Construction of the Science Building “There is no such thing in anyone’s life as an unimportant day.” The Breakdown Up to Date Area B Interior Stone Wall 100% Complete Area B Penthouse Horizontal Piping 75% Complete Area D 3rd Floor Fume Hoods 100% Complete Area D 1st Floor Plumbing 95% Complete In the Now Area A 2nd and 3rd Floor Framing Area A Stainless Steel Duct 2 Area B Limestone at Entryway 2 Area C Drywall TwoSiding 2 Inside this issue: A Look Ahead 3 Area D 2nd Floor Polished Floors 4 Area A Penthouse VFD Install 5 Area D 2nd Floor Casework 6 Above: Ceiling grid starting to be installed in the Area D 2nd Floor Labs.. Below: A Safety Station is set for installation. These will include emergency shut-offs, projector and shade, controls, among others. Man-hours 316,000 Bricks 125,000 Decking 250,000 sf Steel 1,750 tons Below: Workers gather at 7:46 a.m. for a moment of silence, remembering those who lost their lives on September 11, 2001.