Cricket Valley Energy, LLC - Cricket Valley Transmission Upgrade

advertisement
Public Service Commission
Public Statement Hearing
Informational Forum
August 4, 2014
Project Team
 Cricket Valley Energy (CVE)
– Developer of Cricket Valley Energy Center, a fully
permitted $1.4 billion natural gas-fueled,
high-efficiency, combined-cycle power generation
facility in the Town of Dover/Dutchess County
– Subsidiary of Advanced Power, NA
 Epsilon Associates, Inc.
– Project environmental consultant
 DiGioia Gray & Associates
– Project engineer
 Arch Street Communications
– Public information and outreach
2
Agenda











Project Overview
Location
Scope
Objectives
Design
Hypothetical Alternative Route
Simulated Views
Article VII Review Steps
Construction
Public Involvement
Topics of Interest
3
Project Overview
 CVE has been required by New York Independent System
Operator (NYISO) to increase transmission capacity,
redundancy, and operational capabilities by funding and
installing a transmission line in the existing 14.6-mile
Right-of-Way (ROW) between CVE in Dover and the
Con Edison substation in Pleasant Valley. CVE will also
reconductor a 3.4-mile segment of the existing
transmission line in the same ROW between the CVE
substation and the NY-CT state line.
 NOT part of any of the following transmission line
projects: NY Transco Edic to Pleasant Valley;
NEXTERA New Scotland to Pleasant Valley; North
American Transmission; or Boundless Energy
Transmission.
4
Project Location
5
Project Scope
 Install a new 14.6-mile 345 kV transmission line within the
existing Con Edison ROW between CVE in Dover and
Con Edison substation in Pleasant Valley
 Re-conductor existing line #398 between the Project site
the NY/CT border
 Upgrade the Pleasant Valley substation (within existing
footprint) protection and communication infrastructure
 Prioritize local labor for the Project
 Average 40-60 workers for line construction
 Approximately 20 worker crew for re-conductoring
6
Project Objectives
 Ensure the reliability, stability, operability, and transfer
limits of the transmission system are maintained with the
connection to Cricket Valley Energy Center
 Ensure minimal disruption to the environment and
neighboring communities by locating the new transmission
line inside the existing 250-foot-wide Con Edison ROW
 Privately fund the $55 million infrastructure investment
 Transfer ownership to Con Edison upon completion
7
Project Design
 New line:
 State-of-the-art steel monopoles
 Delta configuration
 Generally follows current spacing of existing lattice towers
 New conductors:
 Bundled, “Mallard” Aluminum Conductor Steel-Supported
(ACSS) cables
 Selected for rating/line capacity, cost, line losses and other
performance factors
8
Design Considerations
 ROW land-use and environmental-base mapping in
accordance with the US Fish and Wildlife Service and
NYS Department of Environmental Conservation policies
 Field surveys and time-of-year restrictions for protected
and sensitive species
 Invasive species, archaeological, and historic surveys
 Wetlands delineation with location adjustments to avoid
wetlands and other sensitive areas
 Community input
9
Hypothetical Alternative Route
10
Hypothetical Alternative Route
 Central Hudson 115 kV
 Significant impact to property owners
 Requires 7 miles of new transmission right-of-way
 Significant environmental impacts
 Swamp River
 Habitat, natural environment, wetland
 Requires 20-mile line vs. 14.6-mile line
 Requires 13 miles of expansion of the Central Hudson
ROW to accommodate 345 kV line
11
Simulated View
Town of Dover
12
Simulated View
Town of LaGrange
13
Simulated View
Town of Union Vale
14
Simulated View
Town of Pleasant Valley
15
Simulated View-Taconic Pky
16
Article VII Review Steps
 December 30, 2013: submission of Article VII application;
copies distributed to area libraries
 August 4, 2014: Public Statement Hearing in project area
 Development of joint proposal: Public Service Commission
(PSC) staff with input from interested parties
 Recommendations by Administrative Law Judge (ALJ)
 PSC Hearing and Determination in Albany
 Certificate of Environmental Compatibility and Public Need
17
Construction
 Total expected timeframe for Project completion: 13-24
months
 Construction activity for each structure is estimated to last
approximately 2 weeks
 Pre-Construction Steps:
 Environmental Management and Construction Plan
approved by Department of Public Service (DPS)
 Manage ROW in accordance with Con Edison’s Vegetation
Management Plan (VMP)
 Finalize survey to identify sensitive areas, clearing areas,
and structure locations
18
Construction Process
 Construction Steps:
 Establish laydown/staging areas—one primary area +/- 20
acres; additional storage areas, 2-3 acres each
 Place construction matting where required for temporary
access across wetlands
 Establish structure foundations (rock anchors, rock micropiles, conventional)
 Set structures; install davits, insulators, and stringing blocks;
string conductors
 Re-grade and restore
19
Public Involvement to Date
 December 2013
 Public/Legal notices, Poughkeepsie Journal
 Letters to Town Supervisors, County Executive
 Letters to property owners abutting ROW
 March 2014:
 Launched CricketValleyTransmission.com
 Published Winter Issue, CVE Update Newsletter, distributed
6785 copies
 Posted Public Involvement Plan on website
 Launched email subscription sign up—now more than 350
subscribers
20
Public Involvement to Date
 May/June 2014:
 Presentation to Town Boards—Dover, Pleasant Valley,
LaGrange, Union Vale
 Held 4 public information meetings—Dover, Pleasant Valley,
LaGrange, Union Vale
 Promoted via website, postcards, press release, posters,
advertisement, posting on town websites
 August 2014
 Two Advisory Working Groups scheduled:
 August 26 - Community Outreach Office,
Dover Plains, NY
 August 27 - Pleasant Valley Town Hall
21
Public Involvement Media
 Media outreach:
- Hudson Valley Business
Journal
- Hudson Valley Press
- Hudson Valley Reporter
- Mid Hudson News
- Northern Dutchess News
- Southern Dutchess News
- Poughkeepsie Journal
- Putnam County News
- Harlem Valley News
- Millbrook Independent
- Millerton News
- WAMC Radio
Advertisements
- Poughkeepsie Journal
- Northern Dutchess News
- Southern Dutchess News
- The Millbrook
Independent
- Hudson Valley News
- PennySaver
22
Topics of interest
Pole Height
 Reviewing design to reduce height of new monopoles
Electric and Magnetic Field (EMF)
 Within or below state and federal standards
Underground Transmission Lines
 Study for this project showed:
– Burying a 345 kV transmission line would have a significant
environmental impact
– Blasting would be required
– Additional above ground structures would be needed that would
exceed the boundaries of the ROW
23
Download