Resolution 12-05

advertisement
Resolution 12-05
Sponsors: Ohio Municipal Electric Association; Santee Cooper; Illinois Municipal Utilities
Association
In Support of Flexibility in EPA’s Regulatory Requirements to Ensure Electric Reliability
1
Providing reliable electricity at a reasonable price while protecting the environment has always been a
2
fundamental responsibility of consumer-owned, not-for-profit public power utilities in the United States.
3
4
The American Public Power Association (APPA) is concerned about the possible adverse reliability
5
implications for regional electric systems if recently promulgated and proposed Environmental Protection
6
Agency (EPA) regulations go into effect within the time frames now proposed or already mandated.
7
These rules include: Utility MACT; cooling water requirements under Section 316(b) of the Clean Water
8
Act; coal combustion residuals; New Source Performance Standards (NSPS) for greenhouse gases; Boiler
9
MACT; regional haze; and the Cross-State Air Pollution Rule (CSAPR). Of key concern is the Utility
10
MACT rule imposing very costly and stringent reductions in mercury, other hazardous air pollutants, and
11
particulate matter on coal- and oil-fired generators (finalized in December 2011). There is a need to
12
carefully assess such implications and to stage compliance efforts in each region to avoid reliability
13
events. The cumulative potential impact of both retrofits and retirements on reliability is troubling. The
14
possibility of regional reliability problems is high if a substantial number of coal-fired power plants go
15
out of service for extended periods of time in the same time frame to either accomplish the retrofits
16
required to comply with the EPA requirements, or to replace the plant with a new natural gas-fired plant.
17
18
The North American Electric Reliability Corporation (NERC), whose mission is to ensure the reliability
19
of the North American bulk power system, has projected that, because of the pending EPA environmental
20
rules, there will be announcements of plant retirements with potential reliability impacts. FirstEnergy
21
Corp. alone recently announced that it plans to retire almost three gigawatts of electric capacity because
22
of EPA’s Utility MACT rule. These three gigawatts alone constitute more than 50 percent of the
23
retirements that EPA estimated would result nationwide from the Utility MACT rule. Further, state
24
officials from across the country have called for more flexibility for plants to complete retrofits than is
25
provided under the rule, and for federal protection against civil lawsuits for power plants that have not
26
completed installing mandated pollution controls, but are required to keep operating to maintain
27
reliability.
28
29
For example, APPA strongly believes that the EPA, in its recent Utility MACT rule, should have granted
30
the electric power sector, particularly public power utilities, additional compliance time beyond the
31
standard three years provided under the Clean Air Act, and the additional one year available upon state
32
requests. APPA explained that such an extension is clearly necessary, given the time required to: (i)
33
develop the optimal compliance strategy once the final rules are known; (ii) obtain financing for either
34
pollution controls (scrubbers, baghouses, etc.) or other resource options, e.g., new gas-fired generation
35
units; and (iii) perform the actual execution of the chosen compliance strategies. Public power utilities
36
must deal with a number of unique hurdles during the financing process, including the need to obtain
37
local government approvals, and sometimes additional voter approval, to issue the bonds necessary to
38
fund retrofits or new construction.
39
40
These steps are in addition to the permitting, siting, and other approvals that all electric utilities must
41
obtain. Public power utilities must also comply with state- and locally-mandated administrative
42
procedures for the bidding and award of equipment, service, and construction contracts applicable to
43
governmental entities, as well as, requirements to solicit input from the general public on the proposed
44
project through scheduled hearings and opportunities for written comments. Finally, APPA has
45
substantial concerns about supply chain issues. If many electric utilities are seeking to procure
46
equipment, consulting and contracting services for retrofits or new construction in the same time-frame,
47
smaller utilities are likely to be relegated to a spot further back in line, given the superior purchasing
48
power and negotiating clout of larger investor-owned electric utilities, including entire electric utility
49
holding companies. All of these factors will require some public power utilities to seek more time to
50
comply with EPA regulations like Utility MACT.
51
52
Nonetheless, the procedures outlined in recent documents issued by EPA and the Federal Energy
53
Regulatory Commission (FERC) staff regarding the possibility of obtaining a fifth year to comply with
54
the Utility MACT rule, for example, do not sufficiently recognize the compliance challenges facing both
55
affected public power systems and the larger electric utility industry. The procedures set out in these
56
documents are quite narrowly circumscribed, and taken together do not constitute a viable path which
57
public power systems, acting in good faith, can use to obtain the additional time they might need to
58
comply without being subjected to penalties for non-compliance and citizen lawsuits. Unfortunately,
59
EPA has chosen not to use all of the authorities available to the agency to allow sufficient time for
60
compliance with Utility MACT and other regulations in order to ensure an orderly, least-cost process of
61
achieving the new requirements while maintaining the reliability of the system.
62
63
Given this situation, the federal government should augment the tools available to it in order to ensure
64
electric system reliability. One such tool is the emergency authority available to FERC and the
65
Department of Energy under Section 202(c) of the Federal Power Act. This authority allows those
66
agencies to order specific generating units to operate when an emergency develops and those units are
67
necessary to maintain the integrity of the system. However, under current law, complying with such an
68
order, including voluntary compliance by utilities not subject to FERC’s jurisdiction, could subject those
69
generating units to penalties imposed for violation of EPA regulation.
70
71
NOW, THEREFORE, BE IT RESOLVED: That APPA strongly supports efforts to maintain and
72
improve the reliability of the nation’s electric grid; and
73
74
BE IT FURTHER RESOLVED: That APPA urges FERC, in conjunction with NERC, to undertake a
75
comprehensive, region-by-region review of the potential adverse impacts of impending EPA regulations
76
on the reliable operation of the bulk electric system, and work cooperatively with the EPA to provide the
77
industry with realistic and comprehensive procedures that will permit affected public power utilities to
78
obtain sufficient time to comply with such regulations without adversely impacting regional or local
79
electric system reliability; and
80
81
BE IT FURTHER RESOLVED: That APPA will work with Congress on legislation to provide the
82
needed flexibility in the Federal Power Act to ensure that federal regulations do not threaten electric
83
reliability, and that all electric generation providers that either are ordered, or that voluntarily agree to
84
comply with an order, to operate their generation units to protect local and regional electric system
85
reliability are not subject to penalties or other legal liability under federal, state, or local environmental
86
laws for their compliance with the order to operate.
Download