Chabot College - Facilities Committee Update September 13, 2012 Item Building

advertisement
Chabot College - Facilities Committee Update
September 13, 2012
Item Building
Project / Designer
Phase
Activity / Issue
Punch List
Occupancy April 2010
1
CSSC/700
Community and Student Services
Center - tBP
2
IOB/400
Instructional Office Building - LPA
Punch List
Occupancy Jan 2010
3
Site
Athletic Facilities - Verde Design
DSA Close Out
Awaiting DSA close Out
4
Site
Football Field
DONE
PROJECT CLOSE-OUT COMPLETE
5
1900
Punch List
Occupancy Jan 2010
6
Site
Planetarium / Lecture Halls - DSK
Pool Renovation - Aquatic Design
Group
DONE
PROJECT CLOSE-OUT COMPLETE
7
Site
M & O Facility - Gould
On Hold
On Hold
8
4000
PE Strength Fitness Center
Construction
Occupancy December 2011
9
800, 900, 1000 Classroom Building - HMC
DSA Close Out
B800 Occupancy Jan. 2009, B900 is occupied
10
500
Classroom Building - HMC
DSA Close Out
Occupancy Jan. 2010
11
Site
Portable
Offices
Central Plant / Utility Loop - ESCO DSA Close Out
Temporary Faculty Offices Charles Ham
DONE
12
13
14
1000, 1400,
1200, 1300
508, 904,
1814, 2205
15
Art Gallery Doors, Industrial Tech
Improvements, PAC Interior
Improvements
Phase 3 underway, Completion Dec. 2008
PROJECT CLOSE-OUT COMPLETE
DONE
PROJECT CLOSE-OUT COMPLETE
Technology Enhanced Classroom
Classroom Standards and Office
Standards
DONE
PROJECT CLOSE-OUT COMPLETE
DONE
PROJECT CLOSE-OUT COMPLETE
16
Site
Campus Security Plan - Catalyst
Close Out
Under Construction, complete Nov. 2008
17
300
Construction
Occupancy Ddecember 2012
18
Site
Classroom Building - HMC
College Landscape Guidelines RHAA
DONE
standard is complete
19
Site
Asbestos Inspections - HMS
On-site Investigation Investigating B3400, B1700
20
2500, 2600,
2700, 2800,
2900
PE Complex - SKW
Construction
Construction scheduled completion June 2013
21
Site
Commissioning Authority - AEC
On-going
B1200, B1400, B1800
22
Site
District-Wide FF&E Consultant
On-going
Dovetail working with B1700/1800
23
Site
IT Infrastructure Project - ESCO
Close Out
Scope of work coupled with Central Plant item #11.
Responsibility / Action
On Hold
Chabot College - Facilities Committee Update
September 13, 2012
24
Site
Site Design Committee
25
100
Building Modernization - Steinberg Schematic Design
Schematic package being assembled for review
26
Site
College Marquee - tBP
Working Drawings
90% CDs under review - to be bundled with #44 Security
27
Site
Complete
Finished with CSSC project
28
Site
Founders Plaza - CSSC/tBP
Space / Program Relocation Dovetail
29
2200
Dental Hygiene - HMC
Close Out
Occupancy October 2009 - Project Close -Out
30
Site
Campus Signage - HM
PAC Rigging Beam Analysis George Famous
Working Drawings
CDs under way
DONE
Analysis Done
Parking Lots - tBP
Close Out
Finished Aug. 2008
Renovation - CHA
Construction
Project is substantially complete. Punch list work underway.
31
32 Site
33A 1400
33B 1600
On Call As Needed
Chaired by Tim Nelson
On-going
Renovation - CHA
Construction
Renovation of 1618 and 1620 needs punch list completion
34
Site
Solar - Chevron Energy
DSA Close Out
Solar Panels are operational
35
1800
Renovation - Steinberg
Construction
Construction underway B1800, occupancy scheduled Jan. 2013
36
1700
Renovation - Steinberg
Bidding
to be bid Fall 2012
37
1600
Renovation - TBD
FPP revisions
FPP revised for FY 12/13. Awaiting state input
38
Site
Soccer Field Restoration - Verde
Close Out
Construction finish October 2010/in maintenance period
39
200
1100, 1500,
2000
Light Renovation - Dovetail
Construction
Light Renovation
Pre-Design
project finished
Budget does not allow for wall changes to accommodate the Chabot
College office standard of 100 s.f.
Light Renovation
Pre-Design
42
2300
B1200, SOTA
Plaza
Renovation - bfgc
Construction
Construction underway, occupancy scheduled Jan 2013
43
Site
Parking Lot F Restoration
DONE
February/March 2010
44
Site
Traffic Signal
Construction
project finished
45
Site
Parking Lot G/H/F/J Security
Working Drawings
CDs underway due January 2013 - to be bundled with #26 Marquee
46
Site
Villas Removal
DONE
Removal complete February 2010
47
3400
Light Renovation - CHA
DSA Review
DSA review and Back Check
40
41
48
49
50
Punchlist underway
Download