Issue No. 2009-01
24 October 2008
Type: Policy
In order to better align our workload and requirements with the appropriate level and sources
of funding, it is imperative we establish greater consistency and accuracy in WIP projection
and tracking.
3. Applicability.
This OPS-endorsed ECB applies to NAVFAC Capital Improvements Business Line
Managers/Coordinators (CI BLM/BLCs), Construction Product Line
Leader/Manager/Coordinators (PLL/PLM/PLCs), Integrated Product Team Capital
Improvements Business Line Team Leaders (IPT CI BLTLs), senior CI and military
leadership within PWDs and ROICCs (PWD/ROICCs), and Ech IV Operations Officers
(FEC OPS/DOPS/AOPS).
4. Policy and Implementation.
•
General:
NAVFAC CI Construction PLM/Cs (Ech III CI5s and FEC CI5s), IPT CI BLTLs, and
PWD/ROICCs shall adhere to reference (a). The following sections are highlights of
reference (a).
•
WIP Projections:
The CI BLC shall co-chair, with FEC OPS/DOPS, semi-annual WIP review boards
(typically in late October/early November and March/early April) in alignment with the
RAP schedule to go over WIP projections presented by the individual field offices. The
FEC CI5 shall be the lead in coordinating and organizing these boards. IPT CI BLTLs
are expected to attend, while the FEC CI3 and designated representatives from PW and
EV BLs (to discuss workload that require PWD/ROICC oversight) are highly encouraged
to attend. Specific items of discussion during the WIP review boards shall include the
following:
¾ Workload identified by applicable income and non-income bearing WIP groups.
¾ Most current individual project execution status including potential slippage of
award dates and other risks associated with MILCON/MCON/BRACON/Special
Project execution. This should be provided by FEC IPT CI BLTLs to
PWD/ROICCs with OPS acknowledgement.
¾ Field office’s methodology for WIP projections of awarded carryover projects and
future planned projects greater than $500K. Generally speaking, less review is
needed on a field office that has historically demonstrated its ability to meet or
exceed both their initial income and non-income bearing projections.
¾ Individual field office and aggregate FEC actual historical WIP performance as
compared to initial projections. Upward or downward adjustments to projections
2 of 3
Issue No. 2009-01
24 October 2008
Type: Policy
shall be made as necessary by FEC OPS in collaboration with the CI BLC only
during required submissions associated with the RAP cycle.
•
WIP Tracking:
¾ PWD/ROICCs shall confirm WIP data from COGNOS and ensure the correct
contract purpose code, ACO code, corresponding SIOH rate, and WIP on all
active contracts are appropriately loaded within FIS.
¾ PWD/ROICCs shall provide their FEC CI5 with concise comments concerning
WIP shortfalls (> 5% deficit) of their field office, and monthly planned income
and non-income projections, respectively. Generally, these comments would not
vary greatly from month-to-month once the total dollar amount of anticipated
shortfall is identified as a result of under-execution by either the PWD/ROICC or
associated IPT, over-projections, miscoding, or other reasons encountered during
the FY.
¾ FEC CI5s shall review and track actual WIP posted by WIP groups. FEC CI5s
shall review comments from PWD/ROICCs with FEC OPS on anticipated WIP
shortfalls and provide concise, consolidated speaker notes monthly to Ech III CI5s
for the monthly Ech III OPS brief and the bi-monthly HQ Business Assessment
Briefs and OPS Assessment Briefs.
5. Expiration
This ECB shall remain in effect until superseded or cancelled.