Construction of the Science Building The Breakdown

advertisement
Construction of
the Science
Building
“There is no such thing in anyone’s
life as an unimportant day.”
The Breakdown
Up to Date
 Area B Interior Stone
Wall 100% Complete
 Area B Penthouse Horizontal Piping 75%
Complete
 Area D 3rd Floor Fume
Hoods 100% Complete
 Area D 1st Floor
Plumbing 95% Complete
In the Now
 Area A 2nd and 3rd
Floor Framing
 Area A Stainless Steel
Duct
2
 Area B Limestone at
Entryway
2
 Area C Drywall TwoSiding
2
Inside this issue:
A Look Ahead
3
 Area D 2nd Floor Polished Floors
4
 Area A Penthouse VFD
Install
5
 Area D 2nd Floor
Casework
6
Above: Ceiling grid starting to be installed in the Area D 2nd Floor Labs..
Below: A Safety Station is set for installation. These will include emergency
shut-offs, projector and shade, controls,
among others.
Man-hours
316,000
Bricks
125,000
Decking
250,000 sf
Steel
1,750 tons
Below: Workers gather at 7:46 a.m. for
a moment of silence, remembering
those who lost their lives on September
11, 2001.