March, 2012. 71 Semi Annual Report as of 6/30/2012 Projects In Process Health and Wellness Center and Sitework Health and Wellness Equipment Substantial Completion Date Funding Source State Funds Building 300 Renovation Equipment Watsonville Green Technology Center Watsonville GTC Equipment Building 800 Renovation Building 800 Moves 10,490,000 Remaining Funds Paid to Date Measure C 121,741 121,741 2011 Measure D 15,067,134 14,988,663 Project Sub-total 25,678,875 25,600,404 State Funds 1,185,000 857,240 Spring Measure D 1,105,493 1,075,693 2011 Project Sub-total 2,290,493 1,932,933 27,969,368 27,533,337 1,051,000 1,051,000 State Funds Fall Measure C 33 33 2010 Measure D 1,166,000 1,127,403 Project Sub-total 2,217,033 2,178,436 State Funds 931,000 758,913 Fall Measure D 931,000 768,620 2010 Project Sub-total 1,862,000 1,527,533 Total Project 4,079,033 3,705,969 EDA Funds 3,365,000 3,365,000 373,064 100,000 6,956,546 Total Project 10,965,000 10,421,546 543,454 Total Project 542,000 68,285 473,715 STEM Grant 1,952,530 169,964 Measure D 2,250,000 24,792 2013 Total Project Measure D 4,202,530 313,283 218,940 Total Project Measure C 313,283 218,940 1,915,130 153,606 Summer 2,760,735 Fall 2013 1,000,000 6,172 1,000,000 6,172 Smart Classrooom 201112 Fall 2012 Total Project Measure D 243,587 66,995 Total Project 243,587 66,995 Smart Classrooom 201213 Fall 2013 Measure D 80,000 0 80,000 - TBD Total Project Measure D 323,291 272,365 323,291 272,365 TBD Total Project Measure C 61,337 36,815 Total Project 61,337 36,815 Total Project 140,000 101,392 52,680,164 42,780,178 Summer 2012 Total 845,605 Pending DSA Approval Remaining equipment needed In Planning 194,756 4,007,774 Measure D South Perimeter Road Some remainig equipment will be purchased 100,000 Total Project Measure D DSA Closeout 38,597 7,500,000 Fall Some remainig equipment will be purchased DSA Approved Measure D 2013 Campus Signage 436,031 Foundation Fall Building 600 Remodel 78,471 Fall 2012 VAPA Remediation Pending DSA Approval 2011 Fall 2012 Status/Comments 10,490,000 Spring Total Project Building 300 Renovation Project Budget 94,343 In Process In Process 0 153,606 2,607,129 993,828 176,592 80,000 50,926 24,522 In Planning In Process In Planning On Hold for fall 2012 In Process 38,608 Substantially Complete 72 Projects Completed VAPA Construction Completed Date Complete Funding Source State Capital Outlay Funds Measure C Measure D Project Sub-total VAPA Equipment Completed Projects Complete State Capital Outlay Funds Measure D Project Sub-total Total Project Adjusted Project Budget Paid to Date 20,357,000 20,357,000 5,345,114 51,909,024 77,611,138 5,345,114 51,893,312 77,595,426 1,136,000 1,136,000 1,126,453 1,126,453 2,262,453 79,873,591 79,873,591 2,262,453 79,857,879 79,857,879