Evolved Expendable Launch Vehicle (EELV) Program Overview Affordability Through Innovation 20-Nov-97 Overview • Program Background • Contractor Concepts • Acquisition Reform 2 Program Background EELV Mission Statement • Mission: – Partner with Industry to develop a national launch capability that satisfies the Government’s national mission model requirements and reduces the cost of space launch by at least 25% • Objectives: – Increase the U.S. space launch industry’s competitiveness in the international space launch market – Implement acquisition reform initiatives resulting in reduced government resources necessary to manage system development and acquire launch services 3 Program Background Requirement for EELV Space Launch Modernization Plan (SLMP) [May 94]; Gen Moorman, Chairman Options: (1) Sustain current systems (2) Evolve current expendable systems (3) Develop new “clean sheet” expendable system (4) Develop a new reusable system PDD - Presidential Decision Directive NSTC - National Science and Technology Council DoD Intelligence Civil Industry Natn’l Space Trans Policy (PDD/NSTC-4) [5 Aug 94] DoD Implementation Plan [25 Oct 94] supported Opt. 2 EELV 4 Program Background Acquisition Strategy • Original acquisition strategy formulated in early 1995 – Strategy called for downselecting to one contractor • - Contractor provides a family of launch vehicles to support Government requirements - Contractor in a position to capture a larger share of the international commercial launch market Other features of original strategy: – Cost-type contract for Engineering & Manufacturing Development (EMD) contract – Two system test flights during EMD • Approach in strategy revised on 6 Nov 97 5 Program Background Reason for Acquisition Strategy Change Larger commercial market than envisioned two years ago Sufficient market to support two contractors Industry Investment Gov’t leverage commercial market competition Commercial Space Market Growth COMSTAC Addressable Commercial GTO Market 45 1997 60 High Most 35 30 50 Likely x x x Then Year $Billion Launches per Year 40 Low 25 20 1994 15 10 Actual 5 40 Services User Equip Satellite Launch 30 20 10 Does not include Government spending which was $38B in 1996 and projected to be $40B in 2000 0 '88 '89 '90 '91 '92 '93 '94 '95 '96 '97* '98 '99 '00 '01 '02 '03 '04 '05 '06 '07 '08 '09 '10 *As of Sep 97, 19 actual + 13 planned 0 4 1986 1991 1996 2000 6 Program Background Summary of Strategy Change New Old • Cost-type contract for EMD • Fixed Gov’t investment for development in addition to contractor investment • Two system test flights • No system test flights • Downselect to one • Compete two over life of program • Production • Launch services 7 Program Background EELV Acquisition Schedule FY95 96 MS 0 97 MS I 98 99 00 01 02 MS II 03 04 05 06 07 08 MS III LCCV Pre-EMD 15 Months 17 Mths 4 Contracts 2 Ktrs Development - 2 Contractors Initial Launch Services - 2 Contractors RFP CFI TAILORED TAILORED SRR PDR PDR - Preliminary Design Review DDR - Down-select Design Review RFP DDR TCDR Follow-on Launch Services First Flights (Commercial/Military) RFP - Request for Proposal CFI - Call For Improvements SRR - Systems Requirements Review LCCV - Low Cost Concept Validation TCDR - Tailored Critical Design Review UNCLASSIFIED 8 EELV Contractor Concepts Boeing 9 EELV Contractor Concepts Lockheed Martin MLV-D MLV-A HLV 10 Acquisition Reform Single Acquisition Management Plan • Objective: Streamline effort required for acquisition strategy approval 1000+ Pages 60 Pages Integrated Program Assessment Acquisition Plan Acquisition Program Baseline Live Fire Test and Evaluation Waiver Integrated Logistics Support Plan Manpower Estimate Integrated Program Summary Fixed Price Determination SAMP RESULT: Milestone 1 Approved! 11 Acquisition Reform “Lean SPO” Concept • EELV system program office fraction of typical program office size • Focused insight vs traditional oversight – Less management, more insight – 39 military, 12 civilians, 30 contractor (81 total) Where we’ve been: TRUST Where we are: Insight Insight Manage Work Reduction Track Manage 12 Acquisition Reform Electronic Source Selection • • Maximize information technology solutions No “truckloads” of paper copies – Source selection of this size: 2+ tons of paper Proposal an ge Reference Material ch a os ls n io t r a P lu s a t Ev pu In op RESULT: Ex Proposal Reader ta Evaluation Software TOTALLY ELECTRONIC SOURCE SELECTION Briefings & Reports Da World Wide Web Solicitation Release Ou tpu t Archived Data 13 Acquisition Reform CAIV • EELV is a Cost As an Independent Variable (CAIV) program • System designs must meet key performance parameters – Mass to orbit – Design reliability – Standard launch pads – Standard Payload Interface • All other requirements are tradable Can trade performance for reducing cost (Untraditional approach for launch vehicles) 14 Summary • New EELV Acquisition Approach Provides – Two contractors for long term competition – Significant industry investment commensurate with the growing commercial market – Enhanced use of commercial launch services by the DOD – Reduction in Government’s total cost of launch through 2020 by at least 25% • EELV continues to lead the way in acquisition reform initiatives • Program is on track! 15 Affordability Through Innovation