MINUTES COASTAL PATHFINDER PROGRAMME REFERENCE GROUP 6 April 2011 2pm - Room 1, NNDC Offices Present Reference Group Members Malcolm Kerby Dan Corbett Rob Wise Sue Willis Tony Nash Marti Tipper Peter Battrick Brian Farrow Ian Coupe NNDC Officers Rob Goodliffe Item 1 Apologies Action None. 2 Agree minutes of the last meeting and matters arising. Minutes of the last meeting were agreed. There were no matters arising. 3 Update on progress Updates on all the projects were provided as per the table below, comments raised by the Reference group are indicated in italics. a) Wolferton Private Contribution Project Final draft report is back from RPA. It was thought good of NNDC to allow KL&WN to piggy-back on NNDC’s Pathfinder in order for this report to be done. This area of coast is a section where external contributions would be more forthcoming than others possibly. Where it fits with the EA’s external contributions plans and Norman Lamb’s project would need to be discussed further. The write up to Defra needs to be well worded regarding external contributions as it may not be the right way forward in all circumstances and could be unequitable. • • • b) Cromer (Marrams) Footpath • 99% complete. Contractors Mackinnon have worked really well. Burns family are very happy with the project. They will be paying for the electric gate closure on their property. • Legal work being tied up by Ian Coupe. The dedication of the new footpath is straightforward; however the closure of the old one is more involved as notices have Pathfinder Reference Group 1 8 April 2011 to be served and the Open Spaces Society is extremely thorough with its process. • c) Trimingham Village Hall (the Pilgrim Shelter) • • • d) The evaluation feedback to Defra will need to include the legal issues regarding opening/shutting of footpaths, especially in view of Natural England’s proposed national Coastal Access Path. The funding of £60K has been signed for by the Parish Council and transferred. Some of the Group were previously concerned with the money being given to the Parish Council upfront and were pleased with the staged approach. It was explained that the first payment £60K is for land purchase, drawings and planning application. Further funding will not be released until after this. There will be a time limit of 8 years. If nothing has progressed at 4 years there will be a review with the option for NNDC to cancel any further payments. Ian Coupe (working on behalf of the Parish Council) will be meeting with the land owner and Bruton Knowles on Thursday (7th April) to finalise the land purchase. Easements need to be negotiated with BSAC divers who have a long lease with the current land owner. Easement needed to access village hall. If not granted another local landowner may allow an alternative access. Business Advice & Support • Fully subscribed. 26 businesses completed. Most businesses have completed Business Health Checks from Business Link. This has resulted in a worker being kept on to continue working for businesses in the area. • Vouchers are now being taken up, and payments processed regularly. • NWES has been providing professional advice and 3 businesses have completed Business Plans. • The Service Level Agreement has been extended for 6 months for the successful completion of the project. • The Group discussed the suitability of the Case Studies for the project Toolkit as not necessarily being the best option. Business advice/solution regarding adaptation should be the main focus, not sea defences. Members provided many comments on the toolkit to be passed to NWES. • The Loans Scheme was deferred from full council as there is a need to overcome the financial and legal issues before a decision is made. There is a wish for this to progress as a positive news item. • Business Loans Scheme needs Council support and the loans, grants, networking and skills development will need to be pulled together in one report before going forward. • The Group discussed the perception of some estate agents, surveyors and banks regarding coastal erosion issues and the views that may be generated to the public and the financial implications that can be created. Either a workshop within Pathfinder or after the Programme was considered beneficial for the Council to strengthen understanding of the issues and working between all organisations. The opportunity to report this need should be made in the feedback and evaluation report to Defra. • It was also discussed that EA needs to clarify the situation regarding personal finance used to create/maintain defence works and the impression being created (against the Pathfinder Reference Group 2 8 April 2011 RG Coast Protection Act - 49 and SMPs) that defences can be put in place as long as there is the money available. e) f) g) h) East Norfolk Tourism Marketing Project • East North Norfolk Coast Marketing Action Plan and Tourism Development Plan has been completed and actions have been incorporated into the activities of the Business Support Project. • The Marketing Toolkit has been submitted and a photo library for use of businesses is being compiled. Manor Caravan Site • Norfolk County Council is working with the owners regarding site relocation. • The original agreement was up to 31 March 2011 so this needs to be extended. • The consideration of the new location needs to be dovetailed with the decision on the EN12 house locations. The village school will need to be involved with the consultations and this should be done by liaising with the Governing body and headmaster. Coastal Heritage Project • There has been good feedback on this project and the work done by Richard Hoggett. He held an Open Day in Happisburgh in March and the community has come on board with the project and will continue beyond the end of the project. The approach has encouraged and improved an element of ‘Coastal Literacy’ i.e. those involved have a better all round understanding of coastal issues. • ‘The book of Happisburgh’ by Mary Trett & Richard Hoggett will be published in November 2011. Cliff-top Enhancement and Beach Debris Removal • New car park is awaiting planning permissions back. • Tenders being sent out soon for work on car park, access ramp to beach and lavatory provision. • Designs are done, specification should be agreed by the end of this week, and tenders sent the following week. The lavatories have come in at about £50K. The block work entrance and car park surface are being designed to allow roll back over time. • The Group discussed the possible relocation of the present RNLI sales outlet and the Coastguard building. The Coastguard is having a national review at present which will probably result in not needing a coastal cliff lookout facility. A lock-up may still be required and this could be considered in tandem with the RNLI at Cart Gap. Pathfinder Reference Group 3 8 April 2011 Alternatively, there is talk of Mundesley and Happisburgh Coastguards merging and using a redundant garage. The RNLI moved their Happisburgh launching site for the lifeboat to Cart Gap many years ago, where the facilities are much better for the. They are unlikely to be able to finance a move of their sales outlet at Beach Road to the soon to be created car park however. i) • The risks of increased erosion at the current RNLI and Coastguard buildings due to the beach debris removal were discussed. Although there may be an increase in erosion rates initially due to the dynamic coast, this would be expected to settle to normal rates. • The Debris Removal Project would expect to take 12 weeks from mid June to end of September. • Implications to residents regarding disruption and noise whilst debris removal being carried out during the summer. It was agreed to mitigate complaints by informing beforehand with a leaflet drop and contact details for queries and concerns. Wish to continue good rapport with village. Need to emphasise that although an inconvenience the work is ultimately to improve the future of Happisburgh. Although the summer months may not be seen as ideal due to visitors, it is a good time to complete the beach works due to the improved weather. • The debris on the south side of the new ramp isn’t going to be removed and the ‘bay beach’ at Happisburgh will not be closed to the public whilst work is ongoing, only the beach from the promontory to the metal steps near to the Manor caravan site and the new slope itself, that will be used by plant. • The contractors may be allowed to work bank holidays and weekends if needed. These decisions will be made when needed. Beach Road - Buy to Demolish and Buy to Lease-Back Buy to Demolish • 13 offers have been made. 10 accepted and 3 (2 owners) declined. • There is concern that the non conforming activities on the cliff top may migrate to land alongside. NNDC is looking into acquiring land around the present site to negate this. • The properties can’t be demolished until after the EN12’s have been used at the new site. Work with landowners is ongoing, to secure a suitable relocation site. Demolition likely to begin in the late summer and run through into September. • A NPS contract has been set up for asbestos surveys of all properties prior to demolition. The CDM will cover the Health & Safety legislation required for demolition. All relevant departments of NNDC will be meeting to discuss these issues. • Clarenco (owners of St Mary’s) are looking to put in a permissive path along the woodland from the main road junction to the start of their own newly permitted path around their field on the seaward side of St Mary’s. Pathfinder Reference Group 4 8 April 2011 Buy to Lease-Back • Report circulated earlier this year highlighting the financial projections, approaches and legal risk to the Council if went ahead. • Outcome wished for needs to be attractive to the seller/renter and to the Council. To facilitate the prevention of blight as well as to assist owners to move forward. • Although in the report the financial position is potentially cost neutral in some circumstances, if the Government Treasury discount standards are used, no approach is cost neutral (there was a wish that this would be the case). • Informal discussions have taken place with two possibly interested owners in Beach Road. A report and synopsis to be written with Bruton Knowles. It is yet to been seen if scheme will be attractive to the property owners. • Other concepts can also be looked at and reported back to Defra. Such as: o Maintenance Grants (transferable to new owners if original moves out) o Marketing Assistance (to sell) o Supplementary Payments (for legal costs) The group were keen that a version of CCAG’s ‘underwriting’ concept is considered and reported to Defra. An idea was: o Deferred Purchase to Demolish Scheme The Deferred Purchase to Demolish Scheme would be imaginative and inventive as encouraged by Defra’s Pathfinder brief. Would need to be equitable with other houses bought down Beach Road so not a more valuable option than the existing ‘Buy to Demolish Project’. Conditions could be attached for owners to maintain the property. A scheme would need to negate problems which could occur with properties that are semidetached, where one owner wishes to remain and one may wish to move on. This option along with the others should be detailed for serious consideration and presented to the Project Board. 4 • Officers felt that the ‘Buy to Lease’ project is the most complicated project in the Pathfinder Programme so far and is going to be the greatest hurdle for future Central Government policy. • The Reference Group asked to be kept informed of any further considerations on this Project. Financial Update The financial spend is on target with a contingency of £130K. £50K is to be moved to the Happisburgh beach debris project. The Board is considering allocating the contingency fund. The Cliff top enhancement project may go up due to the removal costs of British Telecom phone wire removal. The state of play at present is: Happisburgh Demolitions Happisburgh Lease Back Pathfinder Reference Group On target £170k at present 5 8 April 2011 RG Happisburgh Heritage Project Spent & completed Happisburgh Manor Caravan Site Business Advice Beginning to be spent. Business Loans/grants Tourism Marketing Project All allocated and committed. All allocated and committed. £30K remaining Main project completed – need to secure payments for next 3 years Cromer Marrams Footpath Completed, slight overspend, may do some landscaping. Trimingham Village Hall Money allocated Project Management Costs On target. £200K has been moved from Capital to Revenue by swapping some money within the Council. This enables Pathfinder to have flexibility as Revenue can be spent on Revenue OR Capital, whereas Capital can ONLY be spent on Capital 5 Open discussion Discussions were completed alongside the project updates. 6 Project evaluations and wrap up The Pathfinder programme has not finished by 31st March 2011; the physical site work is expected to be ongoing to the end of September 2011. The Group reiterated that the Programme had been a daunting prospect and that it is vital that the team is maintained and not distracted until the end of the project. The Reference Group would like to be in place to the end of the Programme and to assist with the evaluation to Defra. 7 8 Any other business The Group asked if Philip Burton had sent the letter to Defra regarding lack of representation at the Norfolk Pathfinder Conference. The Group would like a copy of it. It was asked if David Siely of Oversands, could be given the £6,000 demolition payment retrospectively, as he had previously followed the requests of NNDC in removing his property when it had become vulnerable. It was confirmed that NNDC had received a letter and that Peter Frew had responded saying that further consideration would be given. It was emphasised that Pathfinder is not retrospective and Saltlands didn’t exist when Pathfinder came along. A full reply will be sent in due course. Next Meeting th The date of the next meeting will be at 2pm on Wednesday 8 June 2011. Pathfinder Reference Group 6 8 April 2011 RG RG Coast All