51.2 - Construction Cost Adjustment (B/BT5.25)

advertisement
:
2409.15,51.2
Page 1 of 3
51.2 - Construction Cost Adjustment (B/BT5.25)
1. All Specified Road and Bridge construction cost adjustments shall be forwarded using
Form GP-7720-1 as a cover sheet (Exhibit 1). When the preparer/reviewer is other than the
inspector/ER, the preprinted title shall be crossed out and the appropriate title entered by the
person(s) preparing/reviewing the cost adjustment.
2. All supporting documents, including the cost estimate worksheets, will be included in
the cost adjustment packet. Revised plans and contract pages will also be included in the
adjustment packet.
3. All construction cost adjustments made under provisions, other than those listed below
such as B/BT 8.32 contract modification and FSSS 106.04 (Forest Service Standard
Specifications for Roads and Bridges), shall be documented using Form GP-2450-39 (Exhibit 2).
GP SUPPLEMENT 2409.15-92-1
EFFECTIVE DATE: February 15, 1992
DURATION: Effective until superseded or removed
2409.15,51.2
Page 2 of 3
FSH 2409.15 – TIMBER SALE ADMINISTRATION HANDBOOK
CHAPTER 50 – SPECIFIED TRANSPORTATION FACILITIES
EXHIBIT 1
GP-7720-1 (1/89)
CONSTRUCTION COST ADJUSTMENTS
COVER SHEET
CONTRACT NAME
CONTRACT NUMBER
Project Name/Number
Change Number
Number of Pages
X = SIGNATURE REQUIRED
X
Prepared by (Inspector)
Date
 = ER/COR reviews packet for accuracy,
including calculations.
X
Reviewed by (ER/COR)
Date
 = ZONE ENGINEER will check SO-E block
for review when change exceeds Zone Engineer’s
signing authority and for all Trails/Facilities
changes.
X
Recommended by (Zone E)
Date
 = FSR signs for Timber Sale changes. FSR
reviews for contractual correctness, insures all
necessary material is included, and coordination
as outlined in FSH 2409.15 has been
accomplished.
Reviewed by (FSR)
Date
 = DR/MM signs for changes that affect
resources.
Recommended by (DR/MM)
Date
Recommended by (SO-E)
Date
Approved by (CO)
Date
X
GP SUPPLEMENT 2409.15-92-1
EFFECTIVE DATE: February 15, 1992
DURATION: Effective until superseded or removed
2409.15,51.2
Page 3 of 3
FSH 2409.15 – TIMBER SALE ADMINISTRATION HANDBOOK
CHAPTER 50 – SPECIFIED TRANSPORTATION FACILITIES
EXHIBIT 2
GP 2450-39 (8/88)
CONSTRUCTION COST ADJUSTMENT
FOR SPECIFIED ROADS
Sale Name
Contract No.
Purchaser
Road Name and No.
CHANGE NO.
Project Segment: From Sta.
To Sta.
Description of Change:
Revised Quantities and Purchaser Credit Affected by Change
Item
No.
Description
Unit
Previous
Quantities
Change
Revised
(+) or (-)
Total
Unit Price
Original
Revised
Adjustments
(+) or (-)
Purchaser
Credit Limit
Prev- Revised
ious
I hereby acknowledge this change.
Purchaser
Signature
Title
Date
Prepared by
Approved by
Title
Title
Date
Date
Recommended by
Date
Title
Engineering Representative
Reviewed by
Date
Title
Forest Service Representative
Contracting Officer