Office of Financial Management Washington State Major Project Status Report December 15, 2010 Agency Number: 699 Agency: Olympic College Project Number: 10-2-422 School/Campus Bremerton Campus Project Title: Sophia Bremer Childcare Development Center (SBCDC) Contact Name, phone number, email: Bill Wilkie 360-475-7835 bwilkie@oc.ctc.edu Barbara Martin 360-475-7501 bmartin@oc.ctc.edu Project Description This project will consolidate existing childcare programs in a new childcare development center building with matching funds from the Bremer Trust on land gifted by the Bremer Trust. The facility will almost double the childcare capacity and expands a much needed service to students taking day and evening classes. Opportunities for Early Childhood Education work-based learning will be improved, increasing FTE’s. The facility will be directly adjacent to the Early Childhood Education academic program, directly adjacent to the new outdoor childcare playground, and close to drop-off and student parking. Safety and security code and licensing deficiencies will be resolved in a quality, 50-year facility. The project is directly supported by the 10 Year Capital Request Plan and the Facilities Master Plan. The project is also directly supported by the College’s Vision and Strategic Initiatives to create learning opportunities and provide student support services. Square feet: SBCDC: Predesign: Schematic Design: CD: Project Total Cost: Phase Biennium Predesign 2003-2005 Design 2005-2007 Construction 2007-2009 Other (Approp/NonApprop)* 2007-2009 Equipment/Artwork 2007-2009 Total Appropriation 979 979 991 991 991 16,523 gsf 16,523 gsf 16,523 gsf Amount $244,912 $467,739 $3,226,345 $47,500 $13,504_____ $4,000,000 *Other includes: advertising, aerial photos, LEED publishing, other equipment purchases (such as shelving). 12/15/10 Schedule: SBCDC Predesign Complete Start Design Bid Date Notice to Proceed 50% Complete Substantial Completion Final Acceptance Budget Schedule 12/08 11/09 11/09 01/10 07/10 09/10 12/10 Actual/Forecast 12/08 11/09 11/09 01/10 07/10 09/10 12/10 Variance (wks) 0 0 0 0 0 0 0 Project Status and discussion of Critical Path for Construction The SBCDC has reached substantial completion. The licensor’s punchlist has been completed and the College’s punchlist has been largely completed. The final acceptance letter will be signed as soon as all of the punchlist items have been completed. The occupants will be moving into the building the entire month of December. Contract Award History – SBCDC Building A/E Agreement Original Agreement $ 345,056 Amendments $ 430,564 Pending Changes $ 7,500 Total Current Design $ 775,620 $ 338,936 Construction Contract (excl. sales tax) Bid Award Amount $ 3,400,000 Change Orders $ 412,311 Pending Changes $ 12,500 Equipment & Other $ 254,582 Total $ 4,079,393 Current Construction $ 3,331,956 *Other includes equipment such as Security systems (ID badge printer, speakers) and furniture. *Pending changes includes re-plumbing/inclusion of separator required by City of Bremerton and emergency lighting/receptor design and construction. Potential for Project Cost Overruns/Claims The scope remained the same throughout the project. Electrical and data modifications for security systems put us over the budget, along with additionally needed excavation from bad soils. Complications with flooring caused additional costs. Finally, a badly needed sound wall for construction noise for other entities on campus was installed at the beginning of construction. Discussion of Project Quality This Building was designed to meet the qualitative expectations and standards identified in the Pre-Design document for overall image, functionality, durability and long-term operational performance. Value Engineering and Constructability reviews during the Construction Documents phase were used to confirm that the systems, materials and detailing decisions have remained consistent with these guiding principles for the building. The building is on track for a LEED silver certification, as required. A lot of attention has been given to the LEED aspect for this building, from the design team to the contractor. 12/15/10 Project Photographs Indoor Outdoor 12/15/10