: 2409.15,51.2 Page 1 of 3 51.2 - Construction Cost Adjustment (B/BT5.25) 1. All Specified Road and Bridge construction cost adjustments shall be forwarded using Form GP-7720-1 as a cover sheet (Exhibit 1). When the preparer/reviewer is other than the inspector/ER, the preprinted title shall be crossed out and the appropriate title entered by the person(s) preparing/reviewing the cost adjustment. 2. All supporting documents, including the cost estimate worksheets, will be included in the cost adjustment packet. Revised plans and contract pages will also be included in the adjustment packet. 3. All construction cost adjustments made under provisions, other than those listed below such as B/BT 8.32 contract modification and FSSS 106.04 (Forest Service Standard Specifications for Roads and Bridges), shall be documented using Form GP-2450-39 (Exhibit 2). GP SUPPLEMENT 2409.15-92-1 EFFECTIVE DATE: February 15, 1992 DURATION: Effective until superseded or removed 2409.15,51.2 Page 2 of 3 FSH 2409.15 – TIMBER SALE ADMINISTRATION HANDBOOK CHAPTER 50 – SPECIFIED TRANSPORTATION FACILITIES EXHIBIT 1 GP-7720-1 (1/89) CONSTRUCTION COST ADJUSTMENTS COVER SHEET CONTRACT NAME CONTRACT NUMBER Project Name/Number Change Number Number of Pages X = SIGNATURE REQUIRED X Prepared by (Inspector) Date = ER/COR reviews packet for accuracy, including calculations. X Reviewed by (ER/COR) Date = ZONE ENGINEER will check SO-E block for review when change exceeds Zone Engineer’s signing authority and for all Trails/Facilities changes. X Recommended by (Zone E) Date = FSR signs for Timber Sale changes. FSR reviews for contractual correctness, insures all necessary material is included, and coordination as outlined in FSH 2409.15 has been accomplished. Reviewed by (FSR) Date = DR/MM signs for changes that affect resources. Recommended by (DR/MM) Date Recommended by (SO-E) Date Approved by (CO) Date X GP SUPPLEMENT 2409.15-92-1 EFFECTIVE DATE: February 15, 1992 DURATION: Effective until superseded or removed 2409.15,51.2 Page 3 of 3 FSH 2409.15 – TIMBER SALE ADMINISTRATION HANDBOOK CHAPTER 50 – SPECIFIED TRANSPORTATION FACILITIES EXHIBIT 2 GP 2450-39 (8/88) CONSTRUCTION COST ADJUSTMENT FOR SPECIFIED ROADS Sale Name Contract No. Purchaser Road Name and No. CHANGE NO. Project Segment: From Sta. To Sta. Description of Change: Revised Quantities and Purchaser Credit Affected by Change Item No. Description Unit Previous Quantities Change Revised (+) or (-) Total Unit Price Original Revised Adjustments (+) or (-) Purchaser Credit Limit Prev- Revised ious I hereby acknowledge this change. Purchaser Signature Title Date Prepared by Approved by Title Title Date Date Recommended by Date Title Engineering Representative Reviewed by Date Title Forest Service Representative Contracting Officer