Commissioning & Qualification: Presented by: A Practical Approach Damian Gerstner, President,

advertisement

Commissioning & Qualification:

A Practical Approach

Presented by:

Damian Gerstner, President, systek

Gary Short, CEO, systek

Commissioning & Qualification:

A Practical Approach

Introductions

Commissioning from Viewpoint of General

Industry

Level V Commissioning

Mission Critical Facilities

Practical Applications of Commissioning &

Qualification Baseline ®

Design and Commissioning

Project Management

Introductions:

Damian Gerstner

Education & Professional

BS, Architectural Engineering, KSU

MBA, Rockhurst University

Boehringer Ingelheim – 12 Years

Validation Engineer

Manager, Engineering

Professional focus:

Improving Engineering / Management Processes

Developing Staff

Continuous Learning

Introductions:

Gary Short

Education & Professional

Mechanical Engineering, U. of Wis. – Madison

Started systek in 1995

Member of Building Commissioning Association

Professional focus:

Mission Critical Facilities

Control Systems & Integration

Hands On Troubleshooting & Commissioning

Commissioning in General:

Why Buy Commissioning?

Historically - Lack of reliable data

2004 Lawrence Berkeley National

Laboratory Study “The Cost Effectiveness of

Commercial Building Commissioning)

Analyzed 224 Buildings in 24 States, representing 30.4 million square feet (73% in existing building)

Commissioning in General:

Why Buy Commissioning?

The study showed:

Median payback time versus cost of 4.8 years for new construction and 0.7 years for existing

Existing buildings showed a six fold greater energy savings

Non-energy benefits - hard to quantify include reduced change orders, early problem detection that may lead to equipment breakdowns

In 28 new construction projects, commissioning uncovered a whopping 3,305 deficiencies -

HVAC led the list

Commissioning in General:

Why Buy Commissioning?

New construction Budget breakdown: 30year life-cycle cost of building

2% “First”-Cost of building

6% Operations & Maintenance cost

92% Building Staffing (personnel that live in the building over the lifetime of the building.)

Funding - being cut across all budgets

Maintaining facilities with fewer staff

(automation & scheduling)

Commissioning in General:

Why Buy Commissioning?

Improving staff morale

Maintaining facilities while building occupied

Age of Buildings (30 years or older) = higher maintenance & replacement costs

Commissioning is not a luxury it is a

Necessity

Commissioning in General:

Levels of Commissioning

Level 1 - Design Phase

Develop detailed & comprehensive commissioning specifications & critique of design as it pertains to commissioning

Level 2 - Construction Phase

Review & coordinate the application of the testing plan through observation & documentation of equipment & systems to ensure function complies with systems requirements, objectives, and all contract documents

Commissioning in General:

Levels of Commissioning

Level 3 - Acceptance Phase

Provide on site testing, commissioning and performance testing

Level 4 - Integrated System Testing

At this level, the interaction between the building systems shall be demonstrated under both normal and abnormal operating conditions

Level 5 - Warranty

One-year functional retesting of all equipment & systems within the commissioning contract

Commissioning in General:

Level 1 – Design Phase

Owner’s Performance Requirements (OPR)

Clear and concise document that summarizes the design intent of the project

The OPR serves as conceptual basis for all commissioning & acceptance testing of systems

The OPR identifies ways to maximize innovation, reliability, ease of maintenance, innovation & energy efficiency for all systems & components

Provides written documentation of commissioning consensus

Commissioning in General:

Level 1 – Design Phase

Requires Commissioning Team review of project to identify deficiencies and recommend corrections to Architect and

Owner at the following milestones:

50% and 100% of Schematic Design

Design Development

Construction Documents

Commissioning in General:

Level 1 – Design Phase

Develop & integrate with the designer’s full commissioning specifications for all commissioned equipment and systems

Coordinate with consultants to improve controls systems design & integration

Commissioning scope of work naming components & systems and required testing procedures

Commissioning in General:

Level 2 – Construction

Phase shop drawings and submittals

Limited to equipment relative to commissioning

Critique all RFIs and Change Orders for issues potentially affecting equipment & systems within the commissioning scope of work

Provide CM with checklists & document completion through review & site observation

Commissioning in General:

Level 2 – Construction

Phase installation

Factory test key building system components.

Testing is equipment dependent

As equipment arrives at site, review components for condition and verify features and accessories as provided as specified

Comprehensive check-out is crucial to maintaining a total quality approach

Components are checked before, rather than after installation; and as individual components

Commissioning in General:

Level 2 – Construction

Phase inspection plan for all equipment and systems

Revise commissioning plan as needed, & notify contractor with special requirements or requests

Ensure commissioning activities are included in the construction schedule

Prior to start-up and initial systems inspections, verify current control sequencing and interlocks

Commissioning in General:

Level 3 – Acceptance Phase

Acceptance testing is the most critical phase in the commissioning process

“Where the rubber meets the road”

Provide on site testing, commissioning and performance testing

Commissioning in General:

Level 3 – Acceptance Phase

The term system in this context includes major systems such as:

Chilled Water System

Stand-by Power System

Smoke Control

Building Control Systems

Electrical Switchgear and Interlocks

Test, Adjust and Balancing

Heating Plant and Equipment

Air Handling Systems

Ventilation and Heat Recovery Systems

Commissioning in General:

Level 3 – Acceptance Phase

Capacity test critical equipment such as chillers, AHUs, boilers & pumping systems

Includes tests for internal failures, recovery, reporting, alarms, and abnormal conditions

Capacity testing needs to be outlined in some detail in the contract specifications

Commissioning plan development requires creativity to accomplish capacity testing

Commissioning in General:

Level 3 – Acceptance Phase

There are costs associated with capacity testing that need to be evaluated

Chiller capacity testing may require external heat sources if building heating system can’t be used

Capacity testing AHUs can normally be done by over-cooling & heating the building during startup

Normally a test method can be devised without using temporary equipment for HVAC

Generator & UPS testing requires a load bank

Data center raised floor testing requires multiple load banks

Commissioning in General:

Level 3 – Acceptance Phase

Acceptance and testing procedures include:

Point-to-Point verification of all wiring and tubing within the control system

To reduce cost change scope to random 25%. If errors are found increase scope

Verify control range on all analog outputs, verify stroke and control action. Stroke control valves and damper actuators at 0%, 25%, 50%, &

100%

Software Verification:

Complete step-by-step walk through

Verify & challenge system software, including alarms, loop tuning, setpoints & control sequences

Commissioning in General:

Level 3 – Acceptance Phase

PID control loops require verification & if needed, tuning. Test PID loops by disturbing process & validate time for recovery & over- or under-shoot

Control contractors typically do not tune loops.

They use standard configuration parameters that worked on the last project they did

Lazy control loops create problems

All PID settings should be documented in the

O&M manuals or final commissioning report

Commissioning in General:

Level 3 – Acceptance Phase

Review, confirm & verify point configuration

& parameters for all physical & virtual points

To reduce cost, reduce verification from 100% to

25%. If errors are found increase scope

Graphic (SCADA) system commissioning

Commissioning in General:

Level 4 – Integration Phase

Level 4 commissioning demonstrates how site infrastructure, such as chillers, pumping systems, heating plant, AHUs and life-safety systems will likely perform as a system over the next 60 months

This also provides performance & efficiency benchmarks in diagnosing future maintenance

Stand alone data logger monitoring

Commissioning in General:

Level 4 – Integration Phase

Develop, coordinate & execute functional performance testing on equipment & systems

Control system integration

Staging of equipment based on load (boiler staging, chiller activation etc.)

Transitions from Unoccupied / Occupied modes

Pumping & distribution with varied loading

Summer - Winter Changeover

Test potential system failures and document system recovery & operation

Commissioning in General:

Level 5 – Warranty Phase

Perform 1-year functional retest equipment & systems within commissioning contract

Interview facility staff to discuss building operations and address problems or concerns they have in maintaining building operations

Once identified, make recommendations for improvement

Identify if these are warranty or original construction contract issues and assist in reconciling outstanding issues

Commissioning in General:

Level 5 – Warranty Phase

Re-visit outstanding issues noted in original and seasonal commissioning

Facilitate opposite season or deferred testing and deficiency corrections

Incorporate final testing results, data, and reports into original Commissioning Record as well as current O&M manuals

Provide a re-commissioning plan of systems for future implementation

Commissioning in General:

A Unique Skill Set

Communication

Need to be able to talk several languages such as “Engineer”, “Contractor”, and “Owner”

Communication that motivates (non accusing and solution driven)

Expertise in developing test methods & procedures

Understanding of the big picture (focus on getting the entire building functioning properly)

Creativity

Planning and staging

Commissioning in General:

A Unique Skill Set

Working knowledge of contracting methods and procedures

Contractor protocol

Projects are scheduled driven

Touch it once, touch it right

Ability to understand contractor motives

Personality traits that foster open communication

Commissioning in General:

A Unique Skill Set

Expertise in Controls & System Integration

Control system protocols

Integration methods

Bandwidth and Network Architecture

Alarm transport

Supervisory Control And Data Acquisition

(SCADA)

Troubleshooting

System configuration, physical points, control devices

Control wiring systems

Commissioning in General:

A Unique Skill Set

Engineering Expertise

Expert in system operation

Strong knowledge in engineering principals

Fan and pump laws

Heating and cooling loads

Airflow paths and building pressurization

Ductwork and piping distribution

Commissioning in General:

A Unique Skill Set

Engineering Expertise

Experience in start-up

Chillers, cooling towers and pumping schemes

Air handling systems

Generators

Boiler and heat plants

Critical power

Testing, adjusting and balancing

Design experience

Commissioning in General:

Probable Cost

New Construction

Square foot cost - $1 - $3 / square foot

Total construction 0.06% to 0.08%

Percent of system commissioned 1.5% to 3%

Retro Commissioning

$0.30 - $0.60 per square foot

Clear scope definition and define Owner involvement

Cost Factors

Test, Adjust and Balance

Performance Testing

Commissioning in General:

Payback

For the commissioning of existing buildings:

Median energy cost savings of 15%

Median payback times of 0.7 years

For new building:

Median commissioning costs were 0.6% of total construction costs or ($1.00/ft 2 ),

Median payback time of 4.8 years

Professional satisfaction !

Priceless

Practical Applications:

Where I’m Coming From

Validation experience

Project Management experience at BIVI

“Lack of Resources”

ISPE Commissioning & Qualification

Baseline ® Guide

Gradually retooled BIVI’s Project

Management processes

Practical Applications:

Develop the Process

Document the existing Project Management process flow

Know your stakeholders

End User / Operations

Quality Assurance / Validation

Safety

Calibration / Maintenance / Security

Finance

Engineering

Practical Applications:

Develop the Process

Envision the new Project Management process flow

GAMP® Good Practice Guide: Testing of GxP Systems, International Society for Pharmaceutical

Engineering (ISPE), First Edition, December 2005, p. 15, Figure 2.2: GAMP® ‘V’ Model, www.ispe.org

Practical Applications:

Develop the Process

GAMP® Good Practice Guide: Testing of GxP Systems , International Society for Pharmaceutical Engineering (ISPE), First Edition, December

2005, p. 147, Figure E5.1: Example of Good Testing Practice applied to Infrastructure Hardware Infrastructure Components, www.ispe.org

Practical Applications:

Develop the Process

Document your vision, using language that fits your company’s culture

Visualize how you will “sell” the process

From the bottom up? Or top down?

Mass training? Or smaller groups?

One procedure at a time? Or whole program?

Pilot project? Or all at once?

Practical Applications:

How We Did It

Used C&Q Baseline ® as guide to develop procedures on:

Commissioning

User Requirements Specifications

Impact Assessment

Functional Requirements Specifications

Safety Risk Evaluation

Factory Acceptance Tests

Practical Applications:

How We Did It

Procedures officially “died on the vine”

Mass training attempted

Lackluster support for procedures at Director level

However, baseline established

Selectively followed procedures anyway

Determined what worked / what didn’t

Helped support improvements in Plant Services performance, which enhanced overall credibility

Practical Applications:

How We Did It

Two years later, the company was ready

Finance & Operations aligned to support

Procedures are tested, refined, & improved

“Ideal Project Timeline” developed

Multiple training programs provided

Program successful, but much practice needed

Practical Applications:

Program Overview

Ideal Project Timeline

Practical Applications:

Program Overview

Project Scope of Work

Project Background

Scope of Work

Personnel Requirements

Project Priorities

Documentation Requirements:

Regulations that apply

Engineering Design Documents

Validation Documents

Financial Documents

Quality Assurance Documents

Practical Applications:

Program Overview

Requirements Specification

One per system

Defines user, functional, and detailed design requirements

Impact Assessment & Calibration Classification

Practical Applications:

Program Overview

Safety & Environmental Risk Evaluation

One per project

Covers broad areas of S&E interest, as well as typical Maintenance safety requirements

Practical Applications:

Program Overview

Commissioning Plan

One per system

Work required for

Engineering, Calibration,

Maintenance, and Safety

Review and approval before and after work is complete

Good Documentation

Practices required

Practical Applications:

Program Overview

Other templates developed include:

Component List

Provides data required for Maintenance and

Calibration personnel to enter data into CMMS

Reconciles differences between Engineering drawings & CMMS data

Vendor must provide this information in advance of

Factory Acceptance Test

Factory / Site Acceptance Test Plan

Format similar to Commissioning Plan, but tests developed by equipment vendor

Good Documentation Practices required

Practical Applications:

Controversial Concepts

Document information once, if possible

Push documentation upstream if possible

Significant portions of IQ can be implemented at

FAT – spend more time if necessary

Significant portions of OQ can be implemented during SAT

Commissioning documentation can help minimize IQ

Practical Applications:

Controversial Concepts

Tie payments to documentation, if possible

Require vendor to provide 4 weeks before FAT:

FAT Plan

Component list

Component data sheets

Component manuals

Require vendor to provide at FAT

Skid specific calibration procedures

Completed equipment manuals

If they can’t provide, they’re not ready

If the equipment is not on their floor, they lose their incentive

Practical Applications:

Controversial Concepts

Who is best equipped to do Qualification and/or Cycle Development?

Must understand how individual controls work

Must understand control system works

Must understand technical concepts

Must understand quality assurance concepts

Understand where this talent is and use it, regardless of which department it is in

Practical Applications:

What is Commissioning?

Boundaries of Commissioning defined by:

Level of Resources available to you

Relative skill levels of:

Project Management Staff

Validation / Quality Assurance

End User

Stakeholders Staffs

Practical Applications:

What is Commissioning?

At BIVI, Commissioning started at earliest stages of design and was typically the last task complete before Qualification was accepted

By applying C&G Baseline ® Guide:

Design / Project Management process was completely overhauled

Communication in Project Team, especially support departments, was enhanced

Overall perception of Project Management team was enhanced

Practical Applications:

Take Home Message

Take time to digest C&Q Guide, but don’t be so intimidated that you never start

Know your process! Eliminate duplicate work where you find it

If possible, obtain high-level support to implement your program

Sample documents are available for review during break

Questions?

Download