Chabot College - Facilities Committee Update May 12, 2011 Item Building

advertisement
Chabot College - Facilities Committee Update
May 12, 2011
Item Building
Project / Designer
Phase
Activity / Issue
Punch List
Occupancy April 2010
1
CSSC/700
Community and Student Services
Center - tBP
2
IOB/400
Instructional Office Building - LPA
Punch List
Occupancy Jan 2010
3
Site
Athletic Facilities - Verde Design
DSA Close Out
Awaiting DSA close Out
4
Site
Football Field
DONE
PROJECT CLOSE-OUT COMPLETE
5
1900
Punch List
Occupancy Jan 2010
6
Site
Planetarium / Lecture Halls - DSK
Pool Renovation - Aquatic Design
Group
DONE
PROJECT CLOSE-OUT COMPLETE
7
Site
M & O Facility - Gould
On Hold
8
4000
PE Strength Fitness Center
Construction
On Hold
Construction scheduled complete July 2011, is falling behind
schedule, Contractor working overtime
9
800, 900, 1000 Classroom Building - HMC
DSA Close Out
B800 Occupancy Jan. 2009, B900 is occupied
10
500
Classroom Building - HMC
DSA Close Out
Occupancy Jan. 2010
11
Site
Portable
Offices
Central Plant / Utility Loop - ESCO DSA Close Out
Temporary Faculty Offices Charles Ham
DONE
12
13
14
1000, 1400,
1200, 1300
508, 904,
1814, 2205
15
Art Gallery Doors, Industrial Tech
Improvements, PAC Interior
Improvements
Phase 3 underway, Completion Dec. 2008
PROJECT CLOSE-OUT COMPLETE
DONE
PROJECT CLOSE-OUT COMPLETE
Technology Enhanced Classroom
Classroom Standards and Office
Standards
DONE
PROJECT CLOSE-OUT COMPLETE
DONE
PROJECT CLOSE-OUT COMPLETE
16
Site
Campus Security Plan - Catalyst
Close Out
Under Construction, complete Nov. 2008
17
300
Construction
Construction scheduled complete December 2011
18
Site
Classroom Building - HMC
College Landscape Guidelines RHAA
DONE
standard is complete
19
Site
Asbestos Inspections - HMS
On-site Investigation HazMat removal in B1400 / B1800
20
2500, 2600,
2700, 2800,
2900
PE Complex - SKW
Bidding
Bids opened April 21, 2011. Bids are greater than current budget.
21
Site
Commissioning Authority - AEC
On-going
B4000, B1200, B1400
22
Site
District-Wide FF&E Consultant
On-going
Dovetail working with B300 / B200 groups
Responsibility / Action
On Hold
Chabot College - Facilities Committee Update
May 12, 2011
23
Site
IT Infrastructure Project - ESCO
Close Out
Scope of work coupled with Central Plant item #11.
24
Site
Site Design Committee
On Call As Needed
25
100
Building Modernization - Steinberg Schematic Design
Chaired by Tim Nelson
Enhanced Feasibility study complete - moderate scope being
documented, budget to be determined
26
Site
College Marquee - tBP
Working Drawings
CDs underway
27
Site
Complete
Bricks being installed
28
Site
Founders Plaza - CSSC/tBP
Space / Program Relocation Dovetail
On-going
B1800 empties June 2011, B200 swing space Summer 2011
29
2200
Dental Hygiene - HMC
Close Out
Occupancy October 2009 - Project Close -Out
30
Site
Campus Signage - HM
PAC Rigging Beam Analysis George Famous
Working Drawings
CDs under way
DONE
Analysis Done
Site
Parking Lots - tBP
Close Out
Finished Aug. 2008
Renovation - CHA
Construction
Phase 1 renovation of Auto, Classrooms, Yard complete May 2011.
Phase 2 renovation of Welding complete Aug 2011. Phase 3
renovation of Machine shop complete Aug. 2011
Renovation - CHA
Construction
Renovation of 1618 and 1620 scheduled complete May 2011
34
Site
Solar - Chevron Energy
DSA Close Out
Solar Panels are operational
35
1700/1800
Renovation - Steinberg
DSA review
B1800 Hazmat bids opened April 12, 2011. Bids are under budget.
36
1600
Renovation - TBD
FPP revisions
FPP being revised for FY 12/13. Awaiting state input
37
Site
Soccer Field Restoration - Verde
Close Out
Construction finish October 2010/in maintenance period
38
200
1100, 1500,
2000
Light Renovation - Dovetail
Schematic Design
Light Renovation
Pre-Design
Construction Summer 2011
Budget does not allow for wall changes to accommodate the Chabot
College office standard of 100 s.f.
Light Renovation
Pre-Design
41
2300
B1200, SOTA
Plaza
Renovation - bfgc
DSA review
Budget challenges, SOTA Plaza will be an Add Alternate in bidding.
42
Site
Parking Lot F Restoration
DONE
February/March 2010
43
Site
Traffic Signal
Construction
October 2010 start construction, signal install Summer 2011
44
Site
Parking Lot G/H/F/J Security
Schematic Design
Design underway, may be bid with Marquee
45
Site
Villas Removal
Removal complete February 2010
46
3400
Light Renovation - CHA
DONE
Design Team
Selection
47
300, 500, 800,
900, 1000,
1100
Exterior Aesthetic Improvements
31
32
33A 1400
33B 1600
39
40
48
Design Team
Selection
Board has approved contract w/ CHA.
create budget, determine scope, hire Architect
suggestion to align plant
materials with curriculum
Punchlist underway
Download