Design of a Bridge Inspection System Ahsan Zulfiqar Miryam Cabieses

advertisement
Design of a Bridge Inspection System
(BIS) To Reduce Time & Cost
Ahsan Zulfiqar
Miryam Cabieses
Andrew Mikael
Namra Khan
Faculty Advisor:
Dr. Lance Sherry
Sponsor:
Dr. Lattanzi (GMU CEIE)
Department of Systems Engineering and Operations Research - 2014
1
Agenda
➢
➢
➢
➢
➢
➢
➢
➢
➢
Context
Problem Statement
Stakeholder Analysis
Need Statement
Scope
CONOPS
Proposed Solution
Simulation
Project Plan/Budget
2
Context
❖ The FHWA administers 607,380 bridges
➢ Average age is 42 years.
❖ Manual inspection process
➢ Every two years
■ 1-3 days to inspect one bridge
■ $4,500 per inspection
➢ Bi-Annual inspection cost is $2.7
billion for the U.S.
❖ Bridges infrastructure is deteriorating
➢ Increasing maintenance cost
➢ Increasing inspection process cycle
T. J. Ryan, J. E. Mann, Z. Chill, and B. Ott, “Bridge Inspector’s Reference Manual.” Federal Highway Administration, Dec-2012.
http://www.infrastructurereportcard.org/a/#p/bridges/conditions-and-capacity
3
Structurally Deficient Bridges
4
Bridge Types & Components
Arch:
Beam Bridge
Beam:
Cantilever:
Beam bridge inspection process
Suspension:
T. J. Ryan, J. E. Mann, Z. Chill, and B. Ott, “Bridge Inspector’s
http://www.ikonet.com/en/visualdictionary/transport-and-machinery/road-transport/
Reference Manual.” Federal Highway Administration, Dec-2012.
5
Main Components & Failure Types
Component
Deck
Material
Failure Types
Concrete Section loss
●
Roadway
Primary member damage (ex: collision…)
●
Side walk
Columns with spalling and rebar section loss
Substructure
Concrete Structure critical point (ex: Fracture
critical…)
●
Abutments
Severe deterioration
●
Piers
High stress area
Super-Structure
Metal
Cracking
●
Floor beams
Fatigue (less stiff)
●
Girders
Corrosion (Loss of mass)
●
Stringers
Missing connection
Truss
Metal
Bending (due to high stress)
6
Percentage to Failure Type
Material
Metal
Concrete
Failure Types
Inspection Method Percentage to cause
failure
Cracking
Visual/Physical
Fatigue (less stiff)
Physical
Corrosion (Loss of mass)
Visual/Physical 3.26%
Bending (over load)
Visual
Missing connection
Visual/Physical
Section loss
Visual/Physical 20.65%
High stress area
Visual/Physical
13.05%
2.17%
Structure crack at critical point (ex: Visual/Physical 16.3%
Fracture critical…)
Severe deterioration
Visual
Bridge Failure Rates, Consequences, and Predictive Trends by Wesley Cook
Utah State University
2.17%
Note: This is a Partial List of failure
percentages
7
General Inspection Procedures
http://www.fhwa.dot.gov/bridge/nbis/pubs/nhi12049.pdf
8
Beam Bridge Inspection Sequence
http://www.fhwa.dot.gov/bridge/nbis/pubs/nhi12049.pdf
9
Human Inspector Rating Criteria
10
Agenda
➢
➢
➢
➢
➢
➢
➢
➢
➢
Context
Problem Statement
Stakeholder Analysis
Need Statement
Scope
CONOPS
Proposed Solution
Simulation
Project Plan/Budget
11
Problem Statement
❖ The FHWA requires evaluation of all bridges
➢ Time consuming: 1-3 days for on-site inspection
➢ Requires closing lanes for the span of the inspection
■ Causing traffic congestion
➢ Bi-Annual inspection cost is $2.7 billion in the U.S.
➢ Hazardous for personnel
➢ Rating of inspection is subjective
❖ Increasing demand to inspect bridges
➢ Increase inspection cycle to 6 months - 1 year
12
Agenda
➢
➢
➢
➢
➢
➢
➢
➢
➢
Context
Problem Statement
Stakeholder Analysis
Need Statement
Scope
CONOPS
Proposed Solution
Simulation
Project Plan/Budget
13
Stakeholder Analysis
Lane Shutdown Time and Cost
Hires a consulting engineering company to design a bridge
+
+
Bid
s
Pro the p
vide roje
s th ct to
eb
ridg contra
ed
esig ctors
n
ay
ble er p
w
/Lo
Lia
bs
Jo
Hires them for safety inspection
Designs the Bridge
se
Funds the bridge
DOT
Inspection
Team
-
/
In
e
sp
cts
dg
bri
ts
s
Win
-/
Construction
Team
and
c
stru
n
o
c
b
the
ridg
/
e
Bridge Users
Bridge
+
th
id
eb
le
b
Lia
Liable
e
Interactions
Primary
Secondary
Tensions
Design
Engineer
Lo
Funds part of the bridge and take partial ownership
FHWA
Support
Oppose
Neutral
+
14
Agenda
➢
➢
➢
➢
➢
➢
➢
➢
➢
Context
Problem Statement
Stakeholder Analysis
Need Statement
Scope
CONOPS
Proposed Solution
Simulation
Project Plan/Budget
15
Need Statement
1. Reduce cost
a. Labor Cost
b. Traffic Control Cost
c. Equipment Cost
2. Increase the rate of inspection/detection/prevention of bridge
failures
3.
Remove safety risk for inspection personnel
4. Maintain/Increase Quality
a. Make inspection process objective
16
Agenda
➢
➢
➢
➢
➢
➢
➢
➢
➢
Context
Problem Statement
Stakeholder Analysis
Need Statement
Scope
CONOPS
Proposed Solution
Simulation
Project Plan/Budget
17
Scope
● District Department of
Transportation (DDOT)
Total Bridges: 199
Structurally Deficient Bridges: 121
● Theodore Roosevelt Bridge Beam
Bridge
•3,143 ft
•5 spans
•6 supports
•concrete & metal
•6 Lanes
•50 years
Above Water Inspection
http://www.fhwa.dot.gov/bridge/deficient.cfm
Theodore Roosevelt Bridge
18
Agenda
➢
➢
➢
➢
➢
➢
➢
➢
➢
Context
Problem Statement
Stakeholder Analysis
Need Statement
Scope
CONOPS
Proposed Solution
Simulation
Project Plan/Budget
19
Requirements
Mission Requirements
Design Goal
1.
BIS shall reduce cost
< $4,500
2.
BIS shall reduce time of inspection
4 hours
3.
BIS shall be safe for users
<16 failures (Range of 14 years)
4.
BIS shall be objective
Quantitative results
Functional Requirements
BIS shall Inspect all bridge components
BIS shall categorize the components according to the pass/fail criterion
The pass/fail criterion shall allow the components to be classified into a repaired, and/or
replaced category
BIS shall store the data acquired onto the ground base
20
Agenda
➢
➢
➢
➢
➢
➢
➢
➢
➢
Context
Problem Statement
Stakeholder Analysis
Need Statement
Scope
CONOPS
Proposed Solution
Simulation
Project Plan/Budget
21
Operational Concept of the proposed
system
Material
Type of failure
Inspection
Method
Metal
Cracking
Visual/Physical
Fatigue (less stiff)
Physical
Percentage
to cause
failure
Proposed Detection
Method
13.05%
Vibration Analysis
Concrete
Corrosion (Loss of mass)
Visual/Physical
Bending
Visual
Missing connection
Visual/Physical
Section loss
Visual/Physical
3.26%
Image Capturing device
20.65%
Structure crack at critical
point (ex: Fracture
critical…)
Visual/Physical
16.3%
Severe deterioration
Visual
2.17%
Bridge Failure Rates, Consequences, and Predictive Trends by Wesley Cook
Utah State University
Vibration Analysis
Image Capturing device
22
General Structure of Proposed
System
23
Structural Vibration
❖
❖
❖
❖
❖
Vibration is repetitive motion that can be
measured and observed in a structure.
➢ Unavoidable but deciphers what changes in
vibration mean.
Vibration analysis:
➢ Free vibration
➢ Forced vibration
➢ Sinusoidal vibration
➢ random vibration
Helps characterize the behavior of the structure
Factors that affect vibration are characterized by
the following parameters:
➢ mass
➢ stiffness
➢ damping
knowing these values can predict how structure
will respond to vibration
24
Functional Design for Structural
Vibration Analysis
25
How Accelerometers
Work
❖ Structural vibrations can be measured by electronic sensors
that convert vibration motion into electrical signals.
❖ Motion Sensors/Accelerometers
❖ Based on Piezoelectric Effect
pcb.com
26
BIS Design Alternatives
Time
Manual
Inspection
Cost
Safety
Reliability
Actual inspection (1-3 days)
$4500/inspection
Traffic,
Animals,
Poison Ivy,
Drowning
Mounted
Sensors with
cables
Total time to perform
Inspection (simulation)
Acquisition Cost: $51,000
Concurrent Cost: $450
Not
Hazards for
inspectors
≥ 95%
UAV + Mounted
Sensors with
low-power
communication
systems
Total time to perform
Inspection (simulation)
Acquisition Cost: $75,000
Not
Hazards for
inspectors
≥ 95%
Concurrent Cost: $1000/year
95%
27
Design Alternatives
Design Alternatives
Manual
Pros
●
●
Cons
Current
95% reliable
●
●
●
●
●
Sensor + Cables
●
●
●
UAV + Communication system + Sensors
●
●
●
●
Easy
installation
Fast power
supply
Fast data
transmission
●
Convenient
Safe
Quick-real
time data
Within Range
●
●
●
●
Labor cost
Time
consuming
Not efficient
Subjective
Hazardous
Requires many
accessories
Acquiring new
skills
Complex
Security and
integrity of data
Acquiring new
skills
28
Design Alternative 2: Sensor +
Cables
29
Design Alternative 3: Sensors +
UAV + Communication System
●
●
●
Antennas
Batteries
Memory
30
Design Alternative 3: Sensors +
UAV + Communication System
•
•
•
Wireless Sensor Network
Monitor physical or environmental conditions
Pass their data to a main location.
•Built of nodes
–point to point network
–advanced multi hop wireless mesh network
•Components
–Radio transceiver with antenna
–Microcontroller
–Energy source
searchdatacenter.techtarget.com
31
Agenda
➢
➢
➢
➢
➢
➢
➢
➢
➢
Context
Problem Statement
Stakeholder Analysis
Need Statement
Scope
CONOPS
Proposed Solution
Simulation
Project Plan/Budget
32
Method of Analysis
Forces
Vibration Analysis
Model
Number of
Accelerometers
Life -Cycle
Cost Model
Load Capacity
●
●
Bridge Parameters
●
Manual
Sensors +
Cables
Sensors +
UAV + Comm
Quality /
Performance
Utility
Utility
(weights)
Cost
33
Vibration Analysis Model
Output
Input
●
●
●
●
●
●
●
●
Number of Lanes
Mass/Velocity of Cars
Fluctuation in
Acceleration
External Vibration
Forces of Structure
Min/Max Load Capacity
Length
Time Span
Vibration
Analysis
Model
Characterize the
behavior and
performance of
structure
Natural frequency
Less stiffness
34
Vibration Analysis Model (Cont.)
35
DOE for Vibration Analysis
Input
Length
# of Lanes
4
3,200 ft
6
8
L : Length (3,200 ft)
l : # of lanes (4,6,8)
m : mass of car
Output
Value of
(m)
Value (v)
S
L, M, H
f(L,l,m,k,c)
M
L, M, H
f(L,l,m,k,c)
L
L, M, H
f(L,l,m,k,c)
S
L, M, H
f(L,l,m,k,c)
M
L, M, H
f(L,l,m,k,c)
L
L, M, H
f(L,l,m,k,c)
S
L, M, H
f(L,l,m,k,c)
M
L, M, H
f(L,l,m,k,c)
L
L, M, H
f(L,l,m,k,c)
Value of (k)
k : Stiffness
c : Damping effect
v : velocity
Value of (c)
Freq. Response
36
Life-Cycle Cost Model
Manual
Mounted
Sensors with
cables
UAV + Mounted
Sensors with low
power com.
system
-
$51,000
$75,000
Concurrent Cost
$4,500/inspection
$450/year
$1000/year
Indirect Cost
-
$400/person
$800/person
Total Cost
(50 years)
$24.8 Million
$2.5 Million
$5.6 Million
Acquisition Cost
Assumptions:
Accelerometers use are specific for bridge vibrations (longer life span)
Maintenance (testing the equipment: giving known input are receiving predicted output)
Calculations were made having 6 lanes each direction
Total Cost of BI for DDOT [199 Bridges (SD -> inspected annually)]
Bridge Diagnostics, Inc.
37
Multi-Attribute Utility Theory (MAUT)
38
Agenda
➢
➢
➢
➢
➢
➢
➢
➢
➢
Context
Problem Statement
Stakeholder Analysis
Need Statement
Scope
CONOPS
Proposed Solution
Simulation
Project Plan/Budget
39
Work Breakdown Structure
(WBS)
40
Project Plan/Critical Path
41
Project Budget
42
Risk Assessment
Risk Description
Mitigation Strategy
Data collection:
● If we lack quantitative data, then we have to
make assumptions.
●
Supplement similar data from similar
studies.
Reliability:
● Not meeting the current reliability of bridge
inspection with the proposed solutions.
●
Use the criteria currently used to be able to
meet the current reliability of the inspection
process.
Simulation:
● Critical task to measure if our alternative
designs are accurate.
● Failure to complete on time could delay the
whole project.
●
Start early and try to supplement more time
as necessary.
Work through winter break
Stakeholders:
● Unable to fully understand the objectives of
the stakeholders, and unable to arrange
further contact to obtain data.
●
●
Initiate contact with our sponsor and
VDOT/FHWA until we obtain a response
with the requested information.
43
Questions
44
Download