AGENDA ITEM BACKGROUND TO: GOVERNING BOARD DATE FROM: PRESIDENT September 12, 2011 SUBJECT: Facilities Master Plan (FMP) Semi-Annual Update, Revision and Project Status REASON FOR BOARD CONSIDERATION ENCLOSURE(S) Page 1 of 6 ITEM NUMBER ACTION D.4 Background: This report provides a detailed summary of Facilities Master Plan (FMP) projects recently completed, projects under construction or active planning, projects approved for future construction as well as recommendations for changes to FMP projects, scope, budget or schedule. The FMP is officially revised in the spring and fall each year and was last presented in March 2011, with the latest revisions of June 2011. The following schedules are included with this report: A. Summary of Revisions to the March 2011 FMP and New Activities B. Projects Completed Since January 2011 C. Projects in Progress or Active Planning D. Remaining and Future Projects E. FMP Funding / Cost Summary RECOMMENDATION: It is recommended that the Governing Board approve the Facilities Master Plan as presented in this report. Administrator Initiating Item: Joe Nugent Victoria Lewis Academic and Professional Matter If yes, Faculty Senate Agreement Senate President Signature Yes No Yes No Final Disposition Approved June, 2011 – Cabrillo College Facilities Master Plan A. Summary of Revisions to the Approved March 2011 FMP and New Activities Arts Education Classrooms Project As reported in March 2011, the VAPA Complex continues to be fully occupied and operational not withstanding construction deficiencies. The project has been submitted to DSA for final approval and is expected to receive final certification. Staff is working to identify alternative corrective measures in order to resolve deficiencies such as HVAC (Heating, Ventilation & Air Conditioning) throughout the five buildings and water leaks in the Theater and Music buildings. Health and Wellness Project Nursing, Radiology Technology, Medical Assisting, Dental Hygiene, Health and Wellness, and the Stroke Center are fully operational with the exception of the accessible path and sidewalk project. The ADA ramp and sidewalk project was informally bid in May 2011 and is expected to be completed at the end of the summer. Once the sidewalk is complete this project will be submitted to DSA for final certification and close out. Building 300 Renovation With renovations to the building complete, the twelve classrooms and eight offices have been occupied for an entire semester with minor adjustments to operating systems. Some of the equipment has been purchased and installed. Staff is working with DSA to complete the project closeout. DSA is currently processing project closeout requests received in February 2011. Watsonville Community Education Center (Formally called ITEC, GTC, among others) This project was developed in collaboration with staff and faculty in order to construct a 14,000 square foot Platinum Level LEED certified “green” community education center. The District received a grant for $2.5 million from Economic Development Agency for the project, and the grant was augmented by $865,000 to help fund the upgrade to a Platinum Level LEED certified “green” building. The project name has been changed to the Watsonville Community Center to reflect the new focus. The Division of State Architect (DSA) approved the plans in June of 2010 and EDA approved the plans and specifications in July 2010. The project went to bid in August 2010. In October, the Board approved Dilbeck and Sons as well as an augmentation to the budget of $517,000. A deductive change order for the value engineering items discussed at the October Board meeting was approved at the November Board Meeting. The District has received a generous donation from the Ley Family of $100,000 for construction which allows us to add back some of the items that were value engineered out. Staff is working with the Architect, Contractor and Faculty to add back items as necessary throughout the course of the project. As of June 2011, Building A (the main classroom building) has underground utilities, foundation, slab on grade, and installation of steel and wood framing are all complete. Building “B” (shop building) has underground utilities, foundation, and steel erection and slab on grade are also all complete. Site utilities and roofing on both buildings are the next priority. While the contractor remains behind schedule by approximately two weeks, the project is expected to be back on track by mid August. Page 2 of 6 June 2011 – Cabrillo College Facilities Master Plan A. Summary of Revisions to the Approved March 2011 FMP and New Activities, con’t Measure D Funded Projects As of 6/30/2011 Starting Balance-Measure D Bond Description 1 Arts Education Classrooms (Not Including Equipment) 2 Student Activities Center 3 Allied Health Classrooms 4 ADA Access and Safety 5 Road Resurfacing and Utilities 6 Upgrade Buildings/Classrooms 7 Equipment - General 8 Watsonville Green Technology Center 9 Interest Total Currently Unallocated Totals include Interest available (thru June 30 2011) $118,743,795 Current Budget Spent or Allocated Current Balance Unallocated 53,040,894 20,866,640 28,500,556 2,171,027 1,150,000 9,719,184 4,489,000 7,500,000 53,040,894 20,866,640 28,500,556 1,871,286 1,100,053 5,711,545 4,186,221 7,500,000 127,437,301 122,777,195 0 0 0 299,741 49,947 4,007,639 302,779 0 545,680 5,205,786 9,172,868 8,627,188 545,680 Spreadsheet general notes: a. Spreadsheet reflects Measure D only and does not include funding from other sources (state bond, state scheduled maintenance, Federal or Measure C). b. Building 300 renovation is part of Upgrade Buildings/Classrooms (Item 6). c. Allied Health Classrooms includes $17,493,255 (construction), $10,715,000 (parking structure now closed), $353,404 (relocation of the Sheriff’s office to clear the site now closed) (Item 3) d. The Watsonville Green Technology Center budget includes the library acquisition for $2,911,942. (Item 8) e. The Bond Origination fee of $258,565 allocated from Measure D interest. f. SAC budget includes an augmentation of $1,766,855 of Measure D interest income. (Item 2) g. AEC budget includes an augmentation of $6,660,187 of Measure D interest income. (Item 1) h. All figures are as of June 30, 2011 and are un-audited. i. Current Balance Unallocated is not reserved for any specific project or for any specific category. j. Interest does not include deduction for arbitrage not yet taken. Page 3 of 6 June, 2011 – Cabrillo College Facilities Master Plan A. Summary of Revisions to the Approved March 2011 FMP and New Activities—con’t MEASURE C FUNDED PROJECTS As of 6/30/11 Description North County AEC DSA closeout of previously completed projects Track and Field Improvements Campus Master Plan document updates Amount Allocated Amount Unallocated as of 6-30-11 Total B. Current Allocated 1,590,742 186,833 28,618 63,459 18,437 1,888,088 51,519 $1,939,608 FMP Projects Closed Since January 2011 Student Activities Center (SAC) The Student Activities Center was occupied in October 2007. The Office of General Services, a Division of the State Architect’s Office (DSA), required compliance on a variety of processes, including the monitoring of the soil nail wall, before closing and final certification of the building could occur. The building received final certification on March 22, 2011 and is effectively closed as of June 30, 2011. Page 4 of 6 June, 2011 – Cabrillo College Facilities Master Plan C. FMP Projects in Progress or Active Planning This section includes projects under construction as well as those in active planning as of June 30, 2011. Project & Planned Completion Date Arts Education Classrooms (AEC) Total Construction AEC Equipment Total Equipment Total Project Allied Health Classrooms Total Construction Allied Health Equipment Total Equipment Project Budget Funding Source State Capital 20,357,000 Outlay Funds 5,531,947 Measure C 53,040,894 Measure D 78,929,841 State Capital 1,136,000 Outlay Funds Measure D 1,122,157 Equipment 2,258,157 81,187,998 State Capital 10,490,000 Outlay Funds 121,741 Measure C 17,493,255 Measure D 28,104,996 Measure D 1,209,977 Equipment State Capital 1,185,000 Outlay Funds 2,394,977 Paid to Date (thru 6/30/10) Status / Comment 20,357,000 5,345,114 51,899,527 77,601,641 1,122,157 2,258,157 79,859,798 10,490,000 Substantially complete. Classes being conducted in the 121,741 buildings effective Summer 14,859,136 2010. 25,470,877 1,038,700 State equipment funds have 716,281 been approved. 1,754,981 Total Project Watsonville Green Technology Center Watsonville Green Technology Center Watsonville Green Technology Center 30,499,973 Total Project 10,965,000 6,973,742 122,652,971 114,059,398 Total this Page 27,225,858 7,500,000 Measure D 5,337,352 100,000 Foundation 0 3,365,000 Project in closeout 1,136,000 Federal Grant Page 5 of 6 1,636,390 EDD Grant June, 2011 – Cabrillo College Facilities Master Plan C. FMP Projects in Progress or Active Planning, con’t Project & Planned Completion Date DSA Project Close Out Project Budget 61,337 Building 300 Renovation Building 300 Renovation Building 300 Renovation 2,166,000 1,051,000 33 Building 300- Equipment Building 300- Equipment Total Project Campus Master Plan 931,000 931,000 5,079,033 70,400 Campus Wide Signage Total This Page 323,291 Funding Source Measure C Measure D Building Upgrades State Funds Measure C Measure D Equipment State Funds Measure C Measure D Accessibility Paid to Date (thru 6/30/10) Status / Comment This is an ongoing project to close out projects completed in prior years (curently 12) with 32,719 DSA. State has reduced their portion 1,108,298 from $2,167,000 to $1,051,000 1,047,739 due to bids being below 33 budget. State Equipment allocation will remain 304,764 unchanged 295,058 2,755,892 51,963 Ongoing updates. 261,854 5,534,061 3,102,428 From Page Five $122,652,971 $114,059,398 Total FMP Projects In-Progress $128,187,032 $117,161,826 Page 6 of 6