United States Department of Agriculture Forest Service Volume 13 Number 6 Engineering Field Notes June/July/August 1981 Engineering Staff Washington us D.C. Engineering Technical Information System Precast Concrete Buildings Maximum Grades Forest Roads for Log Trucks on Protective Screening for the Case 1450 Crawler Tractor Repairing Plastic Wet Basements Surveyors Flagging Ribbon San Dimas EDC Develops Cost Analysis for Improved Tree Planting Machine Farkas Article Published Transportation Engineering in a in Research Record Forestry Environment United States Department of Agriculture Engineering June/July/August Serest Field Notes Engineering Staff Engineering Technical Washington pPST it Volume 13 Number 6 D.C. System Information SqC UýS PROFESSIONAL DEVELOPMENT DATA MANAGEMENT RETRIEVAL Information developed contained Department States in for guidance and contractors FIELD NOTES employees United of the of Agriculture-Forest Service cooperating its The Department and Federal REPORTS been has publication this of TECHNICAL its State infor-mation agencies. assumes of Agriculture no responsibility for the interpretation or use of this by other than The use trade of its own employees. names firm or corporation in this en-dorsement Depart-ment publication is for the the reader. Such or and convenience information use does not constitute approval of Agriculture of by the any United product may an States or service text opinions that in the publication of the respective construed as represents and author recommended to the be suitable.-The of others exclusion of official or the personal must not approved be procedures FSM pub-lication mandatory Because references. all should not or instructions read intended of the engineers each issue exclusively policy except type of material and engineering however this for engineers. in by the technicians publication is 1981 PRECAST CONCRETE BUILDINGS Harry Kringler Northern Region Environmental Engineering cost for The escalating contract the wood-frame constructed standard two-unit handicapped vault toilet building prompted the Northern Region to consider other construction possibilities for toilet facilities to serve the Low bids for the handicapped. standard wood-frame constructed toilet have ranged handicapped from $11000 to $21700 with an In price of $14790. most cases the lower bids were received for buildings that were of a much larger contract and lower move-in move-out costs probably were partially responsible for the lower bids. The figures quoted above do not include administration contract costs associated with the 2 or 3 weeks for the field construction of a toilet building. translucent fiberglass roof and concrete screens this type of toilet could be installed for about $2000 per single unit. Unfortunately the appearance of this proposed structure was thought unattractive by many people and the concept was scrapped at an early stage. a con-average two-part The second approach was to struct a building from precast concrete panels that looked like the standard handicapped unit vault toilet building. It felt would be was that concrete more acceptable as a building material if it were incorporated into the standard building design. Preliminary contacts with the concrete precaster dicated that the field erection of a toilet from concrete panels probably would cost about the same as the existing standard wood-frame handicapped toilet. It was decided not to pursue this alternative because the potential cost savings did not warrant the effort. in-required A local concrete had precaster expressed an interest in precasting small structures such as toilet buildings. Concrete apalterpeared to be a reasonable native because of its durability and ease of maintenance. The third option was to design a that would totally new structure fit Forest Service needs. The result was the precast concrete shown in figure 2. structure first approach was to try and form adapt an existing concrete to a vault toilet structure using two concrete pipe sections of standard diameter. The drawing is shown in 1. One pipe section would be installed vertically in the ground to serve as a vault. The bottom of the pipe would be closed with a concrete base cast integrally with the Another pipe secpipe barrel. tion with an integrally cast base would be stacked on top of the With vault as a round building. The incor-figure con-ceptual The concrete structure features the following porates 1. The walls and floor are constructed as one monolithic unit. concrete 2. Urethane form liner gives the exterior walls the look of tongue and groove wood siding. 1 pipe concrete from constructed 2 sections. toilet vault of drawing Conceptual 1. Figure Vent 18x18 Cap Vent Opening Vent Opening Concrete Panel II Roof Flexible Joint Sealant Vent for Toilet Vault Window Wall Cast Louver Unit Iron Pump-out in place Cover Vault Toilet Building 3x6 Steel Concrete Door Screen Screw Anchors Insect Screen 12x18 Vision-proof Louver Bolts Recessed Signs Concrete Screen Grout Exterior Slab Concrete Cantilever Support for Exterior Slab and Screens 18x24 Translucent LEXAN minimum diameter 5/8 Figure Vault Glazing 2. Precast concrete toilet structure. 3 screens have exaggregate finish on ex- 3. posed goal was achieved. are components offsite transported to the site and set in place by The the concrete precaster. tached picture sequence figures 5 through 12 illustrates the installation of toilet nents. This fabri-cated Door 1 day. The toilet at-techniques Vault toilet venting described in Equipand Test Report ment Development 2300-13 Updated Vault Toilet were incorporated whenever possible. Large vent and vent wall on rear cap are as heat chambers to aid venting by convection. 4. compo-Concepts single-designed Colored concrete minimize used to painting quirements. 5. The estimated cost of a unit toilet structure in-place At at this time is $6500. for two units $13000 single the concrete structures are with the lower comparably priced bids received for the existing standard two-unit wood-frame toilet. The concrete toilets will probably have a distinct at trailheads price advantage end-of-road facilities and small where only one or campgrounds two units are required. was re- Interior walls and floor of building are painted with and epoxy paint to seal concrete provide a smooth sanitary surface for cleaning. 6. Translucent glazing in unit is LEXAN industrial plastic polycarbonate which is UL listed as Burglar LEXAN carries a Resistant. 7. of a concrete The major advantage is the structure anticipated Wood lower maintenance cost. sided buildings are prone to and damage from porcupines the dals who remove siding and shingles for bonfires. window louver van-against How-9. replacement guarantee when used for breakage glazing. 3-year one disadvantage of the concrete structure is that there has to be access for a large truck to set the building in place. ever it should be noted that is also required to truck access vault for the pump the concrete existing standard vault toilet. All components of the structure are precast concrete for durability. 8. Toilet has provisions for handicapped such as wide door toilet riser offset to one side of building and stainless steel grab bars. appli-fo steel forms for the toilet to building have been adapted other buildings that have cation in the Forest Service. a pesticide These include storage building a flammable storage building and a pumphouse These 15 and 16. figures units can be delivered to the site prewired or preplumbed as The Precast concrete vault and support serves as foundation building and screens. 10. 11. Cast iron door on rear wall of building allows access for pumping vault through the vent without dragging hoses into the building. 4 required. One of the design goals was to be able to complete the installation of a toilet unit onsite in To have the steel forms for the built would building components 4 re-$30000. $20000 to approximately The Region chose not to own the forms in the hope that some of the form costs would be distributed among other potential users of the concrete structures. In reality this creates a sole source for the structures if the units are ordered a few at a time. There seems to be a normal for sistance to using concrete small Forest Service structures. Most questions are related to the aesthetics of concrete since it is perceived as a cold nonnatural material. The wood grain form liner and colored concrete were used in the design to try and disguise the concrete to make it more appealing to the public. Initial reports from the field indicate that overall the building has been well received by the public. cost Low bids for the existing standard vault toilet varied up to 100 percent above the lowest bid received in the past few years. strucThe cost of the concrete tures will no doubt rise in proportion to the rate of inbut the prices should more stability from project to project. alter-flation con-have Figures 3 With some minor modifications the concrete should buildings prove to be an economical the native to contracting struction of wood-frame toilets at and other small buildings many Forest Service sites. through 5 Z6 follow Figure M Location Color Form Precast 3. Picnic Area Gallatin toilet walkway needs to be completed. Forest National Northern Green Sage Liner concrete handicapped Pattern Estimated Cost Manufacturer Sandblast $5500 Excluding by Symons Form Corp. 1979 Costs Unit shown manufactured by Precast Concrete Inc. JR P.O. Box Three Specifications TG and 178 Forks Drawings MT 59 752 Available and from Environmental Architectural Groups Engineering or Zone Environmental Engineers R.O. 6 Region Figure Location Color Form 4. Precast West Boulder Campground concrete pumphouse. Gallatin Forest National Northern Brown Liner Pattern Estimated Cost Manufacturer Sandblast $3500 Excluding Unit JR shown Box Three and by Symons Plumbing manufactured Precast P.O. Specifications TG Concrete Corp. and Form Costs by Inc. 178 Forks Drawings MT 59 752 Available from Environmental and Architectural Groups R.O. Engineering or Zone Environmental 7 Engineers 1980 Region Excavate hole Excavation. Figure 6 for toilet vault. Spread sand or pea Figure Set vault in hole. 6. Top gravel leveling Installing vault. of vault 8 must be level both ways. course Figure 7. Compact backfiZZ under front slab. . I Figure 8. Setting front slab 9 on cantilevered supports. Figure 9. Setting toilet building on top of vauZte re Figure 10. Setting screens on front slab. 10 Figure 11 Figure 12. Setting roof slab and vent cap Completed vault toilet unit access photo was taken. 11 on trail top was of building. not completed when Figure Note the wood glazing shows Form liner. Dirt grain pattern from the form liner. where someone tried to kick out the LEXAN Figure Interior paint 13. of 14. smudge panel. Interior of building. toilet building is painted with white a smooth surface for cleaning. to provide 12 on epoxy Figure Unit can 15. Precast concrete pumphouse. Interior of precast concrete pumphouse. Figure 16. be delivered to the site almost completely prewired and 13 preplumbed MAXIMUM GRADES FOR ON FOREST ROADS Carl LOG TRUCKS Cain Civil Region Engineer 1 or 34500 kg to be hauled up very steep grades. Most trucks are turbocharged so full at higher power may be developed What is the maximum grade for Forest Service roads and what is it based upon This question 1 recently came before the Region A curEngineering Staff Unit. sory review of the matter many recommendations and guidelines but none were based Therefore data. upon quantified was a search of the subject the results of which undertaken are summarized in this article. lbs re-vealed elevations. The second category considers road surface factors weight distribution and resistance factors. One factor traction is considered critical by most _representa-The engineers equipment tives and log truck drivers. were orfactors considered ganized into three categories vehicle factors traccapacity and tion and resistance factors and material factors. This article discusses these factors and presents quantified data in table 1 on traction and resistance factors applicable to Since other vehicles trucks. associated with logging operations are assumed to act the log truck is the only vehicle considered. Traction can be defined as the the tire surface tension between and road and is expressed as a coefficient. Traction cient values are shown in column 2 in table 1. They vary because of weather conditions the nature of the materials used of the in the manufacture cle wear and maintenance factors. coeffi-utilization vehi-log simi-larly is The traction coefficient reduced by multiplying it by a factor called the traction ratio The traction ratio is or TR. the weight on the driver wheels over the total weight of the vehicle. For an all-wheel drive vehicle the TR is while for a loaded log truck it will be unloaded .4 to and unloaded gyback .6 to with trailer extended .3 to vehicle The first category includes horsefactors capacity transmission types gear power reduction ratios and engine atThese were not found tachments. to be critical. be-tween pig-Modern 1 .4 .6 350 log trucks produce or brake horsepower kW 260 more and are equipped with transthat missions and differentials 77.62.1 to reductions produce up coeffi-full .36 Rolling resistance which may also be expressed as a cient is caused by tire flexing compaction or deformation of the the engine to develop at very slow speeds power thus enabling legal loads 76000 This allows Telephone Williams interview Equipment with Leonard Legreid Kenworth Montana Company Missoula 15 Truck Montana. Salesman Table 1 2 Surface 3 Traction Coeffic.f Rolling Resist MAXIMUM 1. LOG TRUCKS Maximum 4 r GRADES Startin Resist 5 s START ON FROM 7 .6 TR REST Grades Starting 6 .43 TR CAN .3 TR Truck Loaded Empty Trucka Piggybackb Empty Truck Trailer Extendedb .75-.9 .55-.7 Concrete-dry Concrete-wet Gravel-packet wet or excludes clays 19.6 Example 47.0 61.4 17.6 24.8 Given earth 29.6 42.5 9.0 15.5 Reqd maximum 19.3 29.4 42.3 42.4 8.7 2.8 15.2 17.4 dry .50-.8 25.7 25.2 56.3 6.5 22.0 .40-.8 .1 .1 10.5 wet .02 .02 6.3 23.7 17.4 51.6 2.7 19.8 .40-.7 .36-.7 .03 .04 .1 .1 5.7 18.8 17.0 42.0 2.0 14.5 Assume 3.4 20.4 13.6 46.2 -0.2 16.1 weather .55-.7 .03 .1 12.2 20.9 29.0 46.5 8.0 16.8 Solution Under .55-.6 .022-.0 .1 12.2 17.0 29.0 37.8 8.0 12.8 1 dry some .40-.5 .022-.0 .1 5.7 10.5 .20-.5 .10-.6 .02 .04 .1 .1 -2.7 -8.2 .29-.3 .02 .1 .3 .03 .1 .07-.1 .00 .1 15.3 1 2 sanded 1.2 road. adverse for grades the following 19.4 landings loaded log truck to start from rest 3 moving for loaded 6.5%. 25.2 2.0 6.5 2.0 to 12.5 2.5 29.2 -5.0 8.4 2 13.6 -5.1 32.7 -9.8 9.1 rest 2.1 8.9 10.4 -1.8 -1.0 for 3 loaded go done ice or 1 across extended find Earth-wet to col. and read starting col. wet during snow. 5 trucks log to across to 10.5%. go 5.7 be col. landing trailer 17.0 log-trucks hauling will but not on truck from Snow-lightly surface 6.4 snow Dry packed Loose snow 28.1 13.1 To 12.8 Earth-dry Earth-wet 21.6 From .1 .1 Gravel-loose-dry Gravel-loose-wet Rock-crushed .1 .1 To From .02 .01 Asphalt-wet oil oil To .55-.7 .40-.7 Asphalt-dry Gravel-packet .01 .01 From and 7 from from read con-freeshaft sanded Snow-lightly with chains Ice without chains 12.3 2.8 -7.2 -5.1 -0.6 -5.6 -2.3 -8.1 add 10% to -6.4 of vehicles Add Based with turbines 10 percent upon to fTR manual transmissions. Factor for wet would or hydrostatic transmissions these values to obtain the maximum clutches .0 be grade to a hydraulic .05 log torque converters They may may negotiate when may moving. cause downhill - r 1-TR - S based upon fR -T _ r 1-TR - caution steep struction truck S h height of or center b wheel formulas values in composite base from trailer of gravity 18 source column 2 4 coupling 2 and 3 are 2 which truck means 15.7 to a spin out will 20.5%. NOTE Extreme For part log moving loaded somewhere between is recommended in the use over 20%. especially because of impractical grades be and maintenance vehicles direction that to 5 and problem travel in the loose control. col-irregularities road surface irregularities and other surface that impede free It varies rolling of a vehicle. by surface types and conditions. Values for it are listed in column 3 in table 1. in the table. These were used to arrive at the values in and 7 umns for a log truck 6 unloaded loaded piggyback and unloaded with trailer extended Results with less respectively. range would be desirable since there is a wide range in traction coefficient values this is not possible. road surface 5 how-ever Air resistance is negligible. it The SAE method of calculating shows that for air speeds up to 13 mi/h less than 1 horsepower Since log trucks is being used. travel at low speeds on steep grades air resistance may be The third category utilization is an and material factors consideration in grade overriding determination. On steep grades road and equipment maintenance costs damage potential and fuel use increase while ment life decreases. Nonplastic soils on steep grades are more to erosion than plastic subject of soils and the construction steep grades on nonplastic soils costly may therefore necessitate ameliorative measures such as additional drainage facilities surfacing and lining ditches with riprap. Roads used quently by the public should for not be considered obviously extreme grades because most cars do not have the clearance or traction that log trucks have. It should also be noted that some states have grade tions requiring auxiliary means the descent of to control cles on grades over 20 percent. equip-elevation disregarded. curves and super may steepen the grade This a log truck travels over. 5 effect of to have an up may centerline over the percent grade. Although the table does it not take this into account should be considered if a truck Horizontal fre-inertial will start uphill on a curve. resistance is initial resistance when the truck is at rest. One source reported that it is equivalent to an additional 10 percent grade for log trucks with a manual transmission and 3 to 5 percent for those with semi fully automatic transmissions.2 howMost log trucks are equipped with manual transmissions.2 This should be in the design of considered landings and roads used as continuous landings. The table considers this col. 4 in derivthe figures in columns and 7. Starting restric-or vehi-ever as-ing In summary modern log trucks have sufficient power and gear reduction ratios to negotiate Failure in steep grades. cending steep grades results from a lack of traction. is easily quantified and can be used to determine the maximum grades that any vehicle Trac-tion 5 6 uti-sistance de-found last resistance factor is grade normally expressed in The maximum grade repercent. uphill grade that a can start on may be truck log by using the formulas shown The 2Gradeability of Log Trucks State University June 1977. However may perform upon. lization and material factors may be critical in grade termination especially on roads Thesis 17 by Edwin A. Stryker Oregon S. Grade-used Merritt Frederick in fragile areas and those used this by the public. Although article does not give or recommend a definite maximum grade it gives guidance that may be in making and examining guidelines. Standard Engineers 1968 Swami Ken Worth Kenworth Caterpillar Performance Caterpillar Tractor Company October 1980. York McGraw Hill 1962. Handbook Fitch James W. Engineering W. New York McGraw Hill Canadian Limited. Urquhart Leonard C. Ed. Civil Engineering Handbook New REFERENCES James for Civil Stryker Edwin A. ability of Log Trucks thesis Oregon State University June 1977. Truck Handbook Motor Handbook Fitch 1969 18 PROTECTIVE SCREENING FOR THE CASE 1450 CRAWLER TRACTOR Leo Snowden Equipment and Facility Manager Routt National Forest im-meet con-added near-of opera-tional Region 2 of such incidents is low but the consequences are serious particularly if the operator fails to stop the tractor mediately. Crawler tractors supplied through GSA equipment contracts are equipped with rollover protection and protective screening to This OSHA requirements. means that protective screening is usually limited to the top back and sides of the cab. Occasionally some screening is to protect lights exhaust pipes etc. as shown in figwhich illustrates the use ure screening to protect the exThe haust pipe and precleaner. modification does add some addifor the operaprotection tor but it is not adequate for such as some types of activities logging slash or brush. Logs limbs and branches may enter the cab from the front or the entryway. The probability A substantial of slash in the Routt piling forest. it was Therefore sidered necessary to analyze the existing screening to consider the type and number of misses that have occurred and alternatives that would to design to the improve protection tor but not hinder his ability to exit the tractor in case of an emergency. The cost of additional stalling screening was not considered significant and was consequently excluded from the analysis. Among the possibilities analyzed were the amount is performed 1 in-piling following 1. FULL CAB PROTECTION PROTECTIVE SCREENING Full cab screening most protection to COMPLETE offers the the operator slash however elimi-nates from it This an emergency exit. cannot be option really further because it creates a more severe hazard than we presently have. con-sidered 2. FRONT PROTECTION AND SIDE GATE PLACING PROTECTIVE SCREENING ON THE SIDE AND FRONT OF THE CAB Figure 1. Front and side screening offers from the operators protection shoulder to his feet from a pro truding log with one end on the This option would have ground. Additional screening for the exhaust pipe. 19 solid screening placed between the rollover bar and the engine cab with a spring-loaded or magnetic-latched gate on the side. The height of the side gate would be about equal to the height of the fuel tank. In this case emergency exit would be awkward. If the gate did jam the operator would have to exit over the gate and the routine mounting and dismounting of the machine would be interrupted. than having a solid hard grip the operator would have to grip one stationary handle with one hand and open the gate with the other. tank. In this case emergency exit would be only slightly If the gate did jam impeded. the operator could step over the gate and dismount normally and routine mounting would not be affected. If slash were to ride up over the additional screening reaction time for the operator would be very limited. MODIFICA-Rather OPTION NO. 3 WITH SOME THE SIDE PANEL ANGLED FROM INSIDE OF THE ROPS POST TO THE FUEL TANK OR EXISTING SIDE CONSOLE. 4. TIONS A front panel would be required much the same as in Option No. 2 and would provide a step and the free use of the existing hand grips when dismounting the machine. The angled side panel would also force protruding logs to the rear of the machine. 3. ANGLE GATE PLACING A SCREEN GATE DIAGONALLY FROM THE ENGINE CAB TO THE FUEL TANK figure 2 This option would offer protection from the operators midchest to his feet from a protruding log with one end on the ground. The gate would be or magnetic spring-loaded latched and the screening would be placed adjacent to his legs. The height of the gate would equal the height of the fuel 5. ADD NO ADDITIONAL SCREENING PROTECTIVE Routine mounting and emergency exit would remain good. Since this option offers the least mechanical protection from pro-Figure 2. Screening for option Figure 3. 20 3. Screening for option 4. truding logs operators must stay more alert to the hazards. At the conclusion of the field testing the operators agreed that the additional screening was well worth the installation time and cost although they preferred the screening of Option No. 4 because of the ease in mounting and dismounting the tractor. However both types of Since regulations prohibit welding to any part of the rollover protection system and since the rollover posts vibrate continuously some structural and fastening problems might be fu-ing with-to pro-through anticipated with options screening greatly improved tection for the operator and will continue to be used in the ture. As evidenced by the wear and tear on the screening numerous pieces of slash might have entered the entryway out the additional protection. 1 It was finally decided to add protective screenfor field testing to two tractors one of which was to Option equipped according No. and the other according 3 No. at a cost of Option Both tractors $200 per tractor. were used a nearly equal amount of time for piling slash. 4. 4 21 REPAIRING WET BASEMENTS Gerald T. CoghZan Construction Maintenance Operations Group Leader Region and 9 upper part of the wall through cracks or through the porous concrete block. The surface water may follow the crack or hollow blocks downward often appearing on the inside as a wet area close to the floor. Basements become wet from surface water or from ground water. Wetness resulting from surface water is more common and less expensive to repair than that due to ground water. a wet Therefore in evaluating basement problem it is to first consider and due to investigate wetness surface water. appro-priate SURFACE WATER WETNESS Water seeping down along the outside of the wall may enter through cracks or areas missed This is less by the coating. likely for mastic which is somewhat elastic and will stretch The across minor cracks. cement grout however cracks with the concrete wall even fine wall cracks leaving open for possible seepage. -- CAUSES water-proofing Wetness results from surface water being concentrated against the upper basement wall and finding an opening into or Water may through the wall. rain from come running down the side of the building from overflowing gutters clogged at one spot or from gutter downspouts close to the wall. discharging bib connections and hose Leaky lawn sprinklers spraying against wall may also be sources of Planter or flower strips water. the wall may be major conalong tributors to the problem since the built-up borders entrap water and the loose cultivated allows easy infiltration. Wetness resulting from surface water characteristically occurs during or immediately after heavy rains. Wetness may be found along the building wall or corner the prevailing winds or facing along the wall where the clogged gutter overflows or the Similarly spout discharges. due to leaky hose bibs wetness or lawn sprinklers would occur near these sources. Many of these sources of surface water are easily identified and inated or at least minimized. down-the elim-soil concrete basement coated on the outside walls are with a waterproofing asphaltic mastic. However the mastic is discontinued just below the ground surface so that it will Some concrete not be visible. walls are sealed with a waterSurface proofing cement grout. water enters from the top primarily through the unsealed Typically SURFACE WATER WETNESS -- REPAIRS The interior basement walls should first be inspected for major cracks and inward bulging. If the walls are paneled it may be necessary to pry up one vertical edge of at least every second panel to check for cracks. Severe cracks may be horizontal 23 moder-wal addi-scope but many cracks travel down the at about 45. Thus most cracks in an 8-foot wall can be seen within two 4-foot panel widths. Major cracks and bulging are serious problems beyond the of this report and should be given further expert investigation and analysis. should be backfilled and The ately compacted in layers. ground surface should be sloped to-drain away from the wall. If the area was originally lower than the surrounding lawn tional backfill may be needed. Grass or original shrubs can be replaced. tem-to Figure 1 shows a method for protecting basement walls from surface water. Earth is the basement wall along for a width of 2 to 3 feet and a depth at least 1 foot sufficient to expose the waterSod and shrubs proof coating._ can be saved and visquene can be used to protect the lawn from the excavated soil. The wall is cleaned and sealed with a clear silicone or acrylic waterproof sealer. concrete for Coverage these sealers ranges from 100 to 250 SF/gal depending on the and the porosity of the concrete. Particular care should be taken to fill cracks with sealer and to seal around basement windows. GROUND WATER WETNESS ex-cavated -- CAUSES can result from a or water table permanent porary rising above the basement floor. If there are no subfloor drains if the existing drain system becomes clogged or if the sump the becomes inoperative pump ground water seeps through cracks in the floor slab or cracks at the juncture of the floor and wall. Ground water wetness characteristically curs in the spring or after prolonged rainy periods these being common times for temporary high water tables. Wetness oc-product wet-Try The bottom of the trench is sloped outward and sealed with mixed bentonite and soil. amounts of bentonite should be placed close to the wall. to keep the bentonite away from the lower outer edge of the trench. The bentonite and soil will layer prevent deeper infiltration of surface water along the wall and will direct the water away from the wall while soil deep allowing backfill enough to support vegetation. A 50-pound sack of bentonite should suffice for 20 to 25 linear feet of trench. GROUND WATER WETNESS Heav-ier -- REPAIRS Once surface water has been eliminated as the cause of ness ground water causes must be evaluated. Obvious mechanical sump pump problems should be eliminated first. Figure 2a shows the traditional The leaky basement repair. entire outside wall is excavated down to the footing. Weep holes through or under the footing wall will permit drainage from under the slab. If practical the old subfloor drain system should be connected to the weep holes. A conventional gravel and ted pipe drain is constructed around the perimeter of the foundation. Daylighting the drain system where terrain and perfora-However sloped bentonite and soil layer should be well compacted. the lower outer edge should be left loose to allow easy infiltration of the deflected water. The excavation The 24 ORIGINAL LANDSCAPING REPLACED LANDSCAPING ---ADD SILICONE CONCRETE SEALER 12 MIN -COMPACTED BACKFILL SLOPED i - TO SOILi LOOSENED COMPACTED cv ORIGINAL MASTIC OR GROUT SEAL POURED OR AND BENTONITE LAYER SOIL 2 - 31 CONCRETE BLOCK BASEMENT--WALL BASEMENT FLOOR SLAB p a b EXISTING Figure 1. Protecting REPAIRED basement waZZ from surface water. no scale a DRAIN OUTSIDE OF BASEMENT IN COMPACTED EXCAVATE WALL. BACKFILL LAYERS. USE-MASONRY CUT SAW FLOOR SLAB. CONCRETE TRENCH TO BASEMENT EXISTING REMOVE AND EXCAVATE FOR DRAIN. CONCRETE AND FINISH TO EXISTING SLAB AFTER CONSTRUCTING POUR DRAIN. BASEMENT ý- SLAB a N ýý b rye 7r MIN PROVIDE DRAIN POSSIBLE EXISTING SUBFLOOR DRAIN THROUGH CONSTRUCT PIPE OR OF UNDER FOOTING. CONSTRUCT GRAVEL AND PERF PIPE AROUND OUTSIDE OF FOOTING. DRAIN AWAY FROM BUILDING OR INTO PROVIDE b 2. BUILDING DRAIN OR THROUGH OR UNDER FOOTING. REPAIR Figure DRAIN Protecting INTERIOR basement from ground water. no scale AND AROUND SUMP. SUMP. EXTERNAL DRAIN GRAVEL FOOTING. FROM DRAIN a n. o D d a d1 2 FLOOR REPAIR PERF INSIDE AWAY INTO local ordinances permit is the simplest and least expensive relief system. As a second choice connecting through the footing wall to the old sump will save the cost and inconvenience of building an external sump and providing a sump hous- SUMMARY is most commonly Basement wetness caused by surface water. The sources of surface water are moderately easy to identify and minimize and the wall repairs to make. The are economical with can be accomplished hand tools with little impact on the surrounding lawn and re-pairs land-impact Fig-ure ing. the outside of the Excavating basement wall makes a major and reon landscaping quires heavy equipment. 2b shows an alternative Here repair from the inside. the floor slab is cut with a saw to allow excavation of 2- to 3-foot wide subfloor drain along the basement wall. repairing the may involve drain or installing a new drain. Special care must be exercised if there is any chance of striking an electrical conduit in the floor. Again weep holes are made through or The under the footing wall. drains are collected at a sump for discharge away from the scape. Re-masonry advan-This out-existing Basement wetness resulting from ground water is more difficult and expensive to repair. pairing or building new subfloor drains by cutting through the basement floor has many the tages over excavating side of the basement walls. Repairs should be planned as a Efforts simply complete project. to stop a leak at one point often result in a leak at another bulg-building. point. Major cracking and inward ing basement walls are serious problems that should be given further expert investigation. 27 PLASTIC RIBBON SURVEYORS FLAGGING Farnum Burbank Chief Equipment Development Engineer Washington Office WO GSA has also requested that we and further cooperate prepare Reports on Quality Deficiency ribbon or any other material found to be deficient in any This document is the respect. source of information primary used by GSA technical tionspersonnel for identifying problem areas. Apparently users are most frequently questing waivers to purchase from commercial sources. from the waiver cation statement rarely gets back to quality assurance or technical people who are the ones to take action. The Forest Service has recently been contacted by GSA technical specifications personnel regarding problems that have been exwith Plastic Surveyors perienced Flagging Ribbon Spec L-RInasmuch as the Forest 00335A. Service is one of the heaviest of this material GSA wanted us to be aware of steps being taken to improve the qualof the material being supplied. re-ity justifi-The specifica-users Infor-mation major problem being reported as well by the Forest Service as some other users is fading of the red and orange ribbons. It seems that these two colors in only fade to almost colorless 2 to 4 months sometimes more rapidly whereas our field people need distinguishable colored ribbons for 15 to 18 GSA states that they months. are specifying a fade test for the next procurement of ribbon as as an immediate though interim should be This material step. available in the fall of 1981. For the longer range a new Commercial Item Description CID but this will is being prepared not be ready for procurement use When until the summer of 1982. Forest a draft is ready the Service will have the opporThe main tunity for comment. is that GSA is aware of the problem and is taking some corrective action. Another item of interest that in most instances is ribbon purchased through commercial outlets is likely to have been made by the same manufacturer Therefore the supplying GSA. commercially obtained ribbon will probably have the same deficiencies as that procured through GSA--and at 1-1/2 to 3 times the cost. GSA has expressed appreciation to the Forest Service for its cooperation over the years when called upon to provide samples information. GSA now and/or asks our indulgence as they try to correct the reported ciencies. defi-point 29 SAN DIMAS EDC DEVELOPS COST ANALYSIS FOR IMPROVED TREE PLANTING MACHINE Farnum Burbank Chief Equipment Development Engineer Washington Office WO in-mechanical opera-would the past few years a in forestry developed for an improved operations tree planter that combine reliability and During propelled machine. To accomodate the economic factors assumptions were made concerning capital vestments a wide range of ting costs maintenance factors site conditions etc. But it should be pointed out that the assumptions probably would have to be modified to fit a cular situation and assumptions can become invalid as stances change. need has parti-cost circum-termittent economy in long-range operations. The San Dimas Equipment Development Center was assigned a project to develop the criteria and that analysis for a machine could plant seedlings on an in- con-the fac-in re-duce basis. spot planting Such a system could energy requirements and costs related to site preparation since the spot planters shoe or blade would not be in as it is ground continuously the usual furrow planting method. Given similar conditions the hand planting system is the closest comparative to the intermittent planter concept therefore the analysis was made using the known costs of hand planting and the projected costs for the intermittent planter. It was known that the intermittent planter would be more costly than continuous-furrow equipment since the former is more mechanically complex. In the analysis developed by San Dimas only economic factors were addressed. Usually decisionmakers must also sider social and political tors as well as those of site conditions and the species of the seedling stock. Mechanized reforestation may include other features or benefits not readily identified by general cost machines can make analysis uniform high quality plantings that could result in higher unit yield and problems may be avoided that are inherent in locating hiring transporting supervising and caring for labor crews needed for hand planting. for-and The analysis included projected costs for the operation and of the equipment depreciation as well as interest on capital. costs were estimated by including machine characteristics such as equipment weight cost average production rate and crew size for planting containerized or bareroot seedlings by either a towed or self- The cost-determination method at the Center is a developed mathematical approximation no field experience with an is mittentplanter available to determine base planting rates or machine reliability. The mulae in the analysis are based upon assumptions and the results are considered approximations but the method for predicting inter-Parametric 31 the costs of an intermittent planting machine could prove valuable planning tool for forest managers. Regeneration in Raleigh Carolina in March 1981. North The the Test ob-method The a report was published in Equipment Development No. Project Record 8124-1203 June 1981. A copy may be tained by sending a request to the following address complete report on the and performance criteria was presented Mechanical by Dan McKenzie at San Dimas during Engineer the session on Forest Economics the American Society of Agricultural Engineers Symposium on Engineering Systems for Forest Develop-at constraints Forest Service - USDA San Dimas Equipment ment Center 444 E. Bonita Avenue San Dimas CA 91773 32 FARKAS ARTICLE PUBLISHED in Engi-Centers Loca-Economist TRANSPORTATION RESEARCH RECORD in the July 1978 neering Field Notes Location by Z. of District Maintenance by Least Transport Cost Andrew Farkas RPA Staff issue of Volume Number 7 under the title tion Analysis of District WO was published in Record 774 Research Transportation Maintenance Management Systems and The arTransportation Ride Quality. 10 Centers. Copies of the recently-published article are available through the Research Board Transportation National Academy of Science Avenue NW 2101 Constitution 20413. Washington D.C. ticle describes and illustrates a the most method for determining of district economical location A condensed maintenance centers. version of the article appeared 33 SERyi rptEEST U4s ENTOFM TO READERS OF INVITATION NOTES FIELD reader Every author of an article for Field Notes. a potential is If have you a news item or short respec-tive informa-tive article in you would like to we share with Service engineers invite you send to for it publication Field Notes. Material submitted the Washington to Regional Office to see that and of may interest vary from news to items are sentences short and to ideally FSM 7113. The typewritten several to be submitted material pages however Office drawings original by the accurate of length the Washington should illustrations all be reviewed current timely technically is submitted All material preferred. double-spaced Office for publication should information Service Engineers Forest several the short articles should be glossy or typed or prints negatives. Field Notes Area Headquarters list ask to is distributed from the Washington Forests and your Office Manager or the Regional the number increase from the Washington Field personnel their Regional of copies sent office. you are Copies Data back Station Regional not currently Technical of all to. Systems issues are and on the mailing Coordinator also available should submit material for publication or questions concerning Field Notes to Coordinators Bruesch Larry R-2 Mike R-3 Juan Gomez Clinton R-4 Ted Wood R-5 Paul Stutes Kjell Bakke R-6 Tom R-8 problems Engineering your to If Office. R-1 Coordinators Office directly Service retirees. Forest should direct questions concerning format editing Service-USDA Engineering Staff Attn Gordon P.O. L. RP-E Rome Bldg Editor Box 2417 Washington Telephone D.C. R-10 WO Hasan Mujeebul Fred Baxandall Al Colley Vanderpool to Forest R-9 20013 Area Code 703 235-8198 34 publishing dates and other ropEST SERVq U S ENT Of AA INFORMATIONE LSTýý June/July/August Volume 13 1981 Number 6 Engineering Field Notes