Office of Financial Management Washington State Major Project

advertisement

Office of Financial Management

Washington State Major Project

Status Report June 30, 2006

Agency Number : 699 Agency : State Board for Community &

Technical Colleges

Project Number : 04-1-311

Project Title :

Bill Reference :

Mountlake Terrace Hall Renovation

Edmonds Community College

Chapter 26, Section 757, Laws of 2003, 1st Special Session

Chapter 488, Section 774, Laws of 2005

Project Description: This project involves the total renovation of Mountlake Terrace.

This renovation will include the following:

Complete upgrade of all HVAC and electrical systems

Upgrades to existing classrooms and a net increase of general purpose classroom space

Expansion, consolidation and centralization of many Student Services and

Programs, including: Services for Students with Disabilities; Counseling Center;

Career Action Center; Testing Center; and Equity and Diversity Center

Expansion of Communications Center (campus copy and mail center)

Consolidation and centralization of Custodial Services operations

Addition of 2 science labs

Mountlake Terrace Hall was built in the late 1960’s, and has seen many changes in configuration and usage over the years. Updates to HVAC will greatly increase our ability to heat and cool the building properly and efficiently. Electrical and data requirements have greatly increased in the last 30 years due to the incorporation of technology into the teaching environment, and this renovation will allow us to provide our students with the most up-to-date courses and teaching methods.

The net increase in general purpose classroom will give Edmonds Community College some much-needed additional space to accommodate our expanding program offerings and our continually growing student population. Consolidating and centralizing many of our Student Services and Programs will benefit students by giving them a ‘one-stop’ location for these services, as well as providing these services with much-needed expansion and upgrades.

The expansion of the Communications Center will benefit both students and employees of the College as they will be able to expand and improve the services they provide to the campus population. By consolidating and centralizing Custodial Services into Mountlake

Terrace Hall, this department will now be able to provide the campus with more efficient services.

1

Project Total Cost:

Phase

Predesign

Design

Construction*

Other (Approp/Non

Approp)

Total

* MACC = $5,833,300

Schedule:

Biennium

1999-01

2003-05

2003-05

2003-05

Appropriation

G38 – Fund 057

G38 – Fund 057

G38 - Fund 057

Amount

$ 801,900

$7,505,930

$ 519,200

$8,827,030

Predesign Complete

Start Design

Bid Date

Budget Schedule Actual/Forecast Variance (wks)

7/03

6/04

7/03

9/04

0

12

Notice to Proceed

50% Complete

7/04

4/05

Substantial Completion 12/05

Final Acceptance 2/06

10/05

4/05

12/05

6/06

12

0

0

16

Project Status and discussion of Critical Path for Construction:

Construction began in January 2005. Construction is complete with a few punch list items remaining. College landscaping and classroom equipment purchases are in process at this time. We expect final acceptance in June 2006.

Construction Schedule as of June 2006.

Hazardous Materials abatement

Demolition

Build out (walls, doors, windows, etc.)

Mechanical (plumbing, sprinkler, HVAC)

Electrical

Punch list

Critical Path:

Completion of final details for final acceptance.

Start

1/02/05

2/15/05

1/01/05

Finish

2/15/05

4/01/05

10/18/05

4/15/05

4/15/05

10/18/05

11/28/05

11/18/05 6/30/06

2

Contract Award History

A/E Agreement

Original Agreement $ 467,760.97

Amendments

Other Agreements

Pending Changes

$ 265,416.18

$ 98,335.00

$ --

Total $ 831,512.15

Current Design

Contingency ($ 29,612.15)

Potential for Project Cost Overruns/Claims

None at this time

Construction Contract (excl. sales tax)

Bid Award Amount

Change Orders

Pending Changes

$ 5,711,678.00

$ 607,380.45

$

Total $ 6,319,058.45

Current Construction

Contingency $ 573,471.55

Discussion of Project Quality

This project follows established campus building standards, and meets current City and

State codes.

Project Photographs

Mountlake Terrace Hall 2 nd floor foyer

Mediated Classroom

Science lab

3

Print and Mail Center

Download