Cricket Valley Energy, LLC - Cricket Valley Transmission Upgrade

advertisement
Public Information
Presentation
1
Meeting Schedule
 Town of Pleasant Valley
May 07, 2014
 Town of Union Vale
May 08, 2014
 Town of LaGrange
May 21, 2014
 Town of Dover
May 28, 2014
2
Agenda








Project Team
Project Purpose, Scope, and Objectives
Project Benefits
Project Location and Design Considerations
Article VII Review Steps
Construction Process
Public Involvement
Questions
3
Project Team
 Cricket Valley Energy (CVE)
– Developer of Cricket Valley Energy Center, a fully
permitted $1.4 billion natural gas-fueled,
high-efficiency, combined-cycle power generation
facility in the Town of Dover/Dutchess County
– Subsidiary of Advanced Power, NA
 Epsilon Associates, Inc.
– Project environmental consultant
 DiGioia Gray & Associates
– Project engineer
 Arch Street Communications
– Public information
4
Project Purpose
 CVE has been required by New York Independent System
Operator (NYISO) to increase transmission capacity,
redundancy, and operational capabilities by funding and
installing a transmission line in the existing 14.6-mile
Con Edison right-of-way between the Town of Dover
and the Con Edison substation in the Town of Pleasant
Valley.
 Not part of any of the following transmission line
projects: NY Transco Edic to Pleasant Valley; NEXTERA
New Scotland to Pleasant Valley; North American
Transmission; or Boundless Energy Transmission.
5
Project Scope
 New 14.6-mile 345 kV line within the existing Con Edison
right-of-way (ROW) between the Project in Dover and Con
Edison’s Pleasant Valley substation
 Re-conductoring of a 3.4-mile segment of existing line
#398 between the Project site the NY/CT border
 Protection and communication upgrades at the Pleasant
Valley substation (within existing control buildings)
6
Project Objectives
 Ensure the reliability, stability, operability, and transfer
limits of the transmission system are maintained with the
connection of the Cricket Valley Energy Center
 Locate the new transmission line inside the existing
250-foot-wide Con Edison ROW with minimal disruption
to the environment and neighboring communities
 Transfer ownership to Con Edison upon completion
7
Project Benefits
 CVE will fund the approximately $55 million infrastructure
investment
 There will be no cost to utility customers or taxpayers for this
project
 Local labor prioritized for line construction and re-conductoring
 Average 40-60 workers for line construction
 Approximately 20 worker crew for re-conductoring
 Local purchases during construction
 Increased transmission capacity and grid resilience
8
Project Location
9
Project Design
 New line entirely within the existing Con Edison ROW
 New line will use state-of-the-art steel monopole
structures with delta configuration and generally follow
spacing of existing Con Edison lattice towers
 Conductors will be bundled, “Mallard” Aluminum
Conductor Steel-Supported (ACSS) cables, selected
based on rating/line capacity, cost, line losses and other
performance factors
 Protection and communication upgrades at Pleasant
Valley substation (within existing control buildings)
10
Design Considerations
 ROW land-use and environmental-base mapping in
accordance with the US Fish and Wildlife Service and
NYS Department of Environmental Conservation policies.
 Field surveys and time-of-year restrictions for protected
and sensitive species
 Invasive species, archaeological, and historic surveys
 Wetlands delineation with adjustments to structure
locations to avoid wetlands and other sensitive areas
11
Simulated View
Town of Dover
12
Simulated View
Town of LaGrange
13
Simulated View
Town of Union Vale
14
Simulated View
Town of Pleasant Valley
15
Simulated View-Taconic Pky
16
Article VII Review Steps
 December 30, 2013: submit Article VII application; copies
distributed to area libraries – Complete
 Public Statement Hearing, in project area
 Development of joint proposal: Public Service Commission
(PSC) staff with input from interested parties
 Recommendations by Administrative Law Judge (ALJ)
 PSC Hearing and Determination in Albany
 Certificate of Environmental Compatibility and Public Need
17
Construction Process
 Environmental Management and Construction Plan
approved by Department of Public Service (DPS)
 Manage ROW in accordance with Con Edison’s
Vegetation Management Plan (VMP)
 Establish laydown/staging areas—one primary area +/- 20
acres; additional storage areas, 2-3 acres each
 Survey to mark/avoid sensitive areas, clearing areas and
structure locations
18
Construction Process, cont’d
 Construction matting where required for temporary access
across wetlands
 Establish structure foundations (rock anchors, rock
micro-piles, conventional)
 Set structures; install davits, insulators, and stringing
blocks; string conductors
 Re-grading and restoration
19
Public Involvement
 Frequently Updated Website:
CricketValleyTransmission.com
 Public Information Meetings
 Advisory Working Groups
 Newsletter
 Direct mail
 Press releases
 Email sign up
 Ombudsman
 Community Outreach Office
 Legal Notices and Advertisements
20
Questions?
CricketValleyTransmission.com
21
Download