Residence Hall Study University of Wisconsin-Stout Menomonie, Wisconsin

advertisement

Residence Hall Study

University of Wisconsin-Stout

Menomonie, Wisconsin

Date Prepared: Phase 1 - March 2009, Phase II – June 2009

DSF Project #: 08 J 2J | SDS Project #: 0829

Prepared by:

SDS Architects

205 N. Dewey Street

Eau Claire, W I 54703

Plumbing Consultant:

Southport Engineered Systems

205 N. Dewey Street

Eau Claire, W I 54703

HVAC and Electrical Consultant:

KJWW Engineering

802 W est Broadway, Suite 312

Madison, W I 53713

Table of Contents

Executive Summary

............................................................................

Tab 1

Study Parameters

...............................................................................

Tab 2

Phase I – Information Gathering

........................................................

Tab 3

Phase II – Planning Guide

..................................................................

Tab 4

Schedule Information

.........................................................................

Tab 5

Budget Information

.............................................................................

Tab 6

Appendix

............................................................................................

Tab 7

• Existing Statistics

• Existing Conditions Report

• Meeting Minutes

• Building Diagrams

• Budget Detail Information

Executive Summary

Project Name: Residence Hall Study

Location: University of Wisconsin - Stout

DSF#: 08 J 2J

Study Parameters - The purpose of this study was to develop a long range plan for the remodeling of the Campus’ residence halls. The study is to provide planning guidance relative to existing facility deficiencies, scope of potential remodeling projects, estimated project costs, and phasing considerations.

Programmatic Needs – The Campus has indicated that there is not a need to consider major programmatic changes in the long range plan. All of the residence halls addressed in this study currently have two students per room and this is not expected to change in the next 10 years.

Building Condition – Future major projects should include:

Addition of a Fire Protection System – Whether or not required by the current building codes, it is highly recommended that fire protection systems be considered and budgeted for all of the residence halls with any major remodeling project.

ADA Remodeling – Major components of this include toilet room remodeling, elevator additions, and accessible route modifications.

Complete Upgrade of the Plumbing, HVAC, Electrical, and

Telecommunication Systems – This is primarily due to the age of the systems, but also provides an opportunity for greater energy efficiency and indoor air quality.

Window Replacement – Windows are original to all of the buildings except

McCalmont Hall.

Asbestos Abatement – According to documentation on Campus, most of the residence halls have extensive areas of asbestos containing materials.

Much of this is 9”x9” floor tile. Although some areas may have been abated over time, the documentation indicates that much of this material is still in place under the carpeted areas.

Upgraded Finishes – Many areas have finishes that are currently due for replacement, most other areas will be due for replacement within the 10-12 year span of this long range plan. Also, major remodeling projects will likely disturb the existing finishes in many areas of the buildings. The

Campus asked that the remodeling scope and budgets include a complete upgrade for floor, wall, and ceiling finishes.

Door and Hardware replacement – Most of the existing exterior doors and hardware are in poor condition. The Campus expressed a desire to have all interior and exterior doors and hardware replaced with any major remodeling project.

SDS Architects | Page 3 of 25

October 2008

Hovlid Hall Precedent – At the time of this report the remodeling of the Hovlid

Residence Hall is currently underway on the UW -Stout Campus. Hovlid Hall is located on the North Campus and is very similar to Fleming and Wigen Halls in terms of size, layout, and construction. It was agreed during the study that the scope of the remodeling specified for the Hovlid Hall project could be used as a precedent for the scope of work identified for the residence halls addressed in this report. In general, the following scope of work is addressed in the Hovlid project:

• Replacement of all doors and hardware

• Replacement of all interior finishes

• Replacement of windows*

• Exterior masonry tuckpointing/caulking replacement

• Replacement of roof *

Remodeling and expansion of toilet/shower rooms

• Complete replacement of HVAC system

• Addition of fire protection system

• Complete replacement of plumbing system

• Complete replacement of electrical/telecommunication systems

• ADA remodeling, including the addition of an elevators*

*does not apply to scope for all residence halls

Planning Guide – Various options for project scheduling and sequence ordering were developed and evaluated based on overall cost, bed loss limitations, infrastructural implications, swing space availability, and funding limitations. These options were reviewed with Campus with the following outcome.

Final Phasing Order and Schedule Recommendation – The following recommendation was developed for the phasing order and overall schedule. This recommendation assumes the first two phases of construction will occur in 2011 and 2012. It also assumes that during the first two years of phasing, JTC will remain on-line for use as swing space. Following the first two phases, the schedule shifts to what is being called the Spring/Spring schedule option for the remainder of the projects. This schedule option isolates all construction activities and bed losses to the Spring Semesters, avoiding bed losses in the Fall Semesters.

SDS Architects | Page 4 of 25

March 2009

The recommended phasing sequence is as follows:

Project 1 Phase 1

Phase 2

Fleming

Wigen (first round, limited scope)

Project 2 Phase 1

Phase 2

CK

TO

Project 3 Phase 1

Phase 2

HK

MC

Project 4 Phase 1

Phase 2

South Hall Cubes A and B

South Hall Cube C

Project 5 Phase 1

Phase 2

AF

McCalmont

Project 6 Phase 1

Phase 2

North Hall Cube A

North Hall Cubes B and C

Project 7 Phase 1 Wigen (second round, full scope)

This recommendation indicates two rounds of remodeling for Wigen Hall.

This is driven primarily by funding limitations. The Campus does not anticipate having funds available to do the entire Fleming/Wigen remodeling during the 2011-2012 period. It is anticipated that the Campus may be able to fund approximately $2M worth of remodeling for the Wigen project during this period. It is estimated that this level of funding will allow remodeling of the toilet rooms, window replacement, connections to the

Hovlid generator, and other minor site utility modifications only. The remainder of the remodeling would be done at the very end of the cycle

(2023). It should be noted that the entire Wigen remodeling can occur in a single phase within either one of the Wigen time slots identified below if funding limits/opportunities dictate a need for such an adjustment.

SDS Architects | Page 5 of 25

March 2009

Budgets for Solutions - Budget Assumptions

The budgets were developed by first establishing a base cost to represent the scope of work identified in this study in today’s dollars (see Appendix for detail).

These costs were then inserted in to spreadsheets based on the ordering and schedule options being considered to provide an understanding of the effects of cost escalation. The illustration below allows a comparison of the Spring/Spring

Schedule Option (favored by Campus) with the Spring/Fall Schedule option. The ordering of the projects is based on the recommendations above. It should be noted that a third investigation was also developed that included a new 240 bed residence hall. The primary purpose of this investigation was to illustrate the potential escalation savings with a very aggressive long term schedule. Since this investigation was primarily academic, details have not been included in the executive summary

SDS Architects | Page 6 of 25

March 2009

Summary and Other Considerations

The key components of these recommendations in this study are:

• To minimize the loss of resident rooms, additions are preferred to remodeling for programmatic modifications (toilet/shower needs).

• All remodeling will include complete mechanical and electrical infrastructure replacement (comparable to Hovlid)

• The overall timeframe required to carry out the remodeling of all of the halls studied is 2010-2023

• The overall project cost for the recommended approach is approximately $100M

Although scheduling options are available to reduce escalation costs for the project as a whole, funding availability is a primary limiting factor and a key driver for the final recommendation.

As indicated in this study, most of the halls studied are over 40 years old with original building systems. With the recommended schedule, which stretches from

2010-2023, it is very likely that there will be additional operations and maintenance costs, as well as potential systems failures that should be anticipated by the

Campus.

Conversely, the elongated schedule does provide the Campus with time to evaluate trends in student housing and better determine what the long range demand for student housing will be. It is possible that midway through the cycle it is determined that there is a much greater, or much reduced demand for student housing. The recommended schedule allows the Campus time to alter the approach a few years out to accelerate the remodeling, opt to eliminate or replace a hall rather than remodel, make adjustments to housing contracts, etc., rather than potentially overinvesting in remodeling with the assumption that long term demand will continue to grow.

SDS Architects | Page 7 of 25

March 2009

Study Parameters

In November of 2008 SDS Architects was hired to conduct a study involving most of the UW-Stout residence halls. The purpose of this study was to develop a long range plan for the remodeling of the Campus’ residence halls. The study is to provide planning guidance relative to existing facility deficiencies, scope of potential remodeling projects, estimated project costs, and phasing considerations.

During a meeting intended to define the scope of the study it was decided to conduct in two phases. The purpose of this division was to provide a baseline understanding of the extent of the potential building issues prior to developing the scope of study services needed for Phase 2. Following is the general scope associated with each phase:

Phase 1 - Information Gathering

Review Previously Developed Materials

• Document Existing Conditions

• Identify Deficiencies

Phase 2 – Planning Guide

• Develop Solution Options for Deficiencies

• Develop Schedule and Phasing Options

• Develop Budgets for Solutions

Residence Halls included in the scope of this study are:

• AFM - Antrim/Froggat/McCalmont

• CKTO – Curran/Kranzusch/Tustison/Oetting

• HKMC – Hansen/Keith/Milnes/Chinnock

North Hall

• South Hall

• Wigen Hall

• Fleming Hall

SDS Architects | Page 8 of 25

March 2009

Phase I – Information Gathering

Overview SDS Architects involved KJWW Engineers and Southport Engineered

Systems as part of the Architectural/Engineering team during the study to provide analysis and recommendations for the mechanical and electrical systems for each of the residence halls. During Phase 1 the A/E team conducted a walk-though at each of the buildings and reviewed building documentation materials available on

Campus. Building Evaluations were developed during these activities and are included in the appendix of this document. A summary of the most significant deficiencies needing to be addressed in future projects is as follows:

Building Condition – Future major projects should include:

Addition of a Fire Protection System – Whether or not required by the current building codes, it is highly recommended that fire protection systems be considered and budgeted for all of the residence halls with any major remodeling project.

ADA Remodeling – Major components of this include toilet room remodeling, elevator additions (where not currently present), and accessible route modifications.

Complete Upgrade of the Plumbing, HVAC, and Electrical – This is primarily due to the age of the systems, but also provides an opportunity for greater energy efficiency and indoor air quality.

Window Replacement – Windows are original to all of the buildings except

McCalmont Hall.

Asbestos Abatement – According to documentation on Campus, most of the residence halls have extensive areas of asbestos containing materials.

Much of this is 9”x9” floor tile. Although some areas may have been abated over time, documentation indicates that much of this material is still in place under the carpeted areas.

Upgraded Finishes – Many areas have finishes that are currently due for replacement, most other areas will be due for replacement within the 10-12 year span of this long range plan. Also, major remodeling projects will likely disturb the existing finishes in many areas of the buildings. The

Campus asked that the remodeling scope and budgets include a complete upgrade for floor, wall, and ceiling finishes.

Door and Hardware Replacement – Most of the existing exterior doors and hardware are in poor condition. The Campus expressed a desire to have all interior and exterior doors and hardware replaced with any major remodeling project.

SDS Architects | Page 9 of 25

March 2009

Phase II Planning Guide

Overview - The purpose of the this Planning Guide is to provide the UW-Stout

Campus with a tool to assist long range planning for existing residence hall improvements. The guide provides an understanding of the individual and overall costs of the proposed improvements, options available for phasing of the projects, and sequencing implications related to the order in which the projects are undertaken.

Process – To establish a starting point for discussion, this phase began with the development of preliminary concept solutions, budgets, scheduling options, and a phasing order based primarily on the engineering team recommendations, without consideration of specific Campus needs. These preliminary concept materials were then shared with the Campus during an afternoon workshop in April 2009. During the workshop the Campus provided feedback on the concepts, specific limits on schedule options, and other budget driven limitations. This Campus feedback allowed the finalization of the recommendation illustrated in this document.

Hovlid Hall Precedent – At the time of this report the remodeling of the Hovlid

Residence Hall is currently underway on the UW -Stout Campus. Hovlid Hall is located on the North Campus and is very similar to Fleming and Wigen Halls in terms of size, layout, and construction. It was agreed during the study that the scope of the remodeling specified for the Hovlid Hall project could be used as a precedent for the scope of work identified for the residence halls addressed in this report. In general, the following scope of work is addressed in the Hovlid project:

• Replacement of all doors and hardware

• Replacement of all interior finishes

• Replacement of windows*

Exterior masonry tuckpointing/caulking replacement

• Replacement of roof *

• Remodeling and expansion of toilet/shower rooms

• Complete replacement of HVAC system

• Addition of fire protection system

• Complete replacement of plumbing system

Complete replacement of electrical/telecommunication systems

• ADA remodeling, including the addition of an elevators*

*does not apply to scope for all residence halls

Solution Options for Deficiencies

Primary Building Configuration Terms - For ease of communication the following terms will be used to identify and describe the three primary types of residence hall building configurations found on Campus.

SDS Architects | Page 10 of 25

March 2009

Cube – This term applies to residence halls that are configured with multiple cube-like wings linked by corridor/lounge spaces. Each floor of the

“cubes” is made up perimeter resident rooms surrounding a center toilet room/stairwell core. Residence halls of this type include HKMC, CKTO and AF.

Linear – This term applies to residence halls that are configured in a linear fashion with a single double loaded corridor on each floor lined with resident rooms on each side. Residence halls of this type include Wigen,

Fleming, and McCalmont.

North/South – This term applies to North and South Hall .

Programmatic Modifications – During Phase 1 meetings, the Campus indicated that there is not a need to consider major programmatic changes in the long range plan. All of the residence halls addressed in this study currently have two students per room and this is not expected to change in the next 10 years.

Similar to the Hovlid Hall precedent, the areas requiring programmatic modifications include the Toilet/Shower areas and Floor Lounges. The goal is to improve the quality and sizes of the areas to better meet the expectations of the residents. The improvements are to provide visually and functionally modernized facilities with greater levels of privacy and accessibility for the disabled.

Two primary approaches were used to develop options to satisfy the Toilet

Room/Lounge Remodeling. One approach (labeled Option A in the examples below) attempted to work within the current building footprint, remodeling existing areas to meet the programmatic needs without any additions. The second approach (labeled Option B in the examples below) provided additions to accommodate some or all of the proposed programmatic modifications.

CKTO Option A Example

Remodel Only

CKTO Option B Example

Addition & Remodel

SDS Architects | Page 11 of 25

March 2009

Programmatic Modifications Findings and Recommendation – The Options described above were developed in concept form for each of the Residence Halls and shared with the Campus in April 2009. With these options it was noted that

Option A, although likely less expensive initially, was compromised due to the following issues, several of which were lessons learned during the design for the

Hovlid Hall remodeling:

Loss of Beds – Existing resident rooms would need to be sacrificed to gain the amount of space needed for the toilet room and shower facilities.

Because Option B provides new space for these functions, resident rooms are not sacrificed.

Structural Limitations – The existing cast-in-place floor slab structural system does not lend itself to the many new floor penetrations necessary for the relocated plumbing. In some instances, the location of existing structural reinforcing dictates the locations of penetrations for relocated piping and floor drains. This issue, coupled with the very low floor to ceiling space available, causes problems with exposed piping traps from floors above creating headroom clearance and exposed piping appearance issues. Because Option B allows the structural system to be designed around the proposed layout, these issues are minimized.

Compromised Layouts –Option A relies on the insertion of new programmatic functions into existing, and established structures. Because of this, there are inherent limitations in layout options and compromises in the layouts. Because Option B provides new space for these functions, a more optimal layout can be achieved.

Option B Cube Concept Overview – Additions are placed at the corner of each cube to house the Toilet/Shower Rooms (shown green). In some cases, new stairwells should be considered to improve the existing exiting conditions (as indicated in diagram below). The remodeled backfill areas (shown blue), vacated by the toilet/shower area relocation are able to be converted to commons, lounge, and kitchen type spaces. This concept applies to CKTO, HKMC and AF.

CKTO Option B Example CKTO Option B Example, Enlarged

SDS Architects | Page 12 of 25

March 2009

Option B Linear Concept Overview – An addition is placed at the center of the building to allow the expansion of the Toilet/Shower Rooms (shown green). The existing toilet room areas and lounge areas are indicated for remodeling to accommodate the reconfigured toilet/shower areas (shown blue). This concept applies to Fleming and Wigen.

Fleming Option B Example Fleming Option B Example, Enlarged

Option B North/South Concept Overview – Similar to the Cube Concept, additions are placed at the corner of each wing to house the Toilet/Shower Rooms

(shown green). The remodeled backfill areas (shown blue), vacated by the toilet/shower area relocation are able to be converted to commons, lounge, and kitchen type spaces. This concept applies to North and South Halls.

North Option B Example North Option B Example, Enlarged

SDS Architects | Page 13 of 25

March 2009

Infrastructure Improvements The recommendations for infrastructure improvements stem from the findings of Phase 1. Generally, all of the mechanical, electrical infrastructure components in all of the buildings are identified as in need of replacement. The extent of systems replacement or addition in all of the residence halls include:

Plumbing : Replacement of all plumbing piping and fixtures. Removal and replacement of basement floor slab to accommodate piping replacement.

Heating Ventilation : Replacement of all heating and ventilation system components.

Air Conditioning : Included for office spaces only. Air conditioning for other areas was studied and deemed unpractical due to factors of cost, space loss, and other building envelope conditions.

Fire Protection : Addition of a complete fire protection system.

Electrical : Replacement of all power, lighting, and distribution components.

Fire Alarm : Replacement of entire fire alarm system.

Security: Addition of security system.

Emergency Generator : Replacement of existing generators and addition of generators where currently not present

Technology: Per input from the Campus, new infrastructure will be provided to all remodeled residence halls to support the current and future growth of the campus. The infrastructure will consist of single mode and multi-mode fiber optic cabling to support 10G applications and coaxial cable to support current cable television needs. Within each residence hall a universal cabling system will be installed which will consist Category 6A cabling to support future voice over IP and 10G applications.

Other Improvements The recommendations for other improvements stem from the findings of Phase 1 and from the precedent set by the Hovlid Hall project. The extent of other improvements include:

Doors and Hardware: Replacement of all interior and exterior doors and hardware. Existing interior frames to be refinished.

Finishes : Replacement of all finishes including carpet, hard flooring, painting, and ceilings.

Resident Rooms: Replacement of closets and construction of soffits to house new mechanical/electrical/fire protection systems. Removal of existing desks/shelving (replaced with movable furnishings).

Window Replacement: Replacement of all exterior windows (does not apply to McCalmont, windows recently replaced).

Asbestos Abatement: Removal of all asbestos containing materials.

Elevators: Add elevators where elevators are not currently in place to provide accessibility to all floors.

SDS Architects | Page 14 of 25

March 2009

Roof Replacement: Roofing replacement is included in the scope for roofs that are nearing the end of their warranty period at the projected time of remodeling.

Schedule and Phasing Options

Campus Phasing Requirements – The Campus required that the phasing plan limit the loss of resident beds to approximately 240 at one time. Furthermore, whenever possible, the loss of beds should be during the spring semester (January through May) since there is a much higher demand for beds the fall semester compared to the spring semester.

Phasing Units – The 240 bed loss limit set by the Campus is roughly equivalent to the bed capacity of half of HKMC or CKTO type “cube” complexes. Wigen and

Fleming halls each fit within the 240 bed limit individually.

Summary of Phases – Based on the phasing unit requirements, the following twelve phase components were identified (not in phasing order).

McCalmont – 202 beds (potential capacity, typical)

AF (Antrim/Froggat) – 250 beds

CK (Curran/Kranzusch) – 244 beds

TO (Tustison/Oetting) – 248 beds

HK (Hansen/Keith) – 244 beds

MC (Milnes/Chinnock) – 254 beds

North Cube A – 118 beds

North Cubes B and C – 256 beds

South Cube A – 120 beds

South Cubes B and C – 246 beds

Wigen – 238 beds

Fleming – 202 beds

Scheduling Options – Three schedule options were developed for consideration by the Campus. The options were developed to illustrate possible short term phasing cycles for single “projects”, each consisting of two phases. A “project” is defined as one complex, such as HKMC. The exceptions to this are Wigen and

Fleming which are two separate buildings, but considered together as one project due to their size and similarity. Long term schedules are also provided to illustrate the implications of these cycles when repeated to complete all of the twelve phases.

SDS Architects | Page 15 of 25

March 2009

Spring/Fall Option – This option starts each construction cycle with Phase

1 in January and Phase 2 in May. Completion of Phase 2 is in December of the same year.

Benefits: o Shortest disruption period per cycle (13 months) o Shortest overall project time span (6 years of construction) o Lowest escalation cost due to condensed time frame o Lowest cost for temporary infrastructure with Mechanical/Electrical equipment change-over in summer between phases. o No issues with lead time for equipment.

Shortcomings: o Campus looses beds in Fall Semester o Funding may not allow accelerated schedule

SDS Architects | Page 16 of 25

March 2009

Fall/Spring Option – This option starts each construction cycle with Phase

1 in May and Phase 2 in January of the following year and extending through August, eight months later.

Benefits: o Disruption period is 16 months per cycle. o Short overall project time span (7 years of construction) o Cycles can overlap in summer months (ie: year two starts while year one finishes)

Shortcomings: o Campus looses beds in Fall Semester o Funding may not allow accelerated schedule o Design and bidding must consider added lead time for source equipment.

SDS Architects | Page 17 of 25

March 2009

Spring/Spring Option – This option starts all phases in January with completion in August of the same year.

Benefits: o Beds are only lost in Spring Semester (January – May). o May be best fit for funding availability.

Shortcomings: o Highest escalation cost due to extended time frame o Added cost for temporary infrastructure with Mechanical/Electrical equipment change-over at end of cycle.

SDS Architects | Page 18 of 25

March 2009

Campus Preference – During a review of the schedule options above, the Campus indicated that Spring/Spring Option is the only one that will work for them. Since the beginning of the fall semester is the time of highest demand for beds, the two options that include construction during this semester are not possible without additional swing space to accommodate the bed demand in the fall.

Building Divisions – All of the “cube” and “North/South” configured complexes will require phasing to stay within the 240 bed loss limit. Using the preferred

Spring/Spring schedule model above, it was determined that it is best to first remodel the portion of the building that does not house the mechanical and electrical source equipment (electrical service and main mechanical/steam entry).

This is recommended because it allows time for procurement of the long lead source equipment such as transformers, heat exchangers etc. This source equipment would then be installed in phase 2, at the very end of the project.

Temporary service provisions needed until end of Phase 2

Building Division Phasing Diagram

SDS Architects | Page 19 of 25

March 2009

Phasing Order

Overall Condition - If ordered strictly by age, the buildings would be ordered as follows:

Fleming , 1961

McCalmont , 1962

AF , 1966

CKTO 1966 (Oetting 1968)

HKMC , 1966 (Chinnock 1969)

North , 1967

South , 1967

Wigen , 1970

However, other than Wigen Hall, all of the buildings are over 40 years old and have very similar systems deficiencies. Therefore, other factors related to generators, technology, swing space availability, and funding limitations provide direction to the ordering of the phases.

Generators - Emergency loads at AF, CKTO, and HKMC’s are currently served by a single generator located in CKTO. The Campus wishes to maintain this configuration so the first building of those three that should be renovated is CKTO. Additional work will be required to temporarily reconnect AF and HKMC to that new generator, with final connections being done as part of those building’s renovations. North Hall and South

Hall each have their own generator. These generators are currently being installed. Conduit is being provided to Fleming and Wigen as part of the emergency generator work currently underway at the Hovlid Hall project.

Transfer switches and wiring will be required as part of the remodeling for these two halls.

Technology The current south campus technology node that supports the residence halls is located at North Hall. A new node will be set up in HKMC allowing the North Hall node to be phased out as each residence hall is remodeled. For this reason, North Hall should be the last to be remodeled on the south Campus.

Swing Space Availability – Although the Campus can sacrifice up to 240 beds during second semester, options for gaining additional swing space were discussed as possibilities. Although funding availability will not likely allow an accelerated schedule, the purpose of the discussion was to identify ways for acceleration should the need or ability arise to do so. The following swing space scenarios were identified.

McCalmont – Roughly 20% of this hall is currently being used for non-resident room functions. If all of the rooms could be converted back to resident rooms it would provide additional swing space beds. The feasibility of this option is unknown by Campus at this time since it relies heavily on several other campus projects to accommodate those that would be moved from McCalmont.

SDS Architects | Page 20 of 25

March 2009

JTC – Located on the North Campus, JTC is currently used for student housing, but is scheduled to be taken off-line when the

Hovlid Hall Renovation and Addition project is completed. Swing space beds could be provided by this facility if it were able to be kept in service longer. It was noted that this will not be likely for the long term, but may be a possibility for a year or two. If this option is considered, additional investigations are recommended for the North Campus steam capacity. Based on the findings from other recent project on the North Campus, the steam available may not be adequate for the expected loads. It is certain that the existing JTC foodservice functions will need to be taken off-line when the new Hovlid foodservice is completed. Although the JTC complex is not included in the scope of this study, it is known by

Campus that there are issues with the overall condition of the facility that also need to be considered.

New Residence Hall – If a new residence hall were to be constructed, this may provide enough swing space to allow an entire building such as HKMC, to be taken off-line for remodeling at one time. This would allow the overall schedule to be shortened, resulting in escalation cost savings. Furthermore, at the end of the phasing cycle, the campus has the option of demolishing one of the residence halls while maintaining the current bed count, should demand remain constant. Based on feedback from Campus it is understood that this option is not likely available due to funding constraints.

Additions to North and South Halls – North and South Halls were originally designed with only 3 wings (as opposed to 4 like HKMC,

CKTO). New wings could be added to these halls to accomplish a result similar to the one outlined above under “New Residence

Hall”. The same funding limitations also apply.

Funding Limits – According to Campus, the immediate outlook for funding in the near future falls short of the needs identified. Since Fleming is one of the smaller complexes, starting with this building will allow time for a

“ramping up” of the necessary funding for the remainder of the project.

This also happens to be the oldest as well which is added justification for starting with Fleming.

Final Phasing Order and Schedule Recommendation – Based on the factors above, the following recommendation was developed for the phasing order and overall schedule. This recommendation assumes that during the first two years of phasing, JTC North Campus connection will remain on-line for use as swing space. This added swing space allows the use of the Fall/Spring Schedule (illustrated earlier in this study) for the first project cycle in 2011-2012. Following the first two phases, the schedule

SDS Architects | Page 21 of 25

March 2009

shifts to the Spring/Spring option for the remainder of the projects. See following Schedule Illustrations.

The recommended phasing sequence is as follows:

Project 1 Phase 1

Phase 2

Fleming

Wigen (first round, limited scope)

Project 2

Project 3

Project 4

Phase 1

Phase 2

Phase 1

Phase 2

Phase 1

Phase 2

CK

TO

HK

MC

South Hall Cubes A and B

South Hall Cube C

Project 5

Project 6

Phase 1

Phase 2

Phase 1

Phase 2

AF

McCalmont

North Hall Cube A

North Hall Cubes B and C

Project 7 Phase 1 Wigen (second round, full scope)

SDS Architects | Page 22 of 25

March 2009

This recommendation indicates two rounds of remodeling for Wigen Hall.

This is driven primarily by funding limitations. The Campus does not anticipate having funds available to do the entire Fleming/Wigen remodeling during the 2011-2012 period. It is anticipated that the Campus may be able to fund approximately $2M worth of remodeling for the Wigen project during this period. It is estimated that this level of funding will allow remodeling of the toilet rooms, window replacement, connections to the

Hovlid generator, and other minor site utility modifications only. The remainder of the remodeling would be done at the very end of the cycle

(2023). It should be noted that the entire Wigen remodeling can occur in a single phase within either one of the Wigen time slots identified below if funding limits/opportunities dictate a need for such an adjustment.

Budgets for Solutions - Budget Assumptions

The budgets were developed by first establishing a base cost to represent the scope of work identified in this study in today’s dollars (see Appendix for detail). These costs were then inserted into spreadsheets based on the ordering and schedule options being considered to provide an understanding of the effects of cost escalation. The illustration below allows a comparison of the Spring/Spring Schedule Option (favored by

Campus) with the Spring/Fall Schedule Option. The ordering of the projects is based on the recommendations above. Detailed budget information can be found in the Appendix.

Although the option of a new residence hall is not a likely alternative due to funding limitations, a third budget summary and schedule graphic have been provided to illustrate the effects of this approach on overall schedule and escalation costs. This budget summary assumes that a new residence hall is constructed at the beginning of the cycle to allow the subsequent phases to be larger in scope (240 beds in fall and 480 beds in spring), thus reducing the long term cycle period. This illustration should be considered the "most aggressive" approach, designed to reduce escalation costs. It should also be noted that this illustration includes remodeling for all of the existing residence halls covered by this study even though the campus may opt to replace one of the halls, via demolition (likely 240 bed hall, Fleming or Wigen) instead of remodeling. The related demolition costs would also need to be factored into the budget if the replacement option was considered.

SDS Architects | Page 23 of 25

March 2009

Summary and Other Considerations

The key components of these recommendations in this study are:

• To minimize the loss of resident rooms, additions are preferred to remodeling for programmatic modifications (toilet/shower needs).

• All remodeling will include complete mechanical and electrical infrastructure replacement (comparable to Hovlid)

• The overall timeframe required to carry out the remodeling of all of the halls studied is 2010-2023

• The overall project cost for the recommended approach is approximately $100M

Although scheduling options are available to reduce escalation costs for the project as a whole, funding availability is a primary limiting factor and a key driver for the final recommendation.

As indicated in this study, most of the halls studied are over 40 years old with original building systems. With the recommended schedule, which stretches from

2010-2023, it is very likely that there will be additional operations and maintenance costs, as well as potential systems failures that should be anticipated by the

Campus.

Conversely, the elongated schedule does provide the Campus with time to evaluate trends in student housing and better determine what the long range demand for student housing will be. It is possible that midway through the cycle it is determined that there is a much greater, or much reduced demand for student housing. The recommended schedule allows the Campus time to alter the approach a few years out to accelerate the remodeling, opt to eliminate or replace a hall rather than remodel, make adjustments to housing contracts, etc., rather than potentially overinvesting in remodeling with the assumption that long term demand will continue to grow.

SDS Architects | Page 24 of 25

March 2009

Energy Savings Considerations

The proposed remodeling will result in a reduction in energy use for all of the buildings. The estimated annual savings for each building after remodeling (in today's dollars) is:

Fleming

Wigen

$10,000

$11,500

Curran/Kranzusch $12,000

Tustison/Oetting $12,000

Hansen/Keith

Milnes/Chinnok

South A and B

South C

$12,000

$12,500

$11,500

$6,000

Antrim/Frogatt

McCalmont

$12,000

$9,500

North A $5,500

North B and C $12,500

Applying these savings to the schedule options illustrated above results in the following total energy savings by the year 2023:

Recommended Spring/Spring Schedule: $790,000 energy savings.

Alternative Fall/Spring Schedule: $1,128,000 energy savings.

SDS Architects | Page 25 of 25

March 2009

Preliminary Project Budget - Additions Option - Today's Cost

Building Wide Items

Additions

Major Remodeling

Resident Room Remodeling

Corridor Remodeling

Lower Level Floor Removal

Plumbing

Fire Protection

HVAC no AC

Electrical

Technology

Fire Alarm

Security

Msc. Demolition

Window Replacement

Roof Replacement

Elevator (including bldg. cost)

Masonry Repair/Tuckpoint/Caulk

Generator

Site Utilities

Other Site Improvements

Construction Cost Subtotal

General Requirements

Design Contingency

Total Construction Cost

Cost/sf

Other Costs

Contingency

Architectural/Engineering Fees

DSF Fees

Hazardous Materials Removal

Equip./%for Arts/Other Costs

Subtotal

ESTIMATED TOTALS

ESTIMATED TOTAL/BUILDING sf ls allow ea ls ls gsf gsf gsf gsf gsf gsf ea sf sf ea lf sf gsf gsf percent percent

Building Name

Building Area

Footprint Area

Resident Rooms

Resident Beds

Units Unit/Cost

Antrim/Frogatt

66,484

12,674

125

250

AFM

Qty Total

McCalmont

40,899

9,715

101

202

Qty Total

CKTO

Curran/Kranzusch Tustison/Oetting

64,469

10,917

122

244

61,532

10,449

124

248

Qty Total Qty Total

Hansen/Keith

61,593

10,633

122

244

HKMC

Milnes/Chinnok

61,598

10,661

127

254

Qty Total Qty Total Qty

Cube A

27,273

4,560

59

118

Total Qty

North Hall

Cube B

33,524

5,723

67

134

Total Qty

Cube C

30,245

5,050

61

122

Total Qty

Cube A

27,280

4,560

60

120

Total Qty

South Hall

Cube B

33,487

5,711

59

118

Total Qty

Cube C

30,300

5,063

64

128

Total

$160 7,780 $1,244,800

$100

$3,390

$30

$10

3,517

125

1,628

5,550

$5 66,484

$3 66,484

$351,700

$423,750

$48,840

$55,500

2,820

6,177

101

1,052

4,860

$332,420 40,899

$199,452 40,899

$14.00

66,484

$10.50

66,484

$5.00

66,484

$3.00

66,484

$1 66,484

$0.50

66,484

$1,500 125

$8

$200,000

$60,000

1

1

0

1

1

1

10.00%

3.00%

$930,776

$698,082

$332,420

$199,452

$66,484

$33,242

$187,500

$0

$200,000

$20,000

$60,000

$60,000

$15,000

40,899

40,899

40,899

40,899

40,899

40,899

0

$5,459,418

$545,942 10.00%

$180,161

$6,185,521

1

1

0

0

1

1

$451,200 8,130 $1,300,800

$617,700

$342,390

$31,560

$48,600

2,764

122

1,696

5,500

$204,495 64,469

$122,697 64,469

$276,400

$413,580

$50,880

$55,000

7,725

2,693

124

1,650

5,110

$322,345 61,532

$193,407 61,532

$1,236,000

$269,300

$420,360

$49,500

$51,100

8,130

3,457

122

1,596

5,300

$307,660 61,593

$184,596 61,593

$1,300,800

$345,700

$413,580

$47,880

$53,000

7,725

3,160

127

1,600

5,260

$307,965 61,598

$184,779 61,598

$1,236,000

$316,000

$430,530

$48,000

$52,600

4,085

1,773

59

720

2,237

$307,990 27,273

$184,794 27,273

$572,586 64,469

$429,440 64,469

$204,495 64,469

$122,697 64,469

$40,899 64,469

$20,450 64,469

$0 122

$0

$0

$20,000

$60,000

$29,500

$0

$3,318,708

$331,871 10.00%

$0

$3,650,579

3.00%

1

1

0

0

1

1

$902,566 61,532

$676,925 61,532

$322,345 61,532

$193,407 61,532

$64,469 61,532

$32,235 61,532

$183,000

$0

$0

$20,000

$60,000

$92,000

$15,000

$5,174,358

$517,436 10.00%

$170,754

$5,862,548

124

1

0

0

0

1

1

3.00%

$861,448

$646,086

$307,660

$184,596

$61,532

$30,766

$186,000

61,593

61,593

61,593

61,593

61,593

61,593

122

$0 10,633

$0 1

$20,000

$0

$0

$0

$4,816,604

1

1

1

1

$481,660 10.00%

$158,948

$5,457,212

3.00%

$862,302

$646,727

$307,965

$184,779

$61,593

$30,797

$183,000

$85,064 10,661

$200,000 1

$20,000

$60,000

$125,000

$15,000

$5,435,930

$543,593 10.00%

$179,386

$6,158,909

61,598

61,598

61,598

61,598

61,598

61,598

127

1

0

1

1

3.00%

$862,372 27,273

$646,779 27,273

$307,990 27,273

$184,794 27,273

$61,598 27,273

$30,799 27,273

$190,500 59

$85,288

$200,000

$20,000

$0

$0

$0

4,560

0

1

0.50

$5,166,034

$516,603 10.00%

$170,479

$5,853,117

3.00%

1

1

$653,600 4,085

$177,300

$200,010

$21,600

$22,370

1,847

67

936

2,823

$136,365 33,524

$81,819 33,524

$381,822 33,524

$286,367 33,524

$136,365 33,524

$81,819 33,524

$27,273 33,524

$13,637 33,524

$88,500 67

$36,480

$0

$15,000

$30,000

$58,000

$15,000

5,723

0

$2,463,326

$246,333 10.00%

$81,290

$2,790,948

3.00%

1

1

1

1

$653,600 4,085

$184,700

$227,130

$28,080

$28,230

1,779

61

824

2,470

$167,620 30,245

$100,572 30,245

$469,336 30,245

$352,002 30,245

$167,620 30,245

$100,572 30,245

$33,524 30,245

$16,762 30,245

$100,500 61

$45,784

$0

$15,000

$60,000

$0

$0

5,050

0

$2,751,032

$275,103 10.00%

$90,784 3.00%

$3,116,919

1

1

1

1

$653,600 4,085

$177,900

$206,790

$24,720

$24,700

1,558

60

720

2,240

$151,225 27,280

$90,735 27,280

$423,430 27,280

$317,573 27,280

$151,225 27,280

$90,735 27,280

$30,245 27,280

$15,123 27,280

$91,500 60

$40,400

$0

$15,000

$60,000

$0

$0

4,560

1

1

0.50

$2,564,900

$256,490 10.00%

$84,642 3.00%

$2,906,032

1

1

$653,600 4,085

$155,800

$203,400

$21,600

$22,400

1,636

59

936

2,809

$136,400 33,487

$81,840 33,487

$381,920 33,487

$286,440 33,487

$136,400 33,487

$81,840 33,487

$27,280 33,487

$13,640 33,487

$90,000 59

$36,480

$200,000

$15,000

$30,000

$101,000

$15,000

5,711

0

$2,690,040

$269,004 10.00%

$88,771

$3,047,815

3.00%

1

1

1

0

$653,600 4,085

$163,600

$200,010

$28,080

$28,090

1,548

64

824

2,470

$167,435 30,300

$100,461 30,300

$468,818 30,300

$351,614 30,300

$167,435 30,300

$100,461 30,300

$33,487 30,300

$16,744 30,300

$88,500 64

$45,688

$0

$15,000

$0

$0

$0

5,063

0

$2,629,022

$262,902 10.00%

$86,758

$2,978,682

3.00%

1

1

1

0

$653,600

$154,800

$216,960

$24,720

$24,700

$151,500

$90,900

$424,200

$318,150

$151,500

$90,900

$30,300

$15,150

$96,000

$40,504

$0

$15,000

$0

$0

$0

$2,498,884

$249,888

$82,463

$2,831,236

$93 $89 $91 $89 $100 $95 $102 $93 $96 $112 $89 $93 percent percent percent

75%gsf percent

10.00%

8.00%

4.00%

$3 49,863

5.00%

$618,552 10.00%

$494,842 8.00%

$272,163 4.00%

$149,589 30,674

$309,276 5.00%

$1,844,422

$365,058 10.00%

$292,046 8.00%

$160,625 4.00%

$92,023 48,352

$182,529

$1,092,281

5.00%

$586,255 10.00%

$469,004 8.00%

$257,952 4.00%

$145,055 46,149

$293,127

$1,751,393

5.00%

$545,721 10.00%

$436,577 8.00%

$240,117 4.00%

$138,447 46,195

$272,861 5.00%

$1,633,723

$615,891 10.00%

$492,713 8.00%

$270,992 4.00%

$138,584 46,199

$307,945 5.00%

$1,826,125

$585,312 10.00%

$468,249 8.00%

$257,537 4.00%

$138,596 20,455

$292,656

$1,742,349

5.00%

$8,030,000

$12,780,000

$4,750,000 $7,620,000

$14,720,000

$7,100,000 $7,990,000

$15,590,000

$7,600,000

$279,095 10.00%

$223,276 8.00%

$122,802 4.00%

$61,364 25,143

$139,547

$826,084

5.00%

$3,620,000

$311,692 10.00%

$249,354

$137,144

$75,429

$155,846

$929,465

$4,050,000

$11,450,000

8.00%

4.00%

22,684

5.00%

$290,603 10.00%

$232,483

$127,865

$68,051

$145,302

$864,304

$3,780,000

8.00%

4.00%

20,460

5.00%

$304,782 10.00%

$243,825

$134,104

$61,380

$152,391

$896,481

$3,950,000

8.00%

4.00%

25,115

5.00%

$297,868 10.00%

$238,295

$131,062

$75,346

$148,934

$891,505

$3,880,000

$11,510,000

8.00%

4.00%

22,725

5.00%

$283,124

$226,499

$124,574

$68,175

$141,562

$843,934

$3,680,000

Fleming Hall

49,166

8,363

101

202

Qty Total

North Campus

Wigen Hall1st Round

52,900

8,800

119

238

Wigen Hall2nd Round

52,900

8,800

119

238

Qty Total Qty Total

3,760

4,440

101

702

4,200

49,166

49,166

49,166

49,166

49,166

49,166

49,166

49,166

101

1

0.50

0

1

1

1

10.00%

3.00%

$601,600 2,135

$444,000

$342,390

$21,060

$42,000

5,125

0

0

2,000

$245,830 26,450

$147,498 0

$688,324

$516,243

$245,830

$147,498

$49,166

$24,583

$151,500

$0

$200,000

$50,000

$30,000

$20,000

$15,000

$3,982,522

$398,252 10.00%

$131,423 3.00%

$4,512,197

0

0

119

0

0

0

0

0

0.50

0

0

1

1

$341,600 0

$512,500

$0

$0

$20,000

0

119

892

2,450

$132,250 26,450

$0 52,900

$0 52,900

$0 52,900

$0 52,900

$0 52,900

$0 52,900

$0 52,900

$178,500 0

$0

$0

$0

$30,000

$22,000

$15,000

8,800

1

1

0.00

$1,251,850

$125,185 10.00%

$41,311

$1,418,346

3.00%

0

0

$0

$0

$403,410

$26,760

$24,500

$132,250

$158,700

$740,600

$555,450

$264,500

$158,700

$52,900

$26,450

$0

$70,400

$200,000

$20,000

$0

$0

$0

$2,834,620

$283,462

$93,542

$3,211,624

$92 $27 $61

10.00%

8.00%

4.00%

36,875

5.00%

$451,220 10.00%

$360,976 8.00%

$198,537 4.00%

$110,624 39,675

$225,610 5.00%

$1,346,966

$5,860,000

$5,860,000

$141,835 10.00%

$113,468 8.00%

$62,407 4.00%

$119,025 39,675

$70,917

$507,652

5.00%

$1,930,000

$6,150,000

$321,162

$256,930

$141,311

$119,025

$160,581

$999,010

$4,220,000

Preliminary Project Budget - Additions Option - Campus Preferred Order- Spring/Spring Schedule after first Phase

University of Wisconsin - Stout

Menomonie, Wisconsin

Date: June 4, 2009

Construction Cost Subtotal

General Requirements

Design Contingency

Phasing Cost Factor

Escalation Year Multiplier

Escalation Factor

Total Construction Cost

Cost/sf

Other Costs

Contingency

Architectural/Engineering Fees

DSF Fees

Hazardous Materials Removal

Equip./%for Arts/Other Costs

Subtotal

ESTIMATED TOTALS

ESTIMATED TOTAL/BUILDING

Building Name

Building Area

Footprint Area

Resident Rooms

Resident Beds

Units percent percent ls percent

Unit/Cost

3.50%

Qty Total Qty Total Qty

10.00%

3.00%

$5,459,418

$545,942 10.00%

$180,161

$2,000

11.00

10.00

3.50% $2,164,932

$8,352,453

3.50%

$3,318,708

$331,871 10.00%

$0

$1,500

$1,405,473

$5,057,552

3.00%

4.00

3.50%

Total

$820,757

$6,775,304

Qty

$5,174,358

$517,436 10.00%

$170,754

$92,000

3.00%

5.00

3.50%

Total Qty

$4,816,604

$481,660 10.00%

$158,948 3.00%

$31,000

6.00

Total

$5,435,930

$179,386

$82,000

$955,012 3.50% $1,293,371

$6,443,224 $7,534,280

Qty

$543,593 10.00%

3.00%

7.00

3.50%

Total

$5,166,034

Qty

$516,603 10.00%

$170,479

$31,000

$1,434,014

$7,318,130

3.00%

12.00

3.50%

Total

$2,463,326

$246,333 10.00%

$81,290

$73,000

$1,172,198

$4,036,147

Qty

3.00%

13.00

3.50%

Total

$2,751,032

Qty

$275,103 10.00%

$90,784

$1,500

$1,418,198

$4,536,618

3.00%

13.00

3.50%

Total

$2,564,900

$84,642

$1,500

$1,322,244

$4,229,776

Qty

$256,490 10.00%

3.00%

8.00

3.50%

Total Qty

$2,690,040

$269,004 10.00%

$88,771

$92,000

3.00%

8.00

$853,388 3.50%

$3,993,204

Total

$2,629,022

$262,902 10.00%

$86,758

$834,031

$3,812,713

Qty

3.00%

9.00

3.50%

Total

$2,498,884

$249,888

$82,463

$891,839

$3,723,075 percent percent percent

75%gsf percent

Year

10 11

AFM

Antrim/Frogatt

66,484

12,674

125

250

$126

McCalmont

40,899

9,715

101

202

$124

4

$105

5

Curran/Kranzusch

64,469

CKTO

Tustison/Oetting

61,532

10,917 10,449

122

244

124

248

$105

6

Hansen/Keith

61,593

10,633

122

244

7

HKMC

Milnes/Chinnok

61,598

10,661

127

254

$122 $119

12

Cube A

27,273

4,560

59

118

$148

13

North Hall

Cube B

33,524

5,723

67

134

$135

13

Cube C

30,245

5,050

61

122

$140

8

Cube A

27,280

4,560

60

120

$146

8

South Hall

Cube B

33,487

5,711

59

118

$114

9

Cube C

30,300

5,063

64

128

$123

10.00%

8.00%

4.00%

$3 49,863

5.00%

$835,245 10.00%

$668,196 8.00%

$367,508 4.00%

$149,589 30,674

$417,623 5.00%

$2,438,161

$505,755 10.00%

$404,604

$222,532

$92,023 48,352

$252,878 5.00%

$1,477,792

8.00%

4.00%

$677,530 10.00%

$542,024

$298,113

$145,055 46,149

$338,765 5.00%

$2,001,489

8.00%

4.00%

$644,322 10.00%

$515,458 8.00%

$283,502 4.00%

$138,447 46,195

$322,161 5.00%

$1,903,891

$753,428 10.00%

$602,742 8.00%

$331,508 4.00%

$138,584 46,199

$376,714 5.00%

$2,202,977

$731,813 10.00%

$585,450

$321,998

$138,596 20,455

$365,907 5.00%

$2,143,763

8.00%

4.00%

$403,615 10.00%

$322,892

$177,590

$61,364 25,143

$201,807 5.00%

$1,167,268

8.00%

4.00%

$453,662 10.00%

$362,929 8.00%

$199,611 4.00%

$75,429 22,684

$226,831 5.00%

$1,318,462

$422,978 10.00%

$338,382 8.00%

$186,110 4.00%

$68,051 20,460

$211,489 5.00%

$1,227,010

$399,320 10.00%

$319,456 8.00%

$175,701 4.00%

$61,380 25,115

$199,660 5.00%

$1,155,518

$381,271 10.00%

$305,017

$167,759

$75,346 22,725

$190,636 5.00%

$1,120,029

8.00%

4.00%

$372,307

$297,846

$163,815

$68,175

$186,154

$1,088,297

$10,800,000

$17,340,000

$6,540,000 $8,780,000

$17,130,000

$8,350,000 $9,740,000

$19,210,000

$9,470,000 $5,210,000 $5,860,000

$16,530,000

$5,460,000 $5,150,000 $4,940,000

$14,910,000

$4,820,000

2.5

Fleming Hall

49,166

8,363

101

202

3 14

North Campus

Wigen Hall-

1st Round

Wigen Hall-

2nd Round

52,900

8,800

52,900

8,800

119

238

119

238

Qty

10.00%

3.00%

Total Qty

$3,982,522

$398,252 10.00%

$131,423 3.00%

Total Qty

$1,251,850

$125,185 10.00%

$41,311 3.00%

Total

$2,834,620

$283,462

$93,542

2.50

3.50%

3.00

$394,817 3.50%

$4,907,015

14.00

$148,926 3.50% $1,573,696

$1,567,272 $4,785,320

$100 $30 $90

10.00%

8.00%

4.00%

36,875

5.00%

$490,701 10.00%

$392,561 8.00%

$215,909 4.00%

$110,624 39,675

$245,351 5.00%

$1,455,146

$6,370,000

$6,370,000

$156,727 10.00%

$125,382 8.00%

$68,960 4.00%

$119,025 39,675

$78,364 5.00%

$548,458

$2,120,000

$8,340,000

$478,532

$382,826

$210,554

$119,025

$239,266

$1,430,203

$6,220,000

Preliminary Project Budget - Additions Option - Spring/Fall Schedule

University of Wisconsin - Stout

Menomonie, Wisconsin

Date: June 4, 2009

Construction Cost Subtotal

General Requirements

Design Contingency

Phasing Cost Factor

Escalation Year Multiplier

Escalation Factor

Total Construction Cost

Cost/sf

Other Costs

Contingency

Architectural/Engineering Fees

DSF Fees

Hazardous Materials Removal

Equip./%for Arts/Other Costs

Subtotal

ESTIMATED TOTALS

ESTIMATED TOTAL/BUILDING

Building Name

Building Area

Footprint Area

Resident Rooms

Resident Beds

Units Unit/Cost percent percent ls percent percent percent percent

75%gsf percent

Year

3.50%

6.5

7 3.5

4 4.5

5

AFM

Antrim/Frogatt

66,484

12,674

125

250

McCalmont

40,899

9,715

101

202

CKTO

Curran/Kranzusch Tustison/Oetting

64,469

10,917

61,532

10,449

122

244

124

248

Hansen/Keith

61,593

10,633

122

244

HKMC

Milnes/Chinnok

61,598

10,661

127

254

7.5

Cube A

27,273

4,560

59

118

8

North Hall

Cube B

33,524

5,723

67

134

8

Cube C

30,245

5,050

61

122

5.5

Cube A

27,280

4,560

60

120

5.5

South Hall

Cube B

33,487

5,711

59

118

6

Cube C

30,300

5,063

64

128

Qty

10.00%

3.00%

Total Qty

$5,459,418

$545,942 10.00%

$180,161

Total Qty

$3,318,708

$331,871 10.00%

$0 3.00%

Total Qty

$5,174,358

$517,436 10.00%

$170,754 3.00%

Total Qty

$4,816,604

$481,660 10.00%

$158,948 3.00%

Total Qty

$5,435,930

$543,593 10.00%

$179,386 3.00%

Total Qty

$5,166,034

$516,603 10.00%

$170,479 3.00%

Total Qty

$2,463,326

$246,333 10.00%

$81,290 3.00%

Total Qty

$2,751,032

$275,103 10.00%

$90,784 3.00%

Total Qty

$2,564,900

$256,490 10.00%

$84,642 3.00%

Total Qty

$2,690,040

$269,004 10.00%

$88,771 3.00%

Total Qty

$2,629,022

$262,902 10.00%

$86,758 3.00%

Total

$2,498,884

$249,888

$82,463

6.50

3.50% $1,407,206

$7,592,727

$114

7.00

3.50% $894,392

$4,544,971

$111

3.50

3.50% $718,162

$6,580,710

$102

4.00

3.50%

4.50

$764,010 3.50%

$6,221,222

5.00

$970,028 3.50% $1,024,295

$7,128,937 $6,877,412

$101 $116 $112

7.50

3.50% $732,624

$3,523,572

$129

8.00

3.50%

8.00

$872,737 3.50%

$3,989,657

5.50

$813,689 3.50%

$3,719,721

5.50

$586,704 3.50%

$3,634,520

$573,396

$3,552,078

$119 $123 $133 $106

6.00

3.50% $594,559

$3,425,795

$113

10.00%

8.00%

4.00%

$3 49,863

5.00%

$759,273 10.00%

$607,418 8.00%

$334,080 4.00%

$149,589 30,674

$379,636 5.00%

$2,229,996

$454,497 10.00%

$363,598

$199,979

$92,023 48,352

$227,249 5.00%

$1,337,345

8.00%

4.00%

$658,071 10.00%

$526,457

$289,551

$145,055 46,149

$329,035 5.00%

$1,948,170

8.00%

4.00%

$622,122 10.00%

$497,698 8.00%

$273,734 4.00%

$138,447 46,195

$311,061 5.00%

$1,843,062

$712,894 10.00%

$570,315 8.00%

$313,673 4.00%

$138,584 46,199

$356,447 5.00%

$2,091,913

$687,741 10.00%

$550,193

$302,606

$138,596 20,455

$343,871 5.00%

$2,023,006

8.00%

4.00%

$352,357 10.00%

$281,886

$155,037

$61,364 25,143

$176,179 5.00%

$1,026,823

8.00%

4.00%

$398,966 10.00%

$319,173 8.00%

$175,545 4.00%

$75,429 22,684

$199,483 5.00%

$1,168,595

$371,972 10.00%

$297,578 8.00%

$163,668 4.00%

$68,051 20,460

$185,986 5.00%

$1,087,255

$363,452 10.00%

$290,762 8.00%

$159,919 4.00%

$61,380 25,115

$181,726 5.00%

$1,057,238

$355,208 10.00%

$284,166

$156,291

$75,346 22,725

$177,604 5.00%

$1,048,615

8.00%

4.00%

$342,580

$274,064

$150,735

$68,175

$171,290

$1,006,843

$9,830,000

$15,720,000

$5,890,000 $8,530,000

$16,600,000

$8,070,000 $9,230,000

$18,140,000

$8,910,000 $4,560,000 $5,160,000

$14,530,000

$4,810,000 $4,700,000 $4,610,000

$13,750,000

$4,440,000

2.5

Fleming Hall

49,166

8,363

101

202

3

North Campus

Wigen Hall-

1st Round

52,900

8,800

119

238

3

Wigen Hall-

2nd Round

52,900

8,800

119

238

Qty

10.00%

3.00%

Total Qty

$3,982,522

$398,252 10.00%

$131,423 3.00%

Total Qty

$1,251,850

$125,185 10.00%

$41,311 3.00%

Total

$2,834,620

$283,462

$93,542

2.50

3.50%

3.00

$394,817 3.50%

$4,907,015

3.00

$148,926 3.50%

$1,567,272

$337,221

$3,548,845

$100 $30 $67

10.00%

8.00%

4.00%

36,875

5.00%

$490,701 10.00%

$392,561 8.00%

$215,909 4.00%

$110,624 39,675

$245,351 5.00%

$1,455,146

$6,370,000

$6,370,000

$156,727 10.00%

$125,382 8.00%

$68,960 4.00%

$119,025 39,675

$78,364 5.00%

$548,458

$2,120,000

$6,770,000

$354,885

$283,908

$156,149

$119,025

$177,442

$1,091,409

$4,650,000

Preliminary Project Budget - Additions Option - Campus Preferred Order - With NEW HALL and most aggressive schedule

University of Wisconsin - Stout

Menomonie, Wisconsin

Date: June 4, 2009

Construction Cost Subtotal

General Requirements

Design Contingency

Phasing Cost Factor

Escalation Year Multiplier

Escalation Factor

Total Construction Cost

Cost/sf

Other Costs

Contingency

Architectural/Engineering Fees

DSF Fees

Hazardous Materials Removal

Equip./%for Arts/Other Costs

Subtotal

ESTIMATED TOTALS

ESTIMATED TOTAL/BUILDING

Building Name

Building Area

Footprint Area

Resident Rooms

Resident Beds

Units Unit/Cost percent percent ls percent percent percent percent

75%gsf percent

Year

3.50%

6.5

7

AFM

Antrim/Frogatt

66,484

12,674

125

250

McCalmont

40,899

9,715

101

202

4 4.5

CKTO

Curran/Kranzusch

64,469

10,917

Tustison/Oetting

61,532

10,449

122

244

124

248

5

Hansen/Keith

61,593

10,633

122

244

5

HKMC

Milnes/Chinnok

61,598

10,661

127

254

6

Cube A

27,273

4,560

59

118

6

North Hall

Cube B

33,524

5,723

67

134

6

Cube C

30,245

5,050

61

122

5.5

Cube A

27,280

4,560

60

120

5.5

South Hall

Cube B

33,487

5,711

59

118

6

Cube C

30,300

5,063

64

128

Qty

10.00%

3.00%

Total Qty

$5,459,418

$545,942 10.00%

$180,161

Total Qty

$3,318,708

$331,871 10.00%

$0 3.00%

Total Qty

$5,174,358

$517,436 10.00%

$170,754 3.00%

Total Qty

$4,816,604

$481,660 10.00%

$158,948 3.00%

Total Qty

$5,435,930

$543,593 10.00%

$179,386 3.00%

Total Qty

$5,166,034

$516,603 10.00%

$170,479 3.00%

Total Qty

$2,463,326

$246,333 10.00%

$81,290 3.00%

Total Qty

$2,751,032

$275,103 10.00%

$90,784 3.00%

Total Qty

$2,564,900

$256,490 10.00%

$84,642 3.00%

Total Qty

$2,690,040

$269,004 10.00%

$88,771 3.00%

Total Qty

$2,629,022

$262,902 10.00%

$86,758 3.00%

Total

$2,498,884

$249,888

$82,463

6.50

3.50% $1,407,206

$7,592,727

$114

7.00

3.50% $894,392

$4,544,971

$111

4.00

3.50% $820,757

$6,683,304

$104

4.50

3.50%

5.00

$859,511 3.50% $1,077,809

$6,316,723 $7,236,718

$103 $117

5.00

3.50% $1,024,295

$6,877,412

$112

6.00

3.50% $586,099

$3,377,048

$124

6.00

3.50%

6.00

$654,553 3.50%

$3,771,472

5.50

$610,267 3.50%

$3,516,298

5.50

$586,704 3.50%

$3,634,520

$573,396

$3,552,078

$113 $116 $133 $106

6.00

3.50% $594,559

$3,425,795

$113

10.00%

8.00%

4.00%

$3 49,863

5.00%

$759,273 10.00%

$607,418 8.00%

$334,080 4.00%

$149,589 30,674

$379,636 5.00%

$2,229,996

$454,497 10.00%

$363,598

$199,979

$92,023 48,352

$227,249 5.00%

$1,337,345

8.00%

4.00%

$668,330 10.00%

$534,664

$294,065

$145,055 46,149

$334,165 5.00%

$1,976,281

8.00%

4.00%

$631,672 10.00%

$505,338 8.00%

$277,936 4.00%

$138,447 46,195

$315,836 5.00%

$1,869,229

$723,672 10.00%

$578,937 8.00%

$318,416 4.00%

$138,584 46,199

$361,836 5.00%

$2,121,445

$687,741 10.00%

$550,193

$302,606

$138,596 20,455

$343,871 5.00%

$2,023,006

8.00%

4.00%

$9,830,000

$15,720,000

$5,890,000 $8,660,000

$16,850,000

$8,190,000 $9,360,000

$18,270,000

$8,910,000

$337,705 10.00%

$270,164

$148,590

8.00%

4.00%

$61,364 25,143

$168,852 5.00%

$986,675

$4,370,000

$377,147 10.00%

$301,718 8.00%

$165,945 4.00%

$75,429 22,684

$188,574 5.00%

$1,108,812

$351,630 10.00%

$281,304 8.00%

$154,717 4.00%

$68,051 20,460

$175,815 5.00%

$1,031,517

$4,890,000

$13,810,000

$4,550,000

$363,452 10.00%

$290,762 8.00%

$159,919 4.00%

$61,380 25,115

$181,726 5.00%

$1,057,238

$355,208 10.00%

$284,166

$156,291

$75,346 22,725

$177,604 5.00%

$1,048,615

8.00%

4.00%

$342,580

$274,064

$150,735

$68,175

$171,290

$1,006,843

$4,700,000 $4,610,000

$13,750,000

$4,440,000

2.5

Fleming Hall

49,166

8,363

101

202

3

North Campus

Wigen Hall-

1st Round

52,900

8,800

119

238

3

Wigen Hall-

2nd Round

52,900

8,800

119

238

Qty

10.00%

3.00%

Total Qty

$3,982,522

$398,252 10.00%

$131,423 3.00%

Total Qty

$1,251,850

$125,185 10.00%

$41,311 3.00%

Total

$2,834,620

$283,462

$93,542

2.50

3.50%

3.00

$394,817 3.50%

$4,907,015

3.00

$148,926 3.50%

$1,567,272

$337,221

$3,548,845

$100 $30 $67

10.00%

8.00%

4.00%

36,875

5.00%

$490,701 10.00%

$392,561 8.00%

$215,909 4.00%

$110,624 39,675

$245,351 5.00%

$1,455,146

$6,370,000

$6,370,000

$156,727 10.00%

$125,382 8.00%

$68,960 4.00%

$119,025 39,675

$78,364 5.00%

$548,458

$2,120,000

$6,770,000

$354,885

$283,908

$156,149

$119,025

$177,442

$1,091,409

$4,650,000

UW-Stout Residence Hall - Existing Statistics

Project Name:

Client Name:

SDS Project #:

Principal in Charge:

Date Prepared:

Residence Hall Study

UW- Stout

0829

Tom Hanley

3/9/2009

AFM

ANTRIM HALL

Constructed

Areas (sf)

1966

BASEMENT

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

FOURTH FLOOR

ROOF

FROGGAT HALL

Totals

6,120

7,662

5,044

5,044

5,044

7,554

36,468

1966

BASEMENT

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

FOURTH FLOOR

ROOF

MCCALMONT HALL

Totals

4,988

5,012

4,858

4,858

4,858

5,442

30,016

1962

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

FOURTH FLOOR

FIFTH FLOOR

AFM Total

9,715

7,928

7,752

7,752

7,752

Totals 40,899

107,383

61

64

6

17

26

26

26

101

226

13

16

16

16

16

16

16

16

CKTO

CURRAN HALL

BASEMENT

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

FOURTH FLOOR

ROOF

Constructed

Areas (sf)

1966

5,207

5,132

5,059

5,059

5,059

5,458

16

16

16

16

9’-8”

7’-8 5/8”

7’-8 5/8”

7’-8 5/8”

7’-8 5/8”

9’-8”

7’-8 5/8”

7’-8 5/8”

7’-8 5/8”

7’-8 5/8”

9'-8"

7'-8-5/8"

7'-8-5/8"

7'-8-5/8"

7'-8-5/8"

Page 1 of 5

Totals 30974

1966 KRANZUSCH HALL

BASEMENT

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

FOURTH FLOOR

ROOF

Totals

TUSTISON HALL

BASEMENT

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

FOURTH FLOOR

ROOF

Totals

OETTING HALL

BASEMENT

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

FOURTH FLOOR

ROOF

CKTO Total

5,601

5,605

5,453

5,453

5,453

5,640

Totals 33,205

126,001

4,786

4,844

4,641

4,641

4,641

4,774

28327

1968

5,800

5,785

5,430

5,430

5,430

5,620

33495

1966

64

58

64

60

246

HKMC

HANSEN HALL

BASEMENT

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

FOURTH FLOOR

ROOF

KEITH HALL

BASEMENT

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

Totals

Constructed

Areas (sf)

1966

5,278

5,326

5,171

5,171

5,171

5,427

31544

1966

5,318

5,307

4,702

4,702

16

16

16

16

64

10

16

16

10

16

16

16

16

16

16

16

12

16

16

16

9'-8"

7'-8-5/8"

7'-8-5/8"

7'-8-5/8"

7'-8-5/8"

9'-8"

7'-8-5/8"

7'-8-5/8"

7'-8-5/8"

7'-8-5/8"

9'-8"

7'-8-5/8"

7'-8-5/8"

7'-8-5/8"

7'-8-5/8"

9'-0"

7'-8-5/8"

7'-8-5/8"

7'-8-5/8"

7'-8-5/8"

9'-0"

7'-8-5/8"

7'-8-5/8"

7'-8-5/8"

Page 2 of 5

FOURTH FLOOR

ROOF

MILNES HALL

Totals

4,702

5,318

30049

1966

BASEMENT

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

FOURTH FLOOR

ROOF

Totals

CHINNOCK HALL

BASEMENT

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

FOURTH FLOOR

ROOF

HKMC Total

5,343

5,415

5,260

5,260

5,260

5,300

Totals 31838

123,191

5,243

5,246

4,657

4,657

4,657

5,300

29760

1969

16

58

64

63

249

16

16

16

16

15

16

16

16

7'-8-5/8"

9'-0"

7'-8-5/8"

7'-8-5/8"

7'-8-5/8"

7'-8-5/8"

9'-0"

7'-8-5/8"

7'-8-5/8"

7'-8-5/8"

7'-8-5/8"

NORTH

NORTH HALL - Cube A

BASEMENT

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

FOURTH FLOOR

ROOF

Totals

NORTH HALL - Cube B

Constructed

Areas (sf)

1967

4,473

4,560

4,560

4,560

4,560

4,560

27273

1967

BASEMENT

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

FOURTH FLOOR

ROOF

Totals

NORTH HALL - Cube C

BASEMENT

5,645

5,723

5,461

5,461

5,461

5,773

33524

1967

4,940

14

15

15

15

59

8

8

17

17

17

67

9'-5"

7'-9"

7'-9"

7'-9"

7'-9"

9'-5"

7'-9"

7'-9"

7'-9"

7'-9"

9'-5"

Page 3 of 5

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

FOURTH FLOOR

ROOF

North Hall Total

Totals

5,050

5,057

5,057

5,057

5,084

30245

91042

61

187

SOUTH

SOUTH HALL - Cube A

BASEMENT

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

FOURTH FLOOR

ROOF

Totals

SOUTH HALL - Cube B

Constructed

Areas (sf)

1967

4,480

4,560

4,560

4,560

4,560

4,560

27280

1967

BASEMENT

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

FOURTH FLOOR

ROOF

Totals

SOUTH HALL - Cube C

5,618

5,711

5,460

5,460

5,460

5,778

33487

1967

BASEMENT

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

FOURTH FLOOR

ROOF

South Hall Total

Totals

4,940

5,063

5,068

5,068

5,068

5,093

30300

91067

60

59

64

183

15

15

15

15

8

17

17

17

16

16

16

16

16

15

15

15

WIGEN/FLEMING

WIGEN HALL

BASEMENT

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

FOURTH FLOOR

ROOF

Constructed

Areas (sf)

1970

8,896

8,800

8,786

8,786

8,786

8,846

29

30

30

30

7'-9"

7'-9"

7'-9"

7'-9"

9'-5"

7'-9"

7'-9"

7'-9"

7'-9"

9'-5"

7'-9"

7'-9"

7'-9"

7'-9"

9'-5"

7'-9"

7'-9"

7'-9"

7'-9"

Page 4 of 5

Totals 52900

1961 FLEMING HALL

BASEMENT

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

FOURTH FLOOR

ROOF

Totals

8,415

8,363

7,840

7,840

7,840

8,868

49166

119

101

20

27

27

27

Page 5 of 5

EXISTING FACILITIES CONDITION REPORT

University of Wisconsin-Stout Residence Hall Study

Antrim – Froggatt - McCalmont Residence Halls

SUMMARY/OVERVIEW

McCalmont Hall was originally designed as a residence hall in 1962. Today, portions of the building are used for offices and other types of resident and non-resident spaces needed by the Voc-Rehab program.

It appears that the 1966 Antrim-Froggatt (A&F) addition was intended to provide a common front desk for the complex. The floor elevation of the entry/front desk portion of A&F is set to match the adjacent grade, but is not does not match the first floors of McCalmont or A&F. The difference is approximately 7’ from the reception area floor to the adjacent first floors.

A project in the early 1980’s involved the addition of an elevator on the north side of McCalmont. This addition also included a skyway connection to the Vocational Rehabilitation Building to the north.

UTILITY AND SERVICE ANALYSIS

SITE CIVIL/MECHANICAL UTILITIES

1. Water Supply: 4”CI combined water service from the 6” city main to the west in vacated 2 nd

Street east. The water riser is in the SW corner of Antrim Hall. City pressure is 90PSI, with a 3” water meter and a 3” water pressure reducing valve. There is a 4”water supply that exits the building to the south that supplies CKTO

Halls. This water service also supplies McCalmont Hall.

2. Sanitary Sewer: An 8” sewer pipe exits building to the west near the middle of Antrim Hall, material is cast iron

& clay tile.

3. Storm Sewer: An 8” storm sewer pipe exits the building at the NE corner of Froggatt Hall, combines with the storm sewer from CKTO Halls and extends to the city main in 3rd Street, piping is cast iron & clay tile.

4. Plumbing Deficiencies: Water service is undersized for a future fire suppression system. Water service serves multiple buildings, and is undersized. All utility mains are original, 1965. The city water main in 2 nd

Street east does not have adequate pressure/flow for use as a source of water for a fire suppression system, however, there is an 8” city water main in 3rd Street east that will supply adequate pressure/flow for a fire suppression system.

5. Heating Distribution: High pressure steam enters the complex in the lower level of the southwest corner of

McCalmont Hall. Pressure reducing stations in McCalmont Hall reduce the steam pressure below 15 psig for supplying the heat exchanger and ventilation units. The hot water from the heat exchanger is distributed throughout the building for heating. High pressure steam is routed to Antrim and Froggat Halls through an interstitial space connecting the basements of the buildings. Pressure reducing stations in Antrim Hall reduce the steam pressure below 15 psig for supplying the heat exchanger and ventilation units. The hot water from the heat exchanger is distributed throughout the Antrim and Froggat for heating.

6. Cooling Distribution: Chiller is located in the basement of McCalmont serving McCalmont Hall only. The cooling tower is located on the roof. Chilled water and hot water are piped throughout McCalmont Hall, which utilizes a two pipe changeover system with fan coils in each room. Chilled water is not routed to Antrim and

Froggat Halls. Window air conditioning units are used in some locations in Antrim and Froggat Halls.

7. Fuel Distribution: There is a small natural gas meter at the NE corner of Froggatt Hall, it serves 8 gas clothes dryers.

 SDS Architects, Inc.

Page 1

SITE ELECTRICAL UTILITIES

1. Electrical Distribution: 4160 volts is provided to the building through the campus primary manhole and duct bank system. Loop B, tap 3-4 for AF and loop B, tap 2-3 for McCalmont.

2. Site Lighting: Campus pole mounted fixtures at sidewalks.

3. Site Communications and Security: Incoming service consists of multi-pair category 3 cable for voice and a coaxial cable for CATV both by the service provider. Incoming fiber optics consists of 18 strands of 62.5 multimode and 10 strands of single mode from North Hall.

BUILDING ANALYSIS

SUBSTRUCTURE

1. Foundations: Cast in place concrete footings and foundation walls. 4” drain tile around perimeter is indicated on original drawings.

Commentary: Foundation walls all appear sound.

SUPERSTRUCTURE

1. Floor Construction: 6” reinforced concrete flat slabs supported by exterior and interior cast in place concrete columns and spandrel beams.

Commentary: New penetrations through existing floor will likely require careful planning due to extent of reinforcement.

2. Roof Construction: 6” reinforced concrete flat slab supported by exterior and interior cast in place concrete columns and spandrel beams.

EXTERIOR ENCLOSURE

1. Exterior Walls: A&F -Original documents indicate a 10” wide exterior cavity wall consisting of 4” (nominal) brick on the exterior with 3/8” parging on the interior face of the brick and a 4” concrete masonry unit back-up.

Original documents also indicate “cores of concrete block back-up at exterior cavity walls are to be filled with granular insulating material”. A band of 1’-9” (scaled from drawing) cast stone is used as a transition to the roof edge at the top of the exterior wall.

Commentary: Based on the placement of the parging, it is assumed that the 4” brick was set first followed by the parging. Details also indicate that the brick is placed within 1” (scaled estimate) of the cast in place concrete spandrel beams at each level. It is not understood how parging could be placed on the backside of the brick in these conditions since the spandrel beams would be in place prior to the brick. It should also be noted that although there is not much core space in a 4” concrete block for insulation, the technique used to fill the top courses on each floor is unclear since the block is continuous from floor to floor at each level. It may be assumed that the top core on each level is not filled.

McCalmont - Original documents indicate a similar wall system as A&F except the placement of the parging is indicated on the exterior face of the CMU instead of the interior face of the brick.

2. Exterior Windows: A&F - Windows are single pane with clear anodized aluminum frames. Most windows include storm sashes.

Commentary: Window replacement is recommended to increase energy efficiency of the building.

McCalmont - Windows were replaced in 2008.

 SDS Architects, Inc.

Page 2

3. Exterior Doors: a) Primary Doors and Frames: Hollow metal frames with hollow metal doors. b) Secondary Doors and Frames: Same as Primary. c) Overhead Doors: None

Commentary: Exterior doors are damaged and worn. Recommend replacement of all exterior doors

and frames as a part of any major building upgrades.

3. Roofing: Original roofs were built-up. Most recent roof replacement at A&F took place in July 2007.

Replacement roof is an EPDM system.

Commentary: Documentation indicates that an A&F roofing project in 1982 included complete removal of the original built-up roof to the concrete deck. The 1982 project provided an EPDM system with tapered insulation. Available documentation does not indicate whether the 1982 roof system was removed during the 2007 reroofing. The current roof should not need replacement until 2027-2030 based on expected life for this type of roofing.

Documentation was not found for replacement information for McCalmont. The roof is indicated as being an EPDM system.

4. Roof Openings: A single 30” x 36” roof scuttle is located near the center of the southeast wing of A&F. The scuttle is accessed from a storage room on the top floor. A single scuttle is indicated at the west end of

McCalmont.

INTERIORS

1. Interior Construction a) Partitions: All original interior partitions are concrete masonry unit walls. Most of these walls are 6” CMU, non-bearing, and are used to infill between the structural column system. b) Interior Doors a. Doors and Frames: Primarily hollow metal frames with solid core birch doors. Hollow metal doors are used in utilitarian areas on lower level and stairwells. Some doors have been laminated over the past few years. b. Hardware: Most hardware is original in need of replacement. c. Overhead Doors: None

Commentary: All interior doors and hardware should be replaced as a part of any major building upgrades. c) Stairs a. Stair Construction: Reinforced cast-in-place concrete.

Commentary: Interior side of stairwells is constructed with structural glazed masonry tile.

2. Interior Finishes

Wall Finishes

Public Spaces: Paint

Corridors: Paint

Toilet Rooms: Glazed structural tile and ceramic tile

Resident Rooms: Paint

Stairwells: Glazed tile.

 SDS Architects, Inc.

Page 3

Floor Finishes

Public Spaces: Primarily carpet with some VCT and ACT.

Corridors: Carpet

Toilet Rooms: Ceramic tile

Resident Rooms: Carpet

Stairwells: Quarry tile

Ceiling Finishes

Public Spaces: Acoustical tile

Corridors: Acoustical tile

Toilet Rooms: Exposed concrete with sealer

Resident Rooms: Plaster direct to concrete

Stairwells: Plaster direct to concrete.

Commentary: Asbestos floor tile may be present under carpeted areas. Any major remodeling project should include new wall, floor, and ceiling finishes.

SERVICES

1. Conveying

Elevators and Lifts: An elevator was added to McCalmont around 1981. Documentation was not found for this project.

2. Plumbing a) Plumbing Fixtures: Most of the plumbing fixtures are original, they are not water conserving and the faucets are in poor condition. b) Domestic Water Distribution: The water piping is original, water piping is galvanized steel, the valves are original, McCalmont has single wall horizontal tube bundle and 2500GAL storage tank, there is a small electric water heater for summer usage. Antrim-Froggatt has 2 steam fired single wall water heaters are original, there is a no water heater for summer usage. In McCalmont there is a RPBP backflow preventer in the NW mechanical room for HVAC system connection. c) Sanitary Waste: Waste piping is original, it is cast iron and galvanized steel. d) Rain Water Drainage: Conductor piping above ground is galvanized steel, the below ground piping is cast iron. This system is in good condition. e) Other Plumbing Systems: Natural gas is supplied to 8 gas clothes dryers, material is SCH 40 black steel.

Plumbing Commentary: In general all systems have outlived their useful life and will continue to have failures. Any major building upgrade project should include the complete replacement of the following systems:

Plumbing fixtures

Water piping and valves

Water heaters

Waste/vent piping

Roof drains (rain water system can be modified).

Gas piping can be modified instead of completely replaced depending on extent of remodeling.

There is asbestos containing insulation on the water and storm conductor piping systems. Water piping mains also supplies water to CKTO Halls. Code approved backflow protection will be required at HVAC converters.

3. Heating, Ventilating, And Air Conditioning (HVAC) a) Energy Supply: Central campus steam provides heating energy. b) Heat Generation: Campus steam provides the building with heat. c) Refrigeration: Chiller located in basement of McCalmont serving McCalmont Hall only.

 SDS Architects, Inc.

Page 4

d) HVAC Distribution: Steam is routed to the heat exchanger and ventilation units. Hot water from the heat exchanger is distributed throughout the building to fin tube located in each room in Antrim and Froggat

Halls. A two pipe heating/cooling system is utilized in McCalmont Hall with two pipe heating/cooling fan coil units in each room. There is a ventilation unit located in the basement that provides air to the restroom groups on each floor. e) Terminal and Packaged Units: Rooms are served with hot water fin tube. f) HVAC Instrumentation and Controls: Existing limited pneumatic Johnson Controls for ventilation units.

Commentary: The HVAC equipment and piping is all original from the initial building construction over

40 years ago. Heating equipment and piping is nearing the end of its useful life and should be replaced. Chiller was installed in McCalmont Hall in 1982. Ventilation air is provided in the corridor of each building. Restroom groups are exhausted.

1. Fire Protection a) Sprinklers: There are no sprinkler heads in this building. b) Standpipes: In McCalmont Hall there is a 2” fire main that supplies 1½” hose cabinets on each floor, the hose cabinet valves are capped and not in use. In Antrim-Froggatt Halls there is a 4” fire main that supplies 1½” hose cabinets on each floor, the hose cabinet valves are capped and not in use. c) Fire Protection Specialties: None.

Commentary: The water service is not large enough to supply a fire suppression system.

2. Electrical a) Electrical Service and Distribution: a. Service:

1) Size: 300 KVA 4160:208/120 volt 3 phase transformer with 600 amp main distribution panel in AF.

30 KVA 4160:208/120 volt 3 phase transformer with 1000 amp main distribution

panel in McCalmont.

2) Peak Demand: 110.25 KW per the meter in AF. This reading combines AF and

CKTO since the meter is located in the medium voltage gear. AF demand is not just this total minus CKTO due to how demand is calculated.

43.2 KW per the meter in McCalmont b. Interior Distribution: Feeders from the main distribution panel to branch panels in the building.

Resident floor panels are served by common risers as opposed to individual feeders. Interior distribution is contained within each section of building. c. Transformers: None other than the dry type service transformer in AF.

Dry type service transformer and dry type transformer on the generator feeder in McCalmont. d. Panelboards: Panelboards per floor to serve resident rooms. e. Motor Control Centers: None. Motor controls are all individually mounted. b) Lighting and Branch Wiring: a. Branch Circuits: Circuits are fed from the panelboard in their given area. b. Interior Lighting: Primarily fluorescent. c. Lighting Controls: Corridors are manually switched. Occupancy sensors in most common areas in AF. No occupancy sensors were noted in McCalmont.

 SDS Architects, Inc.

Page 5

d. Exterior Building Lighting: HID. e. Emergency/Exit Lighting: Appeared to be somewhat newer compact fluorescent in most areas with the older incandescent or compact fluorescent in the remaining areas. c) Communications and Security: a. Fire Alarm: Notifier addressable system with voice notification in AF. Annunciator in main lobby and panel located in the electrical room. Automatic detection and manual pull stations are provided. Stand alone smoke detectors in resident rooms.

Notifier zoned system with voice notification in McCalmont.

Panel located in the electrical room. Automatic detection and manual pull stations are provided. b. Security/Surveillance: In the main lobby there is one Closed Circuit Television camera near the main office. Access control is located on the interior vestibule door at the main entrance, the main office in the lobby and a secure office on the lower level.

McCalmont has access control at doors on fifth floor. c. Clock/Program Systems: N/A d. Voice and Data Systems: The main distribution frame (MDF) is located in Room 28 on the basement level. The MDF is the service entrance for voice, CATV and fiber. Equipment located in the MDF is rack and wall mounted. From the MDF 12 strands of multi-mode fiber is routed to

Room 39. From Room 39 one 25-pair copper cable and one RG-6 coax is distributed to a surface mounted cabinet located in each module on each floor. Each cabinet has a modular patch panel or 110 block, CATV splitter and switch for horizontal distribution. Category 5e/6 cable for voice and data is routed from each cabinet through 2” square PVC surface raceway tight to ceiling located in the corridor. Each resident room has two information outlet locations. One location has one data, one voice and one coax termination and the other has one voice and one data termination. From each information outlet a 3/4” conduit routes along wall and stubs to surface raceway in corridor.

McCalmont appears to be fed from AF and the telecom room is located on third floor horizontal distribution is the same as AF.

Commentary: The current condition appears to comply with the standards of category 5e cabling system. This system in its current state is acceptable. The pathways the system utilizes may not be ideal if the buildings are remodeled. These may cause conflicts with other trades and may not be aesthetically pleasing. If one building is remodeled and the cabling system is upgraded then the backbone infrastructure may not support the new cabling system within the building and may need to be upgraded as well.

Given the timeline for potential remodels and the advancements in technology, a new cabling system may not be relevant by the end of the schedule. Cabling for 10 years out may be the best option for the campus but could be costly since this technology and standards are fairly new. e. P.A. Systems: N/A f. T.V. Systems: Cable television is distributed from the service providers point of presence in the

MDF in the basement to a cabinet located in each module on each floor utilizing RG-6 coaxial cable. Within each cabinet the RG-6 terminates on a splitter and then one RG-6 is routed to each resident room through the surface raceway. g. Other Systems: Emergency call station is located in the vestibule of the main lobby and is tied to the campus system. A cashless vending system is put in place for laundry and vending machines. d) Other Electrical Systems:

 SDS Architects, Inc.

Page 6

a. UPS Systems: None. b. Engine Generator: AF is served by the generator located in CKTO. AF contains a transfer switch.

McCalmont is served by the 480 volt generator located in Vocational Rehab. McCalmont contains a transfer switch. c. Power Conditioning/Surge Suppression: Surge suppression at main distribution in AF.

Surge suppression at main distribution in McCalmont.

Commentary: The existing electrical distribution equipment is still in good condition, but is original to the buildings. It appears the 5KV switches were more recent additions to the buildings. All the wiring is original to the buildings and should be replaced. All distribution equipment should be replaced to bring it up to the current models instead of the campus having to find replacement parts for obsolete models as they have failures. The medium voltage distribution system should be upgraded to a loop configuration instead of the current tapped configuration, which will require three new 5KV switches in each building. This change will likely require larger electrical rooms, possibly in different locations due to the requirement for two exits from those rooms. Additional panelboards should be planned for each floor to allow for 4 circuits in each resident room (one for each room’s long wall, one for a refrigerator, and one for a window air conditioner).

The fire alarm system panels have been replaced in the recent past (10-20 years). The notification requirements have increased since the buildings were originally built, so the panels should be replaced in order to provide for the increased requirements. The existing panels are in good condition.

END BUILDING ANALYSIS

 SDS Architects, Inc.

Page 7

EXISTING FACILITIES CONDITION REPORT

University of Wisconsin-Stout Residence Hall Study

Curran-Kranzusch-Tustison-Oetting Residence Halls

SUMMARY/OVERVIEW

The original block of Curran, Kranzusch, and Tustison was constructed in 1966. Chinnock was added to this complex in 1969 along with a similar addition to the neighboring HKMC complex. No major additions or remodeling have occurred since 1969.

UTILITY AND SERVICE ANALYSIS

SITE CIVIL/MECHANICAL UTILITIES

1. Water Supply: 4”CI combined water supply extends from A & F Halls and enters in the middle of the north wall of Kranzusch Hall, city pressure is 90 PSI.

2. Sanitary Sewer: An 8”sanitary sewer exits the north wall of Kranzusch Hall, extends to a manhole and turns east to connect to the city sanitary sewer in 3 rd

Street. This sewer also serves Curran & Tustison Halls (all

1965). There is an additional 6” CI sanitary sewer leaving the SE corner of Oetting Hall (1969) flowing south to the city main in vacated 12 th

St east. Materials are cast iron & clay tile.

3. Storm Sewer: A 10” storm sewer exits the east wall near the NE corner of Kranzusch Hall, it extends to a manhole and turns NE to connect to the city storm sewer in 3 rd

Street. This sewer also serves Curran &

Tustison Halls (all 1965). There is an additional 6”CI storm sewer leaves the middle of Oetting Hall (1969) flowing west to the city main in vacated 2 nd

St. Piping materials are cast iron & reinforced concrete pipe.

4. Plumbing Deficiencies: Water service is undersized for a future fire sprinklered building. All utility mains are original, 1965 & 1969. Water is supplied from A & F Halls. There is an 8” city water main in 3 rd

Street East that can provide an adequate water supply for a fire suppression system.

5. Heating Distribution: High pressure steam enters the complex in the lower level of the northeast corner of

Kranzusch Hall. Pressure reducing stations reduce the steam pressure below 15 psig for supplying the heat exchanger and ventilation units. The hot water from the heat exchanger is distributed throughout the building for heating.

6. Cooling Distribution: None.

7. Fuel Distribution: There is a small natural gas meter on the north side of Kranzusch Hall near the NE corner, it serves 10 gas clothes dryers and a gas water heater.

SITE ELECTRICAL UTILITIES

1) Electrical Distribution:

208 volts is provided to the building from AF

2) Site Lighting:

Campus pole mounted fixtures at sidewalks.

3) Site Communications and Security:

 SDS Architects, Inc.

Page 1

Incoming service consists of multi-pair category 3 cable for voice and a coaxial cable for CATV both by the service provider. Incoming fiber optics consists of 18 strands of 62.5 multi-mode and 10 strands of single mode from North Hall.

BUILDING ANALYSIS

SUBSTRUCTURE

1. Foundations: Cast in place concrete footings and foundation walls. 4” drain tile around perimeter is indicated on original drawings.

Commentary: Foundation walls all appear sound.

SUPERSTRUCTURE

1. Floor Construction: 6” reinforced concrete flat slabs supported by exterior and interior cast in place concrete columns and spandrel beams.

Commentary: New penetrations through existing floor will likely require careful planning due to extent of reinforcement.

2. Roof Construction: 6” reinforced concrete flat slab supported by exterior and interior cast in place concrete columns and spandrel beams.

EXTERIOR ENCLOSURE

1. Exterior Walls: Original building documents indicate a 10” wide exterior cavity wall consisting of 4” (nominal) brick on the exterior with 3/8” parging on the interior face of the brick and a 4” concrete masonry unit back-up.

Original documents also indicate “cores of concrete block back-up at exterior cavity walls are to be filled with granular insulating material”. A band of 1’-9” (scaled from drawing) cast stone is used as a transition to the roof edge at the top of the exterior wall.

1966 Addition documents indicate an exterior wall similar to the original with the exception that the parging is placed on the concrete masonry units instead of the brick. Details of the addition indicate that 1” of rigid insulation was included only in the long dimension walls of the corner resident rooms (exterior walls that do not have radiant heat and will have resident beds adjacent). The drawings indicate that the cores of the 4” CMU backup in the other areas are filled with granular insulating material.

Commentary: Based on the placement of the parging in the original building, it is assumed that the 4” brick was set first followed by the parging. Original building details also indicate that the brick is placed within 1” (scaled estimate) of the cast in place concrete spandrel beams at each level. It is not understood how parging could be placed on the backside of the brick in these conditions since the spandrel beams would be in place prior to the brick. It should also be noted that although there is not much core space in a 4” concrete block for insulation, the technique used to fill the top courses on each floor is unclear since the block is continuous from floor to floor at each level. It may be assumed that the top core on each level is not filled or not filled completely.

2. Exterior Windows: Windows are single pane with clear anodized aluminum frames. Most windows include storm sashes.

Commentary: Window replacement is recommended to increase energy efficiency of the building

3. Exterior Doors: a) Primary Doors and Frames: Hollow metal frames with hollow metal doors. b) Secondary Doors and Frames: Same as Primary. c) Overhead Doors: None

 SDS Architects, Inc.

Page 2

Commentary: Exterior doors are damaged and worn. Recommend replacement of all exterior doors and frames as a part of any major building upgrades.

4. Roofing: Original roof was built-up. Roof replacement projects were completed around 1983 and 2004.

Current roof is a ballasted, 45 mil. EPDM system.

.

Commentary: The 1983 project included complete removal of the original roof system to the down to the roof deck. The 1983 system included a base layer of 1/8” per foot tapered polystyrene insulation covered by the roof membrane. The roof membrane was covered with a layer of extruded polystyrene over which a layer of polypropylene fabric and ballast was placed. Documentation indicates that the roofing project in 2004 included 2” of polyisocyanurate insulation installed over the “existing insulation”. Based on the details included in the 2004 project, it is assumed that the “existing insulation was only the tapered base layer from 1983 and that everything above the 1983 base layer was removed. Based on the 2004 drawings, the current total insulation thickness likely ranges 3” with 5” thick with the top 2” being polyisocyanurate and the remainder molded polystyrene. The current roof should not need replacement until 2024-2027 based on expected life for this type of roofing.

5. Roof Openings: A single 30” x 36” roof scuttle is located near the center of the northeast wing. The scuttle is accessed from a storage room on the top floor.

INTERIORS

1. Interior Construction a) Partitions: All original interior partitions are concrete masonry unit walls. Most of these walls are 6” CMU, non-bearing, and are used to infill between the structural column system. b) Interior Doors: a. Doors and Frames: Primarily hollow metal frames with solid core birch doors. Hollow metal doors are used in utilitarian areas on lower level and stairwells. b. Hardware: Most hardware is original in need of replacement. c. Overhead Doors: None

Commentary: All interior doors and hardware should be replaced as a part of any major building upgrades. c) Fittings: a. Toilet Partitions: Plastic; good condition. d) Stairs: a. Stair Construction: Reinforced cast-in-place concrete.

Commentary: Interior side of stairwells are constructed with structural glazed masonry tile.

1. Interior Finishes

Wall Finishes

Public Spaces: Paint

Corridors: Paint

Toilet Rooms: Glazed structural tile and ceramic tile

Resident Rooms: Paint

Stairwells: Glazed tile.

 SDS Architects, Inc.

Page 3

Floor Finishes

Public Spaces: Primarily carpet with some VCT and ACT.

Corridors: Carpet

Toilet Rooms: Ceramic tile

Resident Rooms: Carpet

Stairwells: Quarry tile

Ceiling Finishes

Public Spaces: Acoustical tile

Corridors: Acoustical tile

Toilet Rooms: Exposed concrete with sealer

Resident Rooms: Plaster direct to concrete

Stairwells: Plaster direct to concrete.

Commentary: Asbestos floor tile may be present under carpeted areas. Any major remodeling project should include new wall, floor, and ceiling finishes.

SERVICES

1. Conveying: a) Elevators and Lifts: An elevator was added to the building in 1990. According to the project specifications, the elevator is a passenger type, 3,500 pound capacity, 75 ft. per minute up and 125 ft. per minute down with full capacity. The car size is 6’-8” wide by 5’-5” deep (inside dimensions).

2. Plumbing a) Plumbing Fixtures: Most of the plumbing fixtures are original, they are not water conserving and the faucets are in poor condition. b) Domestic Water Distribution: Water for this building is fed from Antrim-Froggat Halls. The water piping is original, water piping is galvanized steel, the valves are original, the 2 steam fired single wall water heaters are original, there is one new sealed combustion gas water heater and a 200GAL storage tank for summer usage. c) Sanitary Waste: Waste piping is original, it is cast iron and galvanized steel. d) Rain Water Drainage: Conductor piping above ground is galvanized steel, the below ground piping is cast iron. This system is in good condition. e) Other Plumbing Systems: There is a gas meter that serves, 10 clothes dryers and 1 gas water heater in

Kranzusch Hall, material is SCH 40 black steel.

Plumbing Commentary: In general all systems have outlived their useful life and will continue to have failures. Any major building upgrade project should include the complete replacement of the following systems:

Plumbing fixtures

Water piping and valves

Water heaters

Waste/vent piping

Roof drains (rain water system can be modified).

Gas piping can be modified instead of completely replaced depending on extent of remodeling.

There is asbestos containing insulation on the water and storm conductor piping systems.

Code approved Backflow protection will be required at HVAC converters.

3. Heating, Ventilating, And Air Conditioning (HVAC) a) Energy Supply: Central campus steam provides heating energy. b) Heat Generation: Campus steam provides the building with heat. c) Refrigeration: None.

 SDS Architects, Inc.

Page 4

d) HVAC Distribution: Steam is routed to the heat exchanger and ventilation units. Hot water from the heat exchanger is distributed throughout the building to fin tube located in each room. e) Terminal and Packaged Units: Rooms are served with hot water fin tube f) HVAC Instrumentation and Controls: Existing limited pneumatic Johnson Controls for ventilation units g) Testing, Adjusting, and Balancing: Not reviewed.

Commentary: The HVAC equipment and piping is all original from the initial building construction over

40 years ago. All HVAC equipment and piping is nearing the end of its useful life and should be replaced. Ventilation air is provided in the corridor of each building. Restroom groups are exhausted.

4. Fire Protection

Sprinklers:There are no sprinkler heads in this building.

Standpipes: There is a 4” fire main that supplies 1½” hose cabinets on each floor, the hose cabinet valves are capped and not in use. Fire main extends underground after it enters building.

Fire Protection Specialties: None

Commentary:The water service is not large enough to supply a fire suppression system. Underground piping will need to be eliminated.

5. Electrical a) Electrical Service and Distribution: a. Service:

1) Size: 600 amp main distribution panel.

2) Peak Demand: 97.2 KW per the meter. b. Interior Distribution: Feeders from the main distribution panel to branch panels in the building.

Resident floor panels are served by common risers as opposed to individual feeders. c. Transformers: None. d. Panelboards: Panelboards per floor to serve resident rooms. e. Motor Control Centers: None. Motor controls are all individually mounted. b) Lighting and Branch Wiring: a. Branch Circuits: Circuits are fed from the panelboard in their given area. GFCI receptacles are installed in the common bathrooms. b. Interior Lighting: Primarily fluorescent. c. Lighting Controls: Corridors are manually switched. Occupancy sensors in most common areas. d. Exterior Building Lighting: HID. e. Emergency/Exit Lighting: Appeared to be somewhat newer compact fluorescent in most areas with the older incandescent or compact fluorescent in the remaining areas. The medium voltage electrical room contains a wall mounted emergency lighting unit with integral battery backup. c) Communications and Security:

 SDS Architects, Inc.

Page 5

a. Fire Alarm: Notifier addressable system with voice notification. Panel located in main lobby.

Automatic detection and manual pull stations are provided. Stand alone smoke detectors in the resident rooms. b. Security/Surveillance: In the main lobby there is one Closed Circuit Television camera near the main office. Access control is located on the interior vestibule door at the main entrance, the main office in the lobby and a secure office on the lower level. c. Clock/Program Systems: N/A d. Voice and Data Systems: The main distribution frame (MDF) is located in Room 48 on the basement level. Mechanical Room 47 is the service entrance for voice, CATV and fiber.

Incoming cabling routes from room 47 to 48. Equipment located in the MDF is rack and wall mounted. From the MDF one 25-pair copper cable, 4 strands of 62.5 multi-mode fiber and one RG-6 coax is distributed to a surface mounted cabinet located in each module on each floor. Each cabinet has a 66 block, CATV splitter and switch for horizontal distribution.

Category 5 cable for voice and category 5e cable for data is routed from each cabinet through

2” square PVC surface raceway tight to ceiling located in the corridor. Each resident room has two information outlet locations. One location has one data, one voice and one coax termination and the other has one voice and one data termination. From each information outlet a 3/4” conduit routes along wall and stubs to surface raceway in corridor. e. Commentary: The current condition appears to comply with the standards of category 5e cabling system. This system in its current state is acceptable. The pathways the system utilizes may not be ideal if the buildings are remodeled. These may cause conflicts with other trades and may not be aesthetically pleasing. If one building is remodeled and the cabling system is upgraded then the backbone infrastructure may not support the new cabling system within the building and may need to be upgraded as well. f. Given the timeline for potential remodels and the advancements in technology, a new cabling system may not be relevant by the end of the schedule. Cabling for 10 years out may be the best option for the campus but could be costly since this technology and standards are fairly new. g. P.A. Systems: N/A h. T.V. Systems: Cable television is distributed from the service providers point of presence in the MDF in the basement to a cabinet located in each module (4 total) on each floor utilizing

RG-6 coaxial cable. Within each cabinet the RG-6 terminates on a splitter and then one RG-6 is routed to each resident room through the surface raceway. i. Other Systems: Emergency call station is located outside of building near the main lobby and is tied to the campus system. A cashless vending system is put in place for laundry and vending machines. d) Other Electrical Systems: a. UPS Systems: None. b. Engine Generator: 45 KW diesel powered unit located in 88 Oetting. Serves this building, AF, and HKMC. c. Power Conditioning/Surge Suppression: Surge suppression at main distribution.

Commentary: The existing electrical distribution equipment is still in good condition, but is original to the buildings. It appears the 5KV switches were more recent additions to the buildings. All the wiring is original to the buildings and should be replaced. All distribution equipment should be replaced to bring it up to the current models instead of the campus having to find replacement parts for obsolete models as they have failures. The medium voltage distribution system should be upgraded to a loop configuration instead of the current

 SDS Architects, Inc.

Page 6

tapped configuration, which will require three new 5KV switches in each building. This change will likely require larger electrical rooms, possibly in different locations due to the requirement for two exits from those rooms. Additional panelboards should be planned for each floor to allow for 4 circuits in each resident room (one for each room’s long wall, one for a refrigerator, and one for a window air conditioner).

The fire alarm system panels have been replaced in the recent past (10-20 years). The notification requirements have increased since the buildings were originally built, so the panels should be replaced in order to provide for the increased requirements. The existing panels are in good condition.

END BUILDING ANALYSIS

 SDS Architects, Inc.

Page 7

EXISTING FACILITIES CONDITION REPORT

University of Wisconsin-Stout Residence Hall Study

Fleming Residence Hall

SUMMARY/OVERVIEW

Fleming Hall was constructed in 1961. There have been no major subsequent additions to the building.

UTILITY AND SERVICE ANALYSIS

SITE CIVIL/MECHANICAL UTILITIES

1. Water Supply: 3” CI combined water service from the city main to the south in 3 rd

Avenue west, near the center of the building. City pressure is 90PSI, with a 3” water meter.

2. Sanitary Sewer: 6” sewer exits building to the south near the middle of the building and connects to the city main in 3 rd

Avenue west, material is cast iron.

3. Storm Sewer: Storm sewer is 8” and exits the building to the south near the middle of the building and connects to the city main in 3 rd

Ave West, piping is cast iron.

4. Plumbing Deficiencies: Water service is undersized for a future fire suppression system. All utility mains are original, 1961.

5. Heating Distribution: Currently low pressure steam enters the complex in the lower level of the southeast corner of Fleming Hall from the basement of Hovlid Hall. The Hovlid Hall/Dining addition project will reroute the steam so that high pressure steam enters the lower level of the southwest corner of Fleming Hall.

Pressure reducing stations will reduce the steam pressure below 15 psig for distribution throughout the building to steam fin tube. The low pressure steam will also be routed to the new dining addition associated with the upcoming Hovlid Hall renovation project.

6. Cooling Distribution: None.

7. Fuel Distribution: There is a small natural gas meter on the south side of the building near the middle; it serves

5 gas clothes dryers.

SITE ELECTRICAL UTILITIES

1. Electrical Distribution: 4160 volts is provided to the building through the campus primary manhole and duct bank system. LoopE, tap 2A.

2. Site Lighting: Street lighting and campus pole mounted fixtures at sidewalks.

3. Site Communications and Security: Incoming service consists of multi-pair category 3 cable for voice and a coaxial cable for CATV both by the service provider. Incoming fiber optics consists of 18 strands of 62.5 multimode and 10 strands of single mode from Foundation (LST) House.

 SDS Architects, Inc.

Page 1

BUILDING ANALYSIS

SUBSTRUCTURE

1. Foundations: Cast in place concrete footings and foundation walls.

Commentary: Foundation walls all appear sound.

SUPERSTRUCTURE

1. Floor Construction: 6” reinforced concrete flat slabs supported by exterior and interior cast in place concrete columns and spandrel beams.

Commentary: New penetrations through existing floor will likely require careful planning due to extent of reinforcement.

2. Roof Construction: 6” reinforced concrete flat slab supported by exterior and interior cast in place concrete columns and spandrel beams.

EXTERIOR ENCLOSURE

1. Exterior Walls: Exterior Walls: Original building documents indicate a 10” wide exterior cavity wall consisting of 4” (nominal) brick on the exterior with 3/8” parging on the interior face of the brick and a 4” concrete masonry unit back-up. Original documents also indicate “cores of concrete block back-up at exterior cavity walls are to be filled with granular insulating material”. A band of 1’-9” (scaled from drawing) cast stone is used as a transition to the roof edge at the top of the exterior wall.

1966 Addition documents indicate an exterior wall similar to the original with the exception that the parging is placed on the concrete masonry units instead of the brick. Details of the addition indicate that 1” of rigid insulation was included only in the long dimension walls of the corner resident rooms (exterior walls that do not have radiant heat and will have resident beds adjacent). The drawings indicate that the cores of the 4” CMU backup in the other areas are filled with granular insulating material.

Commentary: Based on the placement of the parging in the original building, it is assumed that the 4” brick was set first followed by the parging. Original building details also indicate that the brick is placed within 1” (scaled estimate) of the cast in place concrete spandrel beams at each level. It is not understood how parging could be placed on the backside of the brick in these conditions since the spandrel beams would be in place prior to the brick. It should also be noted that although there is not much core space in a 4” concrete block for insulation, the technique used to fill the top courses on each floor is unclear since the block is continuous from floor to floor at each level. It may be assumed that the top core on each level is not filled or not filled completely.

2. Exterior Windows: Windows are single pane with clear anodized aluminum frames. Most windows include storm sashes.

Commentary: Window replacement is recommended to increase energy efficiency of the building.

3. Exterior Doors: a) Primary Doors and Frames: Hollow metal frames with hollow metal doors. b) Secondary Doors and Frames: Same as Primary. c) Overhead Doors: None

Commentary: Exterior doors are damaged and worn. Recommend replacement of all exterior doors and frames as a part of any major building upgrades.

 SDS Architects, Inc.

Page 2

4. Roofing: Original roof was built-up. Most recent replacement occurred in 2005. Documentation of the 2005 roof replacement was not available for review.

Commentary: Existing EPDM roof will likely be due for replacement in around 2025-2027 based on expected life for this type of roof.

5. Roof Openings: A single roof scuttle is located near the center of the building.

INTERIORS

1. Interior Construction a) Partitions: All original interior partitions are concrete masonry unit walls. Most of these walls are 6” CMU, non-bearing, and are used to infill between the structural column system. b) Interior Doors: a. Doors and Frames: Primarily hollow metal frames with solid core birch doors. Hollow metal doors are used in utilitarian areas on lower level and stairwells. Some doors have been laminated over the past few years. b. Hardware: Most hardware is original in need of replacement. c. Overhead Doors: None

Commentary: All interior doors and hardware should be replaced as a part of any major building

upgrades. c) Fittings: a. Toilet Partitions: Plastic; good condition. d) Stairs a. Stair Construction: Reinforced cast-in-place concrete.

Commentary: Interior side of stairwells is constructed with structural glazed masonry tile.

2. Interior Finishes a) Wall Finishes

Public Spaces: Paint

Corridors: Paint

Toilet Rooms: Glazed structural tile and ceramic tile

Resident Rooms: Paint

Stairwells: Glazed tile. b) Floor Finishes

Public Spaces: Primarily carpet with some VCT and ACT.

Corridors: Carpet

Toilet Rooms: Ceramic tile

Resident Rooms: Carpet

Stairwells: Quarry tile c) Ceiling Finishes

Public Spaces: Acoustical tile

Corridors: Acoustical tile

Toilet Rooms: Exposed concrete with sealer

Resident Rooms: Plaster direct to concrete

Stairwells: Plaster direct to concrete.

 SDS Architects, Inc.

Page 3

Commentary: Asbestos floor tile may be present under carpeted areas. Any major remodeling project should include new wall, floor, and ceiling finishes.

SERVICES

1. Conveying

Elevators and Lifts: None.

2. Plumbing a) Plumbing Fixtures: Most of the plumbing fixtures are original, they are not water conserving and the faucets are in poor condition. b) Domestic Water Distribution: The water piping is original, water piping is galvanized steel, the valves are original, and the 2 steam fired single wall water heaters are original; there is a small electric water heater for summer use. c) Sanitary Waste: Waste piping is original; it is cast iron and galvanized steel. d) Rain Water Drainage: Conductor piping above ground is galvanized steel, the below ground piping is cast iron. This system is in good condition. e) Other Plumbing Systems: Natural gas is supplied to 5 gas clothes dryers, material is SCH 40 black steel

Plumbing Commentary: In general all systems have outlived their useful life and will continue to have failures. Any major building upgrade project should include the complete replacement of the following systems:

Plumbing fixtures

Water piping and valves

Water heaters

Waste/vent piping

Roof drains (rain water system can be modified).

Gas piping can be modified instead of completely replaced depending on extent of remodeling.

There is asbestos containing insulation on the water and storm conductor piping systems.

Code approved backflow protection will be required at HVAC converters.

3. Heating, Ventilating, And Air Conditioning (HVAC) a) Energy Supply: Central campus steam provides heating energy. b) Heat Generation: Campus steam provides the building with heat. c) Refrigeration: None. d) HVAC Distribution: Steam is distributed throughout the building to steam fin tube located in each room. e) Terminal and Packaged Units: Rooms are served with steam fin tube. f) HVAC Instrumentation and Controls: Existing limited pneumatic Johnson Controls for ventilation units.

Commentary: The HVAC equipment and piping is all original from the initial building construction over 40 years ago. All HVAC equipment and piping is nearing the end of its useful life and should be replaced. No ventilation air is provided in the building. Ventilation air is provided in the corridor of each building. Restroom groups are exhausted.

 SDS Architects, Inc.

Page 4

4. Fire Protection a) Sprinklers: There are no sprinkler heads in this building. b) Standpipes: There is a 2 ½” fire main that supplies 1½” hose cabinets on each floor, the hose cabinet valves are capped and not in use. c) Fire Protection Specialties: None

Commentary: The water service is not large enough to supply a Fire suppression system.

System does not have a check valve.

5. Electrical a) Electrical Service and Distribution: a. Service:

1) Size: 112.5 KVA 4160:208/120 volt 3 phase transformer with a 400 amp main distribution panel.

2) Peak Demand: 22.4 KW per the meter. b. Interior Distribution: Feeders from the main distribution panel to branch panels in the building.

Resident floor panels are served by common risers as opposed to individual feeders. Fire alarm and emergency lighting are likely tapped ahead of the main distribution panel’s main based on the panel and conduit configuration. This was a common way to provide “emergency” power when the building was built. It does not provide any backup, but helps keep those systems operational if the main distribution panel’s main breaker would trip. c. Transformers: None other than the dry type service transformer. d. Panelboards: Panelboards per floor to serve resident rooms. e. Motor Control Centers: None. Motor controls are all individually mounted. b) Lighting and Branch Wiring: a. Branch Circuits: Circuits are fed from the panelboard in their given area. GFCI receptacles are installed in the common bathrooms and kitchens. b. Interior Lighting: Primarily fluorescent. c. Lighting Controls: Corridors are manually switched. Occupancy sensors in most common areas. d. Exterior Building Lighting: HID. e. Emergency/Exit Lighting: No battery backup. Appeared to be somewhat newer compact fluorescent in most areas with the older incandescent or compact fluorescent in the remaining areas. The medium voltage electrical room contains a wall mounted emergency lighting unit with integral battery backup. c) Communications and Security: a. Fire Alarm: Notifier zoned system with voice notification. Panel located in main lobby vestibule.

Automatic detection and manual pull stations are provided. b. Security/Surveillance: In the main lobby there is one Closed Circuit Television camera near the main office. Access control is located on the interior vestibule door at the main entrance, the main office in the lobby and a secure office on the lower level. c. Clock/Program Systems: N/A d. Voice and Data Systems: The main distribution frame (MDF) is located in the basement level. The

MDF is the service entrance for voice, CATV and fiber. Equipment located in the MDF is rack and wall mounted. From the MDF one 25-pair copper cable and one RG-6 coax is distributed to

 SDS Architects, Inc.

Page 5

junction box in a janitor’s closet on each floor. Each junction box has a 110 block and CATV splitter for horizontal distribution. Category 5e cable for voice and data is routed from each janitors closet through 1” x 4” PVC surface raceway tight to ceiling located on each side of the corridor.

Each resident room has two information outlet locations. One location has one data, one voice and one coax termination and the other has one voice and one data termination. From each information outlet a 1” surface raceway routes along wall and stubs to surface raceway in corridor.

Commentary: The current condition appears to comply with the standards of category 5e cabling system. This system in its current state is acceptable. The pathways the system utilizes may not be ideal if the buildings are remodeled. These may cause conflicts with other trades and may not be aesthetically pleasing. If one building is remodeled and the cabling system is upgraded then the backbone infrastructure may not support the new cabling system within the building and may need to be upgraded as well.

Given the timeline for potential remodels and the advancements in technology, a new cabling system may not be relevant by the end of the schedule. Cabling for 10 years out may be the best option for the campus but could be costly since this technology and standards are fairly new. e. P.A. Systems: N/A f. T.V. Systems:

Cable television is distributed from the service providers point of presence in the MDF in the basement to a junction box located in a janitors closet on each floor utilizing RG-6 coaxial cable.

Within each junction box the RG-6 terminates on a splitter and then one RG-6 is routed to each resident room through the surface raceway. g. Other Systems: Emergency call station is located in the vestibule of the main lobby and is tied to the campus system. A cashless vending system is put in place for laundry and vending machines. d) Other Electrical Systems: a. UPS Systems: None. b. Engine Generator: None. c. Power Conditioning/Surge Suppression: Surge suppression at main distribution.

Commentary: The existing electrical distribution equipment is still in good condition, but is original to the buildings. It appears the 5KV switches were more recent additions to the buildings. All the wiring is original to the buildings and should be replaced. All distribution equipment should be replaced to bring it up to the current models instead of the campus having to find replacement parts for obsolete models as they have failures. The medium voltage distribution system should be upgraded to a loop configuration instead of the current tapped configuration, which will require three new 5KV switches in each building. This change will likely require larger electrical rooms, possibly in different locations due to the requirement for two exits from those rooms. Additional panelboards should be planned for each floor to allow for 4 circuits in each resident room (one for each room’s long wall, one for a refrigerator, and one for a window air conditioner).

The fire alarm system panels have been replaced in the recent past (10-20 years). The notification requirements have increased since the buildings were originally built, so the panels should be replaced in order to provide for the increased requirements. The existing panels are in good condition.

END BUILDING ANALYSIS

 SDS Architects, Inc.

Page 6

EXISTING FACILITIES CONDITION REPORT

University of Wisconsin-Stout Residence Hall Study

Hansen – Keith – Milnes – Chinnock Residence Halls

SUMMARY/OVERVIEW

The original block of Hansen, Keith, and Milnes was constructed in 1966. Chinnock was added to this complex in 1969 along with a similar addition to the neighboring CKTO complex. No major additions or remodeling have occurred since 1969.

UTILITY AND SERVICE ANALYSIS

SITE CIVIL/MECHANICAL UTILITIES

1. Water Supply: 4” CI combined water service from the city main to the east in 13 th

Ave east, city pressure is

90PSI, with a 2” water meter and a 2” water pressure reducing valve.

2. Sanitary Sewer: A 6” sewer exits the SE corner of Hansen Hall flowing south. It connects to the city main in

13 th

Ave East. There is an additional sanitary sewer leaving the middle of the west side of Keith hall flowing west, it intercepts the sewer from Keith Hall with a manhole connection. Materials are cast iron & clay tile.

3. Storm Sewer: There are multiple storm sewers exiting the buildings they flow to the west past the end of

Hansen Hall and to the south to connect to the city storm sewer in 13thAve East. Piping main is 12”, there are

5 manholes. Piping materials are cast iron & reinforced concrete pipe.

4. Plumbing Deficiencies: Water service is undersized for a future fire sprinklered building. All utility mains are original, 1964/65 & 1969.

5. Heating Distribution: High pressure steam enters the complex in the lower level of the southeast corner of

Keith Hall. Pressure reducing stations reduce the steam pressure below 15 psig for supplying the heat exchanger and ventilation units. The hot water from the heat exchanger is distributed throughout the building for heating

6. Cooling Distribution: Window air conditioning units in some locations.

7. Fuel Distribution: There is a small natural gas meter on the north side of Milnes Hall near the NE corner, it serves 5 gas clothes dryers. There is a 2PSI gas meter on the west wall of Hansen Hall that serves 8 dryers and 2 natural gas water heaters that are located on the south side of Hansen hall.

SITE ELECTRICAL UTILITIES

1. Electrical Distribution: 4160 volts is provided to the building through the campus primary manhole and duct bank system. LoopB, tap 4-5.

2. Site Lighting: Campus pole mounted fixtures at sidewalks.

3. Site Communications and Security:Incoming service consists of multi-pair category 3 cable for voice and a coaxial cable for CATV both by the service provider. Incoming fiber optics consists of 18 strands of 62.5 multimode and 10 strands of single mode from North Hall.

BUILDING ANALYSIS

SUBSTRUCTURE

 SDS Architects, Inc.

Page 1

1. Foundations: Cast in place concrete footings and foundation walls. 4” drain tile around the perimeter is indicated on the original drawings.

Commentary: Foundation walls all appear sound.

SUPERSTRUCTURE

1. Floor Construction: 6” reinforced concrete flat slabs supported by exterior and interior cast in place concrete columns and spandrel beams.

Commentary: New penetrations through existing floor will likely require careful planning due to extent of reinforcement.

2. Roof Construction: 6” reinforced concrete flat slab supported by exterior and interior cast in place concrete columns and spandrel beams.

EXTERIOR ENCLOSURE

1. Exterior Walls: Original building documents indicate a 10” wide exterior cavity wall consisting of 4” (nominal) brick on the exterior with 3/8” parging on the interior face of the brick and a 4” concrete masonry unit back-up.

Original documents also indicate “cores of concrete block back-up at exterior cavity walls are to be filled with granular insulating material”. A band of 1’-9” (scaled from drawing) cast stone is used as a transition to the roof edge at the top of the exterior wall. Cast stone mullions and panels are also used as cladding at the exterior of the common lounge areas.

1966 Addition documents indicate an exterior wall similar to the original with the exception that the parging is placed on the concrete masonry units instead of the brick. Details of the addition indicate that 1” of rigid insulation was included only in the long dimension walls of the corner resident rooms (exterior walls that do not have radiant heat and will have resident beds adjacent). The drawings indicate that the cores of the 4” CMU backup in the other areas are filled with granular insulating material.

Commentary: Based on the placement of the parging in the original building, it is assumed that the 4” brick was set first followed by the parging. Original building details also indicate that the brick is placed within 1” (scaled estimate) of the cast in place concrete spandrel beams at each level. It is not understood how parging could be placed on the backside of the brick in these conditions since the spandrel beams would be in place prior to the brick. It should also be noted that although there is not much core space in a 4” concrete block for insulation, the technique used to fill the top courses on each floor is unclear since the block is continuous from floor to floor at each level. It may be assumed that the top core on each level is not filled or not filled completely.

2. Exterior Windows: Windows are single pane with clear anodized aluminum frames. Most windows include storm sashes.

Commentary: Window replacement is recommended to increase energy efficiency of the building.

3. Exterior Doors: a) Primary Doors and Frames: Hollow metal frames with hollow metal doors. b) Secondary Doors and Frames: Same as Primary.

• c) Overhead Doors: None

Commentary: Exterior doors are damaged and worn. Recommend replacement of all exterior doors and frames as a part of any major building upgrades.

4. Roofing: Original roof was Built Up. Most recent roof replacement took place in June 1998. Replacement roof is an EPDM system.

Commentary: Minimal documentation indicates that the 1998 roofing project took place but documents indicating the extent of removal and specific roof type installed were not available from

 SDS Architects, Inc.

Page 2

Campus. If the latest roof was installed in 1998, it should be scheduled for replacement around 2018-

2020 based on the expected life for this type of system.

5. Roof Openings: Two 30” x 36” roof scuttles are located near the center of the northeast and southwest wing.

The scuttles are accessed from storage rooms on the top floors.

INTERIORS

1. Interior Construction a) Partitions: All original interior partitions are concrete masonry unit walls. Most of these walls are 6” CMU, non-bearing, and are used to infill between the structural column system. b) Interior Doors a. Doors and Frames: Primarily hollow metal frames with solid core birch doors. Hollow metal doors are used in utilitarian areas on lower level and stairwells. b. Hardware: Most hardware is original in need of replacement. c. Overhead Doors: None.

Commentary: All interior doors and hardware should be replaced as part of any major building upgrade.

c) Fittings: a. Toilet Partitions: Plastic; good condition. d) Stairs: a. Stair Construction: Reinforced cast-in-place concrete.

Commentary: Interior side of stairwells are constructed with structural glazed masonry tile.

2. Interior Finishes a) Wall Finishes

Public Spaces: Paint

Corridors: Paint

Toilet Rooms: Glazed structural tile and ceramic tile

Resident Rooms: Paint

Stairwells: Glazed tile. b) Floor Finishes

Public Spaces: Carpet with ACT/VCT in isolated areas.

Corridors: Carpet

Toilet Rooms: Ceramic tile

Resident Rooms: Carpet

Stairwells: Quarry tile c) Ceiling Finishes

Public Spaces: Acoustical tile

Corridors: Acoustical tile

Toilet Rooms: Exposed concrete with sealer

Resident Rooms: Plaster direct to concrete

Stairwells: Plaster direct to concrete.

Commentary: Asbestos floor tile may be present under carpeted areas. Any major remodeling project should include new wall, floor, and ceiling finishes.

SERVICES

1. Conveying a) Elevators and Lifts: None

 SDS Architects, Inc.

Page 3

2. Plumbing a) Plumbing Fixtures: Most of the plumbing fixtures are original, they are not water conserving and the faucets are in poor condition. b) Domestic Water Distribution: The water piping is original, water piping is galvanized steel, the valves are original, the 2 steam fired single wall water heaters are original, there are 2 new sealed combustion gas water heaters for summer usage. c) Sanitary Waste: Waste piping is original, it is cast iron and galvanized steel. d) Rain Water Drainage: Conductor piping above ground is galvanized steel, the below ground piping is cast iron. This system is in good condition. e) Other Plumbing Systems: Milnes Hall has a natural gas that supplies to 5 gas clothes dryers, material is

SCH 40 black steel. Hansen Hall has a 2PSI gas meter that serves, 8 clothes dryers and 2 gas water heaters, material is SCH 40 black steel, there are gas regulators with leak limiters at equipment.

Plumbing Commentary: In general all systems have outlived their useful life and will continue to have failures. Any major building upgrade project should include the complete replacement of the following systems:

Plumbing fixtures

Water piping and valves

Water heaters

Waste/vent piping

Roof drains (rain water system can be modified).

Gas piping can be modified instead of completely replaced depending on extent of remodeling.

There is asbestos containing insulation on the water and storm conductor piping systems.

Code approved Backflow protection will be required at HVAC converters.

3. Heating, Ventilating, And Air Conditioning (HVAC) a) Energy Supply: Central campus steam provides heating energy b) Heat Generation: Campus steam provides the building with heat. c) Refrigeration: None. d) HVAC Distribution: Steam is routed to the heat exchanger and ventilation units. Hot water from the heat exchanger is distributed throughout the building to fin tube located in each room. e) Terminal and Packaged Units: Rooms are served with hot water fin tube. f) HVAC Instrumentation and Controls: Existing limited pneumatic Johnson Controls for ventilation units.

Commentary: The HVAC equipment and piping is all original from the initial building construction over

40 years ago. All HVAC equipment and piping is nearing the end of its useful life and should be replaced. Ventilation air is provided in the corridor of each building. Restroom groups are exhausted.

4. Fire Protection a) Sprinklers: There are no sprinkler heads in this building. b) Standpipes: There is a 4” fire main that supplies 1½” hose cabinets on each floor, the hose cabinet valves are capped and not in use. Fire main extends underground at water meter. c) Fire Protection Specialties: None

Commentary: The water service is not large enough to supply a fire sprinkler system. Underground piping will need to be eliminated.

 SDS Architects, Inc.

Page 4

5. Electrical a) Electrical Service and Distribution: a. Service:

1) Size: Three 50 KVA 4160:240/120 volt single phase transformers with a 600 amp main distribution panel.

2) Peak Demand: 60 KW per the meter. b. Interior Distribution:Feeders from the main distribution panel to branch panels in the building.

Resident floor panels are served by common risers as opposed to individual feeders. c. Transformers: None other than the dry type service transformers. d. Panelboards: Panelboards per floor to serve resident rooms. e. Motor Control Centers: None. Motor controls are all individually mounted. b) Lighting and Branch Wiring: a. Branch Circuits: Circuits are fed from the panelboard in their given area. GFCI receptacles are installed in the common bathrooms. b. Interior Lighting: Primarily fluorescent. c. Lighting Controls: Corridors are manually switched. Occupancy sensors in most common areas. d. Exterior Building Lighting: HID. c) Communications and Security: a. Fire Alarm: Notifier addressable system with voice notification. Panel located in main lobby.

Automatic detection and manual pull stations are provided. Stand alone smoke detectors in the resident rooms. e. Emergency/Exit Lighting: Appeared to be somewhat newer compact fluorescent in most areas with the older incandescent or compact fluorescent in the remaining areas. b. Security/Surveillance: In the main lobby there is one Closed Circuit Television camera near the main office. Access control is located on the interior vestibule door at the main entrance, the main office in the lobby and a secure office on the lower level. c. Clock/Program Systems: N/A d. Voice and Data Systems: The main distribution frame (MDF) is located in Room 27 on the basement level. The MDF is the service entrance for voice, CATV and fiber. Equipment located in the MDF is rack and wall mounted. From the MDF one 25-pair copper cable, 4 strands of 62.5 multi-mode fiber and one RG-6 coax is distributed to a surface mounted cabinet located in each module on each floor. Each cabinet has a modular patch panel or 110 block, CATV splitter and switch for horizontal distribution. Category 5e cable for voice and data is routed from each cabinet through 2” square PVC surface raceway tight to ceiling located in the corridor. Each resident room has two information outlet locations. One location has one data, one voice and one coax termination and the other has one voice and one data termination. From each information outlet a

3/4” conduit routes along wall and stubs to surface raceway in corridor. Wireless access is limited to the main lobby office.

Commentary: The current condition appears to comply with the standards of category 5e cabling system. This system in its current state is acceptable. The pathways the system utilizes may not be ideal if the buildings are remodeled. These may cause conflicts with other trades and may not be aesthetically pleasing. If one building is remodeled and the cabling system is upgraded then the backbone infrastructure may not support the new cabling system within the building and may need to be upgraded as well.

 SDS Architects, Inc.

Page 5

f. T.V. Systems: Cable television is distributed from the service providers point of presence in the

MDF in the basement to a cabinet located in each module (4 total) on each floor utilizing RG-6 coaxial cable. Within each cabinet the RG-6 terminates on a splitter and then one RG-6 is routed to each resident room through the surface raceway. g. Other Systems: Emergency call station is located in the vestibule of the main lobby and is tied to the campus system. A cashless vending system is put in place for laundry and vending machines. d) Other Electrical Systems: a. UPS Systems: None. e. P.A. Systems: Local sound system is in place in the main lobby consisting of four surface mount speakers with the headend equipment located in the main office. b. Engine Generator: Building served the generator installed in CKTO. This building contains a transfer switch.

Given the timeline for potential remodels and the advancements in technology, a new cabling system may not be relevant by the end of the schedule. Cabling for 10 years out may be the best option for the campus but could be costly since this technology and standards are fairly new. c. Power Conditioning/Surge Suppression: None noted.

Commentary: The existing electrical distribution equipment is still in good condition, but is original to the buildings. It appears the 5KV switches were more recent additions to the buildings. All the wiring is original to the buildings and should be replaced. All distribution equipment should be replaced to bring it up to the current models instead of the campus having to find replacement parts for obsolete models as they have failures. The medium voltage distribution system should be upgraded to a loop configuration instead of the current tapped configuration, which will require three new 5KV switches in each building. This change will likely require larger electrical rooms, possibly in different locations due to the requirement for two exits from those rooms. Additional panelboards should be planned for each floor to allow for 4 circuits in each resident room (one for each room’s long wall, one for a refrigerator, and one for a window air conditioner).

The fire alarm system panels have been replaced in the recent past (10-20 years). The notification requirements have increased since the buildings were originally built, so the panels should be replaced in order to provide for the increased requirements. The existing panels are in good condition.

END BUILDING ANALYSIS

 SDS Architects, Inc.

Page 6

EXISTING FACILITIES CONDITION REPORT

University of Wisconsin-Stout Residence Hall Study

North Residence Hall

SUMMARY/OVERVIEW

North Hall was constructed 1967 without any major subsequent additions other than an elevator addition in 1997. An ADA remodeling project was completed in 2007 that included toilet room remodeling. A remodeling of the Director’s Apartment was completed in 2008.

UTILITY AND SERVICE ANALYSIS

SITE CIVIL/MECHANICAL UTILITIES

1. Water Supply: 4” CI combined water supply enters in the middle of the east wall of Cube A, it extends to the 6” city water main in vacated 2 nd

Street east, there is a 2” water meter and pressure reducing valve, city pressure is 90PSI.

2. Sanitary Sewer: An 8” clay tile sanitary sewer exits the SE corner of Cube B flowing east to connect to the city sanitary sewer in vacated 2 nd

Street East. Materials are cast iron & clay tile.

3. Storm Sewer: An 8” clay tile sanitary sewer exits the SE corner of Cube B flowing east to connect to the city storm sewer in vacated 2 nd

Street East. Piping materials are cast iron & reinforced concrete pipe.

4. Plumbing Deficiencies: Water service is undersized for a future fire sprinklered building. All utility mains are original, 1966/67. Water is supplied from a 6” city water main, this will not be large enough for future Fire sprinkler system.

5. Heating Distribution: High pressure steam enters the complex in the lower level of the southeast corner of

North Hall. Pressure reducing stations reduce the steam pressure below 15 psig for supplying the heat exchanger and ventilation units. The hot water from the heat exchanger is distributed throughout the building for heating.

6. Cooling Distribution: None.

7. Fuel Distribution: There is a small natural gas meter on the east side of Cube B near the NE corner, it serves

10 gas clothes dryers and a gas water heater located in Cube A.

SITE ELECTRICAL UTILITIES

1. Electrical Distribution: 4160 volts is provided to the building through the campus primary manhole and duct bank system. Loop A, tap 6-7.

2. Site Lighting: Campus pole mounted fixtures at sidewalks.

3. Site Communications and Security: Incoming service consists of multi-pair category 3 cable for voice and a coaxial cable for CATV both by the service provider. Incoming fiber optics consists of 144 strands of 62.5 multi-mode from Millennium Hall.

BUILDING ANALYSIS

SUBSTRUCTURE

1. Foundations: Cast in place concrete footings and foundation walls.

 SDS Architects, Inc.

Page 1

Commentary: Foundation walls all appear sound.

SUPERSTRUCTURE

1. Floor Construction: 7” reinforced concrete flat slabs supported by exterior and interior cast in place concrete columns and spandrel beams.

Commentary: New penetrations through existing floor will likely require careful planning due to extent of reinforcement.

2. Roof Construction: 7” reinforced concrete flat slab supported by exterior and interior cast in place concrete columns and spandrel beams. Isolated areas are constructed with sloped cast in place concrete.

EXTERIOR ENCLOSURE

1. Exterior Walls: Original documents indicate a 12” wide exterior cavity wall consisting of 4” (nominal) brick on

2. Exterior Windows: Windows are single pane with clear anodized aluminum frames. Most windows include storm sashes.

Commentary: Window replacement is recommended to increase energy efficiency of the building.

3. Exterior Doors: a) Primary Doors and Frames: Hollow metal frames with hollow metal doors. b) Secondary Doors and Frames: Same as Primary. c) Overhead Doors: None the exterior and 8” concrete masonry unit back-up. Parging is indicated on the cavity side of the concrete masonry units. Original documents do not indicate insulation in the cavity or CMU cores. A band of 2’-0” wide cast stone is used as a transition to the roof edge at the top of the exterior wall and another 1’4” band is used at the base of the building.

Commentary: Most of the foundation walls below the 12” masonry cavity walls are 10 9/16” thick. In most cases, the brick and stone veneer is supported by steel angles attached to the foundation wall and is not supported directly by the concrete foundation wall. Although there is no indication that there is insulation in the walls, it is possible that insulation is included in the cores of the 8” CMU backup as was done in similar buildings of this time period on Campus.

Commentary: Exterior doors are damaged and worn. Recommend replacement of all exterior doors and frames as a part of any major building upgrades.

3. Roofing: Original roof was Built Up with metal roofing on isolated areas (links and stairwells). Most recent roof replacements took place in July 2005 (North Cube) and July 2007 (South Cubes). Replacement roof is an

EPDM system.

Commentary: Roofing replacement will likely be needed around 2025-2027 based on the expected life of the existing system.

4. Roof Openings: A single 30” x 36” roof scuttle is located in each cube (3 total) with access from the Custodian

Room.

INTERIORS

1. Interior Construction a) Partitions: All original interior partitions are concrete masonry unit walls. Most of these walls are 6” CMU, non-bearing, and are used to infill between the structural column system. b) Interior Doors

 SDS Architects, Inc.

Page 2

a. Doors and Frames: Primarily hollow metal frames with solid core birch doors. Hollow metal doors are used in utilitarian areas on lower level and stairwells. b. Hardware: Most hardware is original in need of replacement. c. Overhead Doors: None

Commentary: All interior doors and hardware should be replaced as part of any major building upgrade. c) Fittings a) Toilet Partitions: Plastic; good condition. d) Stairs

Stair Construction: Reinforced cast-in-place concrete.

Commentary: Interior side of stairwells are constructed with structural glazed masonry tile.

2. Interior Finishes a) Wall Finishes

Public Spaces: Paint

Corridors: Paint

Toilet Rooms: Glazed structural tile and ceramic tile

Resident Rooms: Paint

Stairwells: Glazed tile. b) Floor Finishes

Public Spaces: Carpet with VCT and ACT in isolated areas.

Corridors: Carpet

Toilet Rooms: Ceramic tile

Resident Rooms:

Stairwells: Quarry tile c) Ceiling Finishes

Public Spaces: Acoustical tile

Corridors: Acoustical tile

Toilet Rooms: Exposed concrete with sealer

Resident Rooms: Plaster direct to concrete

Stairwells: Plaster direct to concrete.

Commentary: Asbestos floor tile may be present under carpeted areas. Any major remodeling project should include new wall and floor finishes.

SERVICES

1. Conveying a) Elevators and Lifts: An elevator was added to the building in 1997. According to the project specifications, the elevator is a passenger type, 2,500 pound capacity, 150 ft. per minute. The car size is 7’-0” wide by

5’-1” deep (inside dimensions).

2. Plumbing a) Plumbing Fixtures: Most of the plumbing fixtures are original, they are not water conserving and the faucets are in poor condition b) Domestic Water Distribution: The water piping is original, water piping is galvanized steel, the valves are original, the 2 steam fired single wall water heaters are original, there is one new sealed combustion gas water heater and a 200GAL storage tank for summer usage. c) Sanitary Waste: Waste piping is original, it is cast iron and galvanized steel.

 SDS Architects, Inc.

Page 3

d) Rain Water Drainage: Conductor piping above ground is galvanized steel, the below ground piping is cast iron. This system is in good condition. e) Other Plumbing Systems:

There is a gas meter that serves, 10 clothes dryers and 1 gas water heater in Both are in Cube C, material is SCH 40 black steel.

Plumbing Commentary: In general all systems have outlived their useful life and will continue to have failures. Any major building upgrade project should include the complete replacement of the following systems:

Plumbing fixtures

Water piping and valves

Water heaters

Waste/vent piping

Roof drains (rain water system can be modified).

Gas piping can be modified instead of completely replaced depending on extent of remodeling.

There is asbestos containing insulation on the water and storm conductor piping systems.

Code approved Backflow protection will be required at HVAC converters.

3. Heating, Ventilating, And Air Conditioning (HVAC) a) Energy Supply: Central campus steam provides heating energy. b) Heat Generation: Campus steam provides the building with heat. c) Refrigeration: None. d) HVAC Distribution: Steam is routed to the heat exchanger and ventilation units. Hot water from the heat exchanger is distributed throughout the building to fin tube located in each room. e) Terminal and Packaged Units: Rooms are served with hot water fin tube. f) HVAC Instrumentation and Controls: Existing limited pneumatic Johnson Controls for ventilation units. g) Other Special HVAC Systems and Equipment:

Commentary: The HVAC equipment and piping is all original from the initial building construction over

40 years ago. All HVAC equipment and piping is nearing the end of its useful life and should be replaced. Ventilation air is provided in the corridor of each building. Restroom groups are exhausted.

4. Fire Protection a) Sprinklers: There are no sprinkler heads in this building. b) Standpipes: There is a 2 ½” fire main that supplies 1½” hose cabinets on each floor, the hose cabinet valves are capped and not in use. c) Fire Protection Specialties: None

Commentary: The water service is not large enough to supply a fire sprinkler system.

5. Electrical a) Electrical Service and Distribution: a. Service:

1) Size: 225 KVA 4160:208/120 volt 3 phase transformer with a 600 amp main distribution panel.

2) Peak Demand: 52.5 KW per the meter. b. Interior Distribution: Feeders from the main distribution panel to branch panels in the building.

Resident floor panels are served by common risers as opposed to individual feeders. Emergency

 SDS Architects, Inc.

Page 4

lighting is likely tapped ahead of the main distribution panel’s main based on the panel and conduit configuration. This was a common way to provide “emergency” power when the building was built. It does not provide any backup, but helps keep those systems operational if the main distribution panel’s main breaker would trip. c. Transformers: None other than the dry type service transformer. d. Panelboards: Panelboards per floor to serve resident rooms. e. Motor Control Centers: None. Motor controls are all individually mounted. b) Lighting and Branch Wiring: a. Branch Circuits: Circuits are fed from the panelboard in their given area. b. Interior Lighting: Primarily fluorescent. Basement has newer 2x4 grid mounted troffers. c. Lighting Controls: Corridors are manually switched. Occupancy sensors in most common areas. d. Exterior Building Lighting: HID. e. Emergency/Exit Lighting: No battery backup. Lighting appeared to be somewhat newer compact fluorescent in most areas with the older incandescent or compact fluorescent in the remaining areas. The medium voltage electrical room contains a wall mounted emergency lighting unit with integral battery backup. c) Communications and Security: a. Fire Alarm: Notifier addressable system with voice notification. Panel located in main lobby.

Automatic detection and manual pull stations are provided. Stand alone smoke detectors in the resident rooms. b. Security/Surveillance: In the main lobby there is one Closed Circuit Television camera near the main office. Access control is located on the interior vestibule door at the main entrance, the main office in the lobby and a secure office on the lower level. c. Clock/Program Systems: N/A d. Voice and Data Systems: The main distribution frame (MDF) is located in Room 40 on the basement level. Room 6 is the service entrance for voice, CATV and fiber and fiber optic cabling is distributed to all other buildings from this room. Twelve strands of multi-mode fiber routes from

Room 6 to Room 40. Equipment located in the MDF is rack and wall mounted. From the MDF one 25-pair copper cable and one RG-6 coax is distributed to a surface mounted cabinet located in each module on each floor. Each cabinet has a 110/66 block, CATV splitter and switch for horizontal distribution. Category 5 cable for voice and category 5e cable for data is routed from each cabinet through 2” square PVC surface raceway tight to ceiling located in the corridor. Each resident room has one information outlet consisting of one data, one voice and one coax termination. From each information outlet a 3/4” conduit routes along wall and stubs to surface raceway in corridor. Wireless access is limited to the lounge area.

Commentary: The current condition appears to comply with the standards of category 5e cabling system. This system in its current state is acceptable. The pathways the system utilizes may not be ideal if the buildings are remodeled. These may cause conflicts with other trades and may not be aesthetically pleasing. If one building is remodeled and the cabling system is upgraded then the backbone infrastructure may not support the new cabling system within the building and may need to be upgraded as well.

Given the timeline for potential remodels and the advancements in technology, a new cabling system may not be relevant by the end of the schedule. Cabling for 10 years out may be the best option for the campus but could be costly since this technology and standards are fairly new.

 SDS Architects, Inc.

Page 5

e. P.A. Systems: N/A f. T.V. Systems: Cable television is distributed from the service providers point of presence in the

MDF in the basement to a cabinet located in each module on each floor utilizing RG-6 coaxial cable. Within each cabinet the RG-6 terminates on a splitter and then one RG-6 is routed to each resident room through the surface raceway. g. Other Systems: Emergency call station is located in the vestibule of the main lobby and is tied to the campus system. A cashless vending system is put in place for laundry and vending machines. d) Other Electrical Systems: a. UPS Systems: None. b. Engine Generator: None. c. Power Conditioning/Surge Suppression: Surge suppression at main distribution.

Commentary: The existing electrical distribution equipment is still in good condition, but is original to the buildings. It appears the 5KV switches were more recent additions to the buildings. All the wiring is original to the buildings and should be replaced. All distribution equipment should be replaced to bring it up to the current models instead of the campus having to find replacement parts for obsolete models as they have failures. The medium voltage distribution system should be upgraded to a loop configuration instead of the current tapped configuration, which will require three new 5KV switches in each building. This change will likely require larger electrical rooms, possibly in different locations due to the requirement for two exits from those rooms. Additional panelboards should be planned for each floor to allow for 4 circuits in each resident room (one for each room’s long wall, one for a refrigerator, and one for a window air conditioner).

The fire alarm system panels have been replaced in the recent past (10-20 years). The notification requirements have increased since the buildings were originally built, so the panels should be replaced in order to provide for the increased requirements. The existing panels are in good condition.

END BUILDING ANALYSIS

 SDS Architects, Inc.

Page 6

EXISTING FACILITIES CONDITION REPORT

University of Wisconsin-Stout Residence Hall Study

South Residence Hall

SUMMARY/OVERVIEW

South Hall was constructed 1967 without any major subsequent additions.

UTILITY AND SERVICE ANALYSIS

SITE CIVIL/MECHANICAL UTILITIES

1. Water Supply: 4” CI combined water supply enters in the NE corner of the east wall of Cube A, it is fed from the 10” city water main in vacated 2 nd

Street east, there is a 2” water meter and pressure reducing valve, city pressure is 90PSI.

2. Sanitary Sewer: An 8” clay tile sanitary sewer exits near the middle of the north wall of Cube C flowing north to connect to the city sanitary sewer in vacated 12 th

Street East. Materials are cast iron & clay tile.

3. Storm Sewer: There are 3 exit locations for the storm sewer. A 6” CI storm sewer exits the NW corner of

Cube a flowing north, a 6”CI storm sewer exits (above the floor) the NE corner flowing east & a 6” storm sewer exits the SE corner of Cube C flowing east. There is a manhole that connects all the branches, flow exits to the NE to connect to the city storm sewer in vacated 2 nd

Street east. Piping materials are cast iron & reinforced concrete pipe.

4. Plumbing Deficiencies: Water service is undersized for a future fire sprinklered building. All utility mains are original, dating from 1966/67.

5. Heating Distribution: High pressure steam enters the complex in the lower level of the southeast corner of

South Hall. Pressure reducing stations reduce the steam pressure below 15 psig for supplying the heat exchanger and ventilation units. The hot water from the heat exchanger is distributed throughout the building for heating.

6. Cooling Distribution: Window air conditioning units in some locations.

7. Fuel Distribution: There is a small natural gas meter on the east side of Cube A near the NE corner, it serves

10 gas clothes dryers and a gas water heater, all located in Cube A

SITE ELECTRICAL UTILITIES

1. Electrical Distribution: 4160 volts is provided to the building through the campus primary manhole and duct bank system. Loop A, tap 8-9.

2. Site Lighting: Campus pole mounted fixtures at sidewalks.

3. Site Communications and Security: Incoming service consists of multi-pair category 3 cable for voice and a coaxial cable for CATV both by the service provider. Incoming fiber optics consists of 18 strands of 62.5 multimode and 10 strands of single mode from Millennium Hall.

BUILDING ANALYSIS

SUBSTRUCTURE

1. Foundations: Cast in place concrete footings and foundation walls.

 SDS Architects, Inc.

Page 1

Commentary: Foundation walls all appear sound.

SUPERSTRUCTURE

1. Floor Construction: 7” reinforced concrete flat slabs supported by exterior and interior cast in place concrete columns and spandrel beams.

Commentary: New penetrations through existing floor will likely require careful planning due to extent of reinforcement.

2. Roof Construction: 7” reinforced concrete flat slab supported by exterior and interior cast in place concrete columns and spandrel beams. Isolated areas are constructed with sloped cast in place concrete.

EXTERIOR ENCLOSURE

1. Exterior Walls: Original documents indicate a 12” wide exterior cavity wall consisting of 4” (nominal) brick on the exterior and 8” concrete masonry unit back-up. Parging is indicated on the cavity side of the concrete masonry units. Original documents do not indicate insulation in the cavity or CMU cores. A band of 2’-0” wide cast stone is used as a transition to the roof edge at the top of the exterior wall and another 1-’4” band is used at the base of the building.

Commentary: Most of the foundation walls below the 12” masonry cavity walls are 10 9/16” thick. In most cases, the brick and stone veneer is supported by steel angles attached to the foundation wall and is not supported directly by the concrete foundation wall. Although there is no indication that there is insulation in the walls, it is possible that insulation is included in the cores of the 8” CMU backup as was done in similar buildings of this time period on Campus.

2. Exterior Windows:

Windows are single pane with clear anodized aluminum frames. Most windows include storm sashes.

Commentary: Window replacement is recommended to increase energy efficiency of the building.

3. Exterior Doors:

Primary Doors and Frames: Hollow metal frames with hollow metal doors.

Secondary Doors and Frames: Same as Primary.

Overhead Doors: None

Commentary: Exterior doors are damaged and worn. Recommend replacement of all exterior doors and frames as a part of any major building upgrades.

4. Roofing:

Original roof was built-up with metal roofing on isolated areas (links and stairwells). Most recent roof replacements took place in June 1993. Replacement roof is an EPDM system.

Commentary: Documentation of the most current roof replacement were not found on Campus.

Plans for the 1983 replacement were available and indicated a complete removal of the original roof system as part of the replacement. The 1983 roof was a built up roofing system. Roofing replacement will likely be needed around 2023-2026 based on the expected life of the existing system.

5. Roof Openings:

A single 30” x 36” roof scuttle is located in each cube (3 total) with access from the Custodian Room.

I NTERIORS

1. Interior Construction a) Partitions: All original interior partitions are concrete masonry unit walls. Most of these walls are 6” CMU, non-bearing, and are used to infill between the structural column system. b) Interior Doors

 SDS Architects, Inc.

Page 2

a. Doors and Frames: Primarily hollow metal frames with solid core birch doors. Hollow metal doors are used in utilitarian areas on lower level and stairwells. b. Hardware: Most hardware is original in need of replacement. c. Overhead Doors: None

Commentary: All interior doors and hardware should be replaced as part of any major building upgrade. c) Fittings a) Toilet Partitions: Plastic; good condition. d) Stairs

Stair Construction: Reinforced cast-in-place concrete.

Commentary: Interior side of stairwells are constructed with structural glazed masonry tile.

2. Interior Finishes a) Wall Finishes

Public Spaces: Paint

Corridors: Paint

Toilet Rooms: Glazed structural tile and ceramic tile

Resident Rooms: Paint

Stairwells: Glazed tile. b) Floor Finishes

Public Spaces: Carpet with VCT and ACT in isolated areas.

Corridors: Carpet

Toilet Rooms: Ceramic tile

Resident Rooms:

Stairwells: Quarry tile c) Ceiling Finishes

Public Spaces: Acoustical tile

Corridors: Acoustical tile

Toilet Rooms: Exposed concrete with sealer

Resident Rooms: Plaster direct to concrete

Stairwells: Plaster direct to concrete.

Commentary: Asbestos floor tile may be present under carpeted areas. Any major remodeling project should include new wall and floor finishes.

SERVICES

1. Conveying a) Elevators and Lifts: None.

2. Plumbing a) Plumbing Fixtures: Most of the plumbing fixtures are original, they are not water conserving and the faucets are in poor condition b) Domestic Water Distribution: The water piping is original, water piping is galvanized steel, the valves are original, the 2 steam fired single wall water heaters are original, there is one new sealed combustion gas water heater and a 200 gallon storage tank for summer usage. c) Sanitary Waste: Waste piping is original, it is cast iron and galvanized steel. d) Rain Water Drainage: Conductor piping above ground is galvanized steel, the below ground piping is cast iron. This system is in good condition.

 SDS Architects, Inc.

Page 3

e) Other Plumbing Systems: There is a gas meter that serves, 10 clothes dryers and 1 gas water heater in

Both are in Cube A, material is SCH 40 black steel.

Plumbing Commentary: In general all systems have outlived their useful life and will continue to have failures. Any major building upgrade project should include the complete replacement of the following systems:

Plumbing fixtures

Water piping and valves

Water heaters

Waste/vent piping

Roof drains (rain water system can be modified).

Gas piping can be modified instead of completely replaced depending on extent of remodeling.

There is asbestos containing insulation on the water and storm conductor piping systems.

Code approved Backflow protection will be required at HVAC converters.

3. Heating, Ventilating, And Air Conditioning (HVAC) a) Energy Supply: Central campus steam provides heating energy. b) Heat Generation: Campus steam provides the building with heat. c) Refrigeration: None. d) HVAC Distribution: Steam is routed to the heat exchanger and ventilation units. Hot water from the heat exchanger is distributed throughout the building to fin tube located in each room. e) Terminal and Packaged Units: Rooms are served with hot water fin tube. f) HVAC Instrumentation and Controls: Existing limited pneumatic Johnson Controls for ventilation units.

Commentary: The HVAC equipment and piping is all original from the initial building construction over40 years ago. All HVAC equipment and piping is nearing the end of its useful life and should be replaced. Ventilation air is provided in the corridor of each building. Restroom groups are exhausted.

4. Fire Protection a) Sprinklers: There are no sprinkler heads in this building. b) Standpipes: There is a 2 ½” fire main that supplies 1½” hose cabinets on each floor, the hose cabinet valves are capped and not in use. c) Fire Protection Specialties: None

Commentary: The water service is not large enough to supply a fire sprinkler system.

5. Electrical a) Electrical Service and Distribution: a. Service:

1) Size: 225 KVA 4160:208/120 volt 3 phase transformer with a 600 amp main distribution panel.

2) Peak Demand: 35 KW per the meter. b. Interior Distribution: Feeders from the main distribution panel to branch panels in the building.

Resident floor panels are served by common risers as opposed to individual feeders. Emergency lighting is likely tapped ahead of the main distribution panel’s main based on the panel and conduit configuration. This was a common way to provide “emergency” power when the building was built. It does not provide any backup, but helps keep those systems operational if the main distribution panel’s main breaker would trip.

 SDS Architects, Inc.

Page 4

c. Transformers: None other than the dry type service transformer. d. Panelboards: Two panelboards per floor to serve resident rooms. Kitchens on basement, first, and third each contain a panelboard with the first and third floor panels being relatively new. e. Motor Control Centers: None. Motor controls are all individually mounted. b) Lighting and Branch Wiring: a) Branch Circuits: Circuits are fed from the panelboard in their given area. b) Interior Lighting: Primarily fluorescent. c) Lighting Controls: Corridors are manually switched. Occupancy sensors in most common areas. d) Exterior Building Lighting: HID. e) Emergency/Exit Lighting: No battery backup. Appeared to be somewhat newer compact fluorescent in most areas with the older incandescent or compact fluorescent in the remaining areas. The medium voltage electrical room contains a wall mounted emergency lighting unit with integral battery backup. c) Communications and Security: a) Fire Alarm: Notifier addressable system with voice notification. Panel located in main lobby.

Automatic detection and manual pull stations are provided. Stand alone smoke detectors in the resident rooms. b) Security/Surveillance: In the main lobby there is one Closed Circuit Television camera near the main office. Access control is located on the interior vestibule door at the main entrance, the main office in the lobby and a secure office on the lower level. c) Clock/Program Systems: N/A d) Voice and Data Systems: The main distribution frame (MDF) is located in Room 8 on the basement level. The MDF is the service entrance for voice, CATV and fiber. Equipment located in the MDF is rack and wall mounted. From the MDF one 25-pair copper cable, 4 strands of 62.5 multi-mode fiber and one RG-6 coax is distributed to a surface mounted cabinet located in each module on each floor.

Each cabinet has a modular patch panel or 66 block, CATV splitter and switch for horizontal distribution. Category 5 cable for voice and category 5e cable for data is routed from each cabinet through 2” square PVC surface raceway tight to ceiling located in the corridor. Each resident room has two information outlet locations. One location has one data, one voice and one coax termination and the other has one voice and one data termination. From each information outlet a 3/4” conduit routes along wall and stubs to surface raceway in corridor.

Commentary: The current condition appears to comply with the standards of category 5e cabling system. This system in its current state is acceptable. The pathways the system utilizes may not be ideal if the buildings are remodeled. These may cause conflicts with other trades and may not be aesthetically pleasing. If one building is remodeled and the cabling system is upgraded then the backbone infrastructure may not support the new cabling system within the building and may need to be upgraded as well.

Given the timeline for potential remodels and the advancements in technology, a new cabling system may not be relevant by the end of the schedule. Cabling for 10 years out may be the best option for the campus but could be costly since this technology and standards are fairly new. e) P.A. Systems: N/A f) T.V. Systems: Cable television is distributed from the service providers point of presence in the MDF in the basement to a cabinet located in each module on each floor utilizing RG-6 coaxial cable. Within

 SDS Architects, Inc.

Page 5

each cabinet the RG-6 terminates on a splitter and then one RG-6 is routed to each resident room through the surface raceway. g) Other Systems: Emergency call station is located in the vestibule of the main lobby and is tied to the campus system. A cashless vending system is put in place for laundry and vending machines. d) Other Electrical Systems: a. UPS Systems: None. b. Engine Generator: None. c. Power Conditioning/Surge Suppression: Surge suppression at main distribution.

Commentary: The existing electrical distribution equipment is still in good condition, but is original to the buildings. It appears the 5KV switches were more recent additions to the buildings. All the wiring is original to the buildings and should be replaced. All distribution equipment should be replaced to bring it up to the current models instead of the campus having to find replacement parts for obsolete models as they have failures. The medium voltage distribution system should be upgraded to a loop configuration instead of the current tapped configuration, which will require three new 5KV switches in each building. This change will likely require larger electrical rooms, possibly in different locations due to the requirement for two exits from those rooms. Additional panelboards should be planned for each floor to allow for 4 circuits in each resident room (one for each room’s long wall, one for a refrigerator, and one for a window air conditioner).

The fire alarm system panels have been replaced in the recent past (10-20 years). The notification requirements have increased since the buildings were originally built, so the panels should be replaced in order to provide for the increased requirements. The existing panels are in good condition.

END BUILDING ANALYSIS

 SDS Architects, Inc.

Page 6

EXISTING FACILITIES CONDITION REPORT

University of Wisconsin-Stout Residence Hall Study

Wigen Residence Hall

SUMMARY/OVERVIEW

Wigen Hall was constructed in 1970. There have been no major subsequent additions to the building.

UTILITY AND SERVICE ANALYSIS

SITE CIVIL/MECHANICAL UTILITIES

1. Water Supply: 4” CI combined water service is fed from the city main that is east of the building in Broadway, it enters the building near the SE corner of the building, city pressure is 90PSI, with a 3” water meter and a 3” water pressure reducing valve.

2. Sanitary Sewer: 8” sewer exits building to the west and connects to the city main in 2 nd

St west, material is cast iron & clay tile.

3. Storm Sewer: 8” Storm sewer exits the building in the NW corner and connects to the city main in 1 st

Ave west, piping is cast iron & clay tile.

4. Plumbing Deficiencies: Water service is undersized for a future fire suppression system. All utility mains are original, dated 1969.

5. Heating Distribution: Low pressure steam enters the complex in the lower level of the southwest corner of

Wigen Hall routed through Hovlid Hall. The low pressure steam supplies the heat exchanger and ventilation units. The hot water from the heat exchanger is distributed throughout the building for heating.

6. Cooling Distribution: None.

7. Fuel Distribution: There is a small natural gas meter on the south side of the building near the middle, it serves

5 gas clothes dryers.

SITE ELECTRICAL UTILITIES

1) Electrical Distribution: 4160 volts is provided to the building through the campus primary manhole and duct bank system via Hovlid Hall. Loop E, tap 2B.

2) Site Lighting: Street lighting and campus pole mounted fixtures at sidewalks.

3) Site Communications and Security: Incoming service consists of multi-pair category 3 cable for voice and a coaxial cable for CATV both served out of Hovlid Hall. The service provider’s point of presence is in Hovlid

Hall. Incoming fiber optics consists of 18 strands of 62.5 multi-mode and 10 strands of single mode from

Hovlid Hall.

BUILDING SUMMARY

SUBSTRUCTURE

1. Foundations: Cast in place concrete footings and foundation walls.

Commentary: Foundation walls all appear sound.

 SDS Architects, Inc.

Page 1

SUPERSTRUCTURE

1. Floor Construction: 6” reinforced concrete flat slabs supported by exterior and interior cast in place concrete columns and spandrel beams.

Commentary: New penetrations through existing floor will likely require careful planning due to extent of reinforcement.

2. Roof Construction: 6” reinforced concrete flat slab supported by exterior and interior cast in place concrete columns and spandrel beams.

EXTERIOR ENCLOSURE

1. Exterior Walls: Cavity wall construction consisting of 6” CMU backup, 2” rigid insulation, air space and 4” brick. Parging is located on the exterior face of the CMU. 8” backup is used at the lowest level. The total wall thicknesses are nominally 12” and 14”.

Commentary: Unlike the other residence halls, these walls are insulated.

2. Exterior Windows: Windows are single pane with clear anodized aluminum frames. Most windows include storm sashes.

Commentary: Window replacement is recommended to increase energy efficiency of the building.

3. Exterior Doors: a) Primary Doors and Frames: Hollow metal frames with hollow metal doors. b) Secondary Doors and Frames: Same as Primary.

• c) Overhead Doors: None

Commentary: Exterior doors are damaged and worn. Recommend replacement of all exterior doors and frames as a part of any major building upgrades.

3. Roofing: Original roof was built-up. Documents indicate the original roof was completely removed and replaced with a ballasted 45 mil EPDM system with 2” of icocyanurate insulation in 1998.

Commentary: The current roof should be scheduled for replacement around 2018-2020 based on expected life for this type of system.

4. Roof Openings: A single roof scuttle is located near the center of the building.

INTERIORS

1. Interior Construction a) Partitions: All original interior partitions are concrete masonry unit walls. Most of these walls are 6” CMU, non-bearing, and are used to infill between the structural column system. b) Interior Doors: a. Doors and Frames: Primarily hollow metal frames with solid core birch doors. Hollow metal doors are used in utilitarian areas on lower level and stairwells. Some doors have been laminated over the past few years. b. Hardware: Most hardware is original in need of replacement. c. Overhead Doors: None

 SDS Architects, Inc.

Page 2

Commentary: All interior doors and hardware should be replaced as a part of any major building upgrades. c) Fittings: a. Toilet Partitions: Plastic; good condition. d) Stairs a. Stair Construction: Reinforced cast-in-place concrete.

Commentary: Interior side of stairwells is constructed with structural glazed masonry tile.

2. Interior Finishes a) Wall Finishes

Public Spaces: Paint

Corridors: Paint

Toilet Rooms: Glazed structural tile and ceramic tile

Resident Rooms: Paint

Stairwells: Glazed tile. b) Floor Finishes

Public Spaces: Primarily carpet with some VCT and ACT.

Corridors: Carpet

Toilet Rooms: Ceramic tile

Resident Rooms: Carpet

Stairwells: Quarry tile c) Ceiling Finishes

Public Spaces: Acoustical tile

Corridors: Acoustical tile

Toilet Rooms: Exposed concrete with sealer

Resident Rooms: Plaster direct to concrete

Stairwells: Plaster direct to concrete.

Commentary: Asbestos floor tile may be present under carpeted areas. Any major remodeling project should include new wall, floor, and ceiling finishes.

SERVICES

1. Conveying a) Elevators and Lifts: None.

2. Plumbing a) Plumbing Fixtures: Most of the plumbing fixtures are original, they are not water conserving and the faucets are in poor condition. b) Domestic Water Distribution: The water piping is original, water piping is galvanized steel, the valves are original, the 2 steam fired single wall water heaters are original, there is a small electric water heater for summer usage. c) Sanitary Waste: Waste piping is original, it is cast iron and galvanized steel. d) Rain Water Drainage: Conductor piping above ground is galvanized steel, the below ground piping is cast iron. This system is in good condition. e) Other Plumbing Systems: Natural gas is supplied to 5 gas clothes dryers, material is SCH 40 black steel.

Plumbing Commentary: In general all systems have outlived their useful life and will continue to have failures. Any major building upgrade project should include the complete replacement of the following systems:

 SDS Architects, Inc.

Page 3

Plumbing fixtures

Water piping and valves

Water heaters

Waste/vent piping

Roof drains (rain water system can be modified).

Gas piping can be modified instead of completely replaced depending on extent of remodeling.

There is asbestos containing insulation on the water and storm conductor piping systems.

Water piping mains also supply water to McCalmont Hall & CKTO Halls.

Code approved Backflow protection will be required at HVAC converters.

3. Heating, Ventilating, And Air Conditioning (HVAC) a) Energy Supply: Central campus steam provides heating energy. b) Heat Generation: Campus steam provides the building with heat.

c) Refrigeration: None. d) HVAC Distribution: Steam is routed to the heat exchanger and ventilation units. Hot water from the heat exchanger is distributed throughout the building to fin tube located in each room. e) Terminal and Packaged Units: Rooms are served with hot water fin tube. f) HVAC Instrumentation and Controls: Existing limited pneumatic Johnson Controls for ventilation units.

Commentary: The HVAC equipment and piping is all original from the initial building construction over

40 years ago. All HVAC equipment and piping is nearing the end of its useful life and should be replaced. Ventilation air is provided in the corridor of each building. Restroom groups are exhausted.

4. Fire Protection

Sprinklers: There are no sprinkler heads in this building.

Standpipes: There is a 2 ½” fire main that supplies 1½” hose cabinets on each floor, the hose cabinet valves are capped and not in use.

Fire Protection Specialties: None

Commentary: The water service is not large enough to supply a Fire sprinkler system.

5. Electrical a) Electrical Service and Distribution: a. Service:

(1) Size: 112.5 KVA 4160:208/120 volt 3 phase transformer with a 400 amp main distribution panel.

(2) Peak Demand: Existing meter was not functioning so a demand reading is not available b. Interior Distribution: Feeders from the main distribution panel to branch panels in the building.

Resident floor panels are served by common risers as opposed to individual feeders. c. Transformers: None other than the dry type service transformer d. Panelboards: Two panelboards per floor to serve resident rooms. Kitchens on basement, first, and third each contain a panelboard with the first and third floor panels being relatively new. e. Motor Control Centers: None. Motor controls are all individually mounted. b) Lighting and Branch Wiring: a. Branch Circuits: Circuits are fed from the panelboard in their given area. GFCI receptacles are installed in the common bathrooms.

 SDS Architects, Inc.

Page 4

e. Emergency/Exit Lighting: No battery backup. Exit signs are old and likely incandescent, possibly compact fluorescent. c) Communications and Security: a. Fire Alarm: Notifier zoned system with voice notification. Panel located in main lobby. Automatic detection and manual pull stations are provided. b. Security/Surveillance: In the main lobby there is one Closed Circuit Television camera near the main office. Access control is located on the interior vestibule door at the main entrance, the main office in the lobby and a secure office on the lower level. b. Interior Lighting: Primarily fluorescent. c. Lighting Controls: Corridors are manually switched. Occupancy sensors in most common areas. d. Exterior Building Lighting: HID. c. Clock/Program Systems: N/A d. Voice and Data Systems: The main distribution frame (MDF) is located in the basement level. The

MDF is the service entrance for voice, CATV and fiber. Equipment located in the MDF is rack and wall mounted. From the MDF one 25-pair copper cable and one RG-6 coax is distributed to junction box in a janitor’s closet on each floor. Each junction box has a 110 or 66 block and CATV splitter for horizontal distribution. Category 5e cable for voice and data is routed from each janitors closet through 2” square PVC surface raceway tight to ceiling located on each side of the corridor.

Each resident room has two information outlet locations. One location has one data, one voice and one coax termination and the other has one voice and one data termination. From each information outlet a 1” surface raceway routes along wall and stubs to surface raceway in corridor.

Commentary: The current condition appears to comply with the standards of category 5e cabling system. This system in its current state is acceptable. The pathways the system utilizes may not be ideal if the buildings are remodeled. These may cause conflicts with other trades and may not be aesthetically pleasing. If one building is remodeled and the cabling system is upgraded then the backbone infrastructure may not support the new cabling system within the building and may need to be upgraded as well.

Given the timeline for potential remodels and the advancements in technology, a new cabling system may not be relevant by the end of the schedule. Cabling for 10 years out may be the best option for the campus but could be costly since this technology and standards are fairly new. e. P.A. Systems: N/A f. T.V. Systems: Cable television is distributed from the service providers point of presence in the

MDF in the basement to a junction box located in a janitors closet on each floor utilizing RG-6 coaxial cable. Within each junction box the RG-6 terminates on a splitter and then one RG-6 is routed to each resident room through the surface raceway. g. Other Systems: Emergency call station is located in the vestibule of the main lobby and is tied to the campus system. A cashless vending system is put in place for laundry and vending machines. d) Other Electrical Systems: a. UPS Systems: None. b. Engine Generator: None. c. Power Conditioning/Surge Suppression: Surge suppression at main distribution.

 SDS Architects, Inc.

Page 5

Commentary: The existing electrical distribution equipment is still in good condition, but is original to the buildings. It appears the 5KV switches were more recent additions to the buildings. All the wiring is original to the buildings and should be replaced. All distribution equipment should be replaced to bring it up to the current models instead of the campus having to find replacement parts for obsolete models as they have failures. The medium voltage distribution system should be upgraded to a loop configuration instead of the current tapped configuration, which will require three new 5KV switches in each building. This change will likely require larger electrical rooms, possibly in different locations due to the requirement for two exits from those rooms. Additional panelboards should be planned for each floor to allow for 4 circuits in each resident room (one for each room’s long wall, one for a refrigerator, and one for a window air conditioner).

The fire alarm system panels have been replaced in the recent past (10-20 years). The notification requirements have increased since the buildings were originally built, so the panels should be replaced in order to provide for the increased requirements. The existing panels are in good condition.

END BUILDING ANALYSIS

 SDS Architects, Inc.

Page 6

SDS Architects, Inc. • 205 N. Dewey Street • Eau Claire, Wisconsin 54703-3537

Meeting Notes

Meeting Date: Friday, January 16, 2009

Regarding: Residence Hall Renovation Plan

UW-Stout

Menomonie, Wisconsin

Location:

Present:

DSF Project Number: 08J2J

SDS Project Number: 0829

UW-Stout Physical Plant Conference Room

Shirley Klebesadel

Jer Duncanson

Linda Anderson

Scott Griesbach

Tom Biasi

Joe Limke

Rick Leverenz

Mike Lawless

UW-Stout Physical Plant

UW-Stout

UW-Stout PP/SLS

UW-Stout Housing

UW-Stout PP/SLS

KJWW

KJWW

KJWW

Ryan Jester

Bob Novak

Tom Hanley

KJWW

Southport Engineered Systems

SDS

The purpose of this meeting was to seek input from Residence Life and Physical Plant regarding the conditions and priorities for the proposed improvements at the residence halls included in this study.

The following matters were discussed.

1. In general, the plumbing, electrical, HVAC and fire alarm systems will need to be replaced completely and the study should assume complete removal and replacement of all these systems.

2. It was noted that the fire alarm system in some areas was upgraded 13 years ago but by the time these projects are undertaken, many of them will likely be replaced anyway.

3. All door operators need to be replaced.

4. A few pumps have been replaced but these are inconsequential in the whole scheme of things.

5. McCalmont, CKTO and South seem to be the worst in terms of the infrastructure plumbing, mechanical and electrical according to the Campus.

6. Fleming had new fans put in about three years ago.

7. Fleming has very leaky windows and there are water problems in the building on the north side around the shower areas between floors 2 and 3.

8. Buildings with the worst windows are Fleming, North and South Hall.

9. North and South Halls have some pretty significant plumbing issues.

10. More effort has been made in the past to make North Hall more handicap accessible, including remodeling of all the toilet room/shower areas.

11. Questioned if elevators should automatically be included for all of these projects. Campus’ approach to this is that elevators should only be included if they are required by code, UWS, or the DSF.

It was noted that in some of the cube buildings such as HK and MC, the project would require multiple elevators since the link between some of the cubes is only single story.

12. There are water line issues at AF, CKTO.

13. The single generator in this area serves multiple buildings. Physical Plant would like each building to have its own services. This would apply to all utilities.

The Campus is currently undertaking a generator project this summer for North and South Hall, one generator for each. o The North generator will likely be sized to allow the elevator to be on emergency power. o The elevator for South Hall likely will not be sized to accommodate an elevator for emergency power.

14. Noted that AF, HKMC are the most modern in terms of cosmetic upgrades.

Residence Hall Renovation Plan

UW-Stout

January 16, 2009

Page 2

15. Questioned whether a sprinkler system should be included in each of the buildings as part of a major upgrade. SDS is to check with DSF on this, as well as the elevator requirement. If they are required, they should be done similar to the

Hovlid Hall project recently designed on the Stout campus.

16. Questioned if the Campus will require air conditioning as part of this project. The Campus would like to consider air conditioning as a possibility. Would like to use the current Campus chilled water loop which is currently being extended.

This would only apply to the South campus residence halls. The chilled water loop will not be extended to the North campus.

17. Questioned if the Campus anticipates major basement reprogramming/remodeling as part of this project since the area will be disrupted with a lot of the utility work that will be anticipated in this area. Campus will likely be remodeling basement areas as part of the project. Noted that some of the areas such as kitchens and lounges have been recently updated and they would like to avoid having to disturb and re-do these areas if possible.

18. Gas water heater for AF is desired by Campus.

19. It should be assumed that all interior and exterior doors and hardware will be replaced with this project.

20. The project should not assume remodeling of the front desk area unless it is required by other projects, such as to solve code compliance issues. The Directors apartments should be considered the same way. The Campus is doing these projects individually as separate projects outside of this study.

21. Joe Limke with KJWW will talk directly to Grady Richardz on campus regarding technology expectations.

22. It is noted that all rooms are doubles and will remain doubles after any remodeling project is done. The Campus would like to avoid losing any rooms with projects, or as few as possible.

23. The electrical proposed for each of the residence rooms should be similar to that done at the recent Hovlid Hall project.

24. The project study should include a refresh for all resident rooms that includes carpet, paint, etc. It was noted that North,

South, and CKTO are in need of the cosmetic upgrades the most. AF and Wigen have the lowest priority for cosmetics.

25. McCalmont is currently being used as follows:

Fifth floor is a residence hall.

Half of second floor and all of third and fourth are used as offices.

First floor and half of second are used for Voc Rehab. Voc Rehab has some residence use and also training areas.

26. This study should include reconfiguration of all toilet/shower rooms. These should be done with a model similar to that done at the recently completed Hovlid Hall project.

27. Campus expects for the future to have McCalmont third, fourth and fifth floors available for housing. The third and fourth floor may be used for swing space during remodeling of the various residence halls.

28. McCalmont Hall should be treated like any of the other buildings with regard to replacement of infrastructure and upgrades.

29. It is noted that there are no current major issues with any of the roofs or tuckpointing.

30. Caulking of the control joints on the exterior will be needed for most of the buildings.

31. In the future, some lower level space will need to be set up for temporary resident rooms. This is important when considering hardware, ventilation, technology and egress.

32. McCalmont lounges on floors three through five should be considered for overflow resident use and may need to be converted back and forth from resident rooms to lounges during peak times of occupation.

33. Noted there is very little, if any, insulation in most of the exterior walls. Asked if the Campus wants to consider the cost implications of insulating these exterior walls. This should be looked at in a preliminary fashion only at this time.

34. Campus would like to have information that will allow them to decide if they can take part of a four block cube off line. For example, can CK be taken off line at CK, TO without affecting the other two parts?

The key here is that each cube is about 120 students and the Campus cannot take down any more than 240 beds at one given time for remodeling projects.

Part of this will depend on McCalmont area being available for swing space.

35. Questioned if Campus can lose a basement only for part of a season while occupants are still in the building? Campus would rather not do this, as a lot of the functions, such as laundry, are located in the basement space and noise will also be a concern.

36. Generally the construction season for the summer is May 20 th

to August 15 th

. It is ok if the utilities are down for an entire summer in a building during remodeling even if some of these areas are not being remodeled. For example, if MC is being remodeled and HK and MC are without utilities for a summer, this is acceptable with the Campus.

37. The overall goal of this project is to have all of these projects done in a 10 to 12 year period. The projects should be budgeted accordingly with an escalation cost built into the phasing.

38. A larger medium voltage room in the basement is needed.

39. Campus has been surveyed and the Hovlid model for toilet room remodeling, both Men’s and Women’s, is preferred by the students. This would be one toilet room per floor for one sex.

40. Campus would like to see options regarding how the toilet rooms are carried out. Campus has preliminarily discussed two primary options for modifying the buildings.

An example would be converting the center of a cube toilet rooms and lounge space, the stair areas could be built on the outside of the building to provide exiting and also to dress up the outside of the building.

Residence Hall Renovation Plan

UW-Stout

January 16, 2009

Page 3

Another option would be to convert the center core of the cube into a lounge space with stairs and provide an addition on the building for the toilet/shower areas.

41. Access to stairs and elevators is an issue on the first floor. People entering the single story area need to travel through the first floor to get to the more distant wings, this is always a concern.

42. Projects should also consider some exterior image improvements too. For example, if additions are put on, they might reflect more of an open glass look similar to Red Cedar Hall.

43. Site work:

There will be some steam/chilled water site work.

There will also be some site work necessary for electrical and signal modifications.

Water service for fire protection will require site work.

44. Discussed the CKTO generator. Natural gas was discussed. This will need to be considered carefully, as if elevators are needed for a means of egress, it may drive the size of the generator up to a size that is more sensible to use diesel fuel.

45. Discussed dumpsters. North Hall trash area may be an area for improvement.

46. Discussed security/card access. Use the same criteria used at the Hovlid project.

47. It was noted that mail boxes will remain at the Commons area, except for Wigen Hall.

48. Rough-ins should be done on all exterior doors if they are replaced for future card access.

49. Residence Halls generally should be set up for emergency use during major disasters as a place of refuge.

END OF NOTES

This confirms and records our interpretation of the discussion that occurred and decisions reached during this meeting.

Unless notified, we will assume that the notes are complete and accurate.

Respectfully Submitted,

SDS ARCHITECTS, INC.

Thomas M Hanley

Vice President/Architect

TMH/cmj

C: Participants

SDS File 0829

SDS Architects, Inc. • 205 N. Dewey Street • Eau Claire, Wisconsin 54703-3537

Meeting Notes

Meeting Date: Thursday, April 23, 2009

Regarding: Residence Hall Renovation Plan

UW-Stout

Menomonie, Wisconsin

Location:

Present:

DSF Project Number: 08J2J

SDS Project Number: 0829

UW-Stout General Services 139

Tim Luttrell

Shirley Klebesadel

Jer Duncanson

Bob Tollefson

Audrey Stabenow

Arlo Frank

Scott Griesbach

Tom Biasi

Ben Markl

Zenan Smolarek

Ann Hoffman

Phil Lyons

Martin Fritz

Amy McGovern

Rick Leverenz

DSF

UW-Stout Physical Plant

UW-Stout SLS

UW-Stout PP/SLS Linda Anderson

UW-Stout PP/SLS Linda Anderson

UW-Stout PP/SLS Linda Anderson

UW-Stout Housing

UW-Stout PP/SLS

UW-Stout Housing

UW-Stout PP

UW-Stout Housing

UW-Stout SLS

UW-Stout Housing

UW-Stout Housing

KJWW

Mike Lawless

Ryan Jester

Bob Novak

Dale Poynter

Tom Hanley

KJWW

KJWW

Southport Engineered Systems

SDS Architects

SDS Architects

1. Remodeling/Additions Options: Determined that Option A with a new toilet/shower room addition for each pod would be the preferred option. It would include two showers and two to three water closets per floor. In addition, requested one unisex toilet which would be handicapped accessible and have a shower similar to Hovlid. One per each cube or at least one per each floor counting all the areas together. Also, less bed loss with Option A.

2. Explain better what we mean by “Hovlid” when we are using as benchmark for comparison because not everyone knows what is planned for Hovlid.

3. Discussed opening up the core area of the various cubes, typically with a kitchenette as much glass as is possible, study area, counter, refrigerator and stove vented. There was some discussion about maybe relocating the new toilets to be adjacent to the lounges on HKMC and CKTO, will consider.

4. Confirmed that 240 was the maximum of beds that could be lost during any point in time and that is only for the spring term. They can’t take any beds out in the fall so the proposed winter/summer and summer/winter schedules will not work and the winter/winter is the only one that allows them to do what they need to do and keep the fall term in complete residential units. It is ok that overall schedule is longer with this schedule model as Campus won’t have enough money to pay for the whole process in seven years. Having beds come back on line in January doesn’t do anything for Campus

5. Some other items that were in general discussion is with the winter/winter schedule perhaps looking at adding the new construction, toilet rooms, everything that is happening outside during the first phase, if that would help move the schedule up. It was also discussed maybe doing the leftover one-third of North at the same time as the leftover one-third of South. It was pointed out that North has the worst technology within it even though it is the IT hub for the area. SDS needs to verify with Grady if that is the way the IT situation is going to remain but North will need to have new interior technology wiring but that may happen as a separate project not in this contract that the Campus will do.

Residence Hall Renovation Plan

UW-Stout

April 23, 2009

Page 2

6. Fleming and Wigen were next on the Campus’ own internal schedule. Fleming is in the worst shape and as soon as

Hovlid is done, it will be connected to the newest. Wigen newest on Campus.

7. The North campus could be split in terms of its schedule. Fleming and Wigen would not necessarily have to happen at the same time. It was undecided as to what McCalmont could do. Campus may consider use as housing eventually, exactly when needs to be determined by Campus.

8. Would it be possible for North or South to be done in total on a January to August time period. Decided that this should be possible if needed.

9. Considered Three Scenarios: a. Scenario A - Keeping JTC on line during Fleming remodel will be considered by Campus. May be related steam line capacity issue that may require $500K to rectify. JTC would remain open until into 2012 with 240 beds. Allows design in 2010 and then construction in 2011 and 2012 for Fleming and Wigen using the summer/winter model. The idea is that with some of the money that they have available, $6 million or so could go into Fleming and that could take care of everything on our scope list except for air conditioning for

Fleming. That would include fire protection, data, electrical, toilets, windows, HVAC generator, elevators might be deferred and then generally fixing up the rooms. Wigen would just be a minimum effort during this initial phase with just toilets and new windows. Wigen would then be finished up as the very last phase in the overall schedule of things. Fleming and Wigen would happen first and then start with CKTO and the rest of the South Campus halls. b. Scenario B - Building new cube adds on to North and South to allow swing space/eventual removal of one older hall. Each about 120 beds, or perhaps a two-cube unit between North and Price Commons keeping in mind that the Campus would prefer to manage two residence hall buildings at once and no more than that.

Presently North and South have three and those are problematic. c. Scenario C - Build new hall first to allow larger bed loss/speedier phasing/reduced escalation cost.

10. Funding to support the last two scenarios is unlikely.

11. With respect to Scenario A, the Campus has a $2 million place holder in the 2009-11 biennium for Fleming and Wigen and it is possible that amount could be changed but at least it is in place for somebody to look at.

12. Another general comment was the idea of eliminating the little first floor basement stairways (ie: HKMC) that pose problems with exiting in the winter and that sort of thing.

13. We discussed schedule for the remainder of this study and that we would send them a draft around the end of May or before and then a final report and presentation would happen in June.

END OF NOTES

This confirms and records our interpretation of the discussion that occurred and decisions reached during this meeting.

Unless notified, we will assume that the notes are complete and accurate.

Respectfully Submitted,

SDS ARCHITECTS, INC.

Dale Burgess Poynter

Principal/Architect

DBP/cmj

C: Participants

SDS File 0829.2.2

MEETING MINUTES

UW Stout – Dorm Study

KJWW #08.0614.00

DSF #08J2J

May 7, 2009

MEETING DATE:

LOCATION:

PRESENT:

ITEMS DISCUSSED:

May 5, 2009

UW Stout - General Services Room 139

Shirley Klebesadel – UWS

Terry Nichols – UWS

Mike Dodor – UWS

Joe Limke - KJWW

1.

2.

3.

4.

5.

Discussed campus standards for dorm study telecommunications.

North Hall is currently the south campus node for resident halls.

All dorms have dedicated voice and CATV feeds.

KJWW should plan on implementing the lasted technology since the schedule is long term.

All resident halls shall receive10 G infrastructure which will consist of single mode fiber optics,

OM3 50 micron multi-mode fiber and Category 6A horizontal cabling.

6.

7.

8.

9.

VOIP is a possibility in the future; therefore, design a universal cabling system.

Developing a node in HKMC would be ideal for new distribution for south campus.

North Hall would then be phased out.

KJWW to discuss in building distribution with Grady Richartz.

10. The only other building served from North Hall that is not in the current project is the Student

Center.

The foregoing constitutes our understanding of the matters discussed during the meeting. Participants are requested to advise KJWW Engineering Consultants in writing of any corrections or additions within ten (10) days of receiving this document.

Prepared by: Joseph M. Limke

JML/bnm

H:\08\08.0614.00\meetings\08J2J - UW Stout - Dorm Study 5-5-09 meeting minutes.docx

cc: All Present