Design of a Bridge Inspection System (BIS) To Reduce Time & Cost Ahsan Zulfiqar Miryam Cabieses Andrew Mikael Namra Khan Faculty Advisor: Dr. Lance Sherry Sponsor: Dr. Lattanzi (GMU CEIE) Department of Systems Engineering and Operations Research - 2014 1 Agenda ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ Context Problem Statement Stakeholder Analysis Need Statement Scope CONOPS Proposed Solution Simulation Project Plan/Budget 2 Context ❖ The FHWA administers 607,380 bridges ➢ Average age is 42 years. ❖ Manual inspection process ➢ Every two years ■ 1-3 days to inspect one bridge ■ $4,500 per inspection ➢ Bi-Annual inspection cost is $2.7 billion for the U.S. ❖ Bridges infrastructure is deteriorating ➢ Increasing maintenance cost ➢ Increasing inspection process cycle T. J. Ryan, J. E. Mann, Z. Chill, and B. Ott, “Bridge Inspector’s Reference Manual.” Federal Highway Administration, Dec-2012. http://www.infrastructurereportcard.org/a/#p/bridges/conditions-and-capacity 3 Structurally Deficient Bridges 4 Bridge Types & Components Arch: Beam Bridge Beam: Cantilever: Beam bridge inspection process Suspension: T. J. Ryan, J. E. Mann, Z. Chill, and B. Ott, “Bridge Inspector’s http://www.ikonet.com/en/visualdictionary/transport-and-machinery/road-transport/ Reference Manual.” Federal Highway Administration, Dec-2012. 5 Main Components & Failure Types Component Deck Material Failure Types Concrete Section loss ● Roadway Primary member damage (ex: collision…) ● Side walk Columns with spalling and rebar section loss Substructure Concrete Structure critical point (ex: Fracture critical…) ● Abutments Severe deterioration ● Piers High stress area Super-Structure Metal Cracking ● Floor beams Fatigue (less stiff) ● Girders Corrosion (Loss of mass) ● Stringers Missing connection Truss Metal Bending (due to high stress) 6 Percentage to Failure Type Material Metal Concrete Failure Types Inspection Method Percentage to cause failure Cracking Visual/Physical Fatigue (less stiff) Physical Corrosion (Loss of mass) Visual/Physical 3.26% Bending (over load) Visual Missing connection Visual/Physical Section loss Visual/Physical 20.65% High stress area Visual/Physical 13.05% 2.17% Structure crack at critical point (ex: Visual/Physical 16.3% Fracture critical…) Severe deterioration Visual Bridge Failure Rates, Consequences, and Predictive Trends by Wesley Cook Utah State University 2.17% Note: This is a Partial List of failure percentages 7 General Inspection Procedures http://www.fhwa.dot.gov/bridge/nbis/pubs/nhi12049.pdf 8 Beam Bridge Inspection Sequence http://www.fhwa.dot.gov/bridge/nbis/pubs/nhi12049.pdf 9 Human Inspector Rating Criteria 10 Agenda ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ Context Problem Statement Stakeholder Analysis Need Statement Scope CONOPS Proposed Solution Simulation Project Plan/Budget 11 Problem Statement ❖ The FHWA requires evaluation of all bridges ➢ Time consuming: 1-3 days for on-site inspection ➢ Requires closing lanes for the span of the inspection ■ Causing traffic congestion ➢ Bi-Annual inspection cost is $2.7 billion in the U.S. ➢ Hazardous for personnel ➢ Rating of inspection is subjective ❖ Increasing demand to inspect bridges ➢ Increase inspection cycle to 6 months - 1 year 12 Agenda ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ Context Problem Statement Stakeholder Analysis Need Statement Scope CONOPS Proposed Solution Simulation Project Plan/Budget 13 Stakeholder Analysis Lane Shutdown Time and Cost Hires a consulting engineering company to design a bridge + + Bid s Pro the p vide roje s th ct to eb ridg contra ed esig ctors n ay ble er p w /Lo Lia bs Jo Hires them for safety inspection Designs the Bridge se Funds the bridge DOT Inspection Team - / In e sp cts dg bri ts s Win -/ Construction Team and c stru n o c b the ridg / e Bridge Users Bridge + th id eb le b Lia Liable e Interactions Primary Secondary Tensions Design Engineer Lo Funds part of the bridge and take partial ownership FHWA Support Oppose Neutral + 14 Agenda ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ Context Problem Statement Stakeholder Analysis Need Statement Scope CONOPS Proposed Solution Simulation Project Plan/Budget 15 Need Statement 1. Reduce cost a. Labor Cost b. Traffic Control Cost c. Equipment Cost 2. Increase the rate of inspection/detection/prevention of bridge failures 3. Remove safety risk for inspection personnel 4. Maintain/Increase Quality a. Make inspection process objective 16 Agenda ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ Context Problem Statement Stakeholder Analysis Need Statement Scope CONOPS Proposed Solution Simulation Project Plan/Budget 17 Scope ● District Department of Transportation (DDOT) Total Bridges: 199 Structurally Deficient Bridges: 121 ● Theodore Roosevelt Bridge Beam Bridge •3,143 ft •5 spans •6 supports •concrete & metal •6 Lanes •50 years Above Water Inspection http://www.fhwa.dot.gov/bridge/deficient.cfm Theodore Roosevelt Bridge 18 Agenda ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ Context Problem Statement Stakeholder Analysis Need Statement Scope CONOPS Proposed Solution Simulation Project Plan/Budget 19 Requirements Mission Requirements Design Goal 1. BIS shall reduce cost < $4,500 2. BIS shall reduce time of inspection 4 hours 3. BIS shall be safe for users <16 failures (Range of 14 years) 4. BIS shall be objective Quantitative results Functional Requirements BIS shall Inspect all bridge components BIS shall categorize the components according to the pass/fail criterion The pass/fail criterion shall allow the components to be classified into a repaired, and/or replaced category BIS shall store the data acquired onto the ground base 20 Agenda ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ Context Problem Statement Stakeholder Analysis Need Statement Scope CONOPS Proposed Solution Simulation Project Plan/Budget 21 Operational Concept of the proposed system Material Type of failure Inspection Method Metal Cracking Visual/Physical Fatigue (less stiff) Physical Percentage to cause failure Proposed Detection Method 13.05% Vibration Analysis Concrete Corrosion (Loss of mass) Visual/Physical Bending Visual Missing connection Visual/Physical Section loss Visual/Physical 3.26% Image Capturing device 20.65% Structure crack at critical point (ex: Fracture critical…) Visual/Physical 16.3% Severe deterioration Visual 2.17% Bridge Failure Rates, Consequences, and Predictive Trends by Wesley Cook Utah State University Vibration Analysis Image Capturing device 22 General Structure of Proposed System 23 Structural Vibration ❖ ❖ ❖ ❖ ❖ Vibration is repetitive motion that can be measured and observed in a structure. ➢ Unavoidable but deciphers what changes in vibration mean. Vibration analysis: ➢ Free vibration ➢ Forced vibration ➢ Sinusoidal vibration ➢ random vibration Helps characterize the behavior of the structure Factors that affect vibration are characterized by the following parameters: ➢ mass ➢ stiffness ➢ damping knowing these values can predict how structure will respond to vibration 24 Functional Design for Structural Vibration Analysis 25 How Accelerometers Work ❖ Structural vibrations can be measured by electronic sensors that convert vibration motion into electrical signals. ❖ Motion Sensors/Accelerometers ❖ Based on Piezoelectric Effect pcb.com 26 BIS Design Alternatives Time Manual Inspection Cost Safety Reliability Actual inspection (1-3 days) $4500/inspection Traffic, Animals, Poison Ivy, Drowning Mounted Sensors with cables Total time to perform Inspection (simulation) Acquisition Cost: $51,000 Concurrent Cost: $450 Not Hazards for inspectors ≥ 95% UAV + Mounted Sensors with low-power communication systems Total time to perform Inspection (simulation) Acquisition Cost: $75,000 Not Hazards for inspectors ≥ 95% Concurrent Cost: $1000/year 95% 27 Design Alternatives Design Alternatives Manual Pros ● ● Cons Current 95% reliable ● ● ● ● ● Sensor + Cables ● ● ● UAV + Communication system + Sensors ● ● ● ● Easy installation Fast power supply Fast data transmission ● Convenient Safe Quick-real time data Within Range ● ● ● ● Labor cost Time consuming Not efficient Subjective Hazardous Requires many accessories Acquiring new skills Complex Security and integrity of data Acquiring new skills 28 Design Alternative 2: Sensor + Cables 29 Design Alternative 3: Sensors + UAV + Communication System ● ● ● Antennas Batteries Memory 30 Design Alternative 3: Sensors + UAV + Communication System • • • Wireless Sensor Network Monitor physical or environmental conditions Pass their data to a main location. •Built of nodes –point to point network –advanced multi hop wireless mesh network •Components –Radio transceiver with antenna –Microcontroller –Energy source searchdatacenter.techtarget.com 31 Agenda ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ Context Problem Statement Stakeholder Analysis Need Statement Scope CONOPS Proposed Solution Simulation Project Plan/Budget 32 Method of Analysis Forces Vibration Analysis Model Number of Accelerometers Life -Cycle Cost Model Load Capacity ● ● Bridge Parameters ● Manual Sensors + Cables Sensors + UAV + Comm Quality / Performance Utility Utility (weights) Cost 33 Vibration Analysis Model Output Input ● ● ● ● ● ● ● ● Number of Lanes Mass/Velocity of Cars Fluctuation in Acceleration External Vibration Forces of Structure Min/Max Load Capacity Length Time Span Vibration Analysis Model Characterize the behavior and performance of structure Natural frequency Less stiffness 34 Vibration Analysis Model (Cont.) 35 DOE for Vibration Analysis Input Length # of Lanes 4 3,200 ft 6 8 L : Length (3,200 ft) l : # of lanes (4,6,8) m : mass of car Output Value of (m) Value (v) S L, M, H f(L,l,m,k,c) M L, M, H f(L,l,m,k,c) L L, M, H f(L,l,m,k,c) S L, M, H f(L,l,m,k,c) M L, M, H f(L,l,m,k,c) L L, M, H f(L,l,m,k,c) S L, M, H f(L,l,m,k,c) M L, M, H f(L,l,m,k,c) L L, M, H f(L,l,m,k,c) Value of (k) k : Stiffness c : Damping effect v : velocity Value of (c) Freq. Response 36 Life-Cycle Cost Model Manual Mounted Sensors with cables UAV + Mounted Sensors with low power com. system - $51,000 $75,000 Concurrent Cost $4,500/inspection $450/year $1000/year Indirect Cost - $400/person $800/person Total Cost (50 years) $24.8 Million $2.5 Million $5.6 Million Acquisition Cost Assumptions: Accelerometers use are specific for bridge vibrations (longer life span) Maintenance (testing the equipment: giving known input are receiving predicted output) Calculations were made having 6 lanes each direction Total Cost of BI for DDOT [199 Bridges (SD -> inspected annually)] Bridge Diagnostics, Inc. 37 Multi-Attribute Utility Theory (MAUT) 38 Agenda ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ Context Problem Statement Stakeholder Analysis Need Statement Scope CONOPS Proposed Solution Simulation Project Plan/Budget 39 Work Breakdown Structure (WBS) 40 Project Plan/Critical Path 41 Project Budget 42 Risk Assessment Risk Description Mitigation Strategy Data collection: ● If we lack quantitative data, then we have to make assumptions. ● Supplement similar data from similar studies. Reliability: ● Not meeting the current reliability of bridge inspection with the proposed solutions. ● Use the criteria currently used to be able to meet the current reliability of the inspection process. Simulation: ● Critical task to measure if our alternative designs are accurate. ● Failure to complete on time could delay the whole project. ● Start early and try to supplement more time as necessary. Work through winter break Stakeholders: ● Unable to fully understand the objectives of the stakeholders, and unable to arrange further contact to obtain data. ● ● Initiate contact with our sponsor and VDOT/FHWA until we obtain a response with the requested information. 43 Questions 44