FOREST SERVICE HANDBOOK
SANDY, OREGON
FSH 2409.22 – TIMBER APPRAISAL
CHAPTER 2 – DEVELOPMENT OF APPRAISAL DATA
Mt. Hood Supplement No.: 2409.22-2001-1
Effective Date: May 11, 2001
Duration: Effective until superseded or removed
Approved: GARY L. LARSEN
Forest Supervisor
Date Approved: 5/07/2001
Posting Instructions: Supplements are numbered consecutively by Handbook number and
calendar year. Post by document name. Remove entire document and replace with this
supplement. Retain this transmittal as the first page of this document.
New Document(s):
Superseded Document(s):
(Last supplement was Mt. Hood
Supplement No.62 June 1998)
Chapter 2
e. (5)
415.55—1,---3
(MH Supp. No. 61 July 1995)
5 Pages
4 Pages
Digest:
e. (5)
Updates Road Maintenance rates for timber sale appraisal. Converts
rates from MBF - Mile to CCF - Mile. Increases those rates in by the
average consumer index since 1995.
MH SUPPLEMENT:2409.22-2001-1
EFFECTIVE DATE: 5/11/01
DURATION: Effective until superseded or removed
e(5)
Page 2 of 5
FSH 2409.22 - TIMBER APPRAISAL
CHAPTER 2 – DEVELOPMENT OF APPRAISAL DATA
e. Adjustment for Sale Characteristics.
(5) Sale Operational Costs
ROAD MAINTENANCE.
Road Maintenance Cost Guide
1. Table I:
Mandatory deposit and user maintained rates for timber haul includes:
A. Recurrent traffic and non-traffic generated maintenance, ie. blading,
spot subgrade repair, spot surface replacement, brushing, logging out,
culvert–ditch maintenance, slough-slide removal, etc.
B. Operational maintenance, ie. pavement markings, signs, traffic controls,
etc.
In addition to the above, mandatory deposit for timber haul includes:
D. Chip seals, surface treatments, bridges, etc.
E. Overhead - 29%.
MAINTENANCE COST PER CCF MILE
MAINTENANCE SURFACE
RECREATION SHARE
LEVEL
TYPE
LOW
MEDIUM
2
NAT & AGG 0.16
/////
2
AC & ST
0.35
/////
3
NAT & AGG / / / /
/////
3
AC & ST
////
0.68
4
NAT & AGG / / / /
/////
4&5
AC & ST
////
0.79
Rd 46
AC
////
0.79
HIGH
/////
/////
0.53
0.52
0.82
0.58
////
MH SUPPLEMENT:2409.22-2001-1
EFFECTIVE DATE: 5/11/01
DURATION: Effective until superseded or removed
e(5)
Page 3 of 5
FSH 2409.22 - TIMBER APPRAISAL
CHAPTER 2 – DEVELOPMENT OF APPRAISAL DATA
2. Table II: Rock haul. Same elements included for timber haul are included in the following
Table.
MAINTENANCE
LEVEL
2
2
3
3
4
4
MAINTENANCE COST PER C.Y. MILE
SURFACE
RECREATION SHARE
TYPE
LOW
MEDIUM
NAT & AGG 0.14
/////
AC & ST
0.30
/////
NAT & AGG / / / /
/////
AC & ST
////
0.59
NAT & AGG / / / /
/////
AC & ST
////
0.79
HIGH
/////
/////
0.45
0.45
0.72
0.50
3. Table III: Rock haul and any other type of haul that can be measured by the
ton. Same elements included for timber haul are included in the
following table.
MAINTENANCE COST PER TON MILE
MAINTENANCE SURFACE
RECREATION SHARE
LEVEL
TYPE
LOW
MEDIUM
2
NAT & AGG 0.10
/////
2
AC & ST
0.22
/////
3
NAT & AGG / / / /
/////
3
AC & ST
////
0.42
4
NAT & AGG / / / /
/////
4
AC & ST
////
0.48
HIGH
/////
/////
0.32
0.32
0.51
0.36
MH SUPPLEMENT:2409.22-2001-1
EFFECTIVE DATE: 5/11/01
DURATION: Effective until superseded or removed
e(5)
Page 4 of 5
FSH 2409.22 - TIMBER APPRAISAL
CHAPTER 2 – DEVELOPMENT OF APPRAISAL DATA
4. Table IV: Water haul. Same elements included for timber haul are included in the
following table.
MAINTENANCE COST PER M GAL MILE
MAINTENANCE SURFACE
RECREATION SHARE
LEVEL
TYPE
LOW
MEDIUM
2
NAT & AGG 0.42
/////
2
AC & ST
0.88
/////
3
NAT & AGG / / / /
/////
3
AC & ST
////
1.67
4
NAT & AGG / / / /
/////
4
AC & ST
////
1.90
HIGH
/////
/////
1.30
1.30
2.04
1.44
5. All Maintenance Level 3, 4, 5, and Asphalt Cement and Surface Treatment
Maintenance Level 2 are mandatory deposit.
6.
All Native and Aggregate Maintenance Level 2 may be accomplished by the
user or by cooperative deposits.
7.
Dust abatement allowance - $1750.00 per lane-mile
INSTRUCTIONS
1. Districts are responsible for furnishing the following information to the Tech
Centers:
a. Sale area map
b. Timber Volume
2. Engineering Departments are responsible for furnishing the following information
to the Districts:
a. Road maintenance appraisal
b. All appropriate “C” provisions
MH SUPPLEMENT:2409.22-2001-1
EFFECTIVE DATE: 5/11/01
DURATION: Effective until superseded or removed
e(5)
Page 5 of 5
FSH 2409.22 - TIMBER APPRAISAL
CHAPTER 2 – DEVELOPMENT OF APPRAISAL DATA
3. Recurrent Maintenance – Includes those activities which are anticipated to be needed
on a continuing basis on all roads under Forest Service jurisdiction. Recurrent maintenance
may be accomplished by the user or by cooperative deposits.
4. Subtract 29% from unit costs in Tables I thru IV for Purchaser performed maintenance.
5. Road maintenance rates listed are based on average road maintenance requirements, the
Engineer has the latitude to adjust the rates if the situation warrants, such variation must be
justified and documented in the appraisal.