AGENDA ITEM BACKGROUND TO: GOVERNING BOARD DATE FROM: PRESIDENT March 7, 2011 SUBJECT: Facilities Master Plan (FMP) Semi-Annual Update, Revision and Project Status REASON FOR BOARD CONSIDERATION Page 1 of 9 ITEM NUMBER ACTION ENCLOSURE(S) C.7 Background: This report provides a detailed summary of Facilities Master Plan (FMP) projects recently completed, projects under construction or active planning, projects approved for future construction as well as recommendations for changes to FMP projects, scope, budget or schedule. The FMP is officially revised in the spring and fall each year and was last presented in June 2010, with the latest revisions of January 2011. The following schedules are included with this report: A. Summary of Revisions to the June 2010 FMP and New Activities B. Projects Completed Since June 2010 C. Projects in Progress or Active Planning D. Remaining and Future Projects E. FMP Funding / Cost Summary RECOMMENDATION: It is recommended that the Governing Board approve the Facilities Master Plan as presented in this report. Administrator Initiating Item: Joe Nugent Victoria Lewis Academic and Professional Matter If yes, Faculty Senate Agreement Senate President Signature Yes No Yes No Final Disposition Approved January, 2011 – Cabrillo College Facilities Master Plan A. Summary of Revisions to the Approved June 2010 FMP and New Activities Arts Education Classrooms Project Buildings 4 (Theater) and 5 (Music) continue to be in the closeout and punch list process. In addition to these activities staff is working to resolve acoustic concerns in 2-D and 3-D Art and the Music Building and water leaks in the Theater and Music buildings. Mediation with the remaining contractors, architect, and construction manager is in process. Health and Wellness Project The Allied Health project consists of two buildings totaling 57,000 square feet, and is the new home for programs such as Nursing, Radiology Technology, Medical Assisting, Dental Hygiene, Health and Wellness, and the Stroke Center. RMW is the architect and Soltek Pacific is the contractor. Construction began in May 2008 and the buildings are 100% complete. Staff is in the process of closing out the project. All remaining issues have been resolved with the contractor. Anticipated future changes are an estimate of potential additional work, not part of initial bid. Current Status Update: The building is entering its second semester of occupancy by students, staff and faculty. The Fitness room is now equipped with exercise apparatus, making the remaining space ready and occupied with the associated classes. The punch list is nearly complete with only touch up type work remaining. Some HVAC (Heating, Ventilation & Air Conditioning) noise mitigation work is also underway in building 2, and Building 1 has sound panels on order and minor adjustments to the system under review. Building 300 Renovation On February 1, 2010 the Governing Board approved awarding a bid in the amount of $1,560,136 to Tombleson Construction of Salinas for the renovation of the 300 building. The project will remodel/reconstruct 12,523 assignable square feet of space to provide needed instructional space for ten general purpose classrooms, two large assembly/class rooms and nine BELA division offices. The construction began in spring 2010 and is substantially complete. Release request for state equipment funds was submitted to the Chancellor’s Office the week of October 4, 2010. Approval of the list was received on October 14, 2010 and most of the equipment has been delivered and installed. Current Status Update: Classes are in session and beneficial occupancy of the building has been accomplished with minor punch list items remaining. The project is currently under budget by approximately $800,000 and is expected to reach final completion in May with the closing of the project with DSA and State funding reconciliation. Watsonville Green Technology Center The District and the City of Watsonville closed escrow on the purchase of the Watsonville Library on July 15, 2008. Since then, the college has demolished the building in order to construct a 14,000 square foot Industrial Training Education Center (ITEC). The District received a grant for $2.5 million from Economic Development Agency for the project, and the grant was augmented by $865,000 this past summer to help fund an upgrade to a Platinum Level LEED certified “green” building. The project name has been changed to the Green Technology Center to reflect the new focus. The Division of State Architect (DSA) approved the plans in June of 2010 and EDA approved the plans and specifications in July. The project went to bid in Page 2 of 9 January, 2011 – Cabrillo College Facilities Master Plan A. Summary of Revisions to the Approved June 2010 FMP and New Activities, con’t August 2010. In October, the Board approved Dilbeck and Sons as well as an augmentation to the budget of $517,000. Dilbeck and Sons were issued a notice to proceed and construction has begun. A deductive change order for the value engineering items discussed at the October Board meeting was approved at the November Board Meeting. The District has received a generous donation from the Ley Family of $100,000 for construction which allows us to add back some of the items that were value engineered out. Current Status Update: A major milestone has been successfully accomplished with the placement of concrete in all of the perimeter footings. Weather remains a concern to the progress of the project as the concrete slab (floor) placement will not occur until the underfloor plumbing and electrical conduit is complete. Additional sub-grade work is scheduled to be accomplished prior to the end of March. Page 3 of 9 January, 2011 – Cabrillo College Facilities Master Plan A. Summary of Revisions to the Approved June 2010 FMP and New Activities, con’t Measure D Funded Projects As of 1/31/2011 Starting Balance-Measure D Bond Description 1 Arts Education Classrooms (Not Including Equipment) 2 Student Activities Center 3 Allied Health Classrooms 4 ADA Access and Safety 5 Road Resurfacing and Utilities 6 Upgrade Buildings/Classrooms 7 Equipment - General 8 Watsonville Green Technology Center 9 Interest Total Currently Unallocated Totals include Interest available (thru January 31 2011) $118,743,795 Current Budget Spent or Allocated Current Balance Unallocated 53,040,894 20,866,640 28,500,556 2,171,027 1,150,000 9,719,184 4,489,000 7,500,000 53,040,894 20,866,640 28,500,556 1,871,286 1,100,053 5,672,661 4,241,179 7,500,000 127,437,301 122,793,269 0 0 0 299,741 49,947 4,046,523 247,821 0 124,160 4,768,192 8,774,767 8,650,607 124,160 Spreadsheet general notes: a. Spreadsheet reflects Measure D only and does not including funding from other sources (state bond, state scheduled maintenance, or Measure C). b. Building 300 renovation is part of Upgrade Buildings/Classrooms (Item 6). c. Allied Health Classrooms includes $17,493,255 (construction), $10,715,000 (parking structure now closed), $353,404 (relocation of the Sheriff’s office to clear the site now closed) (Item 3) d. The Watsonville Green Technology Center budget includes the library acquisition for $2,911,942. (Item 8) e. The Bond Origination fee of $258,565 allocated from Measure D interest. f. SAC budget includes an augmentation of $1,766,855 of Measure D interest income. (Item 2) g. AEC budget includes an augmentation of $6,660,187 of Measure D interest income. (Item 1) h. All figures are as of January 31, 2011 and are un-audited. i. Current Balance Unallocated is not reserved for any specific project or for any specific category. Page 4 of 9 January, 2011 – Cabrillo College Facilities Master Plan A. Summary of Revisions to the Approved March 2010 FMP and New Activities—con’t MEASURE C FUNDED PROJECTS As of 1/31/11 Description North County AEC DSA closeout of previously completed projects Track and Field Improvements Campus Master Plan document updates Amount Allocated Amount Unallocated as of 1-31-11 Total B. FMP Projects Closed Since June 2010 None. Page 5 of 9 Current Allocated 1,590,742 0 39,664 72,672 18,437 1,721,515 17,958 $1,739,473 January, 2011 – Cabrillo College Facilities Master Plan C. FMP Projects in Progress or Active Planning This section includes projects under construction as well at those in active planning as of June 30, 2010. Total Soil Nail Wall Total Project Arts Education Classrooms (AEC) Total Construction 143,555 29,401,670 20,357,000 5,531,947 53,040,894 78,929,841 1,136,000 AEC Equipment 1,122,157 Total Equipment Total Project Total Construction 121,741 17,493,255 28,104,996 1,209,977 Allied Health Equipment 1,185,000 Total Equipment Total Project Watsonville Green Technology Center Watsonville Green Technology Center Watsonville Green Technology Center Total Project Total this Page State Capital Outlay Funds Measure C Measure D State Capital Outlay Funds Measure D Equipment 2,258,157 81,187,998 10,490,000 Allied Health Classrooms 134,668 29,314,629 20,357,000 5,531,947 52,310,157 78,199,104 1,136,000 1,122,157 2,258,157 80,457,261 State Capital Outlay Funds Measure C Measure D 10,490,000 Substantially complete. Classes being conducted in the 121,741 buildings effective Summer 14,847,156 2010. 25,458,897 Measure D Equipment State Capital Outlay Funds 1,048,641 State equipment funds were approved and the equipment 8,158 purchase and installation is substantially complete. 1,056,799 2,394,977 30,499,973 26,515,696 7,500,000 Measure D 3,983,573 100,000 Foundation 0 3,340,000 Project in closeout Federal Grant 200,143 EDD Grant 10,940,000 4,183,716 152,029,641 140,471,302 Page 6 of 9 This Project is currently in construction. January, 2011 – Cabrillo College Facilities Master Plan C. FMP Projects in Progress or Active Planning, con’t Project & Planned Completion Date Building 2100 Upgrades Construction Building 2100 Upgrades Equipment Total Project DSA Project Close Out Project Budget 10,000 80,000 Funding Source Measure D Classroom Upgrades Measure D Classroom Equipment 90,000 Building 300 Renovation 2,166,000 Building 300 Renovation 1,051,000 State Funds Building 300 Renovation 33 Building 300- Equipment 931,000 Measure C Measure D Equipment Building 300- Equipment 931,000 State Funds Total Project Campus Master Plan Campus Wide Signage Total This Page Status / Comment 0 Partially complete 4,958 4,958 Measure C Measure D Building Upgrades 61,337 Paid to Date (thru 6/30/10) 5,079,033 This is an ongoing project to close out projects completed in prior years (curently 14) with 21,673 DSA. 1,212,499 State has reduced their portion 803,776 from $2,167,000 to $1,051,000 33 due to bids being below budget. State Equipment 62,725 allocation will remain unchanged 61,145 2,140,178 70,400 Measure C 323,291 Measure D Accessibility 51,963 Ongoing updates. 261,854 Completed August 2009. 5,624,061 2,480,626 From Page Eight $0 $0 From Page Nine $152,029,641 $140,471,302 Total FMP Projects In-Progress $157,653,702 $142,951,928 Page 7 of 9 January, 2011 – Cabrillo College Facilities Master Plan D. FMP Remaining and Future Projects as of January 31, 2011 The project categories outlined below represent the balance of funds in reserve at this time. As specific projects within these categories are developed and are approved the projects are then reported as active projects and the reserve funds are decremented as appropriate. Project Categories Funding Source Schedule ADA Access & Safety Unallocated Classroom/Buildings Measure D Detailed scope and schedule to be determined Combined with Measure D Building upgrades Road and Utilities Contingency Equipment Funds will be committed and expended as major projects are completed Measure D Measure D Interest Unallocated Measure C Unallocated Planning Budget Reserve Comment Significant number of projects 299,740 completed Currently unallocated 4,046,522 Significant number of projects 49,947 completed Current unallocated Measure D 247,821 Measure D 124,160 Measure C 17,958 Total Budget for Remaining and Future FMP Projects Page 8 of 9 4,786,148 January, 2011 – Cabrillo College Facilities Master Plan E. FMP Funding / Cost Summary CURRENT FUNDING BALANCE FMP Phase Completed Projects Schedule B Projects in Progress Schedule C Remaining / Future Projects (planning budget) Schedule D Budget Paid to Date Balance Comment 0 0 0 157,653,702 142,951,928 14,701,774 4,786,148 4,786,148 Total Remaining FMP Funds Page 9 of 9 19,487,922