Office of Financial Management Washington State Major Project Status Report

advertisement

Office of Financial Management

Washington State Major Project Status Report

December 12, 2005

Agency Number : 699 Agency : State board for Community and

Project Number : 04-1-307 Technical Colleges

School/Campus : Columbia Basin College - Pasco

Project Title :

“T” Building Renovation - WISE

Bill Reference(s) : Chapter 8, Section 786, Laws of 2001, 2 nd

Special Session, Ch. 26-

03X-795, Ch26-03X-904(6)(m), 277-04-264

Contact Name, phone number, email :

William Saraceno

V.P. Administration

Columbia Basin College

2600 N. 20 th

Pasco, WA. 99301

509-547-0511 ext. 2248

Bill.Saraceno@columbiabasin.edu

Project Description: Original project description was to renovate and build an addition to the “T” Building on the Columbia Basin College Pasco campus in order to improve program delivery for math and sciences and increase capacity of our Nursing program.

With the relocation of the Nursing program element to the Richland campus, the Pasco campus project is now called the Washington Institute of Science Education (WISE). The project now includes appropriate space for our Mathematics and Science programs (Plant

Biology, Physics, Chemistry, and Geology) as well as improved space for Information

Technology and Computer Sciences. 20,400 gross square feet of space is assigned to support Diversity based programs. The WISE project also includes a Center for

Laboratory Science which supports not only advanced chemistry programs but will support further partnering with the scientific community in the Tri-Cities area. The architectural firm ( SCM Consultant, Inc.

of Kennewick) provided design and bid services for the Pasco campus WISE project and will provide consultant services through construction completion.

Square feet : 102,669 combined gross square feet

Scope Changes:

At the beginning of pre-design, further opportunities to augment and improve health science education became available. The Nursing program and related elements were relocated from the Pasco campus to the Richland Campus (adjacent to the Kadlec

Medical Center. With the relocation of the Nursing program, the project design shifted to

12/12/05

allow greater emphasis of the sciences. The 2004 legislative approved of this plan and provided a separate allocation to help build a Nursing facility at the Richland campus.

Project Total Cost:

Phase

Predesign

Design

Biennium

2003-2005

Appropriation

G37

Amount

$613,976

Construction * 2003-2005 G37

Other (Approp/NonApprop) 2004-2005 COP

Total

2004-2005

$3,660,055

$8,000,000

$2,966,000

$15,240,031

* MACC

Schedule:

Pre-design Complete

Start Design

Bid Date

Notice to Proceed

50% Complete

Budget

Schedule

7-1-2003

7-7-2003

6-23-2004

7-1-2004

2-9-2005

Actual/Forecast

7-1-2003

7-7-2003

6-23-2004

7-1-2004

1-9-2005

Substantial Completion

Final Acceptance

12-30-2005

2-1-2006

9-15-2005

2-1-2006

*Educational space. Entire project 11 weeks ahead of schedule.

Variance

(wks)

0

0

0

0

-4

-15*

Project Status and discussion of Critical Path for Construction:

Construction started in July 2004 with a projected completion date of 12-30-2005. The project was substantially complete September 15, 2005, eleven weeks ahead of schedule for the instructional spaces. The contractor established an aggressive schedule and within

3 months of start, was ahead of the base project schedule. The project plan was adjusted to allow a phased occupancy of the building. The “T” renovation and the new Math and

Sciences wing were substantially complete by September 15, 2005 as predicted. The

Diversity wing was scheduled to complete next and did so just days after the first phase.

The CLS wing was completed October 28, 2005 as planned. All program areas are now occupied and in service. The balance of construction activities are non occupancy related, many of them exterior related and are expected to be by late February-of 2006, weather permitting.

12/12/05

Contract Award History

A/E Agreement

Original Agreement

Amendments

Pending Changes

$ 94,344 .00

$

$

Construction Contract (excl. sales tax)

Bid Award Amount

218,849.00 Change Orders

1,681,807.00

$13,011,000

$ 401,591

Pending

Changes

Current Design

Contingency

$ TBD

Total $

$

1,995,000.00 Total $13,412,591

Current Construction

200,000.00 Contingency $234,087

Potential for Project Cost Overruns/Claims

Critical path required the contractor to be substantially complete with site work before the winter weather held up the project. The site work contractor met the aggressive schedule and as such, cost claims related to weather were minimized to less than one percent. This project is comprised of mostly new construction which was evaluated during design to ensure best practices were followed. In addition, engineering and constructability reviews were used to correct potential errors and minimize changes during construction. Ongoing project management of the contract documents and on-site representation is intended to minimize potential time impacts and assure timely responses. Completed project costs and changes today are within budget and reasonable expectation.

Discussion of Project Quality

Designed to meet the current International Building Code, the project will incorporate not only code standards, but additional college standards of construction. Project is expected to add 30 years of useful life to the facility. Project quality will be at or above state standards for life and energy conservation. Even though not mandated, the college strove to meet the Leeds Silver Standards for sustainable building construction consistent with the Governor’s Executive Order. We believe that we have a building that meets that intent and quality.

Project Photographs

See Attached

12/12/05

Front entry September 2005

Building Dedication

12/12/05

Main Entry area between Math Science and Diversity Wings

General Classroom in Math Science wing

12/12/05

Plant Biology Lab

12/12/05

Geology Lab

12/12/05

Download