International Journal of Engineering Trends and Technology (IJETT) – Volume 23 Number 9- May 2015 Analysis to Convert Traditional Building to Green Building Utkarsh Jain#1, M. Islamuddin Faraz#2, Shailendra Singh#3, Ketan Jain #4 #1 HOD, Civil Engineering Department, IIST, Rau, RGPV, India. Asst. Prof., Civil Engineering Department, IIST, Rau, RGPV, India. #3 Asst. Prof. , Civil Engineering Department, IIST, Rau, RGPV, India. #4 Asst. Prof., Civil Engineering Department, SDPS, Indore, RGPV, India. #2 Abstract— The term “Green Building” is not just applicable to products, but also to the construction strategies, building design, orientation, landscaping, building operations, maintenance etc. Lesser the impact of a building on human health and environment, the more green it is. In the present study, the existing construction of our institute has been studied in terms of efficient use of resources and energy. The overall consumption of electricity and water has been determined and the energy and water that will be saved after the additional inputs (like ground water harvesting system, grass pavers, vermicomposite plant, aluminium based paints and additional cross ventilators) to improve the efficiency of the building have been also computed. The construction and installation charges have also been computed. The study concentrates on the advantageous outcomes once the building i converted to “green building”. The green building concept is gradually gaining momentum in India. A green building typically applies practices like harvesting energy and water and using environmentally friendly materials in its design, construction, operation and maintenance and sustains the environment. Development of green buildings has many monetary benefits such as low energy, waste disposal, water cost, and low environmental and emission costs (Kats, 2003). The advantages and benefits of the green buildings are spread out over the life span of the building and should be looked at in the long run and not on the initial cost. Keywords— green building, non-powered ventilators, aluminium based paint, segregation, vermi composite plant. II. OBJECTIVES I. INTRODUCTION A green building may be understood as an outcome of the design philosophy focusing on increasing the efficiency of the resources used - i.e.: energy, water and material – along with reduced hazards on environment and human health during the entire building life. This can be achieved through better design, construction, operation, maintenance etc. The green building should be designed and operated in such a manner that it reduces the impact on human health and environment by: 1. Use of energy, water and other resources in an efficient manner, 2. Minimizing occupants, health hazards of 3. Minimizing pollution, waste environmental degradation. ISSN: 2231-5381 the and As per the study conducted on the A BLOCK of IIST, Indore campus many of the parameters were found existing in the building. But it was found that certain aspects were not fulfilled like: rain water harvesting, efficient solid waste maintenance and prudent use of natural energy. Hence following objectives are drawn: 1. To determine the annual water consumption of A - Block. 2. To determine the annual average water harvested by the rain water harvesting system. 3. To determine the additional suitable cross ventilations in A - Block. 4. To suggest a suitable method for solid waste decomposition. http://www.ijettjournal.org Page 432 International Journal of Engineering Trends and Technology (IJETT) – Volume 23 Number 9- May 2015 III. METHODOLOGY The following methodology has been adopted in the present study: 1. The overall annual water consumptions of A – Block has been obtained. 2. The catchment area of the building has been measured. 3. The amount of water that can be recharged/ regained with the help of rain water harvesting has been calculated. 4. The overall cost for installation of rainwater harvesting system has been computed 5. The requirements/feasibility of additional ventilation is determined. 6. The overall construction (installation) cost of additional ventilations is calculated. 7. The amount of energy saved has been reported (approx.) 8. The amount of money saved per annum has been determined. 4. Day Light without glaze 5. Wind direction and orientation of building Opening and courtyard 6. Set back in North side 7. Openings in North 8. Building blocks have space for free wind movement 9. Buffer spaces like toilets service areas. Staircase along east/West Face 10. Spaces for Natural light in North 11. Energy and Indoor comforts layout design as per solar geometry orientation sun breakers 12. Eco. Friendly transportation on site Mass Transport 13. Energy efficient external lighting 14. Min. local amenities required 15. Reduction of outdoor light pollution 16. Roof treatment to reduce heat gain 17. Energy efficient lightly in building 18. Use BEE labelled appliances in all new Buildings 19. Solar Water heating system in all buildings 20. Perform energy audit for existing Buildings IV. PROVISIONS A. Features of the building: The general features of the existing building are tabulated below: TABLE I GENERAL FEATURES OF THE BUILDING PROJECT NAME 1. Longer sides facing North/ South 2. Shading of South and West 3. Streets and courtyard along east/West Axis ISSN: 2231-5381 IPS ACADEMY 21. Provide thermal comfort for air conditioned & naturally ventilated spaces. Natural Fan 22. Maintain outdoor indoor noise. 23. Fresh air requirement and min. air changes required/hour in building. http://www.ijettjournal.org Page 433 International Journal of Engineering Trends and Technology (IJETT) – Volume 23 Number 9- May 2015 emitting the heat. So by the provision of B. Provision for ground water recharging system: In the present scenario, the total aluminium based paint on the southern consumption of water in A- Block is and facing wall this effect can be reduced. the fulfilment of this quantity is done by tube wells which are leading to the E. Provision for grass pavers: Grass pavers depletion of ground water level. Hence are the paving tiles which have large there is an urgent need for provision of number of rhombus shaped openings so ground water harvesting system. that water can percolate through ground and thereby help in raising the ground water table. Grass pavers also help in reducing the heat island effect, as if any other material is used for paving such as concrete road or bitumen road, it absorbs heat in the day time and in the night time when the surrounding landscape gets cooled, the paver material acts as a heating island. At present the area in front of the A – block is paved with the traditional paver tiles. This area can be paved with the grass pavers, and the traditional paver tiles can be reused at the backside of the building which is unpaved. Fig. 1 Rain Water Harvesting C. Provision for cross ventilation: Natural ventilation is the movement of outdoor air into a space without mechanical assistance. This can be controlled by additionally providing doors, windows and non powered ventilators. In A – Block the back side of the building is facing North direction and windows are provided. But still there is a lot of space which can be converted to non-powered ventilators. D. Provision for aluminium based paint: Aluminium based paint has the capacity to reflect the sunrays falling on it which ultimately reduces the heat intake in the building and thereby creates a better atmosphere to live in. For the major period of the day the south facing wall is directly exposed to the sunlight and it absorbs heat during the whole day and then the wall keeps ISSN: 2231-5381 Fig. 2 Grass Pavers F. Provision for Vermicomposite Plant: As there is a mess present in IIST and a large amount of kitchen waste is generated every day. Proper and efficient kitchen waste management necessitates the incorporation of following points: 1.) Reduction 2.) Segregation 3.) Disposal http://www.ijettjournal.org Page 434 International Journal of Engineering Trends and Technology (IJETT) – Volume 23 Number 9- May 2015 REDUCTION: - The first step for Average rainfall in Indore = 1062mm efficient kitchen waste management is to =1m reduce the same at the time of generation of waste. For this purpose, posters should Area of open terrace from where water is be designed for encouraging the students to be collected = 1500 sq m regarding the importance of food and not to waste it. Total runoff = 1500 X 0.8 X1 = 1200 cu m SEGREGATION: - The next step is the proper segregation of kitchen waste as Percentage of water saved = bio-degradable and non-biodegradable, (1200X100)/5400 = 22.22% and the responsibility of segregation of wastes stands on the shoulders of B. Cost of rainwater harvesting system: maidservant. The total cost of the rainwater harvesting Maidservant washes the utensils twice in a system is tabulated below: day. She is asked to follow the following TABLE 2 COST OF RAIN WATER HARVESTING SYSTEM program for washing the utensils. Follow up is also done to ensure that washing is Particulars Figures done as per the program: 1.) Remove all large sized solids (e.g. big Total length of pipe required 330 m pieces of vegetable, empty milk packets No. of joints 20 joints etc.) by hand picking. Cost of joints Rs. 1400 2.) Wash all the utensils with plain water to Total cost of pipe Rs. 30,000 remove the adhered food materials. This is Charge for 2 filters Rs. 20000 concentrated wash. Total plumbing charge Rs. 10000 3.) Apply soap solution to utensils. 4.) Wash with water to remove soap. Rs. TOTAL 5.) Rinse with water. 60,000.00 6.) Washing powder is used only for frying pan and hot pan. C. Design of Vermi composite plant DISPOSAL: - Now for the proper disposal of the kitchen waste management, Vermi composting plant suits the most in the institute building as in return, high value manure is also obtained. Assuming total design load taking future expansion into consideration = 700 kg/week or 100 kg/day Design load of garbage = 100 kg/day Taking loading @ 40 kg/m2 V. CALCULATIONS A. Percentage of water conserved through rain water harvesting: Total water consumed = 20000 litre/day = 20 cub m/day Total working days = 270 Total water consumed by the building = 5400 cub m/year ISSN: 2231-5381 Thus area required = 100/40 = 2.5 m2 Providing L: B as 1:2 L/2 X L = 3 L2 = 6 http://www.ijettjournal.org Page 435 International Journal of Engineering Trends and Technology (IJETT) – Volume 23 Number 9- May 2015 L = 2.4 m G. Total Rs. 1,20,953.00 Cost of Earthworms Rs. 24,000 Thus B = 1.2 m TOTAL Rs. 1,44,953.00 Thus bed dimension = 2.4 X 1.2 m In order to take care of 30 days cycle we will have 10 beds each of 2.4 X 1.2m a.) The garbage will be deposited in three layers 75 mm thick overlaid on a layer of earthworms, Vermi casting powder and cow dung soil of thickness 200 mm. b.) Thus on every bed there will be three layers of garbage covered by three layers of soil. c.) m This will make a total depth of 0.85 d.) Taking 6kg of earthworm to be provided in each bed of 2.4 X 1.2 m e.) The total earthworm required will be = 6 x 10 = 60 kg roughly 6000 earthworms namely dioscorea villesa Considering the prevailing rate for institutional purpose @ Rs. 400 per kg, we will have to spend for an amount of Rs. 24000 D. Cost of Vermi composite plant: the cost required for vermin composite plant is tabulated below: TABLE 3 COST OF VERMI COMPOSITE PLANT Particulars Figures Total cost of excavation Total cost of construction Total Add miscellaneous and contingencies @ 5% Rs. 1608.00 Rs. 1,13,595.00 Rs. 1,15,203.00 Rs. 5,750.00 ISSN: 2231-5381 E. Cost required for aluminium based paint: The overall cost for aluminium based paint is tabulated below: TABLE 4 COST OF ALUMINIUM BASED PAINT Particulars Total area to be painted Total quantity of paint required Total cost of paint Total cost of labour for painting TOTAL Figures 1300sq. m 35 litres Rs. 4200 Rs. 7000 Rs. 11200.00 F. Cost of cross ventilation: The cost analysis of non powered ventilators is tabulated below: TABLE 5 COST OF CROSS VENTILATION Total volume of wall to be dismantled Cost of labour required for dismantling wall Total volume of wall to be constructed No. of bricks required Cost of bricks Volume of mortar required Volume of cement Total no. of cement bags Cost of cement Volume of sand Cost of sand Cost of labour Area of plaster http://www.ijettjournal.org 15 X 2.5 X .01 = 3.75 cu. m Rs. 900 1.5 cu.m 750 Rs. 3000 0.35 cu.m .05 cu. m 2 Rs. 50 0.3 cu.m Rs. 300 Rs. 800 15 sq. m Page 436 International Journal of Engineering Trends and Technology (IJETT) – Volume 23 Number 9- May 2015 H. Analysis of energy and cost saved after Thickness of plaster 10 mm completion of the changes suggested: Volume of mortar 0.15 cu m The analysis of energy saved per hour is Mortar ratio 1:3 given below: Volume of cement 0.35 cum Total number of tube lights = 250 No .of cement bags 1 Power of each tube light = 40 Watt Volume of sand 0.113 cum Total power all tube lights = 250 X 40 Cost of sand Rs. 100 =10,000 Watt Total cu. Feet wood required 7.25 cu. Feet for wooden frame Total number of fans = 120 Cost of per cu. Feet wood Rs. 2200.00 Power of each fans = 50 Watt Total cost of wood (7.25 X = Rs. Total power all fans = 120 X 50 2200) 15950.00 = 6,000 Watt Cost of labour @ Rs 350 per = Rs mesh structure 1050.00 Other miscellaneous consumptions = Size of mesh to be provided 5 X 3 = 15 15,000 Watt (tentative) sq.ft Total no.’s of mesh to be 10 Total energy consumption per hour = provided 31000 Watt = 31 Kilo Watt Total cost for cutting of gate Rs. 1050 Cost of mesh Rs 20/ sq Total energy consumption per year if we feet assume 270 working days and 8 working Total cost of mesh Rs 6000 hours each day = 31000 X 8 X 270 Total cost of curtain(45 X Rs 1350 = 6, 69, 60, 000 Watt 15) x 2 = 66,960 Kilo Watt TOTAL Rs. 33,100 G. Cost analysis of Grass Pavers: The cost analysis of grass pavers is tabulated below: Dimensions of grass pavers = 0.5mX1.0m Dimension of area to be paved = 100mX3m Total no of pavers required = 600 Cost of each paver = Rs. 55 Cost of 1 Kilo Watt electricity = Rs. 8 (approx.) Total cost = Rs. 5, 35, 680 Approximate cost reduction implementation of changes = 40% Total energy saved = 0.4 X 66, 960 =26, 784 Kilo Watt Total Cost saved = 0.4 X 5, 35, 680 = Rs. 2, 14, 272 Total cost of pavers = 55X600 = Rs. 45,000 Placing charges = Rs. 6000 Total cost = Rs. 51,000 ISSN: 2231-5381 after VI. CONCLUSIONS The following conclusions are obtained from the present study: 1. The total quantity of water harvested after construction of water harvesting system is found to be 1200 cub m/year which is http://www.ijettjournal.org Page 437 International Journal of Engineering Trends and Technology (IJETT) – Volume 23 Number 9- May 2015 about 22.22% of the total annual water consumption. 2. The overall construction cost of the water harvesting system is found to be Rs. 60,000. 3. For solid waste disposal vermin composite plants of dimension 2.4 X 1.2m and 10 numbers are suitable for 30 days cycle. 4. The total construction of vermin composite plants is found to be Rs. 1,44,953. 5. The total cost required for aluminium based paint is found out to be Rs. 11,000. 6. The total cost of cross ventilation is found to be Rs. 33,100. 7. The total cost of grass pavers is found to be Rs. 51,000. 8. The tentative electrical energy saved per annum after the suggested changes are found to be 26, 784 Kilo Watt. 9. The amount saved per annum is found to be Rs. 2, 14, 272. REFERENCES [1] [2] [3] [4] [5] [6] [7] [8] Mahsa Qaemi and Gholamreza Heravi, ―Sustainable Energy Performance Indicators of Green Building in Developing countries‖, Construction Research Congress, ASCE, pp. 1962-1970, 2012. Manoj, P. K. "Research Paper Economics Prospects and Challenges of Green Buildings and Green Affordable Homes-Concept: A Study with Reference to Ernakulam, Kerala." Economics, vol. 2, issue 12 ,2013. Reddy, Venkatarama BV. "Sustainable building technologies." Current Science, vol. 87, issue 7, pp. 899-907, 2004. Kibert, Charles J. Sustainable Construction: Green Building Design and Delivery: Green Building Design and Delivery. John Wiley & Sons, 2012. Yudelson, Jerry. The green building revolution. Island Press, 2010. Potbhare, Varun, et al. "Emergence of green building guidelines in developed countries and their impact on India." Journal of Engineering, Design and Technology, vol. 7, issue 1, pp. 99-121, 2009. Sinha, Ritu. "Green building: A step towards sustainable architecture." IUP Journal of Infrastructure, vol. 7, issue 2, pp. 91, 2009 Haapio, Appu, and Pertti Viitaniemi. "A critical review of building environmental assessment tools." Environmental impact assessment review, vol. 28, issue 7, pp. 469-482, 2008. ISSN: 2231-5381 http://www.ijettjournal.org Page 438