BDC14S-06 Page 1 of 2 New Jersey Department of Transportation 1035 Parkway Avenue, PO Box 600, Trenton, New Jersey 08625-0600 Baseline Document Change Announcement ANNOUNCEMENT: BDC14S-06 DATE: June 20, 2014 SUBJECT: Materials Payments and Storage - Revision to Subsection 109.06 of the 2007 Standard Specifications for Road and Bridge Construction. Subsection 109.06 of the 2007 Standard Specifications has been revised to eliminate payment for materials, including storage costs, if such payment is $25,000 or less. It is expected that this change will result in significant time saving for the Department field personnel. The following revision has been incorporated into the Standard Input SI2007 as of June 20, 2014. SECTION 109 – MEASUREMENT AND PAYMENT 109.06 MATERIALS PAYMENTS AND STORAGE THE TEXT BEFORE THE LIST UNDER THE FIRST PARAGRAPH IS CHANGED TO: The Contractor may request payment for the cost of materials, including the storage cost, not incorporated into the Work. If approved by the RE, the Department will make payment for the cost of materials, including storage costs if such payment exceeds $25,000; however, the amount of payment may not exceed 85 percent of the bid price for the associated Item. The Department will not make payment for such materials until the RE is satisfied that: Implementation Code R (ROUTINE) Changes must be implemented in all applicable Department projects scheduled for Final Design Submission at least one month after the date of the BDC announcement. This will allow designers to make necessary plan, specifications, and estimate/proposal changes without requiring the need for an addenda or postponement of advertisement or receipt of bids. BDC14S-06 Page 2 of 2 Recommended By: Approved By: ORIGINAL SIGNED ORIGINAL SIGNED Richard Jaffe, P.E. Director, Capital Program Support Richard T. Hammer Assistant Commissioner, Capital Program Management RJ: KS: HP BDC14S-06.doc