Bid No. B15-05 Upper Campus Security Systems Addendum No. 2 This Addendum No. 2 sets forth modifications to portions of the bid and contract documents for the above-referenced work described as: B15-05 Upper Campus Security Systems RFI Questions and Answers: 1) Trying to understand the wording in the bid documents “Rigid EMT” Please reference Project Specifications Section 2, Subsection 2.16.A. Use this standard at all “rigid EMT” call outs. 2) Specifications, Section 4, 4.1.B.2. 1-5 – What are these referencing? Please reference the Project Specifications Section 3“Telecommunications Specifications” Appendix page 19Testing_WAO Copper Cable. All new work must conform and test to the specified standards. If the runs will exceed the maximum allowable run and/or the Contractor is concerned the run will not meet the testing standard then the Contractor is to furnish and install an intermediate IDF. The equipment specification for the IDF is described in the project specifications Section 4, Subsection 4.1.B.2. 3) Does the Payment and Performance Bond cost go into bid or should cost be separate from bid cost? The Payment and Performance Bond cost should be incorporated into the base bid price. 1 B15-05 Upper Campus Security Systems, Addendum No. 2